HRIS v20 Project: updating
software and infrastructure
to bring business benefits
Anne Harkness, Amber Georgeson and
Mandy Zaccheo
Personnel Services & IT Services
Tuesday 24 March 2015
What are we doing and why?
• Implementing v20 software and 11g database
• Fully supported infrastructure and software
• Improvements sought by users
• Enable future projects
• Standard infrastructure on which to build DR plans
PROJECT SCOPE AND TIMEFRAMES
Scope: functional, training & communications
• Implementation and full Functional Testing of version 20* of the CoreHR
application including :
• CorePay, CorePersonnel, CoreTraining, CoreRecruit, CoreHESA, Core BI,
Core User Security, Absence, (Portal - ESS)
• Document management (Aspose)
• Review of data impact of v20 including ensuring appointment IDs can be
populated for all payroll tables with no loss of historic data
• Current reports and customisations
• Review of new V20 functionality vs user enhancement list
• Communications, train c. 400 users, new v20 training & QRGs
Project overview
Stage Proposed Dates
Investigation/analysis May - December 2014
Business case approval December 2014
Project preparation January 2015
Project kick-off February 2015
System review & test prep February - March 2015
Functional testing April - May 2015
User Acceptance Testing June 2015
Non functional testing May - August 2015
Parallel run September / October 2015
Go-live November 2015
Early life support Two months from Go-Live
Key Milestones Project Manage- ment Functional Team inc Business Change & Comms Test Team Technical & Service Transition Core HR
HRIS V20 – HIGH LEVEL PLAN v0.13A 09/03/15
2015 Sep Oct Feb Mar Apr May Jun Nov Jul Aug
LIVE & SUPPORT PREPARATION TESTING PARALLEL
RUNs
Month 1 2 3 4 5 6 7 8 9 10
GO LIVE PREPARATION
Regression / UAT Support & Data Cleansing Support (inc Issue/Bug Resoluion)
Post Go Live
Support
Handover to Live Support
Support Activities
Build Activities
Project Management / Reporting / Resourcing
Project Management Reporting and Controls Project Close/ Post Go Live
Support
G 1 Ready to Test G 2 End of Func Testing G 3 End Testing G4 Go Live/P Run start
UAT
Reports, Interfaces & End to
End processes
Business Change Activities Preparation for Regression and User Acceptance Testing
Go Live Preparation
Communications Activities
Non Functional Testing
Including SSO, OAT, Perf, Penetration, DR under the
Service Providers as at Go live
Technical Preparation Activities
Training Preparation
Payroll Parallel Runs
Regression Testing
Test Prep
Technical Test Management System Integration Testing
Service Transition
Technical Architect / Technology
Service Transition Andrew Byerley
Reporting Amber Georgeson
Core HR Tommy Dunne
Project Management Amber Georgeson
Testing & Change Management Andrew Goff
Functional Workstream
Les Hewkin
• Delivery
Coordination
• Workshop Facilitation
• Data Change/ Cleanse
• HR & Payroll Test & Business Support
• Issue Identification & Resolution
Technology Delivery
John Toone
• Delivery
Coordination
• Architecture Design Authority
• Systems Integration
• Configuration, and release mgt
• NFT/DR/OAT
• Service Design
Change/ Communication/
Training Mandy Zaccheo
• Delivery
Coordination
• Business Change
• Process & Policy
• Stakeholder Comms
Project Sponsor: Julian Duxfield
HESA Payroll
Personnel Letters Recruit-
ment Training
CoreTime Reporting Security
Sysadmin
HRIS V20 Project Team - Workstreams
Functional, Business Change and Communications
Training Neil Hart
• Training
KEY CHANGES, BENEFITS AND IMPLICATIONS FOR USERS
Applicants and e-Recruitment
• Applicants:
• Ability to forward the URL
• Back button to take applicant back to vacancy search
results
• Jobs by email
• e-Recruitment:
• PDF pack creation – more robust
• ‘foreign characters’ (diacritics) issue fixed
• Inbuilt supporting statement functionality
• Online reference functionality
Personnel (1)
• Comments field added to allowance screen
• Cost allocations visible on salary approvals
• Address maintenance - effective dates to build a
history
• Substantive appointments and exact match:
• Ending substantive appointment where multiples exist -
much easier
• Unique appointment ID on all data items - addresses
data quality and reporting issues
Personnel (2)
• Weeks per year field (automates term time FTE)
• Rules-based continuous service dates
• Templates no longer stored on C drive
• Read only access to Appointment Details
• Direct appointments - gender defaults to unknown
Implications for users
• Training - minimal mandatory training and a low time
commitment
• QRGs - updated to reflect v20
• Webpage and monthly updates for users
• Briefings in preparation for go-live
QUESTIONS?