    Course Objectives

    At the end of the course, participant will :

    1) Have detailed knowledge of all hazards with High Pressure Jetting

    2) Understand the principles of water jetting, type of equipment to

    be use and system

    3) Understand the type PPE being use and all the safety precaution

    Video 1

    http://localhost/var/www/apps/conversion/tmp/scratch_5/Video%201%20-%20High%20Pressure%20washer%20500%20Bar%20Rust%20removal%20testing.mp4http://localhost/var/www/apps/conversion/tmp/scratch_5/Video%201%20-%20High%20Pressure%20washer%20500%20Bar%20Rust%20removal%20testing.mp4
  • 8/9/2019 HP Jetting Awareness Rev 0

    2/17

    Definition

    High Pressure Water Jetting (HP Jetting) is :

    the use of high energy streams of water either

    for cleaning, cutting or removal of solidmaterials.

  • 8/9/2019 HP Jetting Awareness Rev 0

    3/17

    Responsibilities

    Operator(s) are responsible to: Attend the HP jetting awareness

    Carry out the job with compliance to all the safety requirement

    Correct PPE to be worn

    Barriers and safety signs are kept in place

    Video 1

    http://localhost/var/www/apps/conversion/tmp/scratch_5/Video%201%20-%20High%20Pressure%20washer%20500%20Bar%20Rust%20removal%20testing.mp4http://localhost/var/www/apps/conversion/tmp/scratch_5/Video%201%20-%20High%20Pressure%20washer%20500%20Bar%20Rust%20removal%20testing.mp4
  • 8/9/2019 HP Jetting Awareness Rev 0

    4/17

    When high pressure water jet cleaning (hydro

    jetting) is in progress, the particular hazards are:

    Piercing of the skin by the water jet,

    Flying debris from the cleaning operations,

    Release of hazardous materials into theatmosphere from dislodged deposits,

    Noise of the cleaning operation that may

    damage hearing or drown out the sound of an

    alarm, Difficulty in breathing in confined space due to

    the high water vapor content in the air

    Electrostatic charging of nozzles and lances.

    Hazard

  • 8/9/2019 HP Jetting Awareness Rev 0

    5/17

  • 8/9/2019 HP Jetting Awareness Rev 0

    6/17

    Precaution

    The following safety precautions shall be observed when high pressure water

    jet cleaning (hydro jetting) is in progress:

    A Supervisor / Leadman shall be designated for controlling all work

    involving hydro jetting and to be onsite when the job is in progress.

    All operating areas shall be barricaded off with suitable barriers to

    prevent accidental entry of any un-authorized personnel.

    Signs to be displayed :

    DANGER HIGH PRESSURE WATER BLASTING, KEEP OUT !!

    AUTHORISED PERSONNEL ONLY.

    Entry into the area must be authorized by the Supervisor / Leadman.

    HP jetting can only be carried out by a team of at least 2 personnel.

  • 8/9/2019 HP Jetting Awareness Rev 0

    7/17

    (Continue)

    All high pressure equipment shall be earthed before work starts and during

    operation, to prevent the development of electrostatic charges between

    the lance and the workplace.

    Appropriate personal protective equipment shall be worn when operating

    high pressure water jet equipment.

    These PPE must be worn :

    Safety Helmets

    Safety goggles or a full hood with face shield

    Waterproof clothing

    Hearing protection

    Suitable Safety gloves, and safety footwear X

    Precaution

    Note : Safety Glasses are Not suitableVideo 3

    Video 2

    http://localhost/var/www/apps/conversion/tmp/scratch_5/Video%203%20-%20Fluid%20Injection%20Injury%20-%20YouTube.mp4http://localhost/var/www/apps/conversion/tmp/scratch_5/Video%202%20-%20Safety%20at%20work%20-%20Water%20Jetting%20boots%20damaged%20by%20high%20pressure%20water%20-%20YouTube.mp4http://localhost/var/www/apps/conversion/tmp/scratch_5/Video%202%20-%20Safety%20at%20work%20-%20Water%20Jetting%20boots%20damaged%20by%20high%20pressure%20water%20-%20YouTube.mp4http://localhost/var/www/apps/conversion/tmp/scratch_5/Video%203%20-%20Fluid%20Injection%20Injury%20-%20YouTube.mp4
  • 8/9/2019 HP Jetting Awareness Rev 0

    8/17

    (Continue)

    All high pressure equipment shall be isolated and de-pressurized before

    being left unattended.

    Correct Safety Instruction shall be provided before use the equipment

    Ensure the area are free from any loose items and debris to avoid

    dangerous flying projectile(s).

    Operator must have good access to the work site

    Always use Safe Working Platforms and Do Not Use Ladders for the work

    Precaution

  • 8/9/2019 HP Jetting Awareness Rev 0

    9/17

    (Continue)

    All personnel involved with the water jetting operation must be in position

    prior to start up

    The pressure at the unit should be built up gradually. The lowest pressure

    necessary to complete the job should be use.

    Precaution

  • 8/9/2019 HP Jetting Awareness Rev 0

    10/17

    Worker ID Card

    Any person injured by high pressure

    water jetting must be taken to hospital for

    immediate attention, Medical Staff must be

    informed caused of injury was the result of

    high pressure jetting.

    This card must be carried at all times

    when they are working.

  • 8/9/2019 HP Jetting Awareness Rev 0

    11/17

    Checks To Be Made

    1. Hoses must have the correct rating and size, where hoses must be higher

    rating than the pressure pump.

    2. All fittings and couplings must be in good condition and correct pressure

    rating3. Hoses, fitting and nozzles must be checked for signs of damage or wear.

    Any leaks must be rectify before work begins

    4. Hose protectors / Whip-lashes must be in place

    5. Hoses must be located to avoid being run over by vehicles or causing triphazards

    6. Hoses (with Nozzle) must be secured under the armpit before operation of

    high pressure water jetting machine.

    Hoses

    Video 4

  • 8/9/2019 HP Jetting Awareness Rev 0

    12/17

    1. A valid Permit To Work is in place.

    2. If the job carried out in Confined Space, all the

    necessary precaution must be incompliance.

    3. A minimum of two person to carry out the job

    Permit To Work

    Checks To Be Made

  • 8/9/2019 HP Jetting Awareness Rev 0

    13/17

    1. The equipment has been inspected and certify by third party inspection

    2. Lube oil, water and hydraulic fluids has been check and the gauge level

    are correct.

    3. Pressure gauge must function properly4. Repair and maintenance shall be in accordance with manufacturers

    standards, and to be done by a competent mechanic.

    Compressor and Pump

    Checks To Be Made

  • 8/9/2019 HP Jetting Awareness Rev 0

    14/17

    1. Nozzle must be clean and no signs of debris or damage

    2. Jetting guns trigger mechanism must be working correctly

    3. Connector part must be in good condition

    Jetting lance and nozzles

    Checks To Be Made

  • 8/9/2019 HP Jetting Awareness Rev 0

    15/17

    1. Any electrical part has been inspected Any electrical parts must be

    protected from water splash or mist

    2. All the switch and gauge must function properly

    3. Emergency Stop Button must function properly

    Electrical Parts

    Checks To Be Made

  • 8/9/2019 HP Jetting Awareness Rev 0

    16/17

    Before starting the work, team members will agree on a code signals ormeans of communication to be use during operation.

    Communication

  • 8/9/2019 HP Jetting Awareness Rev 0

    17/17

    Questions