    How to Get Resource Loading Histogram/S Curve

    in Primavera P6

    The resource histogram allows us to use projected and historical actualized data to trend resource quantities, resource hours and

    cost in future. It also allows us to determine the potential risks of excessive supply of resources or lack of resourcerequirement.

    This tutorial demonstrates how resources allocation chart (histogram/S curve) is produced in Primavera P6. Assume that you havedone Assigned activities and Sequenced activities to see resource loading histogram/S curve bar chart in Primavera P6. After

    assigning and sequencing of activities,

    (1) Allocate overall resource and their rated cost

    (2) Assign resources in activity detail section and

    (3) View resource loading histogram/S curve.

    1) How to allocate overall resources and cost?

    a) Go to Enterprise> Resource>

    Note: When you are at Resource, you will see the filter name Current Project Resources If you have already opened a resourceloaded project. See figure below

    A blank project resource dictionary only will be displayed if no resource has been added to current project.

    https://lh6.googleusercontent.com/-l4yFVp0llk8/TW9eOqtcgJI/AAAAAAAAALQ/PjHFdSUq8bQ/s1600/Project+Resource.jpg
  • 8/10/2019 How to Get Resource Loading Histogram-S Curve

    2/7

    See below image.

    b)Add New Resource (Note : If the existing resources are not applicable for a specific project or no resource has been assigned to

    current project.You can skip this step if the required resources are available in resource dictionary.)

    When you try to add new resource, you will get the message like In order to add resource, the filter will be changed to display al

    resources

    and you will see all resources for all the projects. New Resource Wizardwill be prompted, and follow the wizard. You wil

    be asked to enter the following,

    Resource ID,

    Resource Name,

    Allocate Resource Type (Labor, Non labor and material),

    Rate (Price/Unit), Default Units/Time and Max Units/Time,

    Contact address if applicable

    Resource roles which describes their skills

    Resource Calendar

    Select Auto- compute if youwant actual units are updated by

    Primavera or select Do not auto-

    compute actual if you can update

    manually for actual man hours spent.

    Timesheets set up and log in

    After entering of all data, you will

    notice that the newly added resources

    are not in the desired location.

    Therefore, allocate those resources

    according to their resource level. For

    example, Pipe fitter, Rigger/Signaler,

    General worker, Fire watches man,Workshop labor, Painter, etc are

    allocated under construction

    department of Petrochemical Projects.

    See figure below.

    https://lh6.googleusercontent.com/-VuUPFXdL5FY/TW9e8uvoTeI/AAAAAAAAALU/ezEOe40DJdg/s1600/Resource+Allocation+in+P6.jpg
  • 8/10/2019 How to Get Resource Loading Histogram-S Curve

    3/7

  • 8/10/2019 How to Get Resource Loading Histogram-S Curve

    4/7

    b) You can customize the

    appearance of bar chart by

    the Resource Usage

    ProfileOptions. Right

    Clickon the bar chart area to

    find Resource Usage Profile

    Options

    . You can select Bydate to see interval data

    (Histogram Chart) and select

    Cumulative (S Curve) to see

    total manpower unit in the

    following check box below.

    c) The following check box is

    used when you want to show

    manpower resource profile

    instead of man hour unit. P6

    will calculate total men perperiod (interval) based on

    working hrs per period

    (interval) and total man

    hours per period. For

    example, total men per week

    would be 10 when total man

    hours for a week are 400 and

    40 working hrs per week.

    https://lh4.googleusercontent.com/-R-dW51dJAv8/TW9g6SYT3YI/AAAAAAAAALg/nJdOu6N-8dQ/s1600/Resouce+Usage+Profile+Options-+Graph+in+P6.jpghttps://lh6.googleusercontent.com/-FzF4nvU9LYQ/TW9giijMFFI/AAAAAAAAALc/xl0NBj7toIc/s1600/Resouce+Usage+Profile+Options+in+P6.jpg
  • 8/10/2019 How to Get Resource Loading Histogram-S Curve

    5/7

    d) And then, select all resources in resource column to view overall man power allocation. To print the bar chart, Go to print preview >

    page set up > Options > Select Profile and unselect Activity Table, All columns, Grid lines and Gantt chart. Set the time s cale start

    from PS-Earliest Project Start to PF-Latest Project Finish. Finally you will see the bar chart as below.

    e)According to above bar chart, the

    weekly interval manpower is shown on

    the left side and total manpower

    allocation is on the right side.

    f) One of the reason for viewing

    resource histogram is to identify

    overallocated resources against the

    available resources. To view any

    overallocated resources in your project,

    go to Data tag on "Resource Usage

    Profile Options" window, then

    select Show Limit and Show

    Overallocation. Any resource unit above

    the limit line (black line) is over

    allocated. Normally, overallocated

    resource is shown in red bar

    http://3.bp.blogspot.com/-5VGrcTX0Ijg/Ua1YLaJwibI/AAAAAAAAAbI/M1s3Wm6Kv-I/s1600/Overallocated+Resources+in+Primavera+P6.jpghttps://lh3.googleusercontent.com/-VdC9Ksn52Fg/TW9hXnbJCZI/AAAAAAAAALk/sCd2-v2cAK8/s1600/Overall+Manpower+Histogram+in+P6.jpg
  • 8/10/2019 How to Get Resource Loading Histogram-S Curve

    6/7

    How to view Stacked Histogram?

    You can also see Stacked Histogram for this manpower allocation.Right Clickon the bar chart area to find Stacked

    Histogram.Firstly, click on "Stacked Histogram" tag, and then you can go to "Resource Usage Profile Options" to get screen shot in

    step-g. See figure below.

    https://lh6.googleusercontent.com/-j7p7IYazCXg/TX4abswFEeI/AAAAAAAAAMM/Mt_v1mzNGvU/s1600/Stacked+Histogram+for+P6.jpghttp://3.bp.blogspot.com/-2-Uhk2vx9XI/Ua1iVAJd3uI/AAAAAAAAAbg/lpB993wUnUg/s1600/Over+allocated+resource+in+P6.jpg
  • 8/10/2019 How to Get Resource Loading Histogram-S Curve

    7/7

    Go to Resource Profile options > Assign Resource Filter/Group Name > Select Total cumulative curve as shown in Figure below.

    Finally, you will get Stacked Histogram as shown in below. The stacked histogram represents the manpower allocation by individual

    trade/discipline for a particular

    period as well as total manpower

    allocation (total manpower = 200

    men, see the following figure) for all

    time . It can be printed the same way

    done on item 3, d.

    When Stacked histogram is viewed,

    one thing to take note is

    "Overallocated Resource" can't beidentified on that view. Switch back

    to normal histogram by deselecting

    "Stacked Histogram" so as to analyse

    overallocated resources.

    https://lh4.googleusercontent.com/-9ouHixDCVyk/TW9iB2thFsI/AAAAAAAAALs/OLyCdTAre2c/s1600/Stacked+Histogram+in+P6.jpghttps://lh4.googleusercontent.com/-tU_GPz3XIBo/TW9hzfx7ilI/AAAAAAAAALo/8q0Kn0UQaBQ/s1600/Resouce+Usage+Profile+Options+for+Stacked+Histogram+in+P6.jpg