How to Get Resource Loading Histogram/S Curve
in Primavera P6
The resource histogram allows us to use projected and historical actualized data to trend resource quantities, resource hours and
cost in future. It also allows us to determine the potential risks of excessive supply of resources or lack of resourcerequirement.
This tutorial demonstrates how resources allocation chart (histogram/S curve) is produced in Primavera P6. Assume that you havedone Assigned activities and Sequenced activities to see resource loading histogram/S curve bar chart in Primavera P6. After
assigning and sequencing of activities,
(1) Allocate overall resource and their rated cost
(2) Assign resources in activity detail section and
(3) View resource loading histogram/S curve.
1) How to allocate overall resources and cost?
a) Go to Enterprise> Resource>
Note: When you are at Resource, you will see the filter name Current Project Resources If you have already opened a resourceloaded project. See figure below
A blank project resource dictionary only will be displayed if no resource has been added to current project.
https://lh6.googleusercontent.com/-l4yFVp0llk8/TW9eOqtcgJI/AAAAAAAAALQ/PjHFdSUq8bQ/s1600/Project+Resource.jpg8/10/2019 How to Get Resource Loading Histogram-S Curve
2/7
See below image.
b)Add New Resource (Note : If the existing resources are not applicable for a specific project or no resource has been assigned to
current project.You can skip this step if the required resources are available in resource dictionary.)
When you try to add new resource, you will get the message like In order to add resource, the filter will be changed to display al
resources
and you will see all resources for all the projects. New Resource Wizardwill be prompted, and follow the wizard. You wil
be asked to enter the following,
Resource ID,
Resource Name,
Allocate Resource Type (Labor, Non labor and material),
Rate (Price/Unit), Default Units/Time and Max Units/Time,
Contact address if applicable
Resource roles which describes their skills
Resource Calendar
Select Auto- compute if youwant actual units are updated by
Primavera or select Do not auto-
compute actual if you can update
manually for actual man hours spent.
Timesheets set up and log in
After entering of all data, you will
notice that the newly added resources
are not in the desired location.
Therefore, allocate those resources
according to their resource level. For
example, Pipe fitter, Rigger/Signaler,
General worker, Fire watches man,Workshop labor, Painter, etc are
allocated under construction
department of Petrochemical Projects.
See figure below.
https://lh6.googleusercontent.com/-VuUPFXdL5FY/TW9e8uvoTeI/AAAAAAAAALU/ezEOe40DJdg/s1600/Resource+Allocation+in+P6.jpg8/10/2019 How to Get Resource Loading Histogram-S Curve
3/7
8/10/2019 How to Get Resource Loading Histogram-S Curve
4/7
b) You can customize the
appearance of bar chart by
the Resource Usage
ProfileOptions. Right
Clickon the bar chart area to
find Resource Usage Profile
Options
. You can select Bydate to see interval data
(Histogram Chart) and select
Cumulative (S Curve) to see
total manpower unit in the
following check box below.
c) The following check box is
used when you want to show
manpower resource profile
instead of man hour unit. P6
will calculate total men perperiod (interval) based on
working hrs per period
(interval) and total man
hours per period. For
example, total men per week
would be 10 when total man
hours for a week are 400 and
40 working hrs per week.
https://lh4.googleusercontent.com/-R-dW51dJAv8/TW9g6SYT3YI/AAAAAAAAALg/nJdOu6N-8dQ/s1600/Resouce+Usage+Profile+Options-+Graph+in+P6.jpghttps://lh6.googleusercontent.com/-FzF4nvU9LYQ/TW9giijMFFI/AAAAAAAAALc/xl0NBj7toIc/s1600/Resouce+Usage+Profile+Options+in+P6.jpg8/10/2019 How to Get Resource Loading Histogram-S Curve
5/7
d) And then, select all resources in resource column to view overall man power allocation. To print the bar chart, Go to print preview >
page set up > Options > Select Profile and unselect Activity Table, All columns, Grid lines and Gantt chart. Set the time s cale start
from PS-Earliest Project Start to PF-Latest Project Finish. Finally you will see the bar chart as below.
e)According to above bar chart, the
weekly interval manpower is shown on
the left side and total manpower
allocation is on the right side.
f) One of the reason for viewing
resource histogram is to identify
overallocated resources against the
available resources. To view any
overallocated resources in your project,
go to Data tag on "Resource Usage
Profile Options" window, then
select Show Limit and Show
Overallocation. Any resource unit above
the limit line (black line) is over
allocated. Normally, overallocated
resource is shown in red bar
http://3.bp.blogspot.com/-5VGrcTX0Ijg/Ua1YLaJwibI/AAAAAAAAAbI/M1s3Wm6Kv-I/s1600/Overallocated+Resources+in+Primavera+P6.jpghttps://lh3.googleusercontent.com/-VdC9Ksn52Fg/TW9hXnbJCZI/AAAAAAAAALk/sCd2-v2cAK8/s1600/Overall+Manpower+Histogram+in+P6.jpg8/10/2019 How to Get Resource Loading Histogram-S Curve
6/7
How to view Stacked Histogram?
You can also see Stacked Histogram for this manpower allocation.Right Clickon the bar chart area to find Stacked
Histogram.Firstly, click on "Stacked Histogram" tag, and then you can go to "Resource Usage Profile Options" to get screen shot in
step-g. See figure below.
https://lh6.googleusercontent.com/-j7p7IYazCXg/TX4abswFEeI/AAAAAAAAAMM/Mt_v1mzNGvU/s1600/Stacked+Histogram+for+P6.jpghttp://3.bp.blogspot.com/-2-Uhk2vx9XI/Ua1iVAJd3uI/AAAAAAAAAbg/lpB993wUnUg/s1600/Over+allocated+resource+in+P6.jpg8/10/2019 How to Get Resource Loading Histogram-S Curve
7/7
Go to Resource Profile options > Assign Resource Filter/Group Name > Select Total cumulative curve as shown in Figure below.
Finally, you will get Stacked Histogram as shown in below. The stacked histogram represents the manpower allocation by individual
trade/discipline for a particular
period as well as total manpower
allocation (total manpower = 200
men, see the following figure) for all
time . It can be printed the same way
done on item 3, d.
When Stacked histogram is viewed,
one thing to take note is
"Overallocated Resource" can't beidentified on that view. Switch back
to normal histogram by deselecting
"Stacked Histogram" so as to analyse
overallocated resources.
https://lh4.googleusercontent.com/-9ouHixDCVyk/TW9iB2thFsI/AAAAAAAAALs/OLyCdTAre2c/s1600/Stacked+Histogram+in+P6.jpghttps://lh4.googleusercontent.com/-tU_GPz3XIBo/TW9hzfx7ilI/AAAAAAAAALo/8q0Kn0UQaBQ/s1600/Resouce+Usage+Profile+Options+for+Stacked+Histogram+in+P6.jpg