# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
1 HNSB 11.30.15 264 213 14-Sep-15 A 28-Sep-16
2 Health, Nursing & Science Building 264 213 14-Sep-15 A 28-Sep-16
3 Design & Engineering 163 100 14-Sep-15 A 19-Apr-16
4 Package 2 Long Lead 163 100 14-Sep-15 A 19-Apr-16
5 Door Frames 20 15 16-Nov-15 A 18-Dec-15 25% WPI Doors
6 Elevator & Equipment 100 54 21-Sep-15 A 15-Feb-16 46% TK
7 Lighting 80 70 16-Nov-15 A 08-Mar-16 12.5% Reynolds
8 Electrical Gear 60 50 16-Nov-15 A 09-Feb-16 16.67% Reynolds
9 HW & CW Pumps 20 5 09-Nov-15 A 04-Dec-15 75% North Umpqua
10 AHU's 1, 2 & 3 40 15 26-Oct-15 A 18-Dec-15 62.5% FM
11 Exhaust Fans 40 15 26-Oct-15 A 18-Dec-15 62.5% FM
12 Mechanical Room Equipment 60 50 16-Nov-15 A 09-Feb-16 16.67% North Umpqua
13 Generator 60 35 26-Oct-15 A 19-Jan-16 41.67% Reynolds
14 Aluminum Storefront System & Glazing 90 75 09-Nov-15 A 15-Mar-16 16.67% Culver
15 Exterior Rain Screen 90 55 09-Nov-15 A 16-Feb-16 38.89% Wood Finishes
16 Exterior Sheet Metal 60 50 09-Nov-15 A 09-Feb-16 16.67% FM Ext
17 Lab Equipment 120 100 16-Nov-15 A 19-Apr-16 16.67% ACCO
18 Lab Casework/Countertops 120 65 14-Sep-15 A 01-Mar-16 45.83% S & B
19 Contractor Supplied Furniture 80 80 30-Nov-15 22-Mar-16 0% ACCO
20 Doors & Hardware 90 80 09-Nov-15 A 22-Mar-16 11.11% WPI Doors
21 Construction Phase 221 213 16-Nov-15 A 28-Sep-16
22 Building Milestones 195 195 24-Dec-15 28-Sep-16
23 Roof Complete & Building Dried In 1 1 24-Dec-15 24-Dec-15 0%
24 Interior Rough In Complete 1 1 10-Mar-16 10-Mar-16 0%
25 Interior Finishes Complete 1 1 04-Aug-16 04-Aug-16 0%
26 Site Finishes & Landscaping Complete 1 1 01-Aug-16 01-Aug-16 0%
27 Substantial Completion 1 1 17-Aug-16 17-Aug-16 0%
28 CO 1 1 28-Sep-16 28-Sep-16 0%
29 MEP Milestones 195 195 21-Dec-15 23-Sep-16
30 Replacement HW/CW Pumps In Service 0 0 21-Dec-15* 21-Dec-15 0%
31 Temp Heat Ready To Run 0 0 21-Dec-15 21-Dec-15 0%
32 Initial Energization 0 0 17-Feb-16 17-Feb-16 0%
33 Mechanical Piping Complete & Flushed 0 0 17-Feb-16 17-Feb-16 0%
34 Intitial AHU Air Run 1st Floor 0 0 24-Feb-16 24-Feb-16 0%
35 Initial AHU Air Run 2nd Floor 0 0 24-Feb-16 24-Feb-16 0%
36 All Coil Connections Complete 5 5 24-Feb-16 01-Mar-16 0%
37 MEP Running Under Control 0 0 18-Mar-16 18-Mar-16 0%
38 Prime & 1st Coat & Building Clean Complete 1 1 17-Mar-16 17-Mar-16 0%
39 Complete Loop Tuning 7 7 18-Mar-16 28-Mar-16 0%
40 Test & Balance Water/Air 20 20 15-Mar-16 11-Apr-16 0%
41 Fire Alarm Test Complete 58 58 12-Apr-16 01-Jul-16 0%
42 Commisioning Complete 58 58 05-Jul-16 23-Sep-16 0%
43 MEP Equipment Install & Startup 50 50 07-Dec-15 16-Feb-16
44 Replace Existing HW/CW Pumps In Mechanical Room 10 10 07-Dec-15 18-Dec-15 0% North Umpqua, Essential, Reynolds
45 HW & CW Pump Startup 5 5 15-Dec-15 21-Dec-15 0% Essential, North Umpqua, Reynolds
46 Install Switch Gear 5 5 10-Feb-16 16-Feb-16 0% Reynolds
47 Install Electrical Distribution 5 5 10-Feb-16 16-Feb-16 0% Reynolds
48 Install AHU-1, AHU-2 & AHU-3 5 5 24-Dec-15 31-Dec-15 0% FM, North Umpqua
49 MEP @ AHU-1, AHU-2 & AHU-3 10 10 04-Jan-16 15-Jan-16 0% North Umpqua, Reynolds, FM, North Umpqua, Essential
50 AHU-1, AHU-2 & AHU-3 Startup 5 5 18-Jan-16 22-Jan-16 0% FM, North Umpqua, Essential, North Umpqua, Reynolds
51 Install EF-1, EF-2 & EF-3 3 3 24-Dec-15 29-Dec-15 0% FM, Essential
52 Connect Electrical/Controls @ EF-1, EF-2 & EF-3 2 2 30-Dec-15 31-Dec-15 0% FM, Essential, Reynolds
53 EF-1, EF-2 & EF-3 Startup 2 2 04-Jan-16 05-Jan-16 0% FM, Essential, Reynolds
54 Underground Civil Outside 5' Outside Of Perimeter 33 33 30-Nov-15 A 15-Jan-16
55 Footing Drains 5 5 30-Nov-15 A 04-Dec-15
56 Complete Drain Rock Around Building Perimeter 5 5 30-Nov-15 A 04-Dec-15 0% North Umpqua, Knife River
57 West Concrete & South Utilities 4 1 30-Nov-15 A 30-Nov-15
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
28-Sep-16, HNSB 11.30.15
28-Sep-16, Health, Nursing & Science Building
19-Apr-16, Design & Engineering
19-Apr-16, Package 2 Long Lead
Door Frames
Elevator & Equipment
Lighting
Electrical Gear
HW & CW Pumps
AHU's 1, 2 & 3
Exhaust Fans
Mechanical Room Equipment
Generator
Aluminum Storefront System & Glazing
Exterior Rain Screen
Exterior Sheet Metal
Lab Equipment
Lab Casework/Countertops
Contractor Supplied Furniture
Doors & Hardware
28-Sep-16, Construction Phase
28-Sep-16, Building Milestones
Roof Complete & Building Dried In
Interior Rough In Complete
Interior Finishes Complete
Site Finishes & Landscaping Complete
Substantial Completion
CO
23-Sep-16, MEP Milestones
Replacement HW/CW Pumps In Service
Temp Heat Ready To Run
Initial Energization
Mechanical Piping Complete & Flushed
Intitial AHU Air Run 1st Floor
Initial AHU Air Run 2nd Floor
All Coil Connections Complete
MEP Running Under Control
Prime & 1st Coat & Building Clean Complete
Complete Loop Tuning
Test & Balance Water/Air
Fire Alarm Test Complete
Commisioning Complete
16-Feb-16, MEP Equipment Install & Startup
Replace Existing HW/CW Pumps In Mechanical Room
HW & CW Pump Startup
Install Switch Gear
Install Electrical Distribution
Install AHU-1, AHU-2 & AHU-3
MEP @ AHU-1, AHU-2 & AHU-3
AHU-1, AHU-2 & AHU-3 Startup
Install EF-1, EF-2 & EF-3
Connect Electrical/Controls @ EF-1, EF-2 & EF-3
EF-1, EF-2 & EF-3 Startup
15-Jan-16, Underground Civil Outside 5' Outside Of Perimeter
04-Dec-15, Footing Drains
Complete Drain Rock Around Building Perimeter
30-Nov-15, West Concrete & South Utilities
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 1 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
58 Complete SD & FDC Piping 4 1 30-Nov-15 A 30-Nov-15 75% Knife River
59 East Civil/Fire Lane 33 33 30-Nov-15 15-Jan-16
60 Fire Hydrant Supply 9 9 30-Nov-15 10-Dec-15
61 Install 12"X 8"Gate Valve & Block/Restrain 2 2 30-Nov-15 01-Dec-15 0% Knife River
62 Install 8" 22-1/2 MJ Bend & Block/Restrain 2 2 02-Dec-15 03-Dec-15 0% Knife River
63 Install 2" Temp Blowoff, For Tie In Install 8" MJ Sleeve & 8" DI Spool 2 2 04-Dec-15 07-Dec-15 0% Knife River
64 Test & Inspections 1 1 08-Dec-15 08-Dec-15 0% Knife River, Fire Marshall, County, UCC
65 Cap Pipe @ New Hydrant Location & Backfill 2 2 09-Dec-15 10-Dec-15 0% Knife River
66 Fire Lane Demo & Civil 24 24 11-Dec-15 15-Jan-16
67 Demo Existing Fire Lane 5 5 11-Dec-15 17-Dec-15 0% Knife River
68 Pothole, Locate & Reroute Existing Gas Lines 7 7 18-Dec-15 29-Dec-15 0% Knife River
69 Cut Tree Roots 1 1 30-Dec-15 30-Dec-15 0% Knife River
70 Install/Compact Base For New Fire Lane 5 5 31-Dec-15 07-Jan-16 0% Knife River
71 Remove Catch Basin, Install Cleanout & Install New Catch Basin 2 2 08-Jan-16 11-Jan-16 0% Knife River
72 Replace Catch Basins, Set Inlets To Elevation & Connect To Existing Storm2 2 12-Jan-16 13-Jan-16 0% Knife River
73 Replace Catch Basin & Install New Basin Near Admin Building 2 2 14-Jan-16 15-Jan-16 0% Knife River
74 Test & Inspections 1 1 15-Jan-16 15-Jan-16 0% County, UCC, Knife River
75 Exterior Facade 82 74 16-Nov-15 A 14-Mar-16
76 West Elevation 60 52 16-Nov-15 A 11-Feb-16
77 Install Roof Soffit/Parapet 5 2 16-Nov-15 A 01-Dec-15 60% Harver
78 Layout & Install Exterior Framing 10 6 16-Nov-15 A 07-Dec-15 40% Harver
79 Framing Inspections 2 1 30-Nov-15 A 30-Nov-15 50% Special Inspection, County
80 Install Exterior Sheathing 5 5 01-Dec-15 07-Dec-15 0% Harver
81 Sheathing Inspection 1 1 07-Dec-15 07-Dec-15 0% County
82 Install Exterior Weather Barrier 5 5 08-Dec-15 14-Dec-15 0% Weather Barrier
83 Install Hollow Metal Door Frames 2 2 21-Dec-15 22-Dec-15 0% Harver
84 Install Flashing Details 5 5 23-Dec-15 30-Dec-15 0% FM Ext
85 Install Aluminum Store Front/Glazing System SF-1 5 5 30-Dec-15 06-Jan-16 0% Culver
86 Install Rigid Installation 5 5 06-Jan-16 12-Jan-16 0% Harver Insulation
87 Install Insect Screen, Furring Strips & Wood Rain Screen System 8 8 08-Jan-16 19-Jan-16 0% Siding Specialist
88 Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile 6 6 15-Jan-16 22-Jan-16 0% Siding Specialist
89 Install Plate Steel Trim/Closure Piece W/Clear Sealer 3 3 25-Jan-16 27-Jan-16 0% FM Ext
90 Install Aluminum Storefront Systems 5 5 27-Jan-16 02-Feb-16 0% Culver
91 Exterior Painting 5 5 01-Feb-16 05-Feb-16 0% WPI Paint
92 Exterior Punch & Corrections 5 5 04-Feb-16 10-Feb-16 0% Opsis, ACCO
93 Back Punch 2 2 10-Feb-16 11-Feb-16 0% UCC, ACCO
94 North Elevation 66 64 16-Nov-15 A 29-Feb-16
95 Layout & Install Exterior Framing 10 3 16-Nov-15 A 02-Dec-15 70% Harver
96 Framing Inspections 3 3 30-Nov-15 02-Dec-15 0% County, Special Inspection
97 Install Exterior Sheathing 8 8 01-Dec-15 10-Dec-15 0% Harver
98 Sheathing Inspection 2 2 09-Dec-15 10-Dec-15 0% County
99 Install Exterior Weather Barrier 10 10 15-Dec-15 29-Dec-15 0% Weather Barrier
100 Install Flashing Details 6 6 28-Dec-15 05-Jan-16 0% FM Ext
101 Install Aluminum Store Front System SF-1 10 10 04-Jan-16 15-Jan-16 0% Culver
102 Install Rigid Insulation 7 7 14-Jan-16 22-Jan-16 0% Harver Insulation
103 Install Insect Screen, Furring Strips & Wood Rain Screen System 10 10 20-Jan-16 02-Feb-16 0% Siding Specialist
104 Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile 10 10 29-Jan-16 11-Feb-16 0% Siding Specialist
105 Install Plate Steel Trim/Closure Piece W/Clear Sealer 5 5 10-Feb-16 16-Feb-16 0% FM Ext
106 Exterior Painting 5 5 16-Feb-16 22-Feb-16 0% WPI Paint
107 Exterior Punch & Corrections 5 5 19-Feb-16 25-Feb-16 0% Opsis, ACCO
108 Back Punch 2 2 26-Feb-16 29-Feb-16 0% UCC, ACCO
109 East Elevation 70 70 30-Nov-15 A 08-Mar-16
110 Layout & Install Exterior Framing 10 9 30-Nov-15 A 10-Dec-15 10% Harver
111 Framing Inspections 2 2 09-Dec-15 10-Dec-15 0% County, Special Inspection
112 Install Exterior Sheathing 7 7 09-Dec-15 17-Dec-15 0% Harver
113 Sheathing Inspection 1 1 17-Dec-15 17-Dec-15 0% County, O & S
114 Install Exterior Weather Barrier 5 5 14-Jan-16 20-Jan-16 0% Weather Barrier
115 Install Flashing Details 5 5 21-Jan-16 27-Jan-16 0% FM Ext
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Complete SD & FDC Piping
15-Jan-16, East Civil/Fire Lane
10-Dec-15, Fire Hydrant Supply
Install 12"X 8"Gate Valve & Block/Restrain
Install 8" 22-1/2 MJ Bend & Block/Restrain
Install 2" Temp Blowoff, For Tie In Install 8" MJ Sleeve & 8" DI Spool
Test & Inspections
Cap Pipe @ New Hydrant Location & Backfill
15-Jan-16, Fire Lane Demo & Civil
Demo Existing Fire Lane
Pothole, Locate & Reroute Existing Gas Lines
Cut Tree Roots
Install/Compact Base For New Fire Lane
Remove Catch Basin, Install Cleanout & Install New Catch Basin
Replace Catch Basins, Set Inlets To Elevation & Connect To Existing Storm
Replace Catch Basin & Install New Basin Near Admin Building
Test & Inspections
14-Mar-16, Exterior Facade
11-Feb-16, West Elevation
Install Roof Soffit/Parapet
Layout & Install Exterior Framing
Framing Inspections
Install Exterior Sheathing
Sheathing Inspection
Install Exterior Weather Barrier
Install Hollow Metal Door Frames
Install Flashing Details
Install Aluminum Store Front/Glazing System SF-1
Install Rigid Installation
Install Insect Screen, Furring Strips & Wood Rain Screen System
Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile
Install Plate Steel Trim/Closure Piece W/Clear Sealer
Install Aluminum Storefront Systems
Exterior Painting
Exterior Punch & Corrections
Back Punch
29-Feb-16, North Elevation
Layout & Install Exterior Framing
Framing Inspections
Install Exterior Sheathing
Sheathing Inspection
Install Exterior Weather Barrier
Install Flashing Details
Install Aluminum Store Front System SF-1
Install Rigid Insulation
Install Insect Screen, Furring Strips & Wood Rain Screen System
Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile
Install Plate Steel Trim/Closure Piece W/Clear Sealer
Exterior Painting
Exterior Punch & Corrections
Back Punch
08-Mar-16, East Elevation
Layout & Install Exterior Framing
Framing Inspections
Install Exterior Sheathing
Sheathing Inspection
Install Exterior Weather Barrier
Install Flashing Details
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 2 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
116 Install Aluminum Store Front System SF-1 5 5 27-Jan-16 02-Feb-16 0% Culver
117 Install Rigid Insulation 5 5 02-Feb-16 08-Feb-16 0% Harver Insulation
118 Install Insect Screen, Furring Strips & Wood Rain Screen System 10 10 04-Feb-16 17-Feb-16 0% Siding Specialist
119 Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile 7 7 15-Feb-16 23-Feb-16 0% Siding Specialist
120 Install Plate Steel Trim/Closure Piece W/Clear Sealer 3 3 24-Feb-16 26-Feb-16 0% FM Ext
121 Install Aluminum Store Front Systems 5 5 26-Feb-16 03-Mar-16 0% Culver
122 Exterior Painting 5 5 25-Feb-16 02-Mar-16 0% WPI Paint
123 Exterior Punch & Corrections 5 5 01-Mar-16 07-Mar-16 0% Opsis, ACCO
124 Back Punch 2 2 07-Mar-16 08-Mar-16 0% UCC, ACCO
125 South Elevation 70 70 04-Dec-15 14-Mar-16
126 Layout & Install Exterior Framing 10 10 04-Dec-15 17-Dec-15 0% Harver
127 Framing Inspections 4 4 14-Dec-15 17-Dec-15 0% Special Inspection, County
128 Install Exterior Sheathing 8 8 14-Dec-15 23-Dec-15 0% Harver
129 Sheathing Inspection 2 2 23-Dec-15 24-Dec-15 0% County
130 Install Exterior Weather Barrier 10 10 30-Dec-15 13-Jan-16 0% Weather Barrier
131 Install Flashing Details 6 6 12-Jan-16 19-Jan-16 0% FM Ext
132 Install Aluminum Store Front System SF-1 10 10 18-Jan-16 29-Jan-16 0% Culver
133 Install Rigid Insulation 7 7 28-Jan-16 05-Feb-16 0% Siding Specialist
134 Install Insect Screen, Furring Strips & Wood Rain Screen System 10 10 03-Feb-16 16-Feb-16 0% Siding Specialist
135 Install Metal Furring, Mineral Wool, 2" x 4" & Concrete Tile 10 10 12-Feb-16 25-Feb-16 0% Siding Specialist
136 Install Plate Steel Trim/Closure Piece W/Clear Sealer 5 5 24-Feb-16 01-Mar-16 0% FM Ext
137 Exterior Painting 5 5 01-Mar-16 07-Mar-16 0% WPI Paint
138 Exterior Punch & Corrections 5 5 04-Mar-16 10-Mar-16 0% Opsis, ACCO
139 Back Punch 2 2 11-Mar-16 14-Mar-16 0% UCC, ACCO
140 Roofing Installation 42 34 16-Nov-15 A 18-Jan-16
141 Install Roof Drains, Mech Curbs & MEP Penetrating Roof 10 5 16-Nov-15 A 04-Dec-15 50% North Umpqua, FM, Reynolds
142 Install PT Parapet Cap & Roof Hatch 9 9 30-Nov-15 10-Dec-15 0% Rough Carpentry
143 Install Parapet Sheathing 5 5 30-Nov-15 04-Dec-15 0% Harver
144 Install Roofing Insulation 10 10 03-Dec-15 16-Dec-15 0% Umpqua Roofing-1
145 Install Roofing Membrane 10 10 10-Dec-15 23-Dec-15 0% Umpqua Roofing-1
146 Install Penetration Flashing Details 5 5 22-Dec-15 29-Dec-15 0% Umpqua Roofing-1
147 Install Mechanical Curb Flashing Details 5 5 28-Dec-15 04-Jan-16 0% FM Ext
148 Install Parapet Flashing Details 10 10 05-Jan-16 18-Jan-16 0% FM Ext
149 Skylight 64 61 23-Nov-15 A 24-Feb-16
150 Field Measure For Skylights 1 1 30-Nov-15 30-Nov-15 0% DeMor
151 Install Wood Cap 2 2 30-Nov-15 01-Dec-15 0% ASI
152 Install Exterior Sheathing 1 1 02-Dec-15 02-Dec-15 0% Harver
153 Install SAM & Metal Flashing Details 5 5 03-Dec-15 09-Dec-15 0% LDC, FM Ext
154 Deliver & Install Skylights 60 60 23-Nov-15 A 23-Feb-16 0% DeMor
155 Inspection 1 1 24-Feb-16 24-Feb-16 0% County
156 Interior Rough In 80 83 30-Nov-15 A 25-Mar-16
157 Level 1 51 54 30-Nov-15 A 15-Feb-16
158 Mech, Riser, Elec Closet, Elevator Control & Shafts 31 34 30-Nov-15 A 18-Jan-16
159 Layout/Framing/Backing 5 5 30-Nov-15 A 04-Dec-15 0% Harver
160 Install Door Frames 1 1 21-Dec-15 21-Dec-15 0% Harver
161 MEP Rough In 10 10 03-Dec-15 16-Dec-15 0% FM, North Umpqua, Essential, Data, O & S, North Umpqua, Reynolds
162 Inspections To Cover Walls 1 1 16-Dec-15 16-Dec-15 0% County
163 QC Doors & Backing 1 1 16-Dec-15 16-Dec-15 0% Harver
164 Install Required Insulation 1 1 24-Dec-15 24-Dec-15 0% Harver
165 Hang Gyp 2 2 28-Dec-15 29-Dec-15 0% Harver
166 Tape Gyp 5 5 30-Dec-15 06-Jan-16 0% Harver
167 Install Fire Stopping Details 1 1 07-Jan-16 07-Jan-16 0% Harver
168 Prime & 1st Coat 2 2 08-Jan-16 11-Jan-16 0% WPI Paint
169 Layout/Form Equipment Pads @ Mechanical Room 2 2 11-Jan-16 12-Jan-16 0% Gerding, North Umpqua, Essential, North Umpqua, Reynolds
170 Inspection @ Equipment Pads 1 1 13-Jan-16 13-Jan-16 0% County, Special Inspection
171 Pour Equipment Pads In Mechanical Room 1 1 14-Jan-16 14-Jan-16 0% Gerding
172 Paint & Install FT Ply @ Telecom Room 2 2 15-Jan-16 18-Jan-16 0% WPI Paint
173 Install Temp Doors W/Locks 1 1 18-Jan-16 18-Jan-16 0% ASI
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Install Aluminum Store Front System SF-1
Install Rigid Insulation
Install Insect Screen, Furring Strips & Wood Rain Screen System
Install Metal Furring, Mineral Wool, 2" X 4" & Concrete Tile
Install Plate Steel Trim/Closure Piece W/Clear Sealer
Install Aluminum Store Front Systems
Exterior Painting
Exterior Punch & Corrections
Back Punch
14-Mar-16, South Elevation
Layout & Install Exterior Framing
Framing Inspections
Install Exterior Sheathing
Sheathing Inspection
Install Exterior Weather Barrier
Install Flashing Details
Install Aluminum Store Front System SF-1
Install Rigid Insulation
Install Insect Screen, Furring Strips & Wood Rain Screen System
Install Metal Furring, Mineral Wool, 2" x 4" & Concrete Tile
Install Plate Steel Trim/Closure Piece W/Clear Sealer
Exterior Painting
Exterior Punch & Corrections
Back Punch
18-Jan-16, Roofing Installation
Install Roof Drains, Mech Curbs & MEP Penetrating Roof
Install PT Parapet Cap & Roof Hatch
Install Parapet Sheathing
Install Roofing Insulation
Install Roofing Membrane
Install Penetration Flashing Details
Install Mechanical Curb Flashing Details
Install Parapet Flashing Details
24-Feb-16, Skylight
Field Measure For Skylights
Install Wood Cap
Install Exterior Sheathing
Install SAM & Metal Flashing Details
Deliver & Install Skylights
Inspection
25-Mar-16, Interior Rough In
15-Feb-16, Level 1
18-Jan-16, Mech, Riser, Elec Closet, Elevator Control & Shafts
Layout/Framing/Backing
Install Door Frames
MEP Rough In
Inspections To Cover Walls
QC Doors & Backing
Install Required Insulation
Hang Gyp
Tape Gyp
Install Fire Stopping Details
Prime & 1st Coat
Layout/Form Equipment Pads @ Mechanical Room
Inspection @ Equipment Pads
Pour Equipment Pads In Mechanical Room
Paint & Install FT Ply @ Telecom Room
Install Temp Doors W/Locks
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 3 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
174 Start MEP Equipment Install 1 1 18-Jan-16 18-Jan-16 0% TK, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua
175 Restrooms, Janitor & Storage 31 31 07-Dec-15 20-Jan-16
176 Layout/Framing/Backing 3 3 07-Dec-15 09-Dec-15 0% Harver
177 Install Door Frames 1 1 21-Dec-15 21-Dec-15 0% Harver
178 MEP Rough In 5 5 07-Dec-15 11-Dec-15 0% FM, North Umpqua, Essential, O & S, North Umpqua, Reynolds
179 Layout Access Doors @ Restroom Walls 1 1 11-Dec-15 11-Dec-15 0% North Umpqua
180 MEP/Framing Inspections To Cover Walls 2 2 14-Dec-15 15-Dec-15 0% County
181 Quality Control Doors & Backing 1 1 14-Dec-15 14-Dec-15 0% Harver
182 Install Acoustical Insulation 1 1 15-Dec-15 15-Dec-15 0% Harver
183 Hang Gyp 3 3 24-Dec-15 29-Dec-15 0% Harver
184 Install Ceiling Framing @ Restrooms 2 2 30-Dec-15 31-Dec-15 0% Harver
185 Complete Above Ceiling MEP 4 4 04-Jan-16 07-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua
186 Layout Access Doors @ Ceilings 1 1 08-Jan-16 08-Jan-16 0% Harver, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua
187 MEP/Framing Inspections To Cover Ceilings 1 1 08-Jan-16 08-Jan-16 0% County
188 Install Gyp @ Restroom Ceilings 2 2 11-Jan-16 12-Jan-16 0% Harver
189 Install Access Doors @ Walls & Ceilings 1 1 11-Jan-16 11-Jan-16 0% Harver
190 Tape Gyp 5 5 12-Jan-16 18-Jan-16 0% Harver
191 Prime & 1st Coat 2 2 19-Jan-16 20-Jan-16 0% WPI Paint
192 Common Hallways & Vestibules 32 32 07-Dec-15 21-Jan-16
193 Layout/Framing/Backing 6 6 08-Dec-15 15-Dec-15 0% Harver
194 MEP Rough In 10 10 07-Dec-15 18-Dec-15 0% FM, North Umpqua, Data, Essential, O & S, Reynolds, North Umpqua
195 MEP/Framing Inspections To Cover Walls 2 2 17-Dec-15 18-Dec-15 0% County
196 Quality Control Doors & Backing 1 1 16-Dec-15 16-Dec-15 0% Harver
197 Hang & Tape Gyp @ Walls 7 7 24-Dec-15 05-Jan-16 0% Harver
198 Prime & 1st Coat 4 4 06-Jan-16 11-Jan-16 0% WPI Paint
199 Install Ceiling Framing 4 4 12-Jan-16 15-Jan-16 0% Harver
200 Complete Above Ceiling MEP 5 5 14-Jan-16 20-Jan-16 0% North Umpqua, Data, Essential, North Umpqua, Reynolds, O & S, FM
201 Layout Access Doors In Ceilings 1 1 20-Jan-16 20-Jan-16 0% Reynolds, Harver, FM, North Umpqua, Data, Essential, North Umpqua
202 MEP/Framing Inspections To Cover Ceilings 2 2 20-Jan-16 21-Jan-16 0% County
203 Labs 35 35 14-Dec-15 02-Feb-16
204 Layout/Framing/Backing 6 6 14-Dec-15 21-Dec-15 0% Harver
205 Install Door Frames 2 2 21-Dec-15 22-Dec-15 0% Harver
206 Frame Ceiling Soffits 8 8 22-Dec-15 04-Jan-16 0% Harver
207 MEP Rough In 15 15 14-Dec-15 05-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds
208 Layout Access Doors 1 1 05-Jan-16 05-Jan-16 0% Harver, North Umpqua, North Umpqua
209 MEP/Framing Inspections To Cover Walls 2 2 05-Jan-16 06-Jan-16 0% County
210 Quality Control Doors & Backing 2 2 05-Jan-16 06-Jan-16 0% Harver
211 Install Acoustical Insulation 3 3 06-Jan-16 08-Jan-16 0% Harver
212 Hang Gyp 5 5 07-Jan-16 13-Jan-16 0% Harver
213 Install Access Doors 2 2 12-Jan-16 13-Jan-16 0% Harver
214 Tape Gyp 7 7 13-Jan-16 21-Jan-16 0% Harver
215 Complete Above Ceiling MEP 5 5 21-Jan-16 27-Jan-16 0% Essential, North Umpqua, O & S, FM, North Umpqua, Data
216 Prime & 1st Coat 4 4 28-Jan-16 02-Feb-16 0% WPI Paint
217 Classrooms 34 34 16-Dec-15 03-Feb-16
218 Layout/Framing/Backing @ Walls 4 4 18-Dec-15 23-Dec-15 0% Harver
219 Install Door Frames 2 2 16-Dec-15 17-Dec-15 0% Harver
220 Frame Ceiling Soffits 3 3 18-Dec-15 22-Dec-15 0% Harver
221 MEP Rough In 10 10 23-Dec-15 07-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds
222 MEP/Framing Inspections 2 2 07-Jan-16 08-Jan-16 0% County
223 Quality Control Doors & Backing 1 1 07-Jan-16 07-Jan-16 0% Harver
224 Install Acoustical Insulation 2 2 08-Jan-16 11-Jan-16 0% Harver
225 Hang Gyp 4 4 12-Jan-16 15-Jan-16 0% Harver
226 Tape Gyp 5 5 18-Jan-16 22-Jan-16 0% Harver
227 Complete Above Ceiling MEP 5 5 22-Jan-16 28-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua
228 Prime & 1st Coat 4 4 29-Jan-16 03-Feb-16 0% WPI Paint
229 Conference, Meeting & Work Rooms 28 28 22-Dec-15 01-Feb-16
230 Layout/Framing/Backing 3 3 24-Dec-15 29-Dec-15 0% Harver
231 Install Door Frames 2 2 22-Dec-15 23-Dec-15 0% Harver
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Start MEP Equipment Install
20-Jan-16, Restrooms, Janitor & Storage
Layout/Framing/Backing
Install Door Frames
MEP Rough In
Layout Access Doors @ Restroom Walls
MEP/Framing Inspections To Cover Walls
Quality Control Doors & Backing
Install Acoustical Insulation
Hang Gyp
Install Ceiling Framing @ Restrooms
Complete Above Ceiling MEP
Layout Access Doors @ Ceilings
MEP/Framing Inspections To Cover Ceilings
Install Gyp @ Restroom Ceilings
Install Access Doors @ Walls & Ceilings
Tape Gyp
Prime & 1st Coat
21-Jan-16, Common Hallways & Vestibules
Layout/Framing/Backing
MEP Rough In
MEP/Framing Inspections To Cover Walls
Quality Control Doors & Backing
Hang & Tape Gyp @ Walls
Prime & 1st Coat
Install Ceiling Framing
Complete Above Ceiling MEP
Layout Access Doors In Ceilings
MEP/Framing Inspections To Cover Ceilings
02-Feb-16, Labs
Layout/Framing/Backing
Install Door Frames
Frame Ceiling Soffits
MEP Rough In
Layout Access Doors
MEP/Framing Inspections To Cover Walls
Quality Control Doors & Backing
Install Acoustical Insulation
Hang Gyp
Install Access Doors
Tape Gyp
Complete Above Ceiling MEP
Prime & 1st Coat
03-Feb-16, Classrooms
Layout/Framing/Backing @ Walls
Install Door Frames
Frame Ceiling Soffits
MEP Rough In
MEP/Framing Inspections
Quality Control Doors & Backing
Install Acoustical Insulation
Hang Gyp
Tape Gyp
Complete Above Ceiling MEP
Prime & 1st Coat
01-Feb-16, Conference, Meeting & Work Rooms
Layout/Framing/Backing
Install Door Frames
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 4 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
232 Frame Ceiling Soffit @ 121 1 1 24-Dec-15 24-Dec-15 0% Harver
233 MEP Rough In 10 10 24-Dec-15 08-Jan-16 0% Essential, Fire Marshall, FM, North Umpqua, Data, North Umpqua, Reynolds
234 MEP/Framing Inspections 1 1 08-Jan-16 08-Jan-16 0% County
235 Quality Control Doors & Backing 1 1 08-Jan-16 08-Jan-16 0% Harver
236 Install Acoustical Insulation 1 1 11-Jan-16 11-Jan-16 0% Harver
237 Hang Gyp 3 3 12-Jan-16 14-Jan-16 0% Harver
238 Tape Gyp 5 5 15-Jan-16 21-Jan-16 0% Harver
239 Complete Above Ceiling MEP 4 4 21-Jan-16 26-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds
240 Prime & 1st Coat 4 4 27-Jan-16 01-Feb-16 0% WPI Paint
241 Offices 33 33 30-Dec-15 15-Feb-16
242 Layout/Framing/Backing 3 3 30-Dec-15 04-Jan-16 0% Harver
243 Install Door Frames 2 2 05-Jan-16 06-Jan-16 0% Harver
244 Frame Ceiling Soffits 3 3 05-Jan-16 07-Jan-16 0% Harver
245 MEP Rough In 10 10 06-Jan-16 19-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua
246 MEP/Framing Inspections 2 2 19-Jan-16 20-Jan-16 0% County
247 Quality Control Doors & Backing 1 1 21-Jan-16 21-Jan-16 0% Harver
248 Install Acoustical Insulation 2 2 22-Jan-16 25-Jan-16 0% Harver
249 Hang Gyp 4 4 26-Jan-16 29-Jan-16 0% Harver
250 Tape Gyp 5 5 28-Jan-16 03-Feb-16 0% Harver
251 Complete Above Ceiling MEP 5 5 02-Feb-16 08-Feb-16 0% Reynolds, O & S, FM, North Umpqua, Data, Essential, North Umpqua
252 Prime & 1st Coat 5 5 09-Feb-16 15-Feb-16 0% WPI Paint
253 Level 2 54 54 04-Jan-16 17-Mar-16
254 Restrooms, MDF & Storage 35 35 04-Jan-16 19-Feb-16
255 Layout/Framing/Backing 3 3 05-Jan-16 07-Jan-16 0% Harver
256 Install Door Frames 1 1 04-Jan-16 04-Jan-16 0% Harver
257 MEP Rough In 10 10 04-Jan-16 15-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds
258 Layout & Install Access Doors @ Restroom Walls 1 1 18-Jan-16 18-Jan-16 0% North Umpqua
259 MEP/Framing Inspections To Cover Walls 2 2 19-Jan-16 20-Jan-16 0% County
260 Quality Control Doors & Backing 1 1 19-Jan-16 19-Jan-16 0% Harver
261 Install Acoustical Insulation 1 1 20-Jan-16 20-Jan-16 0% Harver
262 Hang Gyp @ Walls 3 3 21-Jan-16 25-Jan-16 0% Harver
263 Install Ceiling Framing @ Restrooms 3 3 26-Jan-16 28-Jan-16 0% Harver
264 Complete Above Ceiling MEP 4 4 29-Jan-16 03-Feb-16 0% Essential, Reynolds, North Umpqua, O & S, FM, North Umpqua, Data
265 Layout Access Doors @ Ceilings 1 1 04-Feb-16 04-Feb-16 0% FM, North Umpqua, Data, Essential, Reynolds
266 MEP/Framing Inspections To Cover Ceilings 1 1 05-Feb-16 05-Feb-16 0% County
267 Install Gyp @ Restroom Ceilings 2 2 08-Feb-16 09-Feb-16 0% Harver
268 Install Access Doors @ Walls & Ceilings 1 1 08-Feb-16 08-Feb-16 0% Harver
269 Tape Gyp 6 6 09-Feb-16 16-Feb-16 0% Harver
270 Prime & 1st Coat 3 3 17-Feb-16 19-Feb-16 0% WPI Paint
271 Common Hallways & Vestibules 27 27 06-Jan-16 11-Feb-16
272 Layout/Framing/Backing 10 10 06-Jan-16 19-Jan-16 0% Harver
273 MEP Rough In 10 10 08-Jan-16 21-Jan-16 0% O & S, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua
274 MEP/Framing Inspections To Cover Walls 2 2 20-Jan-16 21-Jan-16 0% County
275 Quality Control Doors & Backing 1 1 21-Jan-16 21-Jan-16 0% Harver
276 Hang & Tape Gyp @ Walls 5 5 22-Jan-16 28-Jan-16 0% Harver
277 Prime & 1st Coat 4 4 27-Jan-16 01-Feb-16 0% Harver
278 Install Ceiling Framing 5 5 29-Jan-16 04-Feb-16 0% O & S, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua
279 Complete Above Ceiling MEP 1 1 04-Feb-16 04-Feb-16 0% Data, Essential, Reynolds, FM, North Umpqua
280 Layout Access Doors In Ceilings 2 2 04-Feb-16 05-Feb-16 0% County
281 MEP/Framing Inspections To Cover Ceilings 4 4 08-Feb-16 11-Feb-16 0% Harver
282 Labs 46 46 14-Jan-16 17-Mar-16
283 Layout/Framing/Backing 5 5 18-Jan-16 22-Jan-16 0% Harver
284 Install Door Frames 3 3 14-Jan-16 18-Jan-16 0% Harver
285 Frame Ceiling Soffits 4 4 19-Jan-16 22-Jan-16 0% Harver
286 MEP Rough In 15 15 25-Jan-16 12-Feb-16 0% O & S, FM, North Umpqua, Data, Essential, Reynolds, North Umpqua
287 Layout Access Doors 1 1 12-Feb-16 12-Feb-16 0% North Umpqua, North Umpqua
288 MEP/Framing Inspections 2 2 11-Feb-16 12-Feb-16 0% County
289 Quality Control Doors & Backing 2 2 15-Feb-16 16-Feb-16 0% Harver
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Frame Ceiling Soffit @ 121
MEP Rough In
MEP/Framing Inspections
Quality Control Doors & Backing
Install Acoustical Insulation
Hang Gyp
Tape Gyp
Complete Above Ceiling MEP
Prime & 1st Coat
15-Feb-16, Offices
Layout/Framing/Backing
Install Door Frames
Frame Ceiling Soffits
MEP Rough In
MEP/Framing Inspections
Quality Control Doors & Backing
Install Acoustical Insulation
Hang Gyp
Tape Gyp
Complete Above Ceiling MEP
Prime & 1st Coat
17-Mar-16, Level 2
19-Feb-16, Restrooms, MDF & Storage
Layout/Framing/Backing
Install Door Frames
MEP Rough In
Layout & Install Access Doors @ Restroom Walls
MEP/Framing Inspections To Cover Walls
Quality Control Doors & Backing
Install Acoustical Insulation
Hang Gyp @ Walls
Install Ceiling Framing @ Restrooms
Complete Above Ceiling MEP
Layout Access Doors @ Ceilings
MEP/Framing Inspections To Cover Ceilings
Install Gyp @ Restroom Ceilings
Install Access Doors @ Walls & Ceilings
Tape Gyp
Prime & 1st Coat
11-Feb-16, Common Hallways & Vestibules
Layout/Framing/Backing
MEP Rough In
MEP/Framing Inspections To Cover Walls
Quality Control Doors & Backing
Hang & Tape Gyp @ Walls
Prime & 1st Coat
Install Ceiling Framing
Complete Above Ceiling MEP
Layout Access Doors In Ceilings
MEP/Framing Inspections To Cover Ceilings
17-Mar-16, Labs
Layout/Framing/Backing
Install Door Frames
Frame Ceiling Soffits
MEP Rough In
Layout Access Doors
MEP/Framing Inspections
Quality Control Doors & Backing
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 5 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
290 Install Acoustical Installation 3 3 17-Feb-16 19-Feb-16 0% Harver
291 Hang Gyp 5 5 18-Feb-16 24-Feb-16 0% Harver
292 Install Access Doors 2 2 23-Feb-16 24-Feb-16 0% Harver
293 Tape Gyp 7 7 25-Feb-16 04-Mar-16 0% Harver
294 Complete Above Ceiling MEP 5 5 04-Mar-16 10-Mar-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds
295 Prime & 1st Coat 5 5 11-Mar-16 17-Mar-16 0% WPI Paint
296 Classrooms 31 31 20-Jan-16 02-Mar-16
297 Layout/Framing/Backing 4 4 21-Jan-16 26-Jan-16 0% Harver
298 Install Door Frames 2 2 20-Jan-16 21-Jan-16 0% Harver
299 Frame Ceiling Soffits 4 4 22-Jan-16 27-Jan-16 0% Harver
300 MEP Rough In 5 5 28-Jan-16 03-Feb-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds
301 MEP/Framing Inspections 2 2 02-Feb-16 03-Feb-16 0% County
302 Quality Control Doors & Backing 1 1 02-Feb-16 02-Feb-16 0% Harver
303 Install Acoustical Insulation 2 2 03-Feb-16 04-Feb-16 0% Harver
304 Hang Gyp 4 4 05-Feb-16 10-Feb-16 0% Harver
305 Tape Gyp 6 6 11-Feb-16 18-Feb-16 0% Harver
306 Complete Above Ceiling MEP 5 5 18-Feb-16 24-Feb-16 0% Essential, O & S, FM, North Umpqua, Data, North Umpqua, Reynolds
307 Prime & 1st Coat 5 5 25-Feb-16 02-Mar-16 0% WPI Paint
308 Conference & Work Room 25 25 26-Jan-16 29-Feb-16
309 Layout/Framing/Backing 3 3 27-Jan-16 29-Jan-16 0% Harver
310 Install Door Frames 1 1 26-Jan-16 26-Jan-16 0% Harver
311 MEP Rough In 6 6 27-Jan-16 03-Feb-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds
312 MEP/Framing Inspections 1 1 04-Feb-16 04-Feb-16 0% County
313 Quality Controls Doors & Backing 1 1 04-Feb-16 04-Feb-16 0% Harver
314 Install Acoustical Insualtion 1 1 05-Feb-16 05-Feb-16 0% Harver
315 Hang Gyp 2 2 08-Feb-16 09-Feb-16 0% Harver
316 Tape Gyp 6 6 10-Feb-16 17-Feb-16 0% Harver
317 Complete Above Ceiling MEP 5 5 17-Feb-16 23-Feb-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds
318 Prime & 1st Coat 4 4 24-Feb-16 29-Feb-16 0% WPI Paint
319 Offices 34 34 29-Jan-16 16-Mar-16
320 Layout/Framing/Backing 4 4 01-Feb-16 04-Feb-16 0% Harver
321 Install Door Frames 2 2 29-Jan-16 01-Feb-16 0% Harver
322 Frame Ceiling Soffits 4 4 02-Feb-16 05-Feb-16 0% Harver
323 MEP Rough In 7 7 04-Feb-16 12-Feb-16 0% Data, Essential, North Umpqua, Reynolds, O & S, FM, North Umpqua
324 MEP/Framing Inspections 2 2 12-Feb-16 15-Feb-16 0% County
325 Quality Control Doors & Backing 1 1 16-Feb-16 16-Feb-16 0% Harver
326 Install Acoustical Insulation 2 2 17-Feb-16 18-Feb-16 0% Harver
327 Hang Gyp 4 4 19-Feb-16 24-Feb-16 0% Harver
328 Tape Gyp 6 6 25-Feb-16 03-Mar-16 0% Harver
329 Complete Above Ceiling MEP 5 5 03-Mar-16 09-Mar-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds
330 Prime & 1st Coat 5 5 10-Mar-16 16-Mar-16 0% WPI Paint
331 Elevator 20 20 29-Feb-16 25-Mar-16
332 Deliver & Install Elevator 20 20 29-Feb-16 25-Mar-16 0% TK
333 Interior Finishes 98 98 17-Mar-16 03-Aug-16
334 Level 1 73 73 17-Mar-16 28-Jun-16
335 Restrooms 22 22 17-Mar-16 15-Apr-16
336 Mens 170 20 20 17-Mar-16 13-Apr-16
337 Uncover & Polish Floor - Install New Floor Protection 2 2 17-Mar-16 18-Mar-16 0% Floor Polish
338 Install Tile 3 3 21-Mar-16 23-Mar-16 0% Tile
339 Grout & Seal Tile 2 2 23-Mar-16 24-Mar-16 0% Tile
340 Install Lighting & Devices 1 1 25-Mar-16 25-Mar-16 0% Reynolds
341 Install Grills 1 1 28-Mar-16 28-Mar-16 0% FM
342 Install Plumbing Fixtures 2 2 29-Mar-16 30-Mar-16 0% North Umpqua
343 Install Partitions 2 2 30-Mar-16 31-Mar-16 0% Accessories
344 Install Accessories 2 2 31-Mar-16 01-Apr-16 0% Accessories
345 Install Door & Hardware 1 1 04-Apr-16 04-Apr-16 0% WPI Doors
346 Final Paint 1 1 05-Apr-16 05-Apr-16 0% WPI Paint
347 Uncover Floor & Final Buff 1 1 06-Apr-16 06-Apr-16 0% Floor Polish
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Install Acoustical Installation
Hang Gyp
Install Access Doors
Tape Gyp
Complete Above Ceiling MEP
Prime & 1st Coat
02-Mar-16, Classrooms
Layout/Framing/Backing
Install Door Frames
Frame Ceiling Soffits
MEP Rough In
MEP/Framing Inspections
Quality Control Doors & Backing
Install Acoustical Insulation
Hang Gyp
Tape Gyp
Complete Above Ceiling MEP
Prime & 1st Coat
29-Feb-16, Conference & Work Room
Layout/Framing/Backing
Install Door Frames
MEP Rough In
MEP/Framing Inspections
Quality Controls Doors & Backing
Install Acoustical Insualtion
Hang Gyp
Tape Gyp
Complete Above Ceiling MEP
Prime & 1st Coat
16-Mar-16, Offices
Layout/Framing/Backing
Install Door Frames
Frame Ceiling Soffits
MEP Rough In
MEP/Framing Inspections
Quality Control Doors & Backing
Install Acoustical Insulation
Hang Gyp
Tape Gyp
Complete Above Ceiling MEP
Prime & 1st Coat
25-Mar-16, Elevator
Deliver & Install Elevator
03-Aug-16, Interior Finishes
28-Jun-16, Level 1
15-Apr-16, Restrooms
13-Apr-16, Mens 170
Uncover & Polish Floor - Install New Floor Protection
Install Tile
Grout & Seal Tile
Install Lighting & Devices
Install Grills
Install Plumbing Fixtures
Install Partitions
Install Accessories
Install Door & Hardware
Final Paint
Uncover Floor & Final Buff
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 6 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
348 Final Clean 1 1 07-Apr-16 07-Apr-16 0% Cleaner
349 Punch & Corrections 3 3 08-Apr-16 12-Apr-16 0% Opsis, UCC
350 Back Punch 1 1 13-Apr-16 13-Apr-16 0% ACCO, UCC
351 Womens 171 20 20 21-Mar-16 15-Apr-16
352 Uncover & Polish Floor - Install New Floor Protection 2 2 21-Mar-16 22-Mar-16 0% Floor Polish
353 Install Tile 3 3 23-Mar-16 25-Mar-16 0% Tile
354 Grout & Seal Tile 2 2 25-Mar-16 28-Mar-16 0% Tile
355 Install Lighting & Devices 1 1 29-Mar-16 29-Mar-16 0% North Umpqua
356 Install Grills 1 1 29-Mar-16 29-Mar-16 0% Accessories
357 Install Plumbing Fixtures 2 2 30-Mar-16 31-Mar-16 0% Accessories
358 Install Partitions 2 2 01-Apr-16 04-Apr-16 0% Reynolds
359 Install Accessories 2 2 05-Apr-16 06-Apr-16 0% FM
360 Install Door & Hardware 1 1 07-Apr-16 07-Apr-16 0% WPI Doors
361 Final Paint 1 1 08-Apr-16 08-Apr-16 0% Cleaner
362 Uncover Floor & Final Buff 1 1 11-Apr-16 11-Apr-16 0% Opsis, UCC
363 Final Clean 1 1 12-Apr-16 12-Apr-16 0% ACCO, UCC
364 Punch & Corrections 2 2 13-Apr-16 14-Apr-16 0% Opsis, ACCO
365 Back Punch 1 1 15-Apr-16 15-Apr-16 0% UCC, ACCO
366 Support Rooms 15 15 22-Mar-16 11-Apr-16
367 Storage 173 12 12 22-Mar-16 06-Apr-16
368 Uncover & Polish Floor - Install New Floor Protection 2 2 22-Mar-16 23-Mar-16 0% Floor Polish
369 Install Lighting & Devices 1 1 24-Mar-16 24-Mar-16 0% Reynolds
370 Install Grills 1 1 25-Mar-16 25-Mar-16 0% FM
371 Install Door & Hardware 1 1 28-Mar-16 28-Mar-16 0% WPI Doors
372 Install Rubber Base 1 1 29-Mar-16 29-Mar-16 0% Flooring
373 Final Paint 1 1 30-Mar-16 30-Mar-16 0% WPI Paint
374 Uncover Floor & Final Buff 1 1 31-Mar-16 31-Mar-16 0% Floor Polish
375 Final Clean 1 1 01-Apr-16 01-Apr-16 0% Cleaner
376 Punch & Corrections 2 2 04-Apr-16 05-Apr-16 0% Opsis, UCC
377 Back Punch 1 1 06-Apr-16 06-Apr-16 0% ACCO, UCC
378 Vending Alcove 103A 9 9 23-Mar-16 04-Apr-16
379 Uncover & Polish Floor - Install New Floor Protection 2 2 23-Mar-16 24-Mar-16 0% Floor Polish
380 Install Lighting & Devices 1 1 25-Mar-16 25-Mar-16 0% Reynolds
381 Install Grills 1 1 28-Mar-16 28-Mar-16 0% FM
382 Install Wood Base 1 1 29-Mar-16 29-Mar-16 0% Wood Finishes
383 Final Paint 1 1 30-Mar-16 30-Mar-16 0% WPI Paint
384 Final Clean 1 1 31-Mar-16 31-Mar-16 0% Cleaner
385 Punch 1 1 01-Apr-16 01-Apr-16 0% Opsis, UCC
386 Back Punch 1 1 04-Apr-16 04-Apr-16 0% UCC, ACCO
387 Janitor 172 13 13 24-Mar-16 11-Apr-16
388 Uncover Floor & Polish - Install New Floor Protection 3 3 24-Mar-16 28-Mar-16 0% Floor Polish
389 Install Lighting & Devices 1 1 29-Mar-16 29-Mar-16 0% Reynolds
390 Install Grills 1 1 30-Mar-16 30-Mar-16 0% FM
391 Install Mop Sink 1 1 30-Mar-16 30-Mar-16 0% North Umpqua
392 Install FRP 1 1 31-Mar-16 31-Mar-16 0% Accessories
393 Remove Floor Protection & Final Buff 1 1 01-Apr-16 01-Apr-16 0% Floor Polish
394 Install Rubber Base 1 1 04-Apr-16 04-Apr-16 0% Flooring
395 Install Door & Hardware 1 1 05-Apr-16 05-Apr-16 0% WPI Doors
396 Final Paint 1 1 06-Apr-16 06-Apr-16 0% WPI Paint
397 Final Clean 1 1 07-Apr-16 07-Apr-16 0% Cleaner
398 Punch 1 1 08-Apr-16 08-Apr-16 0% Opsis, UCC
399 Back Punch 1 1 11-Apr-16 11-Apr-16 0% ACCO, UCC
400 Classrooms 30 30 29-Mar-16 09-May-16
401 Classroom 110 27 27 29-Mar-16 04-May-16
402 Uncover & Polish Floor - Install New Floor Protection 3 3 29-Mar-16 31-Mar-16 0% Floor Polish
403 Install Ceiling Grid & Tile For Devices 2 2 01-Apr-16 04-Apr-16 0% Harver
404 Complete Above Ceiling MEP 3 3 04-Apr-16 06-Apr-16 0% O & S, FM, North Umpqua, Data, Essential, Delta, North Umpqua, Reynolds
405 Inspections To Cover @ Ceiling 2 2 07-Apr-16 08-Apr-16 0% County
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Final Clean
Punch & Corrections
Back Punch
15-Apr-16, Womens 171
Uncover & Polish Floor - Install New Floor Protection
Install Tile
Grout & Seal Tile
Install Lighting & Devices
Install Grills
Install Plumbing Fixtures
Install Partitions
Install Accessories
Install Door & Hardware
Final Paint
Uncover Floor & Final Buff
Final Clean
Punch & Corrections
Back Punch
11-Apr-16, Support Rooms
06-Apr-16, Storage 173
Uncover & Polish Floor - Install New Floor Protection
Install Lighting & Devices
Install Grills
Install Door & Hardware
Install Rubber Base
Final Paint
Uncover Floor & Final Buff
Final Clean
Punch & Corrections
Back Punch
04-Apr-16, Vending Alcove 103A
Uncover & Polish Floor - Install New Floor Protection
Install Lighting & Devices
Install Grills
Install Wood Base
Final Paint
Final Clean
Punch
Back Punch
11-Apr-16, Janitor 172
Uncover Floor & Polish - Install New Floor Protection
Install Lighting & Devices
Install Grills
Install Mop Sink
Install FRP
Remove Floor Protection & Final Buff
Install Rubber Base
Install Door & Hardware
Final Paint
Final Clean
Punch
Back Punch
09-May-16, Classrooms
04-May-16, Classroom 110
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 7 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
406 Install Ceiling Tile 2 2 08-Apr-16 11-Apr-16 0% Harver
407 Install Roller Shades 1 1 12-Apr-16 12-Apr-16 0% Accessories
408 Install Marker Boards 2 2 12-Apr-16 13-Apr-16 0% Accessories
409 Complete Electrical/AV/Data/Controls 3 3 14-Apr-16 18-Apr-16 0% Delta, Essential, Data, North Umpqua
410 Install Relites 1 1 19-Apr-16 19-Apr-16 0% Culver
411 Remove Floor Protection & Final Buff 1 1 20-Apr-16 20-Apr-16 0% Floor Polish
412 Install Rubber Base 1 1 21-Apr-16 21-Apr-16 0% Flooring
413 Install Door & Hardware 1 1 22-Apr-16 22-Apr-16 0% WPI Doors
414 Final Paint 1 1 25-Apr-16 25-Apr-16 0% WPI Paint
415 Final Clean 1 1 26-Apr-16 26-Apr-16 0% Cleaner
416 Punch & Corrections 2 2 27-Apr-16 28-Apr-16 0% Opsis, ACCO
417 Back Punch 2 2 29-Apr-16 02-May-16 0% ACCO, UCC
418 Move In Owner Furniture 2 2 03-May-16 04-May-16 0% UCC
419 Medical Legal Resolutions 120 28 28 31-Mar-16 09-May-16
420 Uncover & Polish Floor - Install New Floor Protection 3 3 31-Mar-16 04-Apr-16 0% Floor Polish
421 Install Ceiling Grid & Tile For Devices 2 2 05-Apr-16 06-Apr-16 0% Harver
422 Complete Above Ceiling MEP 3 3 07-Apr-16 11-Apr-16 0% Delta, Essential, North Umpqua, Reynolds, O & S, FM, North Umpqua, Data
423 Inspections To Cover @ Ceiling 2 2 12-Apr-16 13-Apr-16 0% County
424 Install Ceiling Tile 2 2 14-Apr-16 15-Apr-16 0% Harver
425 Install Roller Shades 1 1 15-Apr-16 15-Apr-16 0% Accessories
426 Complete Electrical/AV/Data/Controls 3 3 18-Apr-16 20-Apr-16 0% Delta, Essential, Reynolds
427 Remove Floor Protection & Final Buff 1 1 21-Apr-16 21-Apr-16 0% Floor Polish
428 Install Aluminum Frame/Relite/Door/Hardware @ 120-2 2 2 22-Apr-16 25-Apr-16 0% Culver
429 Install Rubber Base 1 1 26-Apr-16 26-Apr-16 0% Flooring
430 Final Paint 2 2 27-Apr-16 28-Apr-16 0% WPI Paint
431 Final Clean 1 1 29-Apr-16 29-Apr-16 0% Cleaner
432 Punch & Corrections 3 3 02-May-16 04-May-16 0% ACCO, Opsis
433 Back Punch 1 1 05-May-16 05-May-16 0% ACCO, UCC
434 Move In Owner Furniture 2 2 06-May-16 09-May-16 0% UCC
435 Conference, Meeting & Work Rooms 25 25 04-Apr-16 06-May-16
436 Meeting 121, 122 & 123 25 25 04-Apr-16 06-May-16
437 Install Ceiling Grid & Tiles For Devices 3 3 04-Apr-16 06-Apr-16 0% Harver
438 Complete Above Ceiling MEP 3 3 06-Apr-16 08-Apr-16 0% Data, Delta, Essential, O & S, FM, North Umpqua, Reynolds
439 Inspections To Cover @ Ceiling 1 1 11-Apr-16 11-Apr-16 0% County
440 Install Ceiling Tile 2 2 11-Apr-16 12-Apr-16 0% Harver
441 Install Relites @ 121-1, 122 & 123-1 1 1 13-Apr-16 13-Apr-16 0% Culver
442 Install Carpet & Rubber Base 2 2 14-Apr-16 15-Apr-16 0% Flooring
443 Install Doors & Hardware 3 3 15-Apr-16 19-Apr-16 0% WPI Doors
444 Install Roller Shades 2 2 19-Apr-16 20-Apr-16 0% Accessories
445 Complete Electrical/AV/Data/Controls 3 3 21-Apr-16 25-Apr-16 0% Delta, Essential, Data, Reynolds
446 Final Paint 2 2 26-Apr-16 27-Apr-16 0% WPI Paint
447 Final Clean 1 1 28-Apr-16 28-Apr-16 0% Cleaner
448 Punch & Corrections 3 3 29-Apr-16 03-May-16 0% Opsis, ACCO
449 Back Punch 1 1 04-May-16 04-May-16 0% UCC, ACCO
450 Move In Owner Furniture 2 2 05-May-16 06-May-16 0% UCC
451 Conference 150 21 21 06-Apr-16 04-May-16
452 Install Ceiling Grid & Tiles For Devices 1 1 06-Apr-16 06-Apr-16 0% Harver
453 Complete Above Ceiling MEP 3 3 07-Apr-16 11-Apr-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds, North Umpqua
454 Inspections To Cover @ Ceiling 1 1 12-Apr-16 12-Apr-16 0% County
455 Install Ceiling Tile 2 2 13-Apr-16 14-Apr-16 0% Harver
456 Install Relites, Door & Hardware 2 2 15-Apr-16 18-Apr-16 0% WPI Doors, Culver
457 Complete Electrical/AV/Data/Controls 3 3 19-Apr-16 21-Apr-16 0% Data, Essential, Delta, Reynolds
458 Install Carpet & Rubber Base 2 2 22-Apr-16 25-Apr-16 0% Flooring
459 Final Paint 1 1 26-Apr-16 26-Apr-16 0% WPI Paint
460 Final Clean 1 1 27-Apr-16 27-Apr-16 0% Cleaner
461 Punch & Corrections 2 2 28-Apr-16 29-Apr-16 0% Opsis, ACCO
462 Back Punch 1 1 02-May-16 02-May-16 0% UCC, ACCO
463 Move In Owner Furniture 2 2 03-May-16 04-May-16 0% UCC
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Install Ceiling Tile
Install Roller Shades
Install Marker Boards
Complete Electrical/AV/Data/Controls
Install Relites
Remove Floor Protection & Final Buff
Install Rubber Base
Install Door & Hardware
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
09-May-16, Medical Legal Resolutions 120
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Roller Shades
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Aluminum Frame/Relite/Door/Hardware @ 120-2
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
06-May-16, Conference, Meeting & Work Rooms
06-May-16, Meeting 121, 122 & 123
Install Ceiling Grid & Tiles For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Relites @ 121-1, 122 & 123-1
Install Carpet & Rubber Base
Install Doors & Hardware
Install Roller Shades
Complete Electrical/AV/Data/Controls
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
04-May-16, Conference 150
Install Ceiling Grid & Tiles For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Relites, Door & Hardware
Complete Electrical/AV/Data/Controls
Install Carpet & Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 8 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
464 Work Room 151 19 19 06-Apr-16 02-May-16
465 Uncover & Polish Floor - Install New Floor Protection 2 2 06-Apr-16 07-Apr-16 0% Floor Polish
466 Install Ceiling Grid & Tiles For Devices 1 1 08-Apr-16 08-Apr-16 0% Harver
467 Complete Above Ceiling MEP 2 2 11-Apr-16 12-Apr-16 0% O & S, FM, North Umpqua, Data, Essential, North Umpqua, Reynolds
468 Inspections To Cover @ Ceiling 1 1 12-Apr-16 12-Apr-16 0% County
469 Install Ceiling Tile 1 1 13-Apr-16 13-Apr-16 0% Harver
470 Install Cabinets 2 2 14-Apr-16 15-Apr-16 0% S & B
471 Install Sink & Fixtures 1 1 15-Apr-16 15-Apr-16 0% North Umpqua
472 Install Relite 2 2 15-Apr-16 18-Apr-16 0% Culver
473 Complete Electrical/AV/Data/Controls 1 1 19-Apr-16 19-Apr-16 0% Delta, Data, Essential, Reynolds
474 Remove Floor Protection & Final Buff 1 1 20-Apr-16 20-Apr-16 0% Floor Polish
475 Install Door & Hardware 1 1 21-Apr-16 21-Apr-16 0% WPI Doors
476 Install Rubber Base 1 1 22-Apr-16 22-Apr-16 0% Flooring
477 Final Paint 1 1 25-Apr-16 25-Apr-16 0% WPI Paint
478 Final Clean 1 1 26-Apr-16 26-Apr-16 0% Cleaner
479 Punch & Corrections 2 2 27-Apr-16 28-Apr-16 0% Opsis, ACCO
480 Back Punch 1 1 29-Apr-16 29-Apr-16 0% UCC, ACCO
481 Move In Owner Furniture 1 1 02-May-16 02-May-16 0% UCC
482 Labs 54 54 07-Apr-16 22-Jun-16
483 Nursing 36 36 07-Apr-16 26-May-16
484 Skills Lab 130 36 36 07-Apr-16 26-May-16
485 Uncover & Polish Floor - Install New Floor Protection 3 3 07-Apr-16 11-Apr-16 0% Floor Polish
486 Install Patient Lift Supports 5 5 12-Apr-16 18-Apr-16 0% Accessories
487 Install Ceiling Grid & Tile For Devices 3 3 15-Apr-16 19-Apr-16 0% Harver
488 Complete Above Ceiling MEP 5 5 18-Apr-16 22-Apr-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
489 Inspections To Cover @ Ceiling 2 2 22-Apr-16 25-Apr-16 0% County, Special Inspection
490 Install Ceiling Tile 2 2 26-Apr-16 27-Apr-16 0% Harver
491 Install Cabinets 8 8 21-Apr-16 02-May-16 0% S & B
492 Install Sinks & Fixtures 5 5 26-Apr-16 02-May-16 0% North Umpqua
493 Complete Med Gases Including Inspections 8 8 26-Apr-16 05-May-16 0% North Umpqua, Special Inspection
494 Complete Electrical/AV/Data/Controls 5 5 26-Apr-16 02-May-16 0% Delta, Data, Essential, Reynolds
495 Install Roller Shades 3 3 27-Apr-16 29-Apr-16 0% Accessories
496 Remove Floor Protection & Final Buff 3 3 02-May-16 04-May-16 0% Floor Polish
497 Install Rubber Base 2 2 05-May-16 06-May-16 0% Flooring
498 Install Privacy Curtains 3 3 05-May-16 09-May-16 0% Accessories
499 Final Paint 2 2 10-May-16 11-May-16 0% WPI Paint
500 Final Clean 2 2 12-May-16 13-May-16 0% Cleaner
501 Punch & Corrections 3 3 16-May-16 18-May-16 0% Opsis, ACCO
502 Back Punch 1 1 19-May-16 19-May-16 0% UCC, ACCO
503 Move In Equipment & Furniture 5 5 20-May-16 26-May-16 0% UCC, ACCO
504 Nursing Entry 130A 18 18 11-Apr-16 04-May-16
505 Uncover & Polish Floor - Install New Floor Protection 2 2 11-Apr-16 12-Apr-16 0% Floor Polish
506 Install Ceiling Grid & Tile For Devices 1 1 13-Apr-16 13-Apr-16 0% Harver
507 Complete Above Ceiling MEP 2 2 14-Apr-16 15-Apr-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
508 Inspections To Cover @ Ceiling 1 1 15-Apr-16 15-Apr-16 0% County
509 Install Ceiling Tile 1 1 18-Apr-16 18-Apr-16 0% Harver
510 Complete Electrical/AV/Data/Controls 2 2 18-Apr-16 19-Apr-16 0% Delta, Data, Essential, Reynolds
511 Remove Floor Protection & Final Buff 1 1 20-Apr-16 20-Apr-16 0% Floor Polish
512 Install Rubber Base 1 1 21-Apr-16 21-Apr-16 0% Flooring
513 Install Doors & Hardware 2 2 22-Apr-16 25-Apr-16 0% WPI Doors
514 Final Paint 1 1 26-Apr-16 26-Apr-16 0% WPI Paint
515 Final Clean 1 1 27-Apr-16 27-Apr-16 0% Cleaner
516 Punch & Corrections 2 2 28-Apr-16 29-Apr-16 0% Opsis, ACCO
517 Back Punch 1 1 02-May-16 02-May-16 0% UCC, ACCO
518 Move In Owner Furniture 2 2 03-May-16 04-May-16 0% UCC, ACCO
519 Tech Station 130B 18 18 12-Apr-16 05-May-16
520 Uncover & Polish Floor - Install New Floor Protection 2 2 12-Apr-16 13-Apr-16 0% Floor Polish
521 Install Ceiling Grid & Tile For Devices 1 1 14-Apr-16 14-Apr-16 0% Harver
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
02-May-16, Work Room 151
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tiles For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Sink & Fixtures
Install Relite
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Door & Hardware
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
22-Jun-16, Labs
26-May-16, Nursing
26-May-16, Skills Lab 130
Uncover & Polish Floor - Install New Floor Protection
Install Patient Lift Supports
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Sinks & Fixtures
Complete Med Gases Including Inspections
Complete Electrical/AV/Data/Controls
Install Roller Shades
Remove Floor Protection & Final Buff
Install Rubber Base
Install Privacy Curtains
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Equipment & Furniture
04-May-16, Nursing Entry 130A
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Rubber Base
Install Doors & Hardware
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
05-May-16, Tech Station 130B
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 9 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
522 Complete Above Ceiling MEP 3 3 15-Apr-16 19-Apr-16 0% Data, Delta, Essential, Reynolds, O & S, FM, North Umpqua
523 Inspections To Cover @ Ceiling 1 1 19-Apr-16 19-Apr-16 0% County
524 Install Ceiling Tile 1 1 20-Apr-16 20-Apr-16 0% Harver
525 Install Cabinets/Tech Station 3 3 20-Apr-16 22-Apr-16 0% S & B
526 Complete Electrical/AV/Data/Controls 1 1 25-Apr-16 25-Apr-16 0% Delta, Data, Essential, Reynolds
527 Remove Floor Protection & Final Buff 1 1 26-Apr-16 26-Apr-16 0% Floor Polish
528 Install Rubber Base 1 1 26-Apr-16 26-Apr-16 0% Flooring
529 Final Paint 1 1 27-Apr-16 27-Apr-16 0% WPI Paint
530 Final Clean 1 1 28-Apr-16 28-Apr-16 0% Cleaner
531 Punch & Corrections 3 3 29-Apr-16 03-May-16 0% UCC, ACCO
532 Back Punch 1 1 04-May-16 04-May-16 0% UCC, ACCO
533 Move In Owner Furniture 1 1 05-May-16 05-May-16 0% UCC
534 Storage 131 18 18 13-Apr-16 06-May-16
535 Uncover & Polish Floor - Install New Floor Protection 2 2 13-Apr-16 14-Apr-16 0% Floor Polish
536 Install Ceiling Grid & Tile For Devices 1 1 15-Apr-16 15-Apr-16 0% Harver
537 Complete Above Ceiling MEP 3 3 18-Apr-16 20-Apr-16 0% O & S, North Umpqua, Data, Delta, Essential, FM, Reynolds
538 Inspections To Cover @ Ceiling 1 1 21-Apr-16 21-Apr-16 0% County
539 Install Ceiling Tile 1 1 22-Apr-16 22-Apr-16 0% Harver
540 Complete Electrical/AV/Data/Controls 1 1 25-Apr-16 25-Apr-16 0% Delta, Data, Essential, Reynolds
541 Remove Floor Protection & Final Buff 1 1 26-Apr-16 26-Apr-16 0% Floor Polish
542 Install Rubber Base 1 1 27-Apr-16 27-Apr-16 0% Flooring
543 Install Door & Hardware 1 1 28-Apr-16 28-Apr-16 0% WPI Doors
544 Final Paint 1 1 29-Apr-16 29-Apr-16 0% WPI Paint
545 Final Clean 1 1 02-May-16 02-May-16 0% Cleaner
546 Punch & Corrections 2 2 03-May-16 04-May-16 0% Opsis, ACCO
547 Back Punch 1 1 05-May-16 05-May-16 0% UCC, ACCO
548 Move In Owner Furniture 1 1 06-May-16 06-May-16 0% UCC
549 Simulation Labs & Control 133, 134 & 135 31 31 14-Apr-16 26-May-16
550 Uncover Floor, Polish & Install New Floor Protection 3 3 14-Apr-16 18-Apr-16 0% Floor Polish
551 Install Ceiling Grid & Tile For Devices 2 2 19-Apr-16 20-Apr-16 0% Harver
552 Complete Above Ceiling MEP 5 5 19-Apr-16 25-Apr-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
553 Inspections To Cover @ Ceiling 1 1 25-Apr-16 25-Apr-16 0% County
554 Install Ceiling Tile 2 2 25-Apr-16 26-Apr-16 0% Harver
555 Install Cabinets 5 5 22-Apr-16 28-Apr-16 0% S & B
556 Install Sinks & Fixtures 2 2 28-Apr-16 29-Apr-16 0% North Umpqua
557 Complete Electrical/AV/Data/Controls 4 4 02-May-16 05-May-16 0% Essential, Delta, Data, Reynolds
558 Install One Way Glass @ 134 2 2 05-May-16 06-May-16 0% Culver
559 Install Roller Shades 1 1 09-May-16 09-May-16 0% Accessories
560 Remove Floor Protection & Final Buff 1 1 10-May-16 10-May-16 0% Floor Polish
561 Install Break Away Doors @ 133 & 135 4 4 10-May-16 13-May-16 0% WPI Doors
562 Install Rubber Base 2 2 16-May-16 17-May-16 0% Flooring
563 Final Paint 2 2 18-May-16 19-May-16 0% WPI Paint
564 Final Clean 1 1 20-May-16 20-May-16 0% Cleaner
565 Punch & Corrections 2 2 20-May-16 23-May-16 0% Opsis, ACCO
566 Back Punch 1 1 24-May-16 24-May-16 0% UCC, ACCO
567 Move In Equipment & Owner Furniture 2 2 25-May-16 26-May-16 0% UCC, ACCO
568 Debrief 132 & 136 18 18 18-Apr-16 11-May-16
569 Uncover Floor, Polish & Install New Floor Protection 3 3 18-Apr-16 20-Apr-16 0% Floor Polish
570 Install Ceiling Grid & Tile For Devices 2 2 20-Apr-16 21-Apr-16 0% Harver
571 Complete Above Ceiling MEP 3 3 21-Apr-16 25-Apr-16 0% North Umpqua, Data, Delta, Essential, Reynolds, O & S, FM
572 Inspections To Cover @ Ceiling 1 1 25-Apr-16 25-Apr-16 0% County
573 Install Ceiling Tile 2 2 26-Apr-16 27-Apr-16 0% Harver
574 Complete Electrical/AV/Data/Controls 2 2 27-Apr-16 28-Apr-16 0% Delta, Data, Essential, Reynolds
575 Install Roller Shades 1 1 28-Apr-16 28-Apr-16 0% Accessories
576 Remove Floor Protection & Final Buff 1 1 28-Apr-16 28-Apr-16 0% Floor Polish
577 Install Rubber Base 1 1 29-Apr-16 29-Apr-16 0% Flooring
578 Install Doors & Hardware 2 2 29-Apr-16 02-May-16 0% WPI Doors
579 Final Paint 2 2 02-May-16 03-May-16 0% WPI Paint
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets/Tech Station
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
06-May-16, Storage 131
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Rubber Base
Install Door & Hardware
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
26-May-16, Simulation Labs & Control 133, 134 & 135
Uncover Floor, Polish & Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Sinks & Fixtures
Complete Electrical/AV/Data/Controls
Install One Way Glass @ 134
Install Roller Shades
Remove Floor Protection & Final Buff
Install Break Away Doors @ 133 & 135
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Equipment & Owner Furniture
11-May-16, Debrief 132 & 136
Uncover Floor, Polish & Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Complete Electrical/AV/Data/Controls
Install Roller Shades
Remove Floor Protection & Final Buff
Install Rubber Base
Install Doors & Hardware
Final Paint
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 10 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
580 Final Clean 1 1 04-May-16 04-May-16 0% Cleaner
581 Punch & Corrections 3 3 03-May-16 05-May-16 0% Opsis, ACCO
582 Back Punch 1 1 06-May-16 06-May-16 0% UCC, ACCO
583 Move In Owner Furniture 3 3 09-May-16 11-May-16 0% UCC
584 Clean Prep 137 20 20 20-Apr-16 17-May-16
585 Uncover Floor, Polish & Install New Floor Protection 2 2 20-Apr-16 21-Apr-16 0% Floor Polish
586 Install Ceiling Grid & Tile For Devices 1 1 22-Apr-16 22-Apr-16 0% Harver
587 Complete Above Ceiling MEP 3 3 25-Apr-16 27-Apr-16 0% O & S, FM, North Umpqua, Data, Essential, Delta, Reynolds
588 Inspections To Cover @ Ceiling 1 1 27-Apr-16 27-Apr-16 0% County
589 Install Ceiling Tile 1 1 28-Apr-16 28-Apr-16 0% Harver
590 Install Cabinets 3 3 29-Apr-16 03-May-16 0% S & B
591 Install Sink 1 1 03-May-16 03-May-16 0% North Umpqua
592 Complete Electrical/AV/Data/Controls 2 2 04-May-16 05-May-16 0% Delta, Data, Essential, Reynolds
593 Install Roller Shades 1 1 06-May-16 06-May-16 0% Accessories
594 Remove Floor Protection & Final Buff 1 1 09-May-16 09-May-16 0% Floor Polish
595 Install Rubber Base 1 1 10-May-16 10-May-16 0% Flooring
596 Install Door & Hardware 1 1 10-May-16 10-May-16 0% WPI Doors
597 Final Paint 1 1 11-May-16 11-May-16 0% WPI Paint
598 Final Clean 1 1 12-May-16 12-May-16 0% Cleaner
599 Punch & Corrections 2 2 12-May-16 13-May-16 0% Opsis, ACCO
600 Back Punch 1 1 16-May-16 16-May-16 0% UCC, ACCO
601 Move In Owner Furniture 1 1 17-May-16 17-May-16 0% UCC
602 Clean Supply 138 18 18 21-Apr-16 16-May-16
603 Uncover Floor, Polish & Install New Floor Protection 2 2 21-Apr-16 22-Apr-16 0% Floor Polish
604 Install Ceiling Grid & Tile For Devices 2 2 25-Apr-16 26-Apr-16 0% Harver
605 Complete Above Ceiling MEP 2 2 27-Apr-16 28-Apr-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
606 Inspections To Cover @ Ceiling 1 1 29-Apr-16 29-Apr-16 0% County
607 Install Ceiling Tile 1 1 02-May-16 02-May-16 0% Harver
608 Complete Electrical/AV/Data/Controls 2 2 03-May-16 04-May-16 0% Delta, Data, Essential, Reynolds
609 Remove Floor Protection & Final Buff 1 1 05-May-16 05-May-16 0% Floor Polish
610 Install Rubber Base 1 1 05-May-16 05-May-16 0% Flooring
611 Install Door & Hardware 1 1 05-May-16 05-May-16 0% WPI Doors
612 Final Paint 1 1 06-May-16 06-May-16 0% WPI Paint
613 Final Clean 1 1 09-May-16 09-May-16 0% Cleaner
614 Punch @ Corrections 2 2 10-May-16 11-May-16 0% Opsis, ACCO
615 Back Punch 1 1 12-May-16 12-May-16 0% UCC, ACCO
616 Move In Owner Furniture 2 2 13-May-16 16-May-16 0% UCC
617 Soiled Holding/Laundry 139 18 18 22-Apr-16 17-May-16
618 Uncover Floor, Polish & Install New Floor Protection 2 2 22-Apr-16 25-Apr-16 0% Floor Polish
619 Install Ceiling Grid & Tile For Devices 1 1 26-Apr-16 26-Apr-16 0% Harver
620 Complete Above Ceiling MEP 2 2 26-Apr-16 27-Apr-16 0% Delta, Essential, O & S, FM, North Umpqua, Data, Reynolds
621 Inspections To Cover @ Ceiling 1 1 27-Apr-16 27-Apr-16 0% County
622 Install Ceiling Tile 1 1 28-Apr-16 28-Apr-16 0% Harver
623 Install Cabinets 3 3 29-Apr-16 03-May-16 0% S & B
624 Install Sink 1 1 04-May-16 04-May-16 0% North Umpqua
625 Complete Electrical/AV/Data/Controls 2 2 04-May-16 05-May-16 0% Reynolds, Data, Delta, Essential
626 Remove Floor Protection & Final Buff 1 1 06-May-16 06-May-16 0% Floor Polish
627 Install Rubber Base 1 1 06-May-16 06-May-16 0% Flooring
628 Install Doors & Hardware 2 2 06-May-16 09-May-16 0% WPI Doors
629 Final Paint 1 1 10-May-16 10-May-16 0% WPI Paint
630 Final Clean 1 1 11-May-16 11-May-16 0% Cleaner
631 Punch & Corrections 2 2 11-May-16 12-May-16 0% Opsis, ACCO
632 Back Punch 1 1 13-May-16 13-May-16 0% UCC, ACCO
633 Move Owner Furniture In 2 2 16-May-16 17-May-16 0% UCC
634 Dental 42 42 25-Apr-16 22-Jun-16
635 Dental Department 140 42 42 25-Apr-16 22-Jun-16
636 Uncover & Polish Floor - Install New Floor Protection 2 2 25-Apr-16 26-Apr-16 0% Floor Polish
637 Install Ceiling Grid & Tile For Devices 2 2 27-Apr-16 28-Apr-16 0% Harver
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
17-May-16, Clean Prep 137
Uncover Floor, Polish & Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Sink
Complete Electrical/AV/Data/Controls
Install Roller Shades
Remove Floor Protection & Final Buff
Install Rubber Base
Install Door & Hardware
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
16-May-16, Clean Supply 138
Uncover Floor, Polish & Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Rubber Base
Install Door & Hardware
Final Paint
Final Clean
Punch @ Corrections
Back Punch
Move In Owner Furniture
17-May-16, Soiled Holding/Laundry 139
Uncover Floor, Polish & Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Sink
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Rubber Base
Install Doors & Hardware
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move Owner Furniture In
22-Jun-16, Dental
22-Jun-16, Dental Department 140
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 11 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
638 Complete Above Ceiling MEP 5 5 27-Apr-16 03-May-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
639 Inspections To Cover @ Ceiling 2 2 03-May-16 04-May-16 0% County
640 Install Ceiling Tile 2 2 05-May-16 06-May-16 0% Harver
641 Complete Electrical/AV/Data/Controls 5 5 09-May-16 13-May-16 0% Delta, Data, Essential, Reynolds
642 Complete Med Gas Including Inspections 8 8 09-May-16 18-May-16 0% Special Inspection, North Umpqua
643 Install Roller Shades 1 1 19-May-16 19-May-16 0% Accessories
644 Remove Floor Protection & Final Buff 1 1 20-May-16 20-May-16 0% Floor Polish
645 Install Rubber Base 1 1 23-May-16 23-May-16 0% Flooring
646 Final Paint 2 2 24-May-16 25-May-16 0% WPI Paint
647 Final Clean 2 2 26-May-16 27-May-16 0% Cleaner
648 Punch & Corrections 3 3 27-May-16 01-Jun-16 0% Opsis, ACCO
649 Back Punch 2 2 02-Jun-16 03-Jun-16 0% UCC, ACCO
650 Install Dental Equipment & Furniture 15 15 02-Jun-16 22-Jun-16 0% ACCO, UCC
651 Entry/Lockers 140A 21 21 27-Apr-16 25-May-16
652 Uncover & Polish Floor - Install New Floor Protection 2 2 27-Apr-16 28-Apr-16 0% Floor Polish
653 Install Ceiling Grid & Tile For Devices 1 1 29-Apr-16 29-Apr-16 0% Harver
654 Complete Above Ceiling MEP 3 3 02-May-16 04-May-16 0% Reynolds, North Umpqua, Data, Delta, Essential, O & S, FM
655 Inspections To Cover @ Ceiling 1 1 05-May-16 05-May-16 0% County
656 Install Ceiling Tile 1 1 06-May-16 06-May-16 0% Harver
657 Install Glazing 2 2 06-May-16 09-May-16 0% Culver
658 Install Lockers 3 3 09-May-16 11-May-16 0% S & B
659 Complete Electrical/AV/Data/Controls 2 2 12-May-16 13-May-16 0% Delta, Data, Essential, Reynolds
660 Uncover Floor & Final Buff 1 1 16-May-16 16-May-16 0% Floor Polish
661 Install Rubber Base 1 1 16-May-16 16-May-16 0% Flooring
662 Install Doors & Hardware 2 2 17-May-16 18-May-16 0% WPI Doors
663 Final Paint 1 1 19-May-16 19-May-16 0% WPI Paint
664 Final Clean 1 1 20-May-16 20-May-16 0% Cleaner
665 Punch & Corrections 2 2 20-May-16 23-May-16 0% Opsis, ACCO
666 Back Punch 1 1 24-May-16 24-May-16 0% UCC, ACCO
667 Move In Owner Furniture 1 1 25-May-16 25-May-16 0% UCC
668 Shared Office 141 23 23 28-Apr-16 31-May-16
669 Uncover & Polish Floor - Install New Floor Protection 2 2 28-Apr-16 29-Apr-16 0% Floor Polish
670 Install Ceiling Grid & Tile For Devices 1 1 02-May-16 02-May-16 0% Harver
671 Complete Above Ceiling MEP 3 3 02-May-16 04-May-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
672 Inspections To Cover @ Ceiling 1 1 04-May-16 04-May-16 0% County
673 Install Ceiling Tile 1 1 05-May-16 05-May-16 0% Harver
674 Install Desktops 4 4 05-May-16 10-May-16 0% S & B
675 Complete Electrical/AV/Data/Controls 1 1 11-May-16 11-May-16 0% Reynolds, Delta, Data, Essential
676 Install Relite 2 2 12-May-16 13-May-16 0% Culver
677 Install Roller Shades 1 1 16-May-16 16-May-16 0% Accessories
678 Uncover Floor & Final Buff 1 1 17-May-16 17-May-16 0% Floor Polish
679 Install Rubber Base 1 1 18-May-16 18-May-16 0% Flooring
680 Install Door & Hardware 2 2 19-May-16 20-May-16 0% WPI Doors
681 Final Paint 1 1 23-May-16 23-May-16 0% WPI Paint
682 Punch & Corrections 2 2 24-May-16 25-May-16 0% Opsis, ACCO
683 Back Punch 1 1 26-May-16 26-May-16 0% UCC, ACCO
684 Move In Owner Furniture 2 2 27-May-16 31-May-16 0% UCC
685 Sterilization 143 30 30 29-Apr-16 10-Jun-16
686 Uncover & Polish Floor - Install New Floor Protection 2 2 29-Apr-16 02-May-16 0% Floor Polish
687 Install Ceiling Grid & Tile For Devices 2 2 03-May-16 04-May-16 0% Harver
688 Complete Above Ceiling MEP 5 5 03-May-16 09-May-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
689 Inspections To Cover @ Ceiling 2 2 09-May-16 10-May-16 0% County
690 Install Ceiling Tile 2 2 11-May-16 12-May-16 0% Harver
691 Install Cabinets 5 5 12-May-16 18-May-16 0% S & B
692 Complete Med Gases Including Inspections 5 5 16-May-16 20-May-16 0% North Umpqua, Special Inspection
693 Install Roller Shades 1 1 23-May-16 23-May-16 0% Accessories
694 Uncover Floor & Final Buff 1 1 24-May-16 24-May-16 0% Floor Polish
695 Install Rubber Base 1 1 25-May-16 25-May-16 0% Flooring
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Complete Electrical/AV/Data/Controls
Complete Med Gas Including Inspections
Install Roller Shades
Remove Floor Protection & Final Buff
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Install Dental Equipment & Furniture
25-May-16, Entry/Lockers 140A
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Glazing
Install Lockers
Complete Electrical/AV/Data/Controls
Uncover Floor & Final Buff
Install Rubber Base
Install Doors & Hardware
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
31-May-16, Shared Office 141
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Desktops
Complete Electrical/AV/Data/Controls
Install Relite
Install Roller Shades
Uncover Floor & Final Buff
Install Rubber Base
Install Door & Hardware
Final Paint
Punch & Corrections
Back Punch
Move In Owner Furniture
10-Jun-16, Sterilization 143
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Complete Med Gases Including Inspections
Install Roller Shades
Uncover Floor & Final Buff
Install Rubber Base
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 12 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
696 Complete Electrical/AV/Data/Controls 3 3 25-May-16 27-May-16 0% Delta, Data, Essential, Reynolds
697 Final Paint 2 2 27-May-16 31-May-16 0% WPI Paint
698 Final Clean 2 2 31-May-16 01-Jun-16 0% Cleaner
699 Punch & Corrections 3 3 31-May-16 02-Jun-16 0% Opsis, ACCO
700 Back Punch 1 1 03-Jun-16 03-Jun-16 0% UCC, ACCO
701 Move Equipment & Furniture In 5 5 06-Jun-16 10-Jun-16 0% UCC, ACCO
702 PANO X-Ray 144 18 18 02-May-16 25-May-16
703 Uncover & Polish Floor - Install New Floor Protection 2 2 02-May-16 03-May-16 0% Floor Polish
704 Install Ceiling Grid & Tile For Devices 2 2 04-May-16 05-May-16 0% Harver
705 Complete Above Ceiling MEP 2 2 06-May-16 09-May-16 0% Data, Delta, Essential, Reynolds, O & S, FM, North Umpqua
706 Inspections To Cover @ Ceiling 1 1 10-May-16 10-May-16 0% County
707 Install Ceiling Tile 1 1 11-May-16 11-May-16 0% Harver
708 Install X-Ray Glass 2 2 12-May-16 13-May-16 0% Culver
709 Complete Electrical/AV/Data/Controls 1 1 16-May-16 16-May-16 0% TK, Reynolds
710 Uncover Floor & Final Buff 1 1 17-May-16 17-May-16 0% Floor Polish
711 Install Rubber Base 1 1 18-May-16 18-May-16 0% Flooring
712 Final Paint 1 1 19-May-16 19-May-16 0% WPI Paint
713 Final Clean 1 1 20-May-16 20-May-16 0% Cleaner
714 Punch & Corrections 2 2 20-May-16 23-May-16 0% Opsis, ACCO
715 Back Punch 1 1 23-May-16 23-May-16 0% UCC, ACCO
716 Move In Owner Furniture 2 2 24-May-16 25-May-16 0% UCC, ACCO
717 Model Trim Lab 145 26 26 03-May-16 08-Jun-16
718 Uncover & Polish Floor - Install New Floor Protection 2 2 03-May-16 04-May-16 0% Floor Polish
719 Install Ceiling Grid & Tile For Devices 2 2 05-May-16 06-May-16 0% Harver
720 Complete Above Ceiling MEP 5 5 05-May-16 11-May-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
721 Inspection To Cover @ Ceiling 2 2 12-May-16 13-May-16 0% County
722 Install Ceiling Tile 2 2 13-May-16 16-May-16 0% Harver
723 Install Cabinets 5 5 16-May-16 20-May-16 0% S & B
724 Install Sinks 2 2 20-May-16 23-May-16 0% North Umpqua
725 Install Glazing 2 2 23-May-16 24-May-16 0% Culver
726 Complete Electrical/AV/Data/Controls 2 2 24-May-16 25-May-16 0% Delta, Data, Essential, Reynolds
727 Uncover Floor & Final Buff 1 1 26-May-16 26-May-16 0% Floor Polish
728 Install Rubber Base 1 1 27-May-16 27-May-16 0% Flooring
729 Install Door & Hardware 1 1 27-May-16 27-May-16 0% WPI Doors
730 Final Paint 1 1 31-May-16 31-May-16 0% WPI Paint
731 Final Clean 2 2 01-Jun-16 02-Jun-16 0% Cleaner
732 Punch & Corrections 2 2 02-Jun-16 03-Jun-16 0% Opsis, ACCO
733 Back Punch 1 1 06-Jun-16 06-Jun-16 0% UCC, ACCO
734 Move Owner Equipment & Furniture In 5 5 02-Jun-16 08-Jun-16 0% UCC, ACCO
735 Offices 39 39 04-May-16 28-Jun-16
736 Offices 160A Thru 160L 39 39 04-May-16 28-Jun-16
737 Uncover & Polish Floor - Install New Floor Protection 4 4 04-May-16 09-May-16 0% Floor Polish
738 Install Ceiling Grid & Tile For Devices 4 4 09-May-16 12-May-16 0% Harver
739 Complete Above Ceiling MEP 5 5 10-May-16 16-May-16 0% O & S, FM
740 Inspections To Cover @ Ceiling 2 2 16-May-16 17-May-16 0% County
741 Install Ceiling Tile 5 5 16-May-16 20-May-16 0% Harver
742 Complete Electrical/AV/Data/Controls 5 5 18-May-16 24-May-16 0% Delta, Data, Essential, Reynolds
743 Install Relites 5 5 18-May-16 24-May-16 0% Culver
744 Install Roller Shades 3 3 23-May-16 25-May-16 0% Accessories
745 Remove Floor Protection & Final Buff 5 5 24-May-16 31-May-16 0% Floor Polish
746 Install Doors & Hardware 4 4 27-May-16 02-Jun-16 0% WPI Doors
747 Install Rubber Base 3 3 03-Jun-16 07-Jun-16 0% Flooring
748 Final Paint 5 5 08-Jun-16 14-Jun-16 0% WPI Paint
749 Final Clean 2 2 15-Jun-16 16-Jun-16 0% Cleaner
750 Punch & Corrections 4 4 16-Jun-16 21-Jun-16 0% Opsis, ACCO
751 Back Punch 2 2 22-Jun-16 23-Jun-16 0% UCC, ACCO
752 Move In Owner Furniture 5 5 22-Jun-16 28-Jun-16 0% UCC
753 Office Corridors 18 18 09-May-16 02-Jun-16
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Complete Electrical/AV/Data/Controls
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move Equipment & Furniture In
25-May-16, PANO X-Ray 144
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install X-Ray Glass
Complete Electrical/AV/Data/Controls
Uncover Floor & Final Buff
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
08-Jun-16, Model Trim Lab 145
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspection To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Sinks
Install Glazing
Complete Electrical/AV/Data/Controls
Uncover Floor & Final Buff
Install Rubber Base
Install Door & Hardware
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move Owner Equipment & Furniture In
28-Jun-16, Offices
28-Jun-16, Offices 160A Thru 160L
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Complete Electrical/AV/Data/Controls
Install Relites
Install Roller Shades
Remove Floor Protection & Final Buff
Install Doors & Hardware
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
02-Jun-16, Office Corridors
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 13 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
754 Corridor 103 18 18 09-May-16 02-Jun-16
755 Uncover & Polish Floor - Install New Floor Protection 4 4 09-May-16 12-May-16 0% Floor Polish
756 Install Ceiling Grid & Tile For Devices 3 3 12-May-16 16-May-16 0% Harver
757 Complete Above Ceiling MEP 3 3 16-May-16 18-May-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
758 Instpections To Cover @ Ceiling 2 2 18-May-16 19-May-16 0% County
759 Install Ceiling Tile 2 2 19-May-16 20-May-16 0% Harver
760 Complete Electrical/AV/Data/Controls 2 2 20-May-16 23-May-16 0% Delta, Data, Essential, Reynolds
761 Remove Floor Protection & Final Buff 1 1 23-May-16 23-May-16 0% Floor Polish
762 Install Rubber Base 2 2 24-May-16 25-May-16 0% Flooring
763 Final Paint 2 2 26-May-16 27-May-16 0% WPI Paint
764 Final Clean 1 1 31-May-16 31-May-16 0% Cleaner
765 Punch & Corrections 2 2 31-May-16 01-Jun-16 0% Opsis, ACCO
766 Back Punch 1 1 02-Jun-16 02-Jun-16 0% UCC, ACCO
767 Commons & Circulation 32 32 12-May-16 27-Jun-16
768 Corridor 102 17 17 12-May-16 06-Jun-16
769 Uncover & Polish Floor - Install New Floor Protection 3 3 12-May-16 16-May-16 0% Floor Polish
770 Complete Electrical/AV/Data/Controls 3 3 17-May-16 19-May-16 0% Delta, Data, Essential, Reynolds
771 Remove Floor Protection & Final Buff 2 2 20-May-16 23-May-16 0% Floor Polish
772 Install Rubber Base 2 2 24-May-16 25-May-16 0% Flooring
773 Final Paint 2 2 26-May-16 27-May-16 0% WPI Paint
774 Final Clean 2 2 27-May-16 31-May-16 0% Cleaner
775 Punch & Corrections 3 3 01-Jun-16 03-Jun-16 0% Opsis, ACCO
776 Back Punch 1 1 06-Jun-16 06-Jun-16 0% UCC, ACCO
777 Vestibule 102A 25 25 17-May-16 21-Jun-16
778 Complete MEP @ Walls 2 2 17-May-16 18-May-16 0% North Umpqua, Data, North Umpqua, Delta, Reynolds
779 Inspection To Cover @ Walls 1 1 18-May-16 18-May-16 0% County
780 Install Gyp @ Walls 1 1 19-May-16 19-May-16 0% Harver
781 Install Ceiling Framing 1 1 20-May-16 20-May-16 0% Harver
782 Complete Above Ceiling MEP 3 3 20-May-16 24-May-16 0% Reynolds, Delta, North Umpqua, Data, North Umpqua
783 Inspections To Cover @ Ceiling 1 1 24-May-16 24-May-16 0% County
784 Install Gyp @ Ceiling 1 1 24-May-16 24-May-16 0% Harver
785 Tape Gyp 5 5 24-May-16 31-May-16 0% Harver
786 Prime & 1st Coat 2 2 01-Jun-16 02-Jun-16 0% WPI Paint
787 Install Store Fronts 5 5 02-Jun-16 08-Jun-16 0% Culver
788 Install Ceiling/Wall Devices 3 3 08-Jun-16 10-Jun-16 0% FM, Reynolds, Delta, Essential
789 Install Walk Off Mats 2 2 13-Jun-16 14-Jun-16 0% Flooring
790 Final Paint 1 1 15-Jun-16 15-Jun-16 0% WPI Paint
791 Final Clean 1 1 16-Jun-16 16-Jun-16 0% Cleaner
792 Punch & Corrections 3 3 16-Jun-16 20-Jun-16 0% Opsis, ACCO
793 Back Punch 1 1 21-Jun-16 21-Jun-16 0% UCC, ACCO
794 Corridor 101 17 17 18-May-16 10-Jun-16
795 Uncover & Polish Floor - Install New Floor Protection 3 3 18-May-16 20-May-16 0% Floor Polish
796 Complete Electrical/AV/Data/Controls 2 2 23-May-16 24-May-16 0% Essential, Reynolds, Delta, Data
797 Remove Floor Protection @ Final Buff 2 2 25-May-16 26-May-16 0% Floor Polish
798 Install Rubber Base 2 2 27-May-16 31-May-16 0% Flooring
799 Final Paint 2 2 01-Jun-16 02-Jun-16 0% WPI Paint
800 Final Clean 2 2 03-Jun-16 06-Jun-16 0% Cleaner
801 Punch & Corrections 3 3 07-Jun-16 09-Jun-16 0% ACCO, Opsis
802 Back Punch 1 1 10-Jun-16 10-Jun-16 0% UCC, ACCO
803 Vestibule 100A 25 25 23-May-16 27-Jun-16
804 Complete MEP @ Walls 2 2 23-May-16 24-May-16 0% Reynolds, North Umpqua, Data, North Umpqua, Delta
805 Inspections To Cover @ Walls 1 1 24-May-16 24-May-16 0% County
806 Install Gyp @ Walls 1 1 25-May-16 25-May-16 0% Harver
807 Install Ceiling Framing 1 1 26-May-16 26-May-16 0% Harver
808 Complete Above Ceiling MEP 3 3 26-May-16 31-May-16 0% FM, North Umpqua, Data, North Umpqua, Reynolds, Delta, Essential
809 Inspections To Cover @ Ceiling 1 1 31-May-16 31-May-16 0% County
810 Install Gyp @ Ceiling 1 1 31-May-16 31-May-16 0% Harver
811 Tape Gyp 5 5 31-May-16 06-Jun-16 0% Harver
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
02-Jun-16, Corridor 103
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Instpections To Cover @ Ceiling
Install Ceiling Tile
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
27-Jun-16, Commons & Circulation
06-Jun-16, Corridor 102
Uncover & Polish Floor - Install New Floor Protection
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
21-Jun-16, Vestibule 102A
Complete MEP @ Walls
Inspection To Cover @ Walls
Install Gyp @ Walls
Install Ceiling Framing
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Gyp @ Ceiling
Tape Gyp
Prime & 1st Coat
Install Store Fronts
Install Ceiling/Wall Devices
Install Walk Off Mats
Final Paint
Final Clean
Punch & Corrections
Back Punch
10-Jun-16, Corridor 101
Uncover & Polish Floor - Install New Floor Protection
Complete Electrical/AV/Data/Controls
Remove Floor Protection @ Final Buff
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
27-Jun-16, Vestibule 100A
Complete MEP @ Walls
Inspections To Cover @ Walls
Install Gyp @ Walls
Install Ceiling Framing
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Gyp @ Ceiling
Tape Gyp
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 14 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
812 Prime & 1st Coat 2 2 07-Jun-16 08-Jun-16 0% WPI Paint
813 Install Store Fronts 5 5 08-Jun-16 14-Jun-16 0% Culver
814 Install Ceiling/Wall Devices 3 3 14-Jun-16 16-Jun-16 0% FM, North Umpqua, Data, Reynolds, Delta, Essential
815 Install Walk Off Mats 2 2 17-Jun-16 20-Jun-16 0% Flooring
816 Final Paint 1 1 21-Jun-16 21-Jun-16 0% WPI Paint
817 Final Clean 1 1 22-Jun-16 22-Jun-16 0% Cleaner
818 Punch & Corrections 3 3 22-Jun-16 24-Jun-16 0% Design, ACCO
819 Back Punch 1 1 27-Jun-16 27-Jun-16 0% UCC
820 Level 2 52 52 20-May-16 03-Aug-16
821 Restrooms 19 19 20-May-16 16-Jun-16
822 Mens 270 18 18 20-May-16 15-Jun-16
823 Uncover & Polish Floor- Install New Floor Protection 2 2 20-May-16 23-May-16 0% Floor Polish
824 Install Tile 3 3 24-May-16 26-May-16 0% Tile
825 Grout & Seal Tile 2 2 27-May-16 31-May-16 0% Tile
826 Install Lighting & Devices 1 1 01-Jun-16 01-Jun-16 0% Reynolds
827 Install Grills 1 1 01-Jun-16 01-Jun-16 0% FM
828 Install Plumbing Fixtures 3 3 31-May-16 02-Jun-16 0% North Umpqua
829 Install Partitions 2 2 02-Jun-16 03-Jun-16 0% Accessories
830 Install Accessories 2 2 03-Jun-16 06-Jun-16 0% Accessories
831 Final Paint 1 1 07-Jun-16 07-Jun-16 0% WPI Paint
832 Uncover Floor & Final Buff 1 1 08-Jun-16 08-Jun-16 0% Floor Polish
833 Final Clean 1 1 09-Jun-16 09-Jun-16 0% Cleaner
834 Punch & Corrections 3 3 10-Jun-16 14-Jun-16 0% Opsis, ACCO
835 Back Punch 1 1 15-Jun-16 15-Jun-16 0% UCC, ACCO
836 Womens 271 18 18 23-May-16 16-Jun-16
837 Uncover & Polish Floor - Install New Floor Protection 2 2 23-May-16 24-May-16 0% Floor Polish
838 Install Tile 3 3 25-May-16 27-May-16 0% Tile
839 Grout & Seal Tile 2 2 31-May-16 01-Jun-16 0% Tile
840 Install Lighting & Devices 1 1 02-Jun-16 02-Jun-16 0% Reynolds
841 Install Grills 1 1 02-Jun-16 02-Jun-16 0% FM
842 Install Plumbing Fixtures 3 3 01-Jun-16 03-Jun-16 0% North Umpqua
843 Install Partitions 2 2 03-Jun-16 06-Jun-16 0% Accessories
844 Install Accessories 2 2 06-Jun-16 07-Jun-16 0% Accessories
845 Final Paint 1 1 08-Jun-16 08-Jun-16 0% WPI Paint
846 Uncover Floor & Final Buff 1 1 09-Jun-16 09-Jun-16 0% Floor Polish
847 Final Clean 1 1 10-Jun-16 10-Jun-16 0% Cleaner
848 Punch & Corrections 3 3 13-Jun-16 15-Jun-16 0% Opsis, ACCO
849 Back Punch 1 1 16-Jun-16 16-Jun-16 0% UCC, ACCO
850 Unisex 272 13 13 24-May-16 10-Jun-16
851 Uncover & Polish Floor - Install New Floor Protection 2 2 24-May-16 25-May-16 0% Floor Polish
852 Install Lighting & Devices 1 1 26-May-16 26-May-16 0% Reynolds
853 Install Grills 1 1 26-May-16 26-May-16 0% FM
854 Install Plumbing Fixtures 2 2 27-May-16 31-May-16 0% North Umpqua
855 Install Accessories 2 2 01-Jun-16 02-Jun-16 0% Accessories
856 Final Paint 1 1 03-Jun-16 03-Jun-16 0% WPI Paint
857 Uncover Floor & Final Buff 1 1 06-Jun-16 06-Jun-16 0% Floor Polish
858 Final Clean 1 1 07-Jun-16 07-Jun-16 0% Cleaner
859 Punch & Corrections 2 2 08-Jun-16 09-Jun-16 0% Opsis, ACCO
860 Back Punch 1 1 10-Jun-16 10-Jun-16 0% UCC, ACCO
861 Support Rooms 14 14 25-May-16 14-Jun-16
862 Janitor 252 14 14 25-May-16 14-Jun-16
863 Uncover Floor & Polish - Install New Floor Protection 2 2 25-May-16 26-May-16 0% Floor Polish
864 Install Lighting & Devices 1 1 27-May-16 27-May-16 0% Reynolds
865 Install Grills 1 1 27-May-16 27-May-16 0% FM
866 Install Mop Sink 2 2 31-May-16 01-Jun-16 0% North Umpqua
867 Install FRP 2 2 02-Jun-16 03-Jun-16 0% Accessories
868 Remove Floor Protection & Final Buff 1 1 06-Jun-16 06-Jun-16 0% Floor Polish
869 Install Rubber Base 1 1 07-Jun-16 07-Jun-16 0% Flooring
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Prime & 1st Coat
Install Store Fronts
Install Ceiling/Wall Devices
Install Walk Off Mats
Final Paint
Final Clean
Punch & Corrections
Back Punch
03-Aug-16, Level 2
16-Jun-16, Restrooms
15-Jun-16, Mens 270
Uncover & Polish Floor- Install New Floor Protection
Install Tile
Grout & Seal Tile
Install Lighting & Devices
Install Grills
Install Plumbing Fixtures
Install Partitions
Install Accessories
Final Paint
Uncover Floor & Final Buff
Final Clean
Punch & Corrections
Back Punch
16-Jun-16, Womens 271
Uncover & Polish Floor - Install New Floor Protection
Install Tile
Grout & Seal Tile
Install Lighting & Devices
Install Grills
Install Plumbing Fixtures
Install Partitions
Install Accessories
Final Paint
Uncover Floor & Final Buff
Final Clean
Punch & Corrections
Back Punch
10-Jun-16, Unisex 272
Uncover & Polish Floor - Install New Floor Protection
Install Lighting & Devices
Install Grills
Install Plumbing Fixtures
Install Accessories
Final Paint
Uncover Floor & Final Buff
Final Clean
Punch & Corrections
Back Punch
14-Jun-16, Support Rooms
14-Jun-16, Janitor 252
Uncover Floor & Polish - Install New Floor Protection
Install Lighting & Devices
Install Grills
Install Mop Sink
Install FRP
Remove Floor Protection & Final Buff
Install Rubber Base
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 15 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
870 Install Door & Hardware 2 2 07-Jun-16 08-Jun-16 0% WPI Doors
871 Final Paint 1 1 09-Jun-16 09-Jun-16 0% WPI Paint
872 Final Clean 1 1 10-Jun-16 10-Jun-16 0% Cleaner
873 Punch & Corrections 2 2 10-Jun-16 13-Jun-16 0% Opsis, UCC
874 Back Punch 1 1 14-Jun-16 14-Jun-16 0% ACCO, UCC
875 Closet 233A 12 12 26-May-16 13-Jun-16
876 Install Ceiling Grid & Tile For Devices 1 1 27-May-16 27-May-16 0% Floor Polish
877 Complete Above Ceiling MEP 3 3 26-May-16 31-May-16 0% FM, North Umpqua, Data, North Umpqua, Reynolds, Delta, Essential
878 Complete Electrical Panel Installation 3 3 26-May-16 31-May-16 0% Reynolds
879 Inspections To Cover @ Ceiling 1 1 31-May-16 31-May-16 0% County
880 Install Lights & Grills 1 1 31-May-16 31-May-16 0% Reynolds, FM
881 Install Ceiling Tile 1 1 01-Jun-16 01-Jun-16 0% Harver
882 Complete Electrical/AV/Data/Controls 2 2 01-Jun-16 02-Jun-16 0% Reynolds, Delta, Data, Essential
883 Install Door & Hardware 1 1 03-Jun-16 03-Jun-16 0% WPI Doors
884 Install Flooring & Rubber Base 1 1 06-Jun-16 06-Jun-16 0% Flooring
885 Final Paint 1 1 07-Jun-16 07-Jun-16 0% WPI Paint
886 Final Clean 1 1 08-Jun-16 08-Jun-16 0% Cleaner
887 Punch & Corrections 2 2 09-Jun-16 10-Jun-16 0% Opsis, ACCO
888 Back Punch 1 1 13-Jun-16 13-Jun-16 0% UCC
889 Classrooms 21 21 27-May-16 27-Jun-16
890 Flex Classrooms 210 & 211 21 21 27-May-16 27-Jun-16
891 Uncover & Polish Floor - Install New Floor Protection 2 2 27-May-16 31-May-16 0% Floor Polish
892 Install Ceiling Grid & Tile For Devices 2 2 01-Jun-16 02-Jun-16 0% Harver
893 Complete Above Ceiling MEP 3 3 02-Jun-16 06-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
894 Install Partition 3 3 06-Jun-16 08-Jun-16 0% Accessories
895 Inspections To Cover @ Ceiling 2 2 07-Jun-16 08-Jun-16 0% County
896 Install Ceiling Tile 2 2 08-Jun-16 09-Jun-16 0% Harver
897 Install Roller Shades 1 1 09-Jun-16 09-Jun-16 0% Accessories
898 Install Marker Boards 1 1 09-Jun-16 09-Jun-16 0% Accessories
899 Complete Electrical/AV/Data/Controls 3 3 09-Jun-16 13-Jun-16 0% Reynolds, Data, Delta, Essential
900 Install Relites 2 2 13-Jun-16 14-Jun-16 0% Culver
901 Remove Floor Protection & Final Buff 1 1 15-Jun-16 15-Jun-16 0% Floor Polish
902 Install Rubber Base 2 2 15-Jun-16 16-Jun-16 0% Flooring
903 Install Doors & Hardware 2 2 16-Jun-16 17-Jun-16 0% WPI Doors
904 Final Paint 2 2 17-Jun-16 20-Jun-16 0% WPI Paint
905 Final Clean 2 2 21-Jun-16 22-Jun-16 0% Cleaner
906 Punch & Corrections 2 2 23-Jun-16 24-Jun-16 0% Opsis, ACCO
907 Back Punch 2 2 24-Jun-16 27-Jun-16 0% UCC, ACCO
908 Move In Owner Furniture 1 1 27-Jun-16 27-Jun-16 0% UCC
909 Classrooms 212 & 213 19 19 31-May-16 24-Jun-16
910 Uncover & Polish Floor - Install New Floor Protection 3 3 31-May-16 02-Jun-16 0% Floor Polish
911 Install Ceiling Grid & Tile For Devices 2 2 03-Jun-16 06-Jun-16 0% Harver
912 Complete Above Ceiling MEP 3 3 06-Jun-16 08-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
913 Inspections To Cover @ Ceiling 2 2 07-Jun-16 08-Jun-16 0% County
914 Install Ceiling Tile 2 2 09-Jun-16 10-Jun-16 0% Harver
915 Install Relites 2 2 09-Jun-16 10-Jun-16 0% Culver
916 Install Roller Shades 1 1 13-Jun-16 13-Jun-16 0% Accessories
917 Install Marker Boards 1 1 13-Jun-16 13-Jun-16 0% Accessories
918 Complete Electrical/AV/Data/Controls 3 3 10-Jun-16 14-Jun-16 0% TK, Delta, Data, Essential, Reynolds
919 Remove Floor Protection & Final Buff 1 1 15-Jun-16 15-Jun-16 0% Floor Polish
920 Install Rubber Base 2 2 15-Jun-16 16-Jun-16 0% Flooring
921 Install Doors & Hardware 1 1 17-Jun-16 17-Jun-16 0% WPI Doors
922 Final Paint 1 1 20-Jun-16 20-Jun-16 0% WPI Paint
923 Final Clean 1 1 21-Jun-16 21-Jun-16 0% Cleaner
924 Punch & Corrections 2 2 22-Jun-16 23-Jun-16 0% Opsis, ACCO
925 Back Punch 1 1 24-Jun-16 24-Jun-16 0% UCC, ACCO
926 Move In Owner Furniture 1 1 24-Jun-16 24-Jun-16 0% UCC
927 Conference & Work Room 22 22 03-Jun-16 05-Jul-16
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Install Door & Hardware
Final Paint
Final Clean
Punch & Corrections
Back Punch
13-Jun-16, Closet 233A
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Complete Electrical Panel Installation
Inspections To Cover @ Ceiling
Install Lights & Grills
Install Ceiling Tile
Complete Electrical/AV/Data/Controls
Install Door & Hardware
Install Flooring & Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
27-Jun-16, Classrooms
27-Jun-16, Flex Classrooms 210 & 211
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Install Partition
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Roller Shades
Install Marker Boards
Complete Electrical/AV/Data/Controls
Install Relites
Remove Floor Protection & Final Buff
Install Rubber Base
Install Doors & Hardware
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
24-Jun-16, Classrooms 212 & 213
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Relites
Install Roller Shades
Install Marker Boards
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Rubber Base
Install Doors & Hardware
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
05-Jul-16, Conference & Work Room
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 16 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
928 Conference 250 17 17 03-Jun-16 27-Jun-16
929 Install Ceiling Grid & Tiles For Devices 1 1 03-Jun-16 03-Jun-16 0% Harver
930 Complete Above Ceiling MEP 3 3 06-Jun-16 08-Jun-16 0% Data, Essential, O & S, FM, North Umpqua
931 Inspections To Cover @ Ceiling 1 1 09-Jun-16 09-Jun-16 0% County
932 Install Ceiling Tile 1 1 10-Jun-16 10-Jun-16 0% Harver
933 Install Relites, Door & Hardware 2 2 13-Jun-16 14-Jun-16 0% WPI Doors, Culver
934 Complete Electrical/AV/Data/Controls 3 3 15-Jun-16 17-Jun-16 0% Delta, Essential, Reynolds
935 Install Carpet & Rubber Base 1 1 20-Jun-16 20-Jun-16 0% Flooring
936 Final Paint 1 1 21-Jun-16 21-Jun-16 0% WPI Paint
937 Final Clean 1 1 22-Jun-16 22-Jun-16 0% Cleaner
938 Punch & Corrections 2 2 23-Jun-16 24-Jun-16 0% Opsis, ACCO
939 Back Punch 1 1 27-Jun-16 27-Jun-16 0% UCC, ACCO
940 Move In Owner Furniture 1 1 27-Jun-16 27-Jun-16 0% UCC
941 Work 251 22 22 03-Jun-16 05-Jul-16
942 Uncover & Polish Floor - Install New Floor Protection 2 2 03-Jun-16 06-Jun-16 0% Floor Polish
943 Install Ceiling Grid & Tile For Devices 2 2 07-Jun-16 08-Jun-16 0% Harver
944 Complete Above Ceiling MEP 3 3 08-Jun-16 10-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
945 Inspections To Cover @ Ceiling 1 1 10-Jun-16 10-Jun-16 0% County
946 Install Ceiling Tile 1 1 13-Jun-16 13-Jun-16 0% Harver
947 Install Cabinets 5 5 13-Jun-16 17-Jun-16 0% S & B
948 Install Sink & Fixtures 2 2 17-Jun-16 20-Jun-16 0% North Umpqua
949 Install Relite 1 1 20-Jun-16 20-Jun-16 0% Culver
950 Complete Electrical/AV/Data/Controls 2 2 21-Jun-16 22-Jun-16 0% Delta, Data, Essential, Reynolds
951 Remove Floor Protection & Final Buff 1 1 23-Jun-16 23-Jun-16 0% Floor Polish
952 Install Door & Hardware 1 1 24-Jun-16 24-Jun-16 0% WPI Doors
953 Install Rubber Base 1 1 27-Jun-16 27-Jun-16 0% Flooring
954 Final Paint 1 1 28-Jun-16 28-Jun-16 0% WPI Paint
955 Final Clean 1 1 29-Jun-16 29-Jun-16 0% Cleaner
956 Punch & Corrections 2 2 30-Jun-16 01-Jul-16 0% Opsis, ACCO
957 Back Punch 1 1 05-Jul-16 05-Jul-16 0% UCC, ACCO
958 Move In Owner Furnitrue 1 1 05-Jul-16 05-Jul-16 0% UCC
959 Labs 35 35 06-Jun-16 25-Jul-16
960 Physics & Geology 214 27 27 06-Jun-16 13-Jul-16
961 Uncover & Polish Floor - Install New Floor Protection 2 2 06-Jun-16 07-Jun-16 0% Floor Polish
962 Install Ceiling Grid & Tile For Devices 2 2 08-Jun-16 09-Jun-16 0% Harver
963 Complete Above Ceiling MEP 5 5 09-Jun-16 15-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
964 Inspections To Cover @ Ceiling 2 2 15-Jun-16 16-Jun-16 0% County
965 Install Ceiling Tile 2 2 16-Jun-16 17-Jun-16 0% Harver
966 Install Cabinets 5 5 16-Jun-16 22-Jun-16 0% S & B
967 Install Counter Tops 5 5 21-Jun-16 27-Jun-16 0% S & B
968 Install Sinks & Fixtures 3 3 27-Jun-16 29-Jun-16 0% North Umpqua
969 Install Hood H - 6A 3 3 29-Jun-16 01-Jul-16 0% Accessories
970 Complete G, A ,V & ICW Including Testing 5 5 29-Jun-16 06-Jul-16 0% North Umpqua, North Umpqua
971 Complete Electrical/AV/Data/Controls 5 5 29-Jun-16 06-Jul-16 0% Essential, Delta, Data, Reynolds
972 Install Relites 1 1 06-Jul-16 06-Jul-16 0% Culver
973 Install Marker Boards 1 1 06-Jul-16 06-Jul-16 0% Accessories
974 Uncover Floor & Final Buff 1 1 07-Jul-16 07-Jul-16 0% Floor Polish
975 Install Doors & Hardware 1 1 07-Jul-16 07-Jul-16 0% WPI Doors
976 Install Rubber Base 1 1 07-Jul-16 07-Jul-16 0% Flooring
977 Install Roller Shades 1 1 07-Jul-16 07-Jul-16 0% Accessories
978 Final Paint 1 1 08-Jul-16 08-Jul-16 0% WPI Paint
979 Final Clean 1 1 11-Jul-16 11-Jul-16 0% Cleaner
980 Punch & Corrections 3 3 08-Jul-16 12-Jul-16 0% Opsis, ACCO
981 Back Punch 1 1 13-Jul-16 13-Jul-16 0% UCC, ACCO
982 Move In Owner Equipment 1 1 13-Jul-16 13-Jul-16 0% ACCO, UCC
983 Anatomy/Physiology 220 29 29 07-Jun-16 18-Jul-16
984 Uncover & Polish Floor - Install New Floor Protection 2 2 07-Jun-16 08-Jun-16 0% Floor Polish
985 Install Ceiling Grid & Tile For Devices 2 2 08-Jun-16 09-Jun-16 0% Harver
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
27-Jun-16, Conference 250
Install Ceiling Grid & Tiles For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Relites, Door & Hardware
Complete Electrical/AV/Data/Controls
Install Carpet & Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
05-Jul-16, Work 251
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Sink & Fixtures
Install Relite
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Door & Hardware
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furnitrue
25-Jul-16, Labs
13-Jul-16, Physics & Geology 214
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Counter Tops
Install Sinks & Fixtures
Install Hood H - 6A
Complete G, A ,V & ICW Including Testing
Complete Electrical/AV/Data/Controls
Install Relites
Install Marker Boards
Uncover Floor & Final Buff
Install Doors & Hardware
Install Rubber Base
Install Roller Shades
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Equipment
18-Jul-16, Anatomy/Physiology 220
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 17 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
986 Complete Above Ceiling MEP 5 5 07-Jun-16 13-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
987 Inspections To Cover @ Ceiling 2 2 13-Jun-16 14-Jun-16 0% County
988 Install Ceiling Tile 2 2 14-Jun-16 15-Jun-16 0% Harver
989 Install Cabinets 5 5 15-Jun-16 21-Jun-16 0% S & B
990 Install Counter Tops 5 5 20-Jun-16 24-Jun-16 0% S & B
991 Install Sinks & Fixtures 5 5 23-Jun-16 29-Jun-16 0% North Umpqua
992 Complete LCW, LHW, G, LV & LA Including Testing 5 5 24-Jun-16 30-Jun-16 0% North Umpqua, North Umpqua
993 Complete Electrical/AV/Data/Controls 5 5 24-Jun-16 30-Jun-16 0% Delta, Data, Essential, Reynolds
994 Install Relites 1 1 30-Jun-16 30-Jun-16 0% Culver
995 Install Marker Boards 1 1 01-Jul-16 01-Jul-16 0% Accessories
996 Uncover Floor & Final Buff 1 1 05-Jul-16 05-Jul-16 0% Floor Polish
997 Install Doors & Hardware 2 2 06-Jul-16 07-Jul-16 0% WPI Doors
998 Install Rubber Base 1 1 08-Jul-16 08-Jul-16 0% Flooring
999 Install Roller Shades 1 1 11-Jul-16 11-Jul-16 0% Accessories
1000 Final Paint 1 1 12-Jul-16 12-Jul-16 0% WPI Paint
1001 Final Clean 1 1 13-Jul-16 13-Jul-16 0% Cleaner
1002 Punch & Corrections 3 3 13-Jul-16 15-Jul-16 0% ACCO, Opsis
1003 Back Punch 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO
1004 Move In Owner Equipment 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO
1005 Chemistry Lab 231 27 27 08-Jun-16 15-Jul-16
1006 Install Ceiling Grid & Tile For Devices 2 2 09-Jun-16 10-Jun-16 0% Harver
1007 Complete Above Ceiling MEP 5 5 08-Jun-16 14-Jun-16 0% North Umpqua, Data, Delta, Reynolds, Essential, O & S, FM
1008 Inspections To Cover @ Ceiling 2 2 14-Jun-16 15-Jun-16 0% County
1009 Install Ceiling Tile 2 2 15-Jun-16 16-Jun-16 0% Harver
1010 Install Cabinets 5 5 15-Jun-16 21-Jun-16 0% S & B
1011 Install Counter Tops 5 5 20-Jun-16 24-Jun-16 0% S & B
1012 Install Sinks & Fixtures 4 4 24-Jun-16 29-Jun-16 0% North Umpqua
1013 Install Fume Hoods 5 5 29-Jun-16 06-Jul-16 0% Accessories
1014 Complete G, A, V & ICW Including Testing 5 5 06-Jul-16 12-Jul-16 0% North Umpqua, North Umpqua, Special Inspection
1015 Complete Electrical/AV/Data/Controls 5 5 06-Jul-16 12-Jul-16 0% Delta, Data, Essential, Reynolds
1016 Install Relites 2 2 11-Jul-16 12-Jul-16 0% Culver
1017 Install Marker Boards 1 1 12-Jul-16 12-Jul-16 0% Accessories
1018 Install Doors & Hardware 2 2 12-Jul-16 13-Jul-16 0% WPI Doors
1019 Install Flooring & Rubber Base 2 2 12-Jul-16 13-Jul-16 0% Flooring
1020 Install Roller Shades 1 1 13-Jul-16 13-Jul-16 0% Accessories
1021 Final Paint 1 1 14-Jul-16 14-Jul-16 0% WPI Paint
1022 Final Clean 1 1 14-Jul-16 14-Jul-16 0% Cleaner
1023 Punch & Corrections 3 3 13-Jul-16 15-Jul-16 0% Opsis, ACCO
1024 Back Punch 1 1 15-Jul-16 15-Jul-16 0% UCC, ACCO
1025 Move In Owner Equipment 1 1 15-Jul-16 15-Jul-16 0% UCC, ACCO
1026 Insturment Prep 232 26 26 13-Jun-16 19-Jul-16
1027 Install Ceiling Grid & Tile For Devices 2 2 13-Jun-16 14-Jun-16 0% Harver
1028 Complete Above Ceiling MEP 5 5 13-Jun-16 17-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
1029 Inspections To Cover @ Ceiling 1 1 17-Jun-16 17-Jun-16 0% County
1030 Install Ceiling Tile 1 1 20-Jun-16 20-Jun-16 0% Harver
1031 Install Cabinets 5 5 20-Jun-16 24-Jun-16 0% S & B
1032 Install Counter Tops 5 5 23-Jun-16 29-Jun-16 0% S & B
1033 Install Sink & Fixtures 4 4 29-Jun-16 05-Jul-16 0% North Umpqua
1034 Complete G, A, V & ICW Including Testing 5 5 01-Jul-16 08-Jul-16 0% North Umpqua, Special Inspection, North Umpqua
1035 Complete Electrical/AV/Data/Controls 5 5 01-Jul-16 08-Jul-16 0% Reynolds, Delta, Data, Essential
1036 Install Doors & Hardware 2 2 07-Jul-16 08-Jul-16 0% WPI Doors
1037 Install Flooring & Rubber Base 2 2 11-Jul-16 12-Jul-16 0% Flooring
1038 Final Paint 1 1 13-Jul-16 13-Jul-16 0% WPI Paint
1039 Final Clean 1 1 14-Jul-16 14-Jul-16 0% Cleaner
1040 Punch & Corrections 3 3 14-Jul-16 18-Jul-16 0% Opsis, ACCO
1041 Back Punch 1 1 19-Jul-16 19-Jul-16 0% UCC, ACCO
1042 Move In Owner Equipment 1 1 19-Jul-16 19-Jul-16 0% UCC, ACCO
1043 Stock Room/Closet 233 24 24 14-Jun-16 18-Jul-16
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Counter Tops
Install Sinks & Fixtures
Complete LCW, LHW, G, LV & LA Including Testing
Complete Electrical/AV/Data/Controls
Install Relites
Install Marker Boards
Uncover Floor & Final Buff
Install Doors & Hardware
Install Rubber Base
Install Roller Shades
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Equipment
15-Jul-16, Chemistry Lab 231
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Counter Tops
Install Sinks & Fixtures
Install Fume Hoods
Complete G, A, V & ICW Including Testing
Complete Electrical/AV/Data/Controls
Install Relites
Install Marker Boards
Install Doors & Hardware
Install Flooring & Rubber Base
Install Roller Shades
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Equipment
19-Jul-16, Insturment Prep 232
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Counter Tops
Install Sink & Fixtures
Complete G, A, V & ICW Including Testing
Complete Electrical/AV/Data/Controls
Install Doors & Hardware
Install Flooring & Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Equipment
18-Jul-16, Stock Room/Closet 233
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 18 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
1044 Install Ceiling Grid & Tile For Devices 2 2 15-Jun-16 16-Jun-16 0% Harver
1045 Complete Above Ceiling MEP 5 5 14-Jun-16 20-Jun-16 0% O & S, FM, North Umpqua, Data, Delta, Essential, Reynolds
1046 Inspections To Cover @ Ceiling 2 2 20-Jun-16 21-Jun-16 0% County
1047 Install Ceiling Tile 2 2 21-Jun-16 22-Jun-16 0% Harver
1048 Install Cabinets 5 5 22-Jun-16 28-Jun-16 0% S & B
1049 Install Counter Tops 5 5 24-Jun-16 30-Jun-16 0% S & B
1050 Install Sinks & Fixtures 3 3 30-Jun-16 05-Jul-16 0% North Umpqua, North Umpqua
1051 Complete G, A, V & ICW Including Testing 5 5 29-Jun-16 06-Jul-16 0% North Umpqua, North Umpqua
1052 Complete Electrical/AV/Data/Controls 5 5 29-Jun-16 06-Jul-16 0% Delta, Data, Essential, Reynolds
1053 Install Relite 1 1 06-Jul-16 06-Jul-16 0% Culver
1054 Install Roller Shades 1 1 06-Jul-16 06-Jul-16 0% Accessories
1055 Install Doors & Hardware 2 2 05-Jul-16 06-Jul-16 0% WPI Doors
1056 Install Flooring & Rubber Base 3 3 05-Jul-16 07-Jul-16 0% Flooring
1057 Final Paint 2 2 08-Jul-16 11-Jul-16 0% WPI Paint
1058 Final Clean 2 2 11-Jul-16 12-Jul-16 0% Cleaner
1059 Punch & Corrections 3 3 13-Jul-16 15-Jul-16 0% Opsis, ACCO
1060 Back Punch 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO
1061 Move In Owner Equipment 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO
1062 Roof Access 234 9 9 16-Jun-16 28-Jun-16
1063 Uncover & Polish Floor - Install New Floor Protection 2 2 16-Jun-16 17-Jun-16 0% Floor Polish
1064 Complete Electrical/AV/Data/Controls 1 1 17-Jun-16 17-Jun-16 0% Delta, Data, Essential, Reynolds
1065 Install Door & Hardware 1 1 20-Jun-16 20-Jun-16 0% WPI Doors
1066 Uncover Floor & Final Buff 1 1 21-Jun-16 21-Jun-16 0% Floor Polish
1067 Install Rubber Base 1 1 22-Jun-16 22-Jun-16 0% Flooring
1068 Final Paint 1 1 23-Jun-16 23-Jun-16 0% WPI Paint
1069 Final Clean 1 1 24-Jun-16 24-Jun-16 0% Cleaner
1070 Punch & Corrections 3 3 23-Jun-16 27-Jun-16 0% Opsis, ACCO
1071 Back Punch 1 1 28-Jun-16 28-Jun-16 0% Opsis, ACCO
1072 Chem Storage 235 20 20 20-Jun-16 18-Jul-16
1073 Install Ceiling Grid & Tile For Devices 2 2 20-Jun-16 21-Jun-16 0% Harver
1074 Complete Above Ceiling MEP 3 3 20-Jun-16 22-Jun-16 0% North Umpqua, Data, Delta, Essential, O & S, FM, Reynolds
1075 Inspections To Cover @ Ceiling 1 1 22-Jun-16 22-Jun-16 0% County
1076 Install Ceiling Tile 1 1 23-Jun-16 23-Jun-16 0% Harver
1077 Install Cabinets 5 5 22-Jun-16 28-Jun-16 0% S & B
1078 Install Counter Tops 5 5 27-Jun-16 01-Jul-16 0% S & B
1079 Install Sink & Fixtures 3 3 01-Jul-16 06-Jul-16 0% North Umpqua
1080 Install Hood H-4 2 2 06-Jul-16 07-Jul-16 0% Accessories
1081 Complete G, A, V & ICW Including Testing 5 5 05-Jul-16 11-Jul-16 0% North Umpqua, North Umpqua
1082 Complete Electrical/AV/Data/Controls 5 5 05-Jul-16 11-Jul-16 0% Delta, Data, Essential, Reynolds
1083 Install Doors & Hardware 2 2 08-Jul-16 11-Jul-16 0% WPI Doors
1084 Install Flooring & Rubber Base 3 3 08-Jul-16 12-Jul-16 0% Flooring
1085 Final Paint 1 1 13-Jul-16 13-Jul-16 0% WPI Paint
1086 Final Clean 1 1 13-Jul-16 13-Jul-16 0% Cleaner
1087 Punch & Corrections 3 3 13-Jul-16 15-Jul-16 0% Opsis, ACCO
1088 Back Punch 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO
1089 Move In Owner Furniture 1 1 18-Jul-16 18-Jul-16 0% UCC, ACCO
1090 Biology Lab 236 23 23 22-Jun-16 25-Jul-16
1091 Install Ceiling Grid & Tile For Devices 2 2 22-Jun-16 23-Jun-16 0% Harver
1092 Complete Above Ceiling MEP 3 3 22-Jun-16 24-Jun-16 0% O & S, FM, North Umpqua, Data, Reynolds, Delta, Essential
1093 Inspections To Cover @ Ceiling 2 2 24-Jun-16 27-Jun-16 0% County
1094 Install Ceiling Tile 2 2 24-Jun-16 27-Jun-16 0% Harver
1095 Install Cabinets 5 5 23-Jun-16 29-Jun-16 0% S & B
1096 Install Counter Tops 5 5 27-Jun-16 01-Jul-16 0% S & B
1097 Install Sinks & Fixtures 3 3 01-Jul-16 06-Jul-16 0% North Umpqua
1098 Install Fume Hood 2 2 05-Jul-16 06-Jul-16 0% Accessories
1099 Complete G, A, V & ICW Including Testing 5 5 05-Jul-16 11-Jul-16 0% North Umpqua
1100 Complete Electrical/AV/Data/Controls 5 5 05-Jul-16 11-Jul-16 0% Delta, Data, Essential, Reynolds
1101 Install Relite 1 1 11-Jul-16 11-Jul-16 0% Culver
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Counter Tops
Install Sinks & Fixtures
Complete G, A, V & ICW Including Testing
Complete Electrical/AV/Data/Controls
Install Relite
Install Roller Shades
Install Doors & Hardware
Install Flooring & Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Equipment
28-Jun-16, Roof Access 234
Uncover & Polish Floor - Install New Floor Protection
Complete Electrical/AV/Data/Controls
Install Door & Hardware
Uncover Floor & Final Buff
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
18-Jul-16, Chem Storage 235
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Counter Tops
Install Sink & Fixtures
Install Hood H-4
Complete G, A, V & ICW Including Testing
Complete Electrical/AV/Data/Controls
Install Doors & Hardware
Install Flooring & Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
25-Jul-16, Biology Lab 236
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Install Cabinets
Install Counter Tops
Install Sinks & Fixtures
Install Fume Hood
Complete G, A, V & ICW Including Testing
Complete Electrical/AV/Data/Controls
Install Relite
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 19 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
1102 Install Marker Boards 1 1 11-Jul-16 11-Jul-16 0% Accessories
1103 Install Doors & Hardware 2 2 11-Jul-16 12-Jul-16 0% WPI Doors
1104 Install Flooring & Rubber Base 3 3 11-Jul-16 13-Jul-16 0% Flooring
1105 Install Roller Shades 1 1 14-Jul-16 14-Jul-16 0% Accessories
1106 Final Paint 1 1 15-Jul-16 15-Jul-16 0% WPI Paint
1107 Final Clean 2 2 18-Jul-16 19-Jul-16 0% Cleaner
1108 Punch & Corrections 3 3 20-Jul-16 22-Jul-16 0% ACCO, Opsis
1109 Back Punch 1 1 25-Jul-16 25-Jul-16 0% UCC, ACCO
1110 Move In Owner Equipment 1 1 25-Jul-16 25-Jul-16 0% UCC, ACCO
1111 Offices 18 18 23-Jun-16 19-Jul-16
1112 Offices 260A Thru 260L 18 18 23-Jun-16 19-Jul-16
1113 Uncover & Polish Floor - Install New Floor Protection 3 3 23-Jun-16 27-Jun-16 0% Floor Polish
1114 Install Ceiling Grid & Tile For Devices 3 3 24-Jun-16 28-Jun-16 0% Harver
1115 Complete Above Ceiling MEP 3 3 24-Jun-16 28-Jun-16 0% Reynolds, Delta, Essential, O & S, FM, North Umpqua, Data
1116 Inspections To Cover @ Ceiling 2 2 27-Jun-16 28-Jun-16 0% County
1117 Install Ceiling Tile 3 3 27-Jun-16 29-Jun-16 0% Harver
1118 Complete Electrical/AV/Data/Controls 3 3 28-Jun-16 30-Jun-16 0% Delta, Data, Essential, Reynolds
1119 Install Relites 3 3 28-Jun-16 30-Jun-16 0% Culver
1120 Install Roller Shades 2 2 29-Jun-16 30-Jun-16 0% Accessories
1121 Remove Floor Protection & Final Buff 3 3 29-Jun-16 01-Jul-16 0% Floor Polish
1122 Install Doors & Hardware 3 3 29-Jun-16 01-Jul-16 0% WPI Doors
1123 Install Rubber Base 3 3 01-Jul-16 06-Jul-16 0% Flooring
1124 Final Paint 3 3 06-Jul-16 08-Jul-16 0% WPI Paint
1125 Final Clean 2 2 11-Jul-16 12-Jul-16 0% Cleaner
1126 Punch & Corrections 4 4 12-Jul-16 15-Jul-16 0% Opsis, ACCO
1127 Back Punch 2 2 18-Jul-16 19-Jul-16 0% UCC, ACCO
1128 Move In Owner Furniture 1 1 19-Jul-16 19-Jul-16 0% UCC, ACCO
1129 Office Corridors 18 18 27-Jun-16 21-Jul-16
1130 Corridor 203 18 18 27-Jun-16 21-Jul-16
1131 Uncover & Polish Floor - Install New Floor Protection 3 3 27-Jun-16 29-Jun-16 0% Floor Polish
1132 Install Ceiling Grid & Tile For Devices 3 3 29-Jun-16 01-Jul-16 0% Harver
1133 Complete Above Ceiling MEP 4 4 30-Jun-16 06-Jul-16 0% O & S, FM, North Umpqua, Data, Reynolds, Delta, Essential
1134 Inspections To Cover @ Ceilings 2 2 06-Jul-16 07-Jul-16 0% County
1135 Install Ceiling Tile 2 2 08-Jul-16 11-Jul-16 0% Harver
1136 Complete Electrical/AV/Data/Controls 2 2 11-Jul-16 12-Jul-16 0% Delta, Data, Essential, Reynolds
1137 Remove Floor Protection & Final Buff 1 1 12-Jul-16 12-Jul-16 0% Floor Polish
1138 Install Rubber Base 1 1 13-Jul-16 13-Jul-16 0% Flooring
1139 Final Paint 2 2 14-Jul-16 15-Jul-16 0% WPI Paint
1140 Final Clean 1 1 18-Jul-16 18-Jul-16 0% Cleaner
1141 Punch & Corrections 3 3 18-Jul-16 20-Jul-16 0% Opsis, ACCO
1142 Back Punch 1 1 21-Jul-16 21-Jul-16 0% UCC, ACCO
1143 Commons & Circulation 25 25 29-Jun-16 03-Aug-16
1144 Corridor 202 17 17 29-Jun-16 22-Jul-16
1145 Uncover & Polish Floor - Install New Floor Protection 3 3 29-Jun-16 01-Jul-16 0% Floor Polish
1146 Complete Electrical/AV/Data/Controls 3 3 05-Jul-16 07-Jul-16 0% Delta, Data, Essential, Reynolds
1147 Remove Floor Protection & Final Buff 2 2 08-Jul-16 11-Jul-16 0% Floor Polish
1148 Install Rubber Base 2 2 11-Jul-16 12-Jul-16 0% Flooring
1149 Final Paint 2 2 13-Jul-16 14-Jul-16 0% WPI Paint
1150 Final Clean 2 2 15-Jul-16 18-Jul-16 0% Cleaner
1151 Punch & Corrections 3 3 19-Jul-16 21-Jul-16 0% Opsis, ACCO
1152 Back Punch 1 1 22-Jul-16 22-Jul-16 0% UCC, ACCO
1153 Vestibule 202A 10 10 01-Jul-16 15-Jul-16
1154 Install Ceiling Framing 1 1 05-Jul-16 05-Jul-16 0% Harver
1155 Complete Above Ceiling MEP 2 2 01-Jul-16 05-Jul-16 0% Reynolds, O & S, North Umpqua, Data, Delta, Essential
1156 Inspection To Cover @ Ceiling 1 1 05-Jul-16 05-Jul-16 0% County
1157 Install Store Fronts 3 3 06-Jul-16 08-Jul-16 0% Culver
1158 Install Walk Off Mats 2 2 08-Jul-16 11-Jul-16 0% Flooring
1159 Final Paint 1 1 12-Jul-16 12-Jul-16 0% WPI Paint
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Install Marker Boards
Install Doors & Hardware
Install Flooring & Rubber Base
Install Roller Shades
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Equipment
19-Jul-16, Offices
19-Jul-16, Offices 260A Thru 260L
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceiling
Install Ceiling Tile
Complete Electrical/AV/Data/Controls
Install Relites
Install Roller Shades
Remove Floor Protection & Final Buff
Install Doors & Hardware
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
Move In Owner Furniture
21-Jul-16, Office Corridors
21-Jul-16, Corridor 203
Uncover & Polish Floor - Install New Floor Protection
Install Ceiling Grid & Tile For Devices
Complete Above Ceiling MEP
Inspections To Cover @ Ceilings
Install Ceiling Tile
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
03-Aug-16, Commons & Circulation
22-Jul-16, Corridor 202
Uncover & Polish Floor - Install New Floor Protection
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
15-Jul-16, Vestibule 202A
Install Ceiling Framing
Complete Above Ceiling MEP
Inspection To Cover @ Ceiling
Install Store Fronts
Install Walk Off Mats
Final Paint
UCC Weekly Overall Sub Update 30-Nov-15 10:55
Page 20 of 21
# Activity Name OriginalDuration
RemainingDuration
Start Finish Activity %Complete
Resources
1160 Final Clean 1 1 12-Jul-16 12-Jul-16 0% Cleaner
1161 Punch & Corrections 3 3 12-Jul-16 14-Jul-16 0% Opsis, ACCO
1162 Back Punch 1 1 15-Jul-16 15-Jul-16 0% Opsis, ACCO
1163 Corridor 201 13 13 01-Jul-16 20-Jul-16
1164 Uncover & Polish Floor - Install New Floor Protection 3 3 01-Jul-16 06-Jul-16 0% Floor Polish
1165 Complete Electrical/AV/Data/Controls 3 3 07-Jul-16 11-Jul-16 0% Delta, Data, Essential, Reynolds
1166 Remove Floor Protection & Final Buff 2 2 12-Jul-16 13-Jul-16 0% Floor Polish
1167 Install Rubber Base 2 2 13-Jul-16 14-Jul-16 0% Flooring
1168 Final Paint 2 2 15-Jul-16 18-Jul-16 0% WPI Doors
1169 Final Clean 1 1 18-Jul-16 18-Jul-16 0% Cleaner
1170 Punch & Corrections 3 3 15-Jul-16 19-Jul-16 0% Opsis, ACCO
1171 Back Punch 1 1 20-Jul-16 20-Jul-16 0% UCC, ACCO
1172 Stair 1 & Atrium Handrails 20 20 07-Jul-16 03-Aug-16
1173 Install Handrails @ Stairs & Level 2 Opening 7 7 07-Jul-16 15-Jul-16 0% L & M/Westside Iron
1174 Prime & 1st Coat 3 3 14-Jul-16 18-Jul-16 0% WPI Doors
1175 Install Treads 5 5 18-Jul-16 22-Jul-16 0% Mason
1176 Final Paint 4 4 22-Jul-16 27-Jul-16 0% WPI Doors
1177 Install Cable Handrails 4 4 27-Jul-16 01-Aug-16 0% Accessories
1178 Punch & Corrections 3 3 01-Aug-16 03-Aug-16 0% Opsis, ACCO
1179 Back Punch 1 1 03-Aug-16 03-Aug-16 0% UCC, ACCO
1180 West Bridge 25 25 30-Jun-16 04-Aug-16
1181 Complete Bridge Structure 1 1 30-Jun-16 30-Jun-16 0% L & M/Westside Iron
1182 Install Handrail Supports 5 5 01-Jul-16 08-Jul-16 0% L & M/Westside Iron
1183 Prime & 1st Coat 3 3 11-Jul-16 13-Jul-16 0% WPI Paint
1184 Complete Handrails 5 5 14-Jul-16 20-Jul-16 0% Wood Finishes
1185 Final Paint 2 2 21-Jul-16 22-Jul-16 0% WPI Paint
1186 Final Clean 2 2 25-Jul-16 26-Jul-16 0% Cleaner
1187 Punch & Corrections 5 5 27-Jul-16 02-Aug-16 0% Design, ACCO
1188 Back Punch 2 2 03-Aug-16 04-Aug-16 0% UCC, ACCO
1189 Site Finishes & New Fire Lane 40 40 19-May-16 15-Jul-16
1190 Layout & Install Site Finish & Fire Lane Concrete 40 40 19-May-16 15-Jul-16 0% Knife River, Guido
1191 Landscaping 40 40 03-Jun-16 29-Jul-16
1192 Layout & Install Landscaping 40 40 03-Jun-16 29-Jul-16 0%
1193 Install PV Array 30 30 19-May-16 30-Jun-16
1194 Install PV Array 30 30 19-May-16 30-Jun-16 0%
1195 Project Closeout 56 56 11-Jul-16 27-Sep-16
1196 Substantial Completion 28 28 11-Jul-16 17-Aug-16
1197 Weather Days 10 10 11-Jul-16 22-Jul-16 0% ACCO
1198 Final Inspections Complete 1 1 04-Aug-16 04-Aug-16 0% Opsis, UCC, ACCO
1199 Substantial Completion & Temporary Occupancy 1 1 17-Aug-16 17-Aug-16 0% ACCO, UCC, County, Special Inspection, Fire Marshall
1200 Final Completion 28 28 17-Aug-16 27-Sep-16
1201 Commissioning Complete 1 1 23-Sep-16 26-Sep-16 0% ACCO
1202 Leed Documentation Complete 20 20 17-Aug-16 14-Sep-16 0% ACCO
1203 Certificate of Occupancy & Final Completion 1 1 27-Sep-16 27-Sep-16 0% ACCO, UCC
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
2015 2016
Final Clean
Punch & Corrections
Back Punch
20-Jul-16, Corridor 201
Uncover & Polish Floor - Install New Floor Protection
Complete Electrical/AV/Data/Controls
Remove Floor Protection & Final Buff
Install Rubber Base
Final Paint
Final Clean
Punch & Corrections
Back Punch
03-Aug-16, Stair 1 & Atrium Handrails
Install Handrails @ Stairs & Level 2 Opening
Prime & 1st Coat
Install Treads
Final Paint
Install Cable Handrails
Punch & Corrections
Back Punch
04-Aug-16, West Bridge
Complete Bridge Structure
Install Handrail Supports
Prime & 1st Coat
Complete Handrails
Final Paint
Final Clean
Punch & Corrections
Back Punch
15-Jul-16, Site Finishes & New Fire Lane
Layout & Install Site Finish & Fire Lane Concrete
29-Jul-16, Landscaping
Layout & Install Landscaping
30-Jun-16, Install PV Array
Install PV Array
27-Sep-16, Project Closeout
17-Aug-16, Substantial Completion
Weather Days
Final Inspections Complete
Substantial Completion & Temporary Occupancy
27-Sep-16, Final Completion
Commissioning Complete
Leed Documentation Complete
Certificate of Occupancy & Final Completion
UCC Weekly Overall Sub Update 30-Nov-15 10:55