Upload
aiden-else
View
221
Download
6
Tags:
Embed Size (px)
Citation preview
Hopkins – St. Louis Park – Minneapolis Regional Sanitary Sewer Improvements
Draft Facility PlanJanuary 20, 2010
Metropolitan CouncilMetropolitan CouncilPublic Information MeetingPublic Information Meeting
Bill Moeller – MCES Assistant General Manager Bill Cook – MCES Engineering Services Manager Scott Dentz – MCES Interceptor Engineering
Manager Adam Gordon – MCES Project Manager Tim O’Donnell – MCES Senior Information
Coordinator
Bill Lueck – Project Manager, CDM
consulting engineers Jodi Polzin – Project Manager, CDM
consulting engineers
1. Overview of Regional Wastewater System 2. Overview of Project Facility Plan
Existing Facilities and Conditions Alternatives Recommendations and Schedule Public Participation
3. Question & Answer/Open House
St. CroixValley
EaglesPoint
Empire
Anoka
Washington
Hennepin
Carver
Scott
Dakota
Ramsey
Hastings
BlueLake
Metro
Seneca
St. CroixValley
EaglesPoint
Empire
Anoka
Washington
Hennepin
Carver
Scott
Dakota
Ramsey
Hastings
BlueLake
Metro
Seneca
Definitions Conveyance – Facilities used to move wastewater (includes
pumps, pipes and sewers) Force main – A pressure pipe in which wastewater is
conveyed with the use of pumps (pump station) Gravity sewer – A pipe that is constructed with a continuous
drop in elevation to convey flow Temporary conveyance – A temporary wastewater
conveyance pipe typically run above ground and permits the existing pipe to be drained, cleaned, inspected, and repaired
Interceptor – A force main or gravity sewer that intercepts wastewater from multiple communities and conveys it to one of the regional wastewater treatment plants.
Increase pumping station capacity to accommodate growth and improve efficiency
Correct known problems Construct redundant facilities to allow
condition assessment and repair
Existing SystemExisting System MCES L27 Pump Station
◦ Constructed in 1971◦ Receives all wastewater generated in Hopkins
MCES 7026 Sanitary Force Main◦ Five mile long force main between L27 and 27th
Street and Humboldt Avenue South in Minneapolis City Pump Stations
◦ Three pump stations serving nearly 20% of St. Louis Park
◦ One pump station serving an area near Lake of the Isles in Minneapolis
Current Ultimate
Average, mgd Peak, mgdAverage, mgd Peak, mgd
Hopkins (L-27)
1.6 4.6 2.3 6.3
St. Louis Park(LS1, LS19, LS2)
1.0 3.2 1.4 4.2
Minneapolis(L-5)
0.01 0.04 0.01 0.04
Total 2.6 7.0 3.7 9.3
The L-27 lift station has reached its useful life expectancy and maintenance issues in conjunction with the need to increase its capacity warrant consideration of replacement.
Age, operatingconditions, unknown pipe condition, and previous repairs warrant improvements to force main 7026.
Recommend Interceptor Sewer Corridor Identify Type of Interceptor Sewer Facilities
(Pumping/Gravity) Evaluate Alternative Sites for Pump Station
Location Develop a Plan for Interceptor Sewer
Construction
Facility Plan GoalsFacility Plan Goals
1-MN-330
1-MN-344
To Blue Lake WWTP
1) To Blue Lake WWTP via Force MainSecond Highest CostCapacity Reserved for Existing Service Area
3) To 1-MN-341 via Force Main Insufficient CapacityNot Considered Further
2) To 1-MN-344 via Force MainThird Highest Cost
1-MN-330
1-MN-344
To Blue Lake WWTP
4) To 1-MN-330 via Gravity Highest CostMost DisruptionMost Difficult ConstructionNo Redirection of Local
Connections
5) To 1-MN-330 via Force MainLowest CostLeast DisruptionNo Redirection of Local
Connections
Alternative Phase 1 Phase 2
1Rehabilitate existing force main w/ temporary conveyance
Construct parallel, redundant force main
2Construct parallel, redundant force main w/ temporary conveyance
Rehabilitate existing force main
3Construct dual pipe force main w/ temporary conveyance
Abandon existing force main
Phase I
Install 2 New Force Mains
Phase I
Install New Force Main
Phase II
Line Portions of Existing Force
Main
Phase II
Line Portions of Existing
Force Main
Phase I
Construct New Force Main
Goals For Minneapolis SegmentGoals For Minneapolis Segment Provide short term assurance that the
interceptor system is providing reliable service Replace previously
repaired sections of force main
Relocate inaccessible force main
Reline remaining force main
Install a redundant force main
Existing Force MainExisting Force Main
Temporary ConveyanceTemporary Conveyance
Recommended Plan - Minneapolis Segment: PHASE IRecommended Plan - Minneapolis Segment: PHASE I
New Force Main
Rehabilitated Force Main
Abandoned Force Main
Install New Force Main
Reline Remaining Force Main
Abandon Force Main
Recommended Plan - Minneapolis Segment: PHASE 2Recommended Plan - Minneapolis Segment: PHASE 2
New Force Main
Existing Force Main
Summary of L27 Site Criteria Cost Effective Available Property Site Compatibility
◦ Land Use◦ Adjacent Land Use
Environmental Issues◦ Flood Plain and Wetland Proximity◦ Environmental Contamination
Recreational Impact Transportation Disruption
Lowest Cost for Full Replacement Options Existing Infrastructure Conveys Hopkins
Wastewater to this Location MCES Currently Owns and Operates Existing
Site as a Pump Station
City Suggested Site For L-27City Suggested Site For L-27
Head House
Wet Well
Tunnel
2010 2011 2012 2013 2014
2015 2016 through 2020
2010-2011 Minnehaha Creek
2010-2012 Minneapolis – Phase 1
2011-2014 L-27 Reconstruction
2011-2015 Hopkins/Saint Louis Park – Phase 1
2011-2015 Highway 100 – Phase 1&2
As Required Hopkins/Saint Louis Park – Phase 2
As Required Minneapolis – Phase 2
Project Construction ScheduleProject Construction Schedule
Lift Station/Force Main Segment
Capital Cost
L-27 $9,700,000
West Saint Louis Park $14,100,000
Highway 100 $4,700,000
East Saint Louis Park $11,100,000
Minneapolis $24,000,000
Total Estimated Cost $63,600,000
The estimated cost includes construction cost, design and administration, land
acquisition, and contingencies.
Metropolitan Council projects are funded by bonds and Public Facilities Authority Loans, which are paid by regional sewer connection fees & user charges.
One-time increase of $150.01 per unit for new connection to sewer system (SAC)
$1.35 increase per year per household region-wide for 20 years (based on average annual water usage)
No assessment by Metropolitan Council
Copies of Draft Facility Plan available for review
Hopkins City Hall Hopkins Library St. Louis Park City Hall St. Louis Park Library Kenwood Community Center Metropolitan Council’s Data Center Three Public Information Meetings Public Hearing Comments will be incorporated into the Final
Facility Plan.
Written comments 02/08/2010
due no later than Full Metropolitan Council 02/24/2010 Approval Submit Facility Plan to MPCA 03/01/2010 MPCA Public Notice of EAW to follow
Facility Plan Approval
Facility Plan ScheduleFacility Plan Schedule
Submit comments no later than February 8, 2010. Submit comments to Tim O’Donnell, MCES Senior
Information Coordinator, by: Email comments to: [email protected] Send written comments to: Tim O’Donnell at
Metropolitan Council Environmental Services, 390 Robert Street North, St. Paul, MN 55101
Fax comments to Tim O’Donnell at 651-602-1477 Record comments on Metropolitan Council Public
Comment Line at 651-602-1500 Send TTY comments to 651-291-0904
Public CommentsPublic Comments