33
EMCO Procedure – Tilt-up Concrete & Precast Construction Procedure Document No: HSEPC011 Version No: 2 Issue Date: AUGUST 2009 Page No: Page 1 of 33 Author: MARK GOMEZ To Be Reviewed: AUGUST 2011 Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009 Tilt-up Concrete & Precast Construction Procedure

HSEPC011 EMCO Procedure Tilt Up Precast Concr

Embed Size (px)

DESCRIPTION

Example of a tilt-up concrete and precast construntion procedure

Citation preview

Page 1: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 1 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Tilt-up Concrete & Precast Construction Procedure

Page 2: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 1 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

CONTENTS

1 PURPOSE 3

2 SCOPE 3

3 PROCEDURE 3

3.1 Training 3

3.1.1 GENERAL TRAINING AND SAFETY AWARENESS 3

3.1.2 Carry out Tilt-Up Work Safely 4

3.1.3 Supervise Tilt-Up Work 4

3.1.4 RECORDING AND MAINTENANCE OF TRAINING DOCUMENTATION 4

1.3.4 RESPONSIBLE PERSONS 4

3.2 PLANNING 5

3.2.1 PRE PLANNING AND CO-ORDINATION 5

3.2.2 DOCUMENTATION 5

3.2.3 NOTIFICATION TO WORKSAFE COMMISSIONER 6

3.2.4 WORK METHOD STATEMENTS 6

3.2.5 SHOP DRAWINGS 7

3.2.6 STACKING AND ERECTION SEQUENCE 7

3.2.7 RIGGING ACTIVITIES 8

3.3 PRODUCTION AND ERECTION 9

3.3.1 PANEL PRODUCTION 9

3.3.2 PANEL LIFTING 9

Page 3: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 2 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

3.3.3 POST ERECTION SITE CONTROL 10

4. ROLES AND RESPONSIBILITIES 11

5. REFERENCES 11

6. DOCUMENT CONTROL 11

7. APPENDICES 11

APPENDIX A - STAGE & TASK INDEX 12

APPENDIX B - METHOD STATEMENT & JSA 13

APPENDIX C – PANEL CONSTRUCTION MASTER CHECKLIST 17

APPENDIX D – PANEL LIFTING SCHEDULE 20

APPENDIX E – CASTING BED SCHEDULE 21

Appendix F – Panel Fabrication Checklist 22

APPENDIX G – CONCRETE POUR RECORD 25

APPENDIX H – RIGGING METHOD STATEMENT FOR PANEL INSTALLATION 26

APPENDIX I – BRACE BOLT TORQUE & PANEL VISUAL INSPECTION REGISTER 27

Page 4: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 3 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

1 Purpose

This procedure has been written to ensure, all Tilt-up and Precast Construction by EMCO complies with Australian Standard AS 3850 Tilt-up concrete construction and the Code of Practice Tilt-up and Precast Concrete Construction and as far as is practicable an environmentally sound and safe system of work for tilt-up concrete construction activities.

The following legislation is applicable to all construction activities:

• Occupational Safety and Health Act 1984 • Occupational Safety and Health Regulations 1996 • Environmental Protection Act 1986 • All other relevant Commonwealth and Western Australian Environment, Health and

Safety Legislation and regulations.

2 Scope

This procedure covers the manufacture, handling, storage and erection of tilt-up and precast concrete elements on projects under the control of EMCO Building.

3 Procedure

3.1 Training

EMCO Building will ensure that all personnel undertaking work on projects were Tilt–Up panels are being manufactured or erected have the necessary training to ensure that work is conducted in a manner which minimises the risks to the persons carrying out the work, fellow workers, visitors to site and members of the public.

3.1.1 General Training and Safety Awareness

EMCO Building will ensure that all personnel undertaking work on projects where Tilt-Up panels are being manufactured or erected, receive, at a minimum, training pertaining to the hazards and risks associated with the manufacture and erection of Tilt – Up panels.

The EMCO Site Manager/Supervisor will ensure that the hazards and risks associated with the manufacturer and erection of Tilt-Up Panels are communicated through:

• The induction process

• Toolbox Meetings

• Pre Starts

• Emergency Preparedness and Response Drills

Page 5: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 4 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

3.1.2 Carry out Tilt-Up Work Safely

EMCO Building will ensure that persons undertaking any of the following tasks involving Tilt-Up panels have completed a Worksafe approved Tilt Panel Safety Awareness Course (CPCCCM1007A) in accordance with legislative requirements (OSH Reg 3.88J):

• Casting of tilt panels

• Transporting of tilt panels

• Cranage of tilt panels

• Erection of tilt panels

• Stabilisation of tilt panels

• Conducting other work such as drilling, grouting, painting, to tilt panels while they are propped and until they are incorporated into the final structure.

EMCO Building will ensure that all EMCO employees including Site Managers, Site Supervisors, Project Managers, labourers, and apprentices have completed a Worksafe approved Tilt Panel Safety Awareness Course prior to commencing work on EMCO Building projects where Tilt-Up panels are being manufactured, or erected.

3.1.3 Supervise Tilt-Up Work

EMCO Building will ensure that persons supervising work involving the manufacture, cranage, erection and stabilisation of Tilt-Up panels have completed a Worksafe approved Supervise Tilt –Up Course (CPCCBC4022A) in accordance with legislative requirements (OSH Reg 3.88J [1a])

EMCO Building will ensure that all Site Managers and Site Supervisors have completed a Worksafe approved Supervise Tilt-Up Course where they are managing or supervising work on projects where Til-Up panels are being manufactured, or erected.

3.1.4 Recording and Maintenance of Training Documentation

EMCO Building will ensure that the recording and maintenance of training documentation is carried out in accordance with HSEPC007 EMCO Procedure – Induction & Training.

1.3.4 Responsible Persons

Certified Engineer: is responsible for the panel design including the reinforcing and steel and the structural integrity of the panels.

Bracing Engineer: is responsible for temporary bracing and any of the casting items used for lifting the panel into its final position. The Bracing Engineer

Page 6: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 5 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

decides whether there is extra reinforcing required on the panel to enable it to be lifted, also responsible for all temporary inserts.

Site Manager: to ensure a competent person is appointed on site to supervise the Tilt-Up and Precast Concrete Construction. Notify the WorkSafe Western Australia Commissioner of the intention to carry out tilt-up construction work. This notification is to be made available 5 working days prior to work intended to begin.

to ensure sufficient lead-time for the planning and documentation phase of the project and to factor this into letting of the contract.

to ensure environmental legislative requirements are met.

Rigging Contractor: delivery of workers who possess certificates of competency in rigging. The rigging contractor has a responsibility for performing pre-start meetings with his staff and advising EMCO of any deviations from the work plan or JSA submitted.

Crane Driver: Person holding a competency certificate relevant to the crane required to undertake the panel lift.

Panel Manufacturer; Person to manufacture pre-cast or tilt-up panels to design criteria

3.2 Planning

3.2.1 Pre planning and Co-ordination

Pre-planning and close coordination is essential for the safe, efficient and environmentally sound construction and erection of tilt-up construction.

EMCO will, in association with the design engineer, the manufacturer and erector ensure the complete construction and erection sequences have been planned and signed off prior to work commencing.

Factors to be considered in pre planning include:

• site limitations; • local street access; • element sizes, shapes and masses; • crane size, mobility and access; • casting sequence; • overhead obstructions, especially overhead power lines and • environmental considerations of the location (near waterways, neighbours etc)

3.2.2 Documentation

The following documentation will be available at any EMCO site involved in Tilt-up and Precast Concrete construction as per the requirements of the Occupational Safety and Health Regulations 1996 (r 3.88):

Page 7: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 6 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

• AS 3850 Tilt-up concrete construction; • WorkSafe Commission Code of Practice Tilt-up and Precast Concrete Construction; • copy of the approval by the WorkSafe Western Australia Commissioner in relation to

the work; • copy of EMCO’ procedure for Tilt-up and Precast Concrete Construction; • copy of the Method Statements and JSA for casting and erection; • a copy of design engineer approved shop drawings; and • a statement by the manufacturer that each precast or tilt-up concrete element has

been manufactured in accordance with design engineer approved shop drawings.

The Project Manager is responsible for compiling the Site Folder that contains all documentation and plans for the precast and tilt-up work. A copy is to be maintained for the rigger, and a condensed version for the fabricator. The fabricator’s condensed version includes the certified drawings, installation methods and requirements for all casting and items, engineer’s certification of panel compliance, concrete strengths and design mixes, and any other material relating to the fabrication that the engineer deems necessary.

3.2.3 Notification to WorkSafe Commissioner

Regulation 3.88 requires that the WorkSafe Western Australia Commissioner be notified of the intention to carry out tilt-up construction work. This notification is to be made available 5 working days prior to work intended to begin. The Site Manager will perform the notification on behalf of EMCO.

3.2.4 Work Method Statements

All contractors involved in the tilt-up construction will be required to submit Method Statements (Code of Practice Tilt-up and Precast Concrete Construction for Buildings section 8.3) for approval to the Site Manager and Erection Design Engineer prior to the work commencing.

The Method Statements will comply with the requirements in the Appendices and will contain:

• Persons involved in the work, site induction details and specifying their competencies (to be sighted by the Site Manager) and responsibilities on site for each stage of the erection process (Appendix A);

• a risk analysis to identify critical activities involved in the erection and description of how the risks will be eliminated or minimised – including a traffic management plan (Appendix A)

• a panel construction master checklist with stage sign-offs (Appendix B) • a panel lifting schedule (Appendix C); • a panel casting schedule - derived from the erection sequence (Appendix D); • a panel fabrication checklist with stage sign-offs (Appendix E); • a concrete pour record (Appendix F); • description of the erection procedure (Appendix G);

Page 8: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 7 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

• methods of stabilisation (temporary or permanent) of the structure including brace torque checks and visual inspection of panels (Appendix H);

• a statement by the erection design engineer that the erection design and detailing is in accordance with AS 3850 and AS 3600;

• design calculations prepared by the erection design engineer.

3.2.5 Shop Drawings

The design engineer will ensure that the shop drawings comply with the structural design. The project manager must check the shop drawings for compliance with dimensions. Shop drawings should include all the following as a minimum standard for panel drawings:

• Overall dimensions of the panel • All reinforcement information • All necessary lifting and propping points • Any other cast–in items • The concrete pour strength • The concrete lift strength • The panel thickness • The panel area • The volume (amount of concrete) • The mass of each panel • The location, orientation and depth of embedment of inserts, and where the insert

type is known, the configuration and cover of any component reinforcement required. • The diagonals • The connection loadings for all temporary propping • The brace type, size, safe working load limit, extended and closed limits, details (both

temporary and permanent) • The torque and limitation • The fixing lengths and angle • The sling or rigging configuration • The engineers approval (signature) and date • The name of the panel designer • The panel identification number

3.2.6 Stacking and Erection Sequence

The following factors shall be taken into consideration when determining the stacking and erection sequence:

• The shape, size and mass of precast members. • Specific design requirements, including the concrete strength required for handling

and the stability of long or unusually shaped members during handling, transportation and erection.

• The size and mobility of the crane needed to erect at the precast members. • The suitability of the site crane, if available, should be determined at the project

design stage if possible.

Page 9: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 8 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

• The manufactured size of the precast members will depend on the availability of suitable cranes with particular attention given to the lift capacity at maximum radius.

• Where a mobile crane is to be used, the adequacy and strength of the erection platform. Where the erection platform is a suspended slab, the suspended slab may either be designed to carry the additional loads, or temporary supports may be used.

• All suspended slabs and temporary support systems intended for use as erection platforms should be confirmed as being adequate to withstand the anticipated loading.

• Access for the crane and the precast members through local streets and all-other access onto and across the site.

• Overhead obstructions, particularly power lines • Erection equipment and capacity and location of lifting inserts • Temporary storage, where required

3.2.7 Rigging Activities

The following factors shall be taken into consideration when planning the rigging activities:

• Size of panels • Specific design requirements eg the required concrete strength at time of lift. • Size and mobility of crane needed to lift the panels. • Adequacy and strength of the erection platform. • Access for the crane – through local streets, onto and across the site and on or

alongside the casting bed for erection including the provision of a lifting plan, which considers underground services.

• Casting sequence, positioning of panel stacks, erection sequence and mobility of crane for erection.

• Overhead obstructions, particularly power lines • Intended location of inserts and rigging system to be used. • The possible need for on-site transportation of panels. • Traffic management plan – interface plan • Site interface -Traffic management plan, fall zones, exclusion zones, ground

conditions and services • Surrounding interface – traffic management, fall zones, and exclusion zones

pertaining to public, plant, equipment, vehicles, existing structures, power lines, ground conditions, underground services.

• Job Safety Analysis - as identified in the Method Statement, high-risk activities to be written as separate JSA’s.

• Risk assessment as per the JSA. • Toolbox meeting/communication – Contractor specific and site toolbox meeting to be

planned for each lift.

Page 10: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 9 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

3.3 Production and Erection

3.3.1 Panel production

• Refer to the pre-planning phase, to ensure a plan is developed for the appropriate location of the pour, given consideration for lifting sequence, crane access.

• Ensure the erection platform is capable of withstanding the downward forces of the proposed panels.

• All steel dockets to be kept as per document. • Formwork is prepared (Appendix E). • Project Manager to ask Electrician to locate panels with any conduits required prior.

When pouring is to be performed conduits can be placed. • The Box Numbers for each panel are to be recorded, as per the Building Casting Bed

Schedule (Appendix D). • Panels then released for pouring after the Site Manager signs off on the Panel

Fabrication Checklist (Appendix E). • Record the Date, Time and Ambient Temperature for each Concrete pour. • Sign off on the Panel Construction Master Checklist. • A Concrete Pour Record is then developed (Appendix F). • Testing/Sampling: The Site Manager needs to determine how the sampling regime is

to be managed. The Panel Fabrication Checklist (Appendix E) covers the fabrication of the panel. The concrete pour record (Appendix F) provides information on date, time and type of concrete that was included, weather conditions etc. The Site Manager is to discuss with the engineer to find a suitable sampling schedule. The Engineer determines the increase and the safety factor, so that the lifting can occur at a nominated period of days after the pouring. Cylinders from various panels are taken and then crush tested. It is important that during the curing of the sample it is left next to the panel to enable the same rate of curing. The progressive crush is to be verified by NATA laboratory, to achieve the required lift strength as specified by the temporary engineer.

3.3.2 Panel Lifting

• Ensure the site is briefed in the Site Toolbox meeting of the activity and location of the lifting of the panels. Site Communication is essential for ensuring the workers are kept informed of the lifting to occur. These are all to be documented, both site specific (everyone) and for rigging contractor performing the lifting. Everyone is to be signed on the toolbox meeting form.

• If practicable, exclude the non-essential trades from the site. • Rigging Contractor to discuss the Job Safety Analysis for the lift. • Rigging Contractor to check again the crane selected is suitable for the task, and the

boom is within radius.

Page 11: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 10 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

• Rigging Contractor to refer to the Rigging Method Statement for Panel Installation (Appendix G).

• Ensure the copy of the Master file to be at the location for the rigging contractor is accurate.

• Cordon off the area to exclude all personnel not involved in the lift. If practicable, close entry to the gate and where practical the cordoned off area is to be three times the height of the panel.

• Use and compile the Panel Lifting Schedule (Appendix C).

Refer to and follow the Panel Construction Master Checklist (Appendix B)

• The panels are sequenced for the lift, as required by the engineer. It is the responsibility of the Site Manager to ensure each panel is lifted in the correct sequence.

• Rigging contractor to place temporary props. Stabilisation of both temporary and permanent structures is critical to the safe operation of the job.

• Rigger to torque each bolt and carryout checks as specified by the Bracing Engineer. • Panels inspected after erection and Brace Bolt Torque Checks & Panel Visual

Inspection Register completed (Appendix D). • Certifying Engineer to sign for the structure being in place. • Site Manager then signs off Panel Construction Master Checklist (Appendix B).

3.3.3 Post Erection Site Control

• All incidents will be investigated as per EMCO Safety and Health Management Plan.

Page 12: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 11 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

4. Roles and Responsibilities

EMCO Project Manager

EMCO Site Manager

EMCO Site Supervisor

EMCO HSE Officer

EMCO employees

Subcontractors and their employees

5. References

Occupational Safety and Health Act 1984

Occupational Safety and Health Regulations 1996

AS/NZS 4360:2004 Risk Management

AS 3850:2003 Tilt Up Concrete Construction

National Code of Practice for Precast, Tilt-Up and Concrete Elements in Building Construction 2008

6. Document Control

EMCO Building

7. Appendices

Appendix A Stage and Task Index

Appendix B Method Statement & JSA

Appendix C Panel Construction Master Checklist

Appendix D Panel Lifting Schedule

Appendix E Casting Bed Schedule

Appendix F Panel Fabrication Checklist

Appendix G Concrete Pour Record

Appendix H Rigging Method Statement for Panel Installation

Appendix I Brace Bolt Torque & Panel Visual Inspection Register

Page 13: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 12 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Appendix A - Stage & Task Index

Project: Project No:

Stage Task Reference Completed

Site Set up

Complete Set-up Section of Panel Construction Master Checklist

Method Statement completed by Sub Contractors

Appendix B (p19)

Appendix A (p14)

Panel Fabrication

Complete Panel Fabrication Section of Panel Construction Master Checklist

Casting Bed Schedule provided

Complete Panel Fabrication Checklist

Appendix B (p19)

Appendix D (p23)

Appendix E (p24)

Note: Panel Fabrication Checklist Sign-off required before each panel poured

Panel Concrete Pour

Complete Concrete Pour Record Appendix F (p28)

Note: Sign-off required in Master Checklist on concrete strength before lifting

Panel Erection

Complete Panel Erection Section of Panel Construction Master Checklist

Panel Lifting Schedule completed

Appendix B (p20)

Appendix C (p22)

Note: Sign-off required in Master Checklist before Erection commences

Panel Bracing

Complete Brace Bolt Torque & Visual Inspection Register

Appendix H (p30)

Note: Sign-off required in Master Checklist before tying panels into structure commences

Panels in Structure

Complete Panel in Structure Section of Panel Construction Master Checklist

Appendix B (p21)

Note: Sign-off required of completed Master Checklist on completion of job

Page 14: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 13 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Appendix B - Method Statement & JSA

Project Name: Sub Contractor Name:

Site: Sub Contractors Address:

Description of Work: Tilt Panel Casting and Erection

Start Date:

Responsible person for reviewing Plan: Finish Date:

PERSONS INVOLVED IN WORK

No Name & Company

Blue Card N

o

Expiry

Date Competencies/Licenses.

Page 15: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 14 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

No SCHEDULE OF WORK ACTIVITY HAZARD / RISK RISK CONTROLS RESPONSIBILITY

1 Shop drawings documentation. Drawings not approved giving rise to tilt panel failure.

Structural Engineer to inspect and approve all shop drawings

Structural Engineer

2 Ensure all documents are onsite. Not all contractors have access to the required documentation.

Complete drawing register and specification kept in the site office.

Complete copy of safety procedures and plans kept in the site office.

Concrete pour record to be completed at each panel pour.

Record of tilt panel checklist completed and signed off kept on file.

Site manager

3 Personnel Competency Personnel do not have the correct level of competency.

Undertake site induction for all personnel.

Check crane operators certification

Riggers to provide tilt up certification.

Ensure crane lift study and method statement is submitted.

Site Manager

4 Onsite panel storage Panel failure or collapse due to incorrect storage.

Ensure panel storage as per the engineer’s specifications.

Panels shall not be leant against temporary bracing.

Site Manager

Page 16: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 15 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

5 Crane Operation Crane topple or failure.

Check crane capacity working radius competent min 1.5m.

Check mobile crane capacity min 3 times greater than mass of heaviest panel.

Ensure crane-slewing area clear.

Ensure crane level within 1-degree tolerance.

Ensure crane outriggers fully extended.

Check that no underground services located under crane and that crane access is planned around underground services.

Crane Operator

Site Manager

5 Crane Operation (cont’d) Crane topple or failure.

Ensure adequate clearance to overhead power lines and obstructions.

Check lifting clutches inspected every 6 months.

Check condition and length of slings.

Check chains tagged SWL etc.

Check crane slings condition Eg: - corrosion, broken stands.

Ensure only recommended lifting equipment being used.

Crane owner to provide documentation of currency for crane and all lifting gear.

Crane Operator

Site Manager

Page 17: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 16 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

6 Fall Zone People being injured by possible fall objects.

Check riggers erection method statement

Clear fall zone around panel while erecting, minimum 1.5 x panel height.

Barricade area from non-essential workers.

Rigging Crew

Site Manager

7 Plant Injuries due to plant operation or failure.

Access machine operators all have certified licenses.

Barricade areas where necessary to prevent access machines in conflict with panels or braces.

Barricade areas where necessary, e.g. over holes in slab, edges with drops.

Ensure all boom pump operators have the correct certification.

Machine Operator

Rigging Crew

Site Manager

8 Maintenance of Temporary Bracing Equipment failure due to lack of maintenance

Bolts checked and panels inspected at regular intervals

Panel braces and props maintained as per the suppliers specifications

Rigging Crew

Site Manager

9 General conditions Work being performed in unacceptable conditions

Monitor the weather forecast and conditions and do not undertake works with excessive wind or rain.

Check ground conditions are acceptable where works are being performed.

Ensure clear and unobstructed access in works areas.

Undertake measures to prevent general traffic access from work area

Rigging Crew

Site Manager

Crane Operator

Page 18: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 17 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Appendix C – Panel Construction Master Checklist

Project: Project No:

Date Checklist Completed: / /

EMCO Representative:

EMCO Representative Signature:

Item Yes No N/A

Set-up for Panel Construction.

Sub Contractors briefed on Tilt-up Concrete Construction Procedure and Method Statement requirements in Appendices A - H

JSAs supplied by Fabricator & Rigger

Site Inductions completed and competencies sighted by Site Manager

Shop drawings including layout, engineer’s approval, and connection details.

Certified approved including cast in points

Master copy filed on site

Copy supplied to fabricator

Copy supplied to rigger

Panel Fabrication

Panel Fabrication Checklist complete (Appendix E)

Casting Bed Schedule supplied (Appendix D or equivalent)

Concrete Pour Record completed (Appendix F)

Concrete test performed

Test results received indicating that concrete strength, as specified, has been achieved for lifting.

Inspected By:

Signature: Date:

Page 19: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 18 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Item Yes No N/A

Panel erection

Rigger complies with Rigging Method Statement (Appendix G) and JSA

Crane log completed

Crane inspection completed

Interface & traffic management / safety zones in place including appropriate barricades and signage.

Panel Lifting Schedule completed (Appendix C)

Hold point - Panel must not be erected until all the above items are satisfied.

Inspected By:

Released for Erection

Signed: Date:

Item Yes No N/A

Panels in place and temporary supports

Braces installed as per documentation

Connections as per documentation

Panel tied in at footing

Brace torque check & panel visual inspection log completed (Appendix H)

Braces supplied with work loading limits, inspection/maintenance certificate

Hold point - Panels cannot be tied into complete structure or final footings poured until all the above items are satisfied.

Inspected By:

Released for tying into structure

Signed: Date:

Page 20: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 19 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Item Yes No N/A

Panel in structure

All connections in place as per the engineered drawings

All members in place as per the engineered drawings

All structural components in place as per the engineered drawings

Hold point - Temporary propping cannot be released until the above items have been satisfied.

Consulting Engineering Representative:

Released for prop removal

Signed: Date:

Page 21: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 20 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Appendix D – Panel Lifting Schedule

Project: Project No:

Panel Numbers: / / / / / / / / / / / / /

Crane Size:

Maximum radius inc. 1.5m competent minimum:

Date: / /

Rigging Representative:

Panel Number Panel Weight Lifting Radius Actual Lifting Radius

Page 22: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 21 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Appendix E – Casting Bed Schedule

Project: Project No:

Panel Erector: Rigging Representative:

Ground Slab or Casting Bed

Ground Slab or Casting Bed

Ground Slab or Casting Bed

• Record date of pour, panel no, panel weight in appropriate box for each panel poured

on a casting bed or floor slab.

• The above casting bed and panel layout is typical only. Produce a schedule to suit the project.

• Sketch additional documentation of panel casting layout.

Page 23: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 22 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Appendix F – Panel Fabrication Checklist

Project: Date: / /

EMCO Representative: EMCO Representative Signature:

Panel Drawing No:

ITEM COMPLETED Panel __

Panel __

Panel __

Panel __

Panel __

Panel __

Panel __

Panel __

Formwork

1. Formwork set out and dimensions are as detailed

2. Check panel thickness is as detailed

Reinforcement

1. Reinforcement sizes and numbers is as detailed

2. Reinforcement distribution is as detailed.

3. Reinforcement tied together correctly

4. Lifting point number and sizes as detailed

5. Lifting point locations as detailed

6. Lifting points tied in as per manufacturers details

7. Brace points size and number as detailed

8. Brace point locations as detailed

9. Brace points tied in as per the manufacturers details.

Page 24: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 23 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Panel Drawing No:

ITEM COMPLETED Panel __

Panel __

Panel __

Panel __

Panel __

Panel __

Panel __

Panel __

10. Reinforcement displaced around cast in items.

11. Edge bar placement as detailed

12. Edge bar size and number as detailed

13. Edge bars tied in as detailed

14. Starter bar placement as detailed

15. Starter bar size and number as detailed

16. Starter bars tied in as per the engineers approved shop drawings.

17. Cast in dowels location as detailed

18. Cast in dowel size as detailed

19. Cast in dowels tied in as detailed

20. Ferrule locations as detailed

21. Ferrule size and numbers as detailed

22. Ferrules tied in as per manufacturers details

23. Cast in plates locations as detailed

24. Cast in plate sizes and number as detailed

25. Cast in plates tied in as detailed

26. Strong back ferrules installed as detailed

Page 25: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 24 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Panel Drawing No:

ITEM COMPLETED Panel __

Panel __

Panel __

Panel __

Panel __

Panel __

Panel __

Panel __

Services

1. Check for installation or requirement of services

2. Check block outs for penetrations

3. Check conduit run ins.

Hold point - Panel concrete pour must not commence until all the above items are satisfied.

Inspected By:

Date:

Initialled:

Concrete

1. Complete concrete pour record:

2. Panel number marked on panel.

3. Panel weight marked on panel.

4. Date panel poured marked on panel.

Note: Duplicate Checklist as required to cover the number of panels

Page 26: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 25 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Appendix G – Concrete Pour Record

Project: Project No:

Area of work /

Panel No

Delivery Date

& Time Docket N

o

Quantity Poured (m

3)

Ambient Temperature

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Date: / /

Time: :

Page 27: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 26 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Appendix H – Rigging Method Statement for Panel Installation

Project: Project No:

Panel Erector: Rigging Representative:

1) Complete Panel Lift Schedule as required in the Panel Construction Master Checklist.

2) Set-up selected crane in the correct location at a suitable predetermined radius for the panel being lifted.

3) Select correct rigging equipment using chains and slings etc with suitable W.L.L.

4) Place required temporary prop on panel and fix using specified fixings.

5) Connect rigging equipment to panels.

6) Hoist panel from panel bed under guidance of 2 Riggers (ensure JSA is being followed).

7) Hold firm and place bars or brackets on panel as required.

8) Place panel into design location and fix temporary brackets.

9) Remove rigging equipment.

10) Continue step 4 to 9 until next move of crane is required.

Page 28: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 27 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Appendix I – Brace Bolt Torque & Panel Visual Inspection Register

Project: Project No:

Proposed Panel Erection Date: Actual Panel Erection Date:

Panel Erector: Panel Rigger:

Brace Bolt Torque Checks & Panel Visual Inspections

Torque Check on erection

Visual Inspection

2nd Torque (24hrs)

Visual Inspection

3rd Torque check

Visual Inspection

Panel No Brace 1 Brace 2 Brace 1 Brace 2 Brace 1 Brace 2

AS 3850-2003 SECTION 6.2 – Torque checks of bolts and visual inspections of panels, braces and brace insert connections are to be carried out 24hrs after erection and at regular intervals after erection.

Page 29: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 28 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Appendix J – Tilt up & Precast Panel Awareness Training for Site Personnel

The contents of this information sheet must be communicated to all site personnel on EMCO Building projects where Tilt up & Precast Panels have been erected and braced prior to incorporation into the final structure.

1. Background

Tilt up & Precast Panels are a typical method of construction within the commercial building sector. Tilt up & Precast Panels may come in various sizes, shapes, thicknesses and finishes. While the use of Tilt up & Precast Panels is common, the hazards associated with their construction must never be

There have been and continue to be numerous cases of tilt panel collapse within the construction industry in Western Australia. In September of 2002 at a construction site in Myaree, a worker was killed as the result of a tilt panel collapse.

All site personnel are asked to take the utmost care when undertaking work on construction sites where Tilt up & Precast panels exist.

2. Training

It is a legislative requirement to have completed a Worksafe approved Carry Out Tilt Up Work Safely Course if your work involves the casting, transport, carnage, storage, erection, or stabilisation of tilt up or precast panels.

It is a legislative requirement to have completed a Worksafe approved Supervise Tilt Up Work Course if your work involves the supervision of any of the aforementioned activities.

It is a requirement of EMCO Building that persons involved in the drilling, coring, grouting, painting, cutting, patching of, or fixing to tilt panels while they are braced to have completed a Worksafe approved Carry out Tilt up Work Safely Course.

Site personnel must speak to their EMCO Site Manager of Supervisor if they are required to undertake work with Tilt up or Precast Panels and believe they do not have the necessary training.

3. Working Safely Around Tilt & Precast Panels

1. At no time are non essential site personnel permitted to enter the exclusion zone where tilt panels are being lifted or stabilised.

2. At no time are site personnel to touch, tamper with, or move props, braces or any other component which is used to lift, brace or support tilt panels.

3. At no time are site personnel permitted to climb on or over props or braces which are supporting tilt panels

Page 30: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 29 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

4. Site personnel are asked to maintain a safe distance from propped or braced tilt panels at all times.

5. At no time are site personnel permitted to operate mobile plant (bobcats, EWPS, cranes, telehandlers) in the vicinity of propped or braced tilt panels. Where it is necessary to operate plant in close proximity to propped or braced panels, the EMCO Site Manager/ Supervisor must be informed so that adequate controls can be put in place to prevent panels collapsing.

Page 31: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 30 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

Page 32: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 31 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

TILT UP & PRECAST SAFE WORKING PROCEDURE REGISTER

I have been made aware of the safe working procedure on EMCO Building sites where Tilt up & Precast

panels exist. I will adhere to the requirements of the safe working procedure

NAME SIGNATURE DATE NAME SIGNATURE DATE

Page 33: HSEPC011 EMCO Procedure Tilt Up Precast Concr

EMCO Procedure – Tilt-up Concrete & Precast

Construction Procedure

Document No: HSEPC011

Version No: 2

Issue Date: AUGUST 2009

Page No: Page 32 of 33

Author: MARK GOMEZ To Be Reviewed: AUGUST 2011

Approved by: DON COUSENS / JOHN RIPP Print Date: AUGUST 2009

TILT UP & PRECAST SAFE WORKING PROCEDURE REGISTER

I have been made aware of the safe working procedure on EMCO Building sites where Tilt up & Precast

panels exist. I will adhere to the requirements of the safe working procedure

NAME SIGNATURE DATE NAME SIGNATURE DATE