HR WM 01 February SR I 2009s11Indian Power Scenario Revised

Embed Size (px)

Citation preview

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    1/45

    INDIAN POWER SCENARIOINDIAN POWER SCENARIO

    PAST,PRESENT,FUTUREPAST,PRESENT,FUTURE

    ByByJITENDRA KUMAR BALJITENDRA KUMAR BAL

    CHIEF MANAGER (HRD)CHIEF MANAGER (HRD)POWERGRIDPOWERGRIDEDC, HYDERABADEDC, HYDERABAD

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    2/45

    INDIAN POWER SYSTEM GROWTHEVOLUTION

    Installed capacity growth from 1349MW in 1947to 140GW by 2007 and 210 GW by 2012

    Transmission system transformed from isolatedsmall grids to state grids and inter state grids.

    Formation of state grid in 1960s

    Formation of Regional grids in 1970s

    Asynchronous interconnection of regional gridsin1990s

    Towards formation of National grid from 2000 onwards

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    3/45

    INDIAN POWER SYSTEM SIGNIFICANT

    PARAMETERS AS ON 30.06.08

    14.75%All India Deficit April to June 08

    89602 MWDemand met (April-07)

    104007 MWAll India Peak demand (April-07)

    154230Villages yet to be electrified

    606 units/yearPer capita consumption (04-05)

    74:26Thermal Hydro Mix

    1 44 913 MWTotal Installed capacity (Present)

    Thermal 92565 MW

    Hydro - 36033 MW

    Nuclear - 4120 MW

    RES - 12194 MW

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    4/45

    PER CAPITA CONSUMPTION A

    COMPARISON

    431 unitsPakistan

    606unitsIndia

    1651unitsChina

    5710 unitsUK

    10905 unitsAustralia

    12250 unitsUS

    3012units per annumWorld average per capitaconsumption

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    5/45

    INDIAN POWER SYSTEM VILLAGES

    YET TO BE ELECTRIFIED

    Total No. of Villages : 593732

    Villages Electrified : 439615

    %Villages Electrified : 74%

    Villages yet to be Electrified : 154117

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    6/45

    INDIAN POWER SYSTEM

    TRANSMISSION NETWORK

    5872ckmHVDC

    110916ckm220kV

    70565ckm400kV

    2013ckm765/800kV

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    7/45

    SOUTHERN REGION POWER SYSTEM

    AT GLANCE As on JUNE 08

    ALL INDIA INSTALLED CAPACITY

    NR ---- 38237 MW

    WR ---- 44768 MW

    ER ----- 19809 MW

    SR ---- 39656 MW

    NER --- 2366 MW

    ISLANDS- 76 MW

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    8/45

    SOUTHERN REGION POWER SYSTEM

    AT GLANCE As on April 08

    INSTALLED CAPACITY IN SOUTHERN REGION

    AP - 9455 MW

    KARNATAKA - 7672 MW

    TAMILNADU - - 10846 MW

    KERALA - - 2311 MW

    PONDY - 33 MW

    CGS - 9340 MWTOTAL - 39656 MW

    GROSS DEMAND MET - 25714 MW

    GROSS UNRESTRICTED REQ IN SR- 26737 MW

    DEFICIT - 1023 MW May 08.

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    9/45

    ER

    SR

    NR

    HVDC BACK TO BACK LINKS

    Evolution of National Grid

    1.VINDYACHAL

    2.CHANDRAPUR

    3.GAZUWAKA4.SASARAM

    Stage I NationalGrid completed

    Interlinking all the

    Regions with HVDC

    Back to Back links.

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    10/45

    ASYNCHRONOUS LINKS Part of National Grid

    NER

    ER

    SR

    NRNER

    ER

    SR

    NRRIHAND-DELHI -- 1500 MW

    CHANDRAPUR-PADGE 1500 MW

    TALCHER-KOLAR 2000 MW

    SILERU-BARASORE - 100 MW

    HVDC BTB VINDYACHAL 500 MW

    HVDC BTB CHANDRAPUR 1000 MW

    HVDC BTB VIZAG - 500 MW

    HVDC BTB SASARAM - 500 MW

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    11/45

    SOUTHER

    N REGION

    WESTERN

    REGION

    EASTERN

    REGION

    NORTHERN

    REGION

    NORTH-

    EASTERN

    REGION

    1

    2

    3

    With the

    commissioning of

    Raipur-Rourkela

    between WR and ER

    during March 2003,

    Indian power system

    operating in three

    electrical Regions.

    3 ELECTRICAL

    REGIONS

    EVOLUTION OF NATIONAL GRID

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    12/45

    SOUTHE

    RN

    REGION

    WESTER

    NREGION

    EASTERN

    REGION

    NORTHER

    N REGION

    NORTH-

    EASTERN

    REGION1

    2

    With theCommissioning of

    the Tala

    Transmission

    system during Oct

    06 the E.R ,W.R and

    N.R Grids weresynchronised and

    Indian Power

    systems is

    operating on Two

    Electrical Grids.

    2 ELECTRICAL

    REGIONS

    EVOLUTION OF NATIONAL GRID

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    13/45

    POWER SYSTEM 2012 Target Installed capacity growth from 140GW in

    2007 to 210GW in 2012.

    Transmission system voltage up gradationfrom 400kV to 765KV for HVAC systemsand from 500kV to 800kV for HVDCsystems.

    Enhancement in Inter Regional powertransfer capacity from the present 13700MW to 37000MW in 2012.

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    14/45

    POWER SYSTEM 2012 Target

    ESTABLISHMENT OF ULTRA MEGA POWER PLANTS WITHASSOCIATED TRANSMISSION SYSTEM

    MUNDRA GUJARAT 4000 MW BY TATAS-WORK COMMENCED SASAN M.P - 4000 MW BY RELIANCE-WORK COMMENCED.

    KRISHNAPATNAM-AP- 4000 MW.- BY RELIANCE

    TILAIYA JHARKAND 4000 MW ---Bids yet to be opened.

    GIRYE MAHARASTRA 4000 MW TADRI KARNATAKA --- 4000 MW

    AKALTARA CHATTISGARH 4000 MW

    7 such Power plants (28000 MW) of above size are planned to be taken up inthe entire country during NEXT 7 YEARS .

    2 more plants identification is under progress by PFC. In T.N , Orissa

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    15/45

    POWER SYSTEM 2012 Target

    KRISHNAPATNAM- TRANSMISSION SYSTEM 3 * D/C lines 400 KV QUAD MOOSE

    (One D/C to Kurnool , One DC To Nellore and One D/Cto Gooty )

    765 kV line from Kurnool to Raichur 765 kV 2 S/C from Raichur to Sholapur 765 kV sub stations at kurnool & Raichur with 3000

    MVA transformation each. (Single phase Transformerseach 500 MVA)

    . LINE REACTORS OF EACH 240 MVAR at either end.(1 Ph 80 MVAR)

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    16/45

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    17/45

    POWER SYSTEM VISION 2022

    Installed capacity at 600GW Likely additions

    Hydro :80GW

    Coal based :80GW

    Coastal :90GW (Imported fuel) Nuclear :90GW

    Distributed Gen :50GW

    Next five decades Nuclear power predominates

    upto 35 % total power generated by 2050.

    By 2050 11 to 12 Lakhs MW required and 3 lakhs MWfrom Nuclear.

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    18/45

    POWER SCENARIO BEYOND 2025

    Peak Demand : 450000MW

    Installed capacity :600000MW

    Inter Regional capacity :140000MW

    Need to go for super grid with transmissionvoltage level: 1200kV UHVAC & 800kV

    HVDC

    Support Tr. Network:

    765kV EHVAC and 500kV HVDC Sub Transmission network :

    400kV HVAC Transmission system

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    19/45

    2025 Hierarchy of Transmission &

    Distribution

    1200kV UHVAC

    765kV EHVAC

    800 kV UHVDC

    Distribution TransmissionSub transmission

    66/ 33kV AC

    11kV AC

    0. 4 kV AC

    400kv

    132 Kv

    220 kv

    ICTICT

    Generatingstations

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    20/45

    Grid Operation 2025 Major

    challenges

    Reactive power Management

    1200kV UHVAC line generates about

    6MVAR/KM

    400kV HVAC line generates about 0.55

    MVAR/KM

    High short circuit levels (70-100KA)

    1200kV UHVAC line generates about 6MVAR/KM

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    21/45

    SASARAM

    SIPAT

    DHULE

    SOLAPUR

    PUNE

    LAKSHADWEEP

    ITARSI

    BINA

    WARDHA

    RAICHUR

    INDORE

    SEONI

    SATNA

    SASAN

    KOTA

    JAIPUR

    AGRA

    MOGA

    MUNDKA

    GWALIOR

    KISHENPUR

    TEHRI

    LUCKNOW

    FATEHPUR

    BAREILLY

    MEERUT

    NICOBAR

    1200KV UHVAC LINES

    765KV EHVAC LINES

    800kV HVDC BIPOLE

    LEGEND

    NKSTPP

    RANCHI

    ANDAMAN&

    GAYA

    BALIA

    B'CHARYALI

    POOLINGANGUL

    AURANGABAD

    RAIGARH POOL

    RAIPUR POOL

    JABALPURPOOL DHARAMJAYGARH

    SAWAI M'PUR

    SIKAR

    BARNALA

    JALANDHAR

    BARODA

    SUPER GRID /HYBRID GRID

    APPILCATION TOTHE TUNE OF

    1.00 Lakh MW CapacityAddition in LTOANOW ITSELF

    REQUIREMENT OF

    INTELLEGENT GRID

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    22/45

    INDIA IS DIVIDED INTO 5 ELECTRICALREGIONS TO FECILITATE

    BETTER GRID MANAGEMENT

    ELIMINATION OF TOTAL BLACK OUTS

    QUICK RESTORATION IN THE EVENT OF

    FAILURES.

    OPERATION OF REGIONAL GRIDS WITH SOUND

    COMMERCIAL PRINCIPLES

    NATIONAL GRID OPERATION

    PRESENT PRACTICE

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    23/45

    GRID MANAGEMENT & LOAD DISPATCH

    CENTERS

    N L D C

    NRLDC ERLDC SRLDC WRLDC NERLDC

    APTRANS KPTCL TNEB KSEB PONDYCPCC

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    24/45

    RLDC - FUNCTIONS

    Monitoring of system parameters and Grid security. To ensure the integrated operation of theRegional

    Grids

    System studies, planning and contingency analysis.

    Analysis of tripping/disturbances and facilitatingimmediate remedial measures. Daily scheduling and operational planning.

    Facilitating bilateral and inter-regional exchanges. Computation of energy despatch and drawal values

    using SEMs.

    Augmentation of telemetry, computing andcommunication facilities

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    25/45

    RLDC MAJORACHEIVEMENTS

    Improved system parameters ever sincethe implementation of Availability basedtariff.

    Sharp decline in the Grid disturbances. High system security & redundant

    system operation with theimplementation of real time data

    acquisition system. Ease in commercial accounting system

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    26/45

    AVAILABILITY BASED TARIFF -- ABT

    1. IT IS A THREE PART TARIFF SYSTEM

    a) Fixed/Capacity charges for the Generator

    b) Energy Charges

    c) Charges for Deviation which is frequency linked (UI)

    2. Normal frequency range 49.0 to 50.50 Hz

    3. UI charges The generating station has to abide by the

    declaration of availability on each day .If Generator generates

    less than declared at low frequency , the generator is

    penalised. If the deviations are above High frequency side the

    generator will not be entitled for payment.

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    27/45

    AVAILABILITY BASED TARIFF -ABT

    The UI rate varies according to the frequency prevailing in the grid

    745

    UI rate in paise/Unit

    337

    228

    0

    49 49.5 49.8 50.5

    Frequency in HzTotal Payment for the day = Capacity charges + Energy charge UI char

    9 Paise/Kwh for 0.02 Hz

    16 paise/Kwh for 0.02 Hz step

    6 Paise/Kwh for 0.02 Hz

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    28/45

    IMPLIMENTATION OF ABTSR 01.01.2003

    WR 01.07.2002

    NR 01.12.2002

    ER 01.04.2003

    NER 01.04.2007

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    29/45

    Reactive Energy charges :To control the voltage in the grid additional charges in the form of

    Reactive energy charges are also charged

    a. Payable for i) VAR drawl at voltage below 97 % of Voltage level

    ii) VAR injection at voltage above 103 %of voltage level

    b) Receivable for i) VAR injection at voltage below 97% of Voltage

    ii) VAR drawl at voltages above 103 % of voltage level

    c) Applied for VAR exchanges between i)Beneficiary system and

    ISTS through pool account ii) Two beneficiary systems oninter state ties by themselves

    Reactive Energy charges are @ 4 paise/KVARh with an escalation

    5 % per year.

    AVAILABILITY BASED TARIFF -ABT

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    30/45

    ADVANTAGES OF ABT

    -- FACILITATES GRID DISCIPLINE

    -- FACILITATES TRADING IN CAPACITY AND ENERGY

    -- FACILITATES MERIT ORDER DESPATCH AS AND

    WHEN MADE EFFECTIVE

    -- IMPROVED FREQUENCY AND VOLTAGE

    -- ECONOMIC DESPATCH

    AVAILABILITY BASED TARIFF -ABT

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    31/45

    FREQUENCY COMPARISION

    Jan 02 & Jan 03

    AVAILABILITY BASED TARIFF -ABT

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    32/45

    FREQUENCY COMPARISION

    Feb 02 & Feb 03

    AVAILABILITY BASED TARIFF -ABT

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    33/45

    Feb 02 & Feb 0374

    53

    72 1 0

    3 40 0 0 0

    0

    20

    40

    60

    80

    100

    2001-02 2002-03 2003-04 2004-05 2005-06 2006-07

    Year

    GridDisturbances

    Minor

    Major

    Minimum Grid disturbances after ABT

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    34/45

    DEFINITION OF OPEN ACCESS INTHE ELECTRICITY ACT, 2003

    The non-discriminatory provision for the use of

    transmission lines or distribution system or

    associated facilities with such lines or system byany licensee or consumer or a person engaged

    in generation in accordance with the regulations

    specified by the Appropriate Commission

    CERCs Order on Open Access is effective from

    06.02.2004

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    35/45

    Salient Features of CERC Order/Regulations

    Open Access customers categorised :

    Short-Term - Upto One year.Long-Term - Twenty Five years or more

    All Open Access customers to abide by IndianElectricity Grid Code.

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    36/45

    NODAL AGENCY FOR OPEN ACCESS

    For Short-Term Customers

    RLDC of the Region in which the drawal point is

    located.

    For Long-Term Customers

    Central Transmission Utility (CTU)

    STU of the region in which the drawal point is

    located when CTU system is not involved.

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    37/45

    POWERGRID AT GLANCE

    MISSION : Establishment and operation of Regional and

    National Power Grid to facilitate transfer of

    power within and across the regions with

    Reliability, Security and Economy on sound

    commercial principles.

    Total length of transmission lines ---- 68035 Ckt Km

    Total no. of 400 kv/220kv/132 kv S/S 113 Nos

    Total transformation capacity --- 74382 MVA as on 30.05.08

    Transmission system availability -- > 98.5 %

    First power utility to get ISO-9001 certificate

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    38/45

    POWERGRID SOUTHERN REGION

    AT GLANCE As on 01.04.08

    1No. of 220kV GIS sub station

    1No. of HVDC Terminal stations2

    No. of HVDC Back to Back links

    23No. of 400kV sub stations

    4000 MWInter Regional Transfer capacity

    10008 MVATotal Transformation capacity

    11176.26 Ckt km

    2016 Ckt km

    Total Transmission network

    - 400kV HVAC

    - 500kV HVDC

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    39/45

    ABOUT POWERGRID

    POWERGRID HAS EXPERTISE IN THE FOLLOWING

    UPTO 800 KV AC SYSTEMS

    500 KV HVDC SYSTEMS GAS INSULATED SUB STATIONS

    STATIC VAR COMPENSATORS

    SERIES COMPENSATION

    CONTROLLED SHUNT REACTORS

    FLEXIBLE AC TRANSMISSION SYSTEM

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    40/45

    ABOUT POWERGRID

    CONSULTANCY WORKS AT ABROAD

    Construction of 220 KV , 200 KM long Transmission

    linein Afghanistan which is at a height of 4000 Mts above

    sea level with snow for 9 months.

    Execution of Optical Fibre network / Transmission

    system in Bhutan.

    Construction of 400KV GIS and associated

    transmission network at Dubai

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    41/45

    MAJOR ACHIEVEMENTS & CHALLENGES

    1. ESTABLISHED ASYCHRONOUS NATIONAL GRID

    WITH THE HELP OF HVDC LINKS/ HVDC

    TRANSMISSION

    2. ESTABLISHED UNIFIED LOAD DISPATCH SCHEMES

    IN SR,NR,ER. ULDC WORKS ARE UNDER PROGRESS

    IN WR

    3. ESTABLISHMENT OF SYNCHRONOUS NATIONAL GRIDBY 2012

    4. ESTABLISHMENT OF NATIONAL BACKBONE

    TELECOM NETWORK

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    42/45

    MAJOR ACHIEVEMENTS & CHALLENGES

    5. STRENGTHENING OF DISTRIBUTION SYSTEM AND

    RURAL ELECTRIFICATION OF 87300 VILLAGES

    IN 68 DISTRICTS OF 9 STATES.

    6. INVESTMENT TO THE TUNE OF Rs 70,000 CRORES

    ENVISAGED BY 2012

    7. SETTING UP OF SUPER GRID AND HYBRID GRID

    BEYOND 2017

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    43/45

    UNIFIED LOAD DISPATCH SCHEMES ULDC

    POWERGRID IMPLEMENTED LOAD DISPATCH ANDCOMMUNICATION SCHEMES THROUGH OUT COUNTRY

    ER, NR,SR ULDC SCHEMES ARE COMPLETED AND

    PRESENTLY UNDER OPERATION

    BENEFITS OF ULDC

    ECONOMIC DISPATCH OF POWER AMONG THE

    REGIONS/STATES ON REAL TIME BASIS.

    EFFECTIVE MONOTORING OF REAL/REACTIVE POWER

    FLOWS AND AVOIDS GRID DISTURBANCES

    NLDC IS UNDER FINAL STAGE OF COMPLETION

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    44/45

    TELECOM NETWORK

    1. POWERGRID ESTABLISHED TELECOM BACKBONE

    NETWORK OF ABOUT 14000 KMS TO CONNECT 56 CITIES

    2. OUT OF 14000 KM ,-- 10 000 KM ARE WITH OPGW AND

    4000 KM WITH OPTIC FIBRE CABLE

    3. 56 CITIES SHALL BE CONNECTED TO TELECOM

    NETWORK IN 1ST PHASE.

    4. PRESENTLY TELECOM ROUTES ARE UNDER OPERATION

    A, DELHI MUMBAI

    B. DELHI CHANDIGARH

    C. DELHI -- JAIPUR

  • 8/2/2019 HR WM 01 February SR I 2009s11Indian Power Scenario Revised

    45/45