How to Plan, Design & ImplementA Bad Schedule

Lessons Learned: The Scheduler as Generalist

North Florida Section MeetingCanaveral Council of Technical Societies

Cocoa Beach, FL

20 March 2014

John Orr, PSPURS Corporation

Page 2: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

2

Author Biography:  John P. Orr, PSP

• Degrees / Certifications:– BS Chemical Engineering– BA Biology– PSP, Planning & Scheduling Professional,  AACE International

• University:– Bucknell University “Ray, Bucknell …”

• Years of Experience:– 29+ years, beginning in the golden days of yore, when scheduling was still 

performed with IBM punch cards.  Worked for James J. O’Brien, O’Brien‐Kreitzberg& Associates

• Professional Field & Affiliations– Construction Management, including scheduling, cost control, value engineering, 

project administration and claims analysis.– North Florida Section President, AACE International.  Technical Board member.

• Something you do not know about me:– My first logged hours as a student pilot were in a de Havilland Tiger Moth.

Page 3: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

INTRODUCTION:THE PURPOSE OF SCHEDULING

3

Page 4: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

INTRODUCTION ‐ Purposes for the Schedule

4

In the Beginning, there was the CPM Network …

… and afterwards came the CPM Cost Estimate, which did not appear until Chapter 14, page 163.

©McGraw‐Hill, 1971

Primary Purpose:  Planning Tool• To plan and schedule the project work 

sequence,• To support project management 

during the construction phase,• To provide a “road map” for and 

projections of Project Completion.

The focus is on the time element.

Page 5: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

INTRODUCTION ‐ Purposes for the Schedule

5

Enhancements to the Planning Tool:• Long‐lead Procurement activities to schedule delivery dates• Major equipment resources (cranes, hoists) scheduled based 

on the construction activities they support• Work Breakdown by subcontract to allow the efficient staging 

of subcontractors as work areas become available• Cost loading the contract value and projecting (planned) 

expenditures over time• Resource loading of manpower, equipment, trades and 

persons to report (and level) resource curves and peaks• Record‐keeping/Project Documentation for actual dates, log 

records, and costs over time• Productivity calculations developed from resources over time

Page 6: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

INTRODUCTION ‐ Purposes for the Schedule

6

Additional Competing PurposesTo Measure and Manage:

Time CoordinationCost Work OrganizationEarned Value ForecastingResources Financial PlanningRisk Record‐KeepingInformation/Communication Dispute Resolution

• Each individual purpose is well‐intended• Each technique or methodology places new requirements on the Schedule database

• Stakeholders provide different input and usually expect different output and results

Page 7: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

INTRODUCTION ‐ Purposes for the Schedule

7

The Key Role of the Scheduler:To Facilitate Collaboration between the Stakeholders!

Project Managers SuperintendentsCost / Budget Analysts TimekeepersEarned Value Specialists Financial PlannersRisk Analysts VP for EquipmentDesigners Material SuppliersSubcontractors Cost EstimatorsClaims / Dispute Resolution SpecialistsResources / Productivity Evaluation / Future Estimating

Takeaway:  The most common thread of failed projects and slipped schedules is inadequate collaborative planning

Page 8: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

SCHEDULE DEVELOPMENT: PART I ‐ THE PLANNING PROCESS

or:All Prior Planning Should Be 

Done in Advance

8

Page 9: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

SCHEDULE DEVELOPMENT:  Planning

9

• What Can Go Wrong During the Planning Process?– Stakeholder interests vary:

• Some Use Schedules To Plan• Some Use Schedules To Control• Some Use Schedules To Monitor• Some Use Schedules To Generate Progress Payments• Some Use Schedules To Prepare Delay Claims

(Is the schedule badly flawed or deliberately deceptive … you decide!)• Some Use Schedules To Defend Against Claims

One Schedule Cannot Achieve All Ends With Equal Effectiveness!Some Stakeholder Goals and Interests Will Compete or Conflict!

The Scheduler Must Control Schedule Development– Anything that detracts from the primary purpose, a tool to measure time, is 

going to distort the time aspects and invalidate the completion projections

Page 10: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

SCHEDULE DEVELOPMENT:  Planning

10

• The Cost Estimate/WBS and the Planning ProcessThe WBS Approach to Planning can be detrimental– The Cost Estimate and WBS presuppose that every work item is a deliverable

• The Coordination of work items is the key effort in planning• The Schedule is the tool that models how the elements go together

A Focus on Cost Management can be detrimental– Budget, work authorizations, tracking logs, delivery tickets/receiving reports, 

inventory cost coding, schedule of values, earned value management, accounting system and timekeeping input/output strain the schedule

• The Primary Interest of the Scheduler should be in the Project achieving its Time Objectives– Are you a Planner?– Are you a Scheduler?– Are you a Project Controls Professional?– Are you a Forensic Scheduling Claims Consultant?

Page 11: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

SCHEDULE DEVELOPMENT:  Planning

11

• A Bad Schedule Development Scenario:Your business card says that are a Scheduler, 28 years old with a Master’s degree in Construction Management– You are given the Cost Estimate (the winning cost estimate) and the WBS

• Transfer the estimate and WBS into the scheduling software;• Create new activities floor‐by‐floor, or zone‐by‐zone and distribute the hours from the cost estimate and add logic relationships;

• Establish original durations using default crew sizes (or a template from a prior project).  Run the first schedule calculation pass, then use the software’s resource leveling functions to adjust the crew sizes until you get a smooth resource usage curve that completes within the contract performance period.

• Add in the front end mobilization activities (a fragnet from a previous project);• Add in the back end commissioning and closeout activities;• Add procurement of long lead items and link to the initial installation activities• Add constraints to make the bars appear where they belong

What is wrong with this scenario?  The bar chart looks great!

Page 12: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

SCHEDULE DEVELOPMENT:  Planning

12

• What are we missing?Workflow!  Means and Methods!  What schedulers should do best!

– We spent very little time on the core execution schedule elements (scope, duration, relationship)

– We have not focused on the transition points from one trade to another

Disturbing Observations:1. The majority of large commercial and industrial projects finish 

between 5‐10% longer than their planned project length.

2. A study of large infrastructure projects showed an average of 17% time overruns.  (Carson/Palmer Construction CPM Conference Session THU16)

3. Upwards of 90% of all actual durations are within +/– 5% of the original durations.

Page 13: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

SCHEDULE DEVELOPMENT: PART B ‐ THE PLANNING PROCESS

or:Mind the Gap!

13

Page 14: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

SCHEDULE DEVELOPMENT:  MIND THE GAP!

14

• Where do projects lose time?– Process of elimination; if the activity durations are not the culprit …– What is the nature of the transition points (relationships) from one 

activity to another?

Two activities: The Predecessor activity has a 20 day duration, and subcontractor wants it at least 25% complete before he starts his follow‐on:

Relationship link:  SS/+5There is no clear scope associated with this relationship or the duration of the lag factor.There is no reasonableness test we can use to check.

Page 15: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

SCHEDULE DEVELOPMENT:  MIND THE GAP!

15

A Start‐to‐Start/+5 link from Activity A to Activity B:Activity B cannot start until some amount of productive work has been performed on Activity A.

This is the Productive Time GapActivity A [Wash Dishes] may have administrative predecessors:Access to dirty dishes Scrub padDish rack to drain dishes Dish soapSomeone to wash the dishes  WaterActivity B [Dry Dishes] may have administrative predecessors:Access to wet dishes Someone to dry the dishesDishtowel Somewhere to put clean dishes

This is the basis of the Administrative Time Gap

Page 16: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

SCHEDULE DEVELOPMENT:  MIND THE GAP!

16

Failure to perform any of the administrative actions can easily preclude or delay either activity from starting or continuing to completion

The Administrative Time Gap in ConstructionConstruction activity administrative predecessors:

– People to perform the work of the activity– Tools, equipment and materials– A place for the work to occur– Vital information

Example Administrative Time Gap / DelayActivity A – Erect Hollow Metal StudsActivity B – Hang DrywallRelationship  SS/+3 days

Page 17: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

SCHEDULE DEVELOPMENT:  MIND THE GAP!

17

• What does this mean to a scheduler?The daily work of the Project Manager and the Superintendents is often quite independent of the project schedule.  They are frequently focusing on Administrative Gap type items.

The daily priorities of the project management team do not appear to correlate to the priorities reflected in the schedule (indicated by the total float values).

• What value can the scheduler add?Carson/Palmer Worst Scheduling Practice #9 –Inconsistent Level of Detail Between the TradesOrr Addendum: Evaluate the handoffs between the Trades

Page 18: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

Bad Scheduling Practicesor:

What We Learned at the

2014 Construction CPM Conference

18

Page 19: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

Bad Scheduling Practices:  Dick Faris’ Eight Steps Backwards

19

Slipping Backwards – The Devolution of Scheduling:1. Drag and Drop Gantt Charts;2. Misuse of Constraints;3. Lack of Logic Relationships;4. Start‐to‐Start Ladders;5. Bad Durations;6. Improper Use of Lags (and no, he doesn’t know what SF is used for);7. Lack of Training;

… And the worst problem?

8. LACK OF OWNERSHIP BY THE PROJECT PARTICIPANTS[Read:  schedules that satisfy the client, but not the project team]

Page 20: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

Bad Scheduling Practices: Chris Carson/Glen Palmer

20

The Ten Worst Scheduling Practices Used Today:10. Incomplete Scope & Logic – High Float Value activities9. Inconsistent Level of Detail Between Trades8. Misuse of Lag Factors7. Failure to Update Periodically w/in Small Windows6. Failure to Perform Time Impact Analysis of Delays5. Lack of Schedule Risk Management4. Poor Critical Path Analysis / Management3. Lack of Resource Planning2. Adjustments to Logic & Durations to Stay on Schedule1. Failure to Perform Constructability ReviewsCarson/Palmer Construction CPM Conference Session THU16

Page 21: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

Bad Scheduling Practices:  Chris Carson/Glen Palmer

21

The Worst Schedule Development Failures:10. Incomplete Scope & Logic – High Float Value activities9. Inconsistent Level of Detail Between Trades8. Misuse of Lag Factors7. Failure to Update Periodically w/in Small Windows6. Failure to Perform Time Impact Analysis of Delays5. Lack of Schedule Risk Management4. Poor Critical Path Analysis / Management3. Lack of Resource Planning2. Adjustments to Logic & Durations to Stay on Schedule1. Failure to Perform Constructability ReviewsCarson/Palmer Construction CPM Conference Session THU16 (highlighting added)

Page 22: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

CONCLUSIONSFOR

SCHEDULE DEVELOPMENTOR:

WHAT DOES THE YOUNG SCHEDULERTAKE HOME FROM THE CONSTRUCTION

CPM CONFERENCE?AND WHAT DOES SHE TELL HER BOSS? 

22

Page 23: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

Conclusions and Guidance for Schedule Development

23

• But First, a Warning:  The Fallacy of Greater Detail– The law of diminishing returns– One day duration activities are not good scheduling practice

• The Best Advice to a young Lieutenant– Connect with your Sergeants (and Chiefs)– Goal: Prepare schedules that the Superintendents will use– Plan the Work, Work the Plan, Monitor and Revise the Plan– If the PM and Superintendent aren’t using it, Fix it!

• The Schedule is a Model of a Plan– Make sure you understand the plan

• Don’t blame government specifications– Make sure the schedule is the working schedule

Page 24: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

Conclusions and Guidance for Schedule Development

24

• Fight for Prior Planning, Done in Advance– Constructability Reviews– Schedule Risk Workshops – If you can’t obtain them formally, prepare as if you were:

• Add Risk Drivers/impact points to your schedule• Anything that can stop the project should be included

• Understand the Role of the Scheduler as Generalist– Modeling the Plan means modeling the workflow, the transitions between trades, collaboration of suppliers, trades, commissioning agents

– Workflow is the heart of the schedule– The schedule models the entire project scope, including third party impact points and potential drivers that were not included in the cost estimate and WBS

Page 25: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

Conclusions and Guidance for Schedule Development

25

• Avail Yourself of the Resources & Experience of Others– Construction CPM Conference – AACE International Recommended Practices

• Read them• Attend local Section meetings; discuss them• Help write and revise  them

• Remember that the Schedule is Irreplaceable– The external inputs, outputs all require the establishment, monitoring and adjusting of the time element of the project

– None of them work without an accurate schedule• Facilitating the collaboration and compilation of the inputs and experience of the project team is the primary role of the Scheduler.  It is ALL your turf!

Page 26: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

Upcoming Annual Meetings 

– Come to our 2014 AACE International annual meeting at the Sheraton New Orleans!

– Industry focus at the next two annual meetings: • June 15‐18,  2014 – Energy/Oil & Gas – New Orleans• June 28 – July 1, 2015 – Mining – Las Vegas

Page 27: How to Plan, Design Implement A Bad Schedule - … · • Resource loading of manpower, equipment, trades and ... • Establish original durations using default crew sizes (or a template

Questions?