HSE External Report suai airport - December 2014

Embed Size (px)

Citation preview

  • 8/18/2019 HSE External Report suai airport - December 2014

    1/24

    December2014

    PT. Waskita Karya (Persero) Tbk

    Upgrading of Existing Suai Airport Project

    December 2014

    Health & Safety Monthly Report 

  • 8/18/2019 HSE External Report suai airport - December 2014

    2/24

    Health & Safety Monthly Report    December 2014

    1

    VALIDATION SHEET

    Health & SafetyREPORT

    UPGRADING OF EXISTING SUAI AIRPORT PROJECT

    PERIOD : DECEMBER 2014 (Nov 24 – Dec 15)22 Wor ing Days

    Verify by,

    Contractor

    PT. Waskita Karya (Persero) Tbk

    Ir. Sugiharto

    Project Manager

    Prepared by,

    Contractor

    PT. Waskita Karya (Persero) Tbk

    Dannys S.W

    HSE Officer

    Reviewed by, Approved by

    Consultan Supervisor Minister of Transportation & Communication

    Ir. Dahlim Mungkil Mr. Pedro Lay de Silva

    Project Manager Client

  • 8/18/2019 HSE External Report suai airport - December 2014

    3/24

    Health & Safety Monthly Report    December 2014

    2

    Table of Contents

    I. Waskita Policy..................................................................................................................... 3

    II. Executive summary............................................................................................................. 4

    III. General...............................................................................................................................   4

    IV. Project HSE Plan.................................................................................................................   4

    V. Organization Chart.............................................................................................................   5

    VI. Health Performance

    a. Complaining of Disease..........................................................................................  5

    b. Occupational disease.............................................................................................. 5

    c. Referral case..........................................................................................................

      5

    VII. Safety Performance

    a. Manpower..............................................................................................................   6

    b. Man Hours..............................................................................................................  7

    c. ncident Record........................................................................................................ 8

    d. Hazard Report......................................................................................................... 9

    e. Inspection...............................................................................................................   10

    f. Traffic safety, sign and control............................................................................... 11

    g. Temporary drainage ..............................................................................................

      12

    h. Flight Intensity Report............................................................................................ 13

    i. HSE Meeting...........................................................................................................   15

    VIII. Conclusion.......................................................................................................... 17

    IX. Documentation.................................................................................................. 19

  • 8/18/2019 HSE External Report suai airport - December 2014

    4/24

    Health & Safety Monthly Report    December 2014

    3

    I. Waskita Policy

    Waskita PolicyPT Waskita Karya (Persero) Tbk as the Agency for Construction Services always

    control the risk to Safety - Occupational Health, Environment, Quality and

    Security Management System by implementing Waskita to the satisfaction of 

    stakeholders.

    As part of this commitment, management always:

    1. Comply with laws and regulations and other applicable requirements.

    2. Improving performance on an ongoing basis.

    3. Prevent injury, occupational illness, environmental pollution and the

    occurrence of security incidents that affect the company's business

    processes.

    4. Providing training, providing a healthy and working facilities, safe and

    convenient to all stakeholders.

    Jakarta, October 24, 2013

    President Director,

    Ir. M. Choliq, M.M.

  • 8/18/2019 HSE External Report suai airport - December 2014

    5/24

    Health & Safety Monthly Report    December 2014

    4

    II. Executive Summary

    This report records the Health and Safety activities of Waskita Karya (Persero) Tbk. Especially

    Unpgrading of Existing Suai Airport Project for the months of December 2014.

    III.General

    In carrying out a job, health and safety issues are important factors that should be the

    primary concern of all parties. Our success in executing the work not only measured from

    the completion of the job. Many things can be used as a parameter assessment of the

    success of a job. The work was considered successful if the health and safety of all existing

    resources is assured, can be completed on time or even earlier than the time specified,

    provide benefits to the company, to give satisfaction to all parties (management, employees

    and employers).

    Health and safety issues are very important, since the establishment of health and safety

    at work means can reduce operating costs. If in performing the work of an accident, it will

    increase the cost of expenditure, which finally reduces the profits of the company. In the

    case of a severe accident, the losses are not only related to financial aspects (funding), but it

    can cause defects in the worker or even death.

    Construction work contains a lot of potential to pose a risk of occupational accidents,

    occupational diseases, environmental pollution, and the discrepancy in the quality of work.

    And not least in the Upgrading of Existing Project Suai Airport.

    IV. Project HSE Plan

    Current Revision : Rev2/ July 2014

    Status : Approved by Engineer (JPZ)

    Comments : -

    Suggested changes and : -

    Enhancement

  • 8/18/2019 HSE External Report suai airport - December 2014

    6/24

    Health & Safety Monthly Report    December 2014

    5

    V. HSE Organization Chart

    VI. Health Performance

    a. Complaining of Disease

    Increased rainfall in the December can increase the risk of the disease.

    complaining of pain that will increase still around influenza, cought and

    fatigue. medications has been available on site.

    b. Occupational Disease

    There is no Occupational diseases during PT. Waskita Karya (Persero) Tbk.

    carrying out construction and campaigns on the prevention and control will

    continue to be gradual when the health and safety talk.

    c. Referral Case

    There is no referral case on December 2014

  • 8/18/2019 HSE External Report suai airport - December 2014

    7/24

    Health & Safety Monthly Report    December 2014

    6

    VII. Safety Performancea. Man power

    Total Waskita Karya (Persero) Tbk. There is no increased from the

    previous period as many as 26 people. PT. WTJ (Subcontractor) with rentalequipment, additional manpower has increase 4 personell for this month.

    Especially in the foreman as a whole will continue to increase with the

    progress of the work. Total employees working in Waskita Suai Airport

    Project site as many as 144 people overall.

    Table VII.1

    Table of Manpower On Suai Airport Project

    Description August-14 Sep-15 Okt-15 Nov-15 Dec-15

    PT Waskita Karya   24 25 25 26 26

    Daily personel

    Ass.survey 4 4 4 4 4

    Airport 6 6 6 6 6

    Basecamp 7 10 12 12 19

    Security 9 9 9 9 9

    Equipment 2 3 4 5 7

    Total   52 54 56 62 72

    PT WTJ   15 16 16 21 25

    PT. Tugu Beton   3 3Total   67 70 72 86 99

    Table VII.2

    Table of additional manpower / workmanship on December 2014

    Workmanship Personel

    Main drain Right 7

    Main drain Left 15

    Cutting trees 4

    Steel Fabrication/ Quarter 8

    RCP AFRS 8

    Basecamp facilities 18

    Total   45

  • 8/18/2019 HSE External Report suai airport - December 2014

    8/24

    Health & Safety Monthly Report    December 2014

    7

    Picture VII.1

    Total Man power on Suai Airport Project

    b. Man Hours

    The number of manhours until December 15th 2014 amounted to

    24.290 hours of work and working hours Increase compared to the previous

    period. due to along with increasing intensity of work on site and there is no

    time lost working hours due to an accident on this month,   total cumulativehours of work until now of 104.954 hours and no Loss Time Injury and

    fatality (Start from May 1st). but there were incidents were not caused from

    the job (riot), which cause the victim does not want to work anymore

    Picture VII.2

    Total of Man Hours (Nov 24 – Dec 15)

  • 8/18/2019 HSE External Report suai airport - December 2014

    9/24

    Health & Safety Monthly Report    December 2014

    8

    c. Incident report

    There is 1 incidents on this month. No victim.   This Project is still

    ZERO ACCIDENT fatality.

    Table VII.3

    Accident Report

    Table VII.4

    * Landslide Chronology (Basecamp) 11/12/2014 - Attachment 

  • 8/18/2019 HSE External Report suai airport - December 2014

    10/24

    Health & Safety Monthly Report    December 2014

    9

    Occupational Health and Safety Performance

    * Incident rate becomes large because the number of working hours in use only 8 months

    d. Hazard report

    Based on the report hazards recorded in HSE unit on December period,

    there is no hazards findings occurred in the area of basecamp . From the last

    month finding of hazard, the corrective actions taken are still in progress and

    late. because majority of worker are focus to erection batching plant and

    AMP. For inspection results classified into 2 types of hazards, unsafe action

    and unsafe condition. From the results of the inspection period December

    ( Nov 24 - Dec 15) resulted in findings.

  • 8/18/2019 HSE External Report suai airport - December 2014

    11/24

    Health & Safety Monthly Report    December 2014

    10

    Picture VII.3

    Hazard report

    e. Inspection

    Inspection activities in December 2014 carried out at the airport and

    the basecamp area. Every inspection finding will be record on CAR document

    (Corrective & Preventive Action Request) and will be signed & follow up bythe person in charge of the area.

    Table VII.5

    Inspection Summary

  • 8/18/2019 HSE External Report suai airport - December 2014

    12/24

    Health & Safety Monthly Report    December 2014

    11

    f. Traffic safety, sign and Control (Update December)

    Picture VII.6

    Sign Placement and traffic Map

    Note :

    Main Drain Excavation

    Work access road

    Detour Road / Temporary acces for public

    Speed limit Sign

    Watch rof moving vehicle Sign

    Heavy Equipment Sign

    PPE Sign

    Constuction Area Sign

    Assembly point

    Aircraft sign

    Detour road

    River diversion

  • 8/18/2019 HSE External Report suai airport - December 2014

    13/24

    Health & Safety Monthly Report    December 2014

    12

    Picture VII.7 Picture VII.8

    Aircraft sign Temporary public acces road

    g. Temporary Drainage

    Picture VII.9

    Drainage work & Temporary Drain

    Note :

    Main Drain Excavation Mitigation Pond

    Temporary Drainage

    To Holbelis

    To Matai

  • 8/18/2019 HSE External Report suai airport - December 2014

    14/24

    Health & Safety Monthly Report    December 2014

    13

    h. Flight Report

    Picture VII.10

    Suai Airport Flight Report.

    Flight report started in September, and in December there is 1 flight

    in Suai. No flight incidents related to existing work in the field. Take off and

    Landing went smoothly without distubed the work. To avoid the accident in

    the airside area, will be applied siren system if there is about flight to Suai

    Airport. So before the aircraft will be landing, the run way area will clearance

    from all activity and equipment.

    Picture VII.11 Picture VII.12

    Take off Landing

  • 8/18/2019 HSE External Report suai airport - December 2014

    15/24

    Health & Safety Monthly Report    December 2014

    14

    1.   Clearance Area along the "Runway", which counted 60 meters from thecenter line of the width of "Runway". This area should be completely free

    from all outside activities on the flight activity of the airport operating hours.

    2.   If there is a plane that will land, the contractor must ensure the runway is

    free of any obstacles (clearance area), at least 700 meters.

    Picture VII.13

    Existing runway

    Existing runway lenght remaining 829m due to demolished work,   so

    clearance area are still on safe distance for emergency landing and take off .

    Clearance area for

    emergency landing and Take

    off minimum 700 meters

  • 8/18/2019 HSE External Report suai airport - December 2014

    16/24

    Health & Safety Monthly Report    December 2014

    15

    i. HSE meeting

    HSE meeting is an activity to remind workers of the importance of 

    safety in the workplace, hazards in the workplace, the incidents that occurred

    in the workplace and safety related issues. In this case we usually call safety

    morning. HSE meeting attended by all personnel in the project, and also

    subcon foreman. in the November has been done 2 times a safety morning.

    - December 5, 2014

    Minutes of HSE Meeting

    Picture VII.14

    Safety morning December 5, 2014

  • 8/18/2019 HSE External Report suai airport - December 2014

    17/24

    Health & Safety Monthly Report    December 2014

    16

    - December 12, 2014

    Minutes of HSE Meeting

    Picture VII.15

    Safety morning December 12, 2014

  • 8/18/2019 HSE External Report suai airport - December 2014

    18/24

    Health & Safety Monthly Report    December 2014

    17

    VIII. Conclusion

    Some things that become problems to activity and work in the HSE in

    the period December 2014 can be seen in Table IX.1

    Table IX.1

    This month issues

      Pr blem C rrective Acti n PIC

    1

    There has been a landslide on

    the retaining embankment

    building access roads to thehopper.

    The access road will be

    repaired, and its design will a

    little away from the Electrical

    transmission tower. And willbe installed gabion Minimum

    2 layers.

    PRODUCTION

    SUPERVISOR

    2

    Increased rainfall can boost the

    risk of flooding in the area

    basecamp

    Prepare for flood emergency

    response plan  HSE

  • 8/18/2019 HSE External Report suai airport - December 2014

    19/24

    Health & Safety Monthly Report    December 2014

    18

    Table IX.2

    Last Month issues

      Pr blem C rrective Acti n PIC Status

    1

    Security around the project

    site have not been fully

    able to ensure smoothness

    work (Airport &

    Basecamp)

    Coordination with police

    station, and hiring security

    guard

    Project

    Manager  Closed

    2

    Construction of temporary

    storage facility forhazardous material at all

    site has not available

    (Basecamp)

    Provide secure storage

    facility for hazardous

    material provided with

    proper containment

    Construction

    Manager, HSE  Process

  • 8/18/2019 HSE External Report suai airport - December 2014

    20/24

    Health & Safety Monthly Report    December 2014

    19

    IX.Documentation

    Picture X.1

    PPE Demonstration

    Picture X.2

    Practice for using Fire Extenguisher

  • 8/18/2019 HSE External Report suai airport - December 2014

    21/24

    Health & Safety Monthly Report    December 2014

    20

     Attachment 

    Landslide Chronology (Basecamp) - 11/12/2014

  • 8/18/2019 HSE External Report suai airport - December 2014

    22/24

    Health & Safety Monthly Report    December 2014

    21

    LANDSLIDE INCIDENT 

    Chronology :

    On Thursday afternoon at 14:00 happen very heavy rain in the area basecamp. Because of 

    heavy rain, the production process is stopped and workers in the field stopped. After 1 hour

    the rain, suddenly, gabion retaining not strong enough to hold the load increase due to

    rainwater and finally collapse on the side of the house generators. Landslides are not get to

    generator house, no work activity at the site, and none of the victims.

    Picture 1. Land slide condition

    Land slide area

  • 8/18/2019 HSE External Report suai airport - December 2014

    23/24

    Health & Safety Monthly Report    December 2014

    22

    Picture 2. Access road condition

    Conclusion :

    A. At the time of manufacture of is not done with vibro compaction, only by using the

    excavator, so it is not in getting the maximum density to hold the load.

    B. Gabion retaining the height > 5m only installed one layer and a width of 1 m, so that

    the strength is not maximum.

    C. In the event of heavy rain, the water that is in the top pile into the soil compacting

    gravel are less than the maximum. Thereby increasing the pressure on the gabion.

    And finally gabion not able to hold the pressure.

    Corrective Action :

    A. The access road will be repaired, and its design will a little away from the Electrical

    transmission tower.

    B. At the end of the access road will be installed gabion Minimum 2 layers.

    C. Most of the embankment will be made the slope, so that the water in the top can

    sliding down.

    Landslide area

    Access road to

    Hopper

  • 8/18/2019 HSE External Report suai airport - December 2014

    24/24

    Health & Safety Monthly Report    December 2014

    Picture 3. Repair Construction Plan.

    There were no victims in the incident, and there was no damage to property, it's just we lost

    production process for 7 days for a period of repair.