http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

Embed Size (px)

Citation preview

Page 1: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

http://indico.cern.ch/event/373053/

GS activities during LS1Christophe Delamare GS-ASE

EDMS 1499839

Page 2: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

2

Agenda

• Access Systems (GS-ASE)

• Alarm Systems (GS-ASE) and Fire Brigade (GS-FB)

• Logistics, Stores and other site services (GS-IS)

• Civil Engineering (GS-SE)

Ch. Delamare GS-ASE

Page 3: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

3

Access Systems (GS-ASE)

Ch. Delamare GS-ASE

Page 4: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

4

Access Systems – Brief summaryLACS – LHC Access Control System

Main functions:Authorisation verification Person identification andauthenticationvalid IMPACT

Physical BarrierDatabase: person authorisation

& valid trainingBiometry, Single person passageVideo surveillancePersonnel counting in a zone

LASS – LHC Access Safety System

Main Interlocks:Beam => No AccessAccess => No Beam

Input: position sensors of the EISOutput: Veto to EIS

Channel1: Siemens PLC Channel2: Hardwired relay loop

Integrated concept for LHC Machine & Experiments to protect personnel against the radiation hazards

Ch. Delamare GS-ASE

Page 5: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

7 mai 2009T.Ladzinski, P.Ninin, E.Sanchez GS/ASE

EDMS [998406]5

P. Ninin/L. Scibile/T. Ladzinski/S. Grau EDMS: 600659

LHC sites access

LHC buildings access

LHC experimental services areas access * ACCESSIBLE during beam operation

the LHC accelerator and experiment Access Service Access Tunnel Access Experiment NON ACCESSIBLE during beam operation

Page 6: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

6

Access Systems – « LS1 Mode »

• LHC Access Safety System “in reduced mode”

• EIS-beam “out-of-chain”

• No Interlock safety actions

• Veto to EIS-access (doors, access devices) inhibited

• Beam Imminent Warning sirens inhibited

• Under control of BE DSO (+EDMS procedure)

• LHC Access Control System fully operational

• Heavily solicited (while upgraded!)

Ch. Delamare GS-ASE

Page 7: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

Access Systems – LS1 LHC key changesTask Name Where Description ECR

Sectorisation Changes

TI2 Displacement of Door PPG2145 separating the LHC and the SPS in the TI2 tunnel 1253832

LHC1 Displacement of PADs from UJ14/16 to UL14/16 1218906

LHC4 Displacement of PAD UX451 1346280

USC55 Creation End-of-Zone Door for Material Transfer Between USC55 and the Bypass 1236542

Interlocking PM32 PM/TZ32 Creation of an Interlocked Service Zone PM32 1254796

Access Point Maintenance Doors LHC LACS/LASS Top of the Pit Maintenance Doors 1317397

New Radiation Veto Sectors LHC2,6,8 Additional Radiation Vetoes in Access Locations Leading to the Injection Lines and

Beam Dump Transfer Galleries 1254007

Monitoring of Helium Conf. Doors in LASS

TI2/TI8 Interlocking of Injection Tunnel Upstream Areas with LHC Powering 1257949

LHC Monitoring of pressure resistant doors in LASS 1288596Access – Powering Interlock CCR, LHC Change of the Interlocking of Powering and Access systems 1246780

Monitoring of Doors Important for Control of Activated Air

US32/US76 Add the following ventilation doors to LASS: YCPV01=US32, YCPV01=US76

1288596UP53 Add the following ventilation door to LASS: YCPV01=UP53

LHC2,4,6,8 Monitor the ventilation doors between Service and Tunnel areas in even points

Point 7 Collimation LHC7 LHC Point-7 Collimator Region Enclosure and Ventilation Bypass 1303048

Upgrade of LASS IT Infrastructure CCC/CCR Exchange of LASS servers and client computers, upgrade of Siemens PCS7

LACS CCC New tool for video, TIM views replace Evolynx LASS ones, upgrade from XP

7Ch. Delamare GS-ASE

Page 8: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

Access Systems – LS1 New PS Access

• Linac 4

• Linac 2

• PS Booster

• Switch-Yard

• PS Ring

• TT2/TFP

• TFT

• AD Target

• AD Ring

• East Hall

• IRRAD

• Isolde

• LEIR

• Linac 4

8Ch. Delamare GS-ASE

Page 9: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

9

Access Systems – LS1 New PS Access

• 14 interlocked zones

• 135 EIS beam/machine/external

• 19 Access Points

• PAD, MAD, mini-MAD

• 123 EIS-Access

• doors, grids, shielding walls, etc.

• 128 patrol boxes

• 72 cameras

• Public Address

• 16 amplifiers, 391 loudspeakers

• 90 electrical racks

• 50 PLCs and PCs

• 24 consoles and servers

• Full renovation of evacuation/Beam Imminent WarningCh. Delamare GS-ASE

Page 10: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

10

Access Systems – SPS primary ions

• New safety system for SPS primary ion runs:

• New kind of independent active safety interlock

• Prevents extraction of a high-intensity proton beam into the North Area during mixed proton-ion super cycles

• Intensity measurement with BCTs to interlock North Area extraction septa

• Project collaboration between GS, BE, TE, EN, RP

Ch. Delamare GS-ASE

Page 11: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

11

Access Systems – Performance

Peak: 4’434 entries & exits (3rd April 2014)

Ch. Delamare GS-ASE

Total: 1'507'276

Page 12: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

12

Access Systems – Performance

• How many persons in the complexe(s) ?

• Data available by LHC point. Useful for

• Safety issues (evacuation)

• Risk analysis and mitigation

• Distribution of Personal Protection Equipment

Ch. Delamare GS-ASE

Persons in LHC – Sept. 2014 – March 2015

Page 13: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

13

Access Systems – Special SMACC

Ch. Delamare GS-ASE

• «James Bond» suitcase

• Specific development

• Used in some LHC points

• Easier access of the SMACC train

Our opinion: useful system but not essential

Page 14: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

14

Access Systems – Availability/flexibility

• Availability

• Very few incidents with the Access Systems

• MAD difficulties => remote operation by CSA

• Systems heavily solicited

• More maintenance

• Always difficult to find slots for maintenance

• “Swap”/juggling between the access points

• Typical use case: incident with lifts

• Flexibility well appreciated by EN-MEF

• Manual procedure for the LS1

Ch. Delamare GS-ASE

Page 15: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

Ch. Delamare GS-ASE 15

Access Systems – Lessons learnt

• Two different contexts

• Large Project (owner)

• E.g. PS Access, LHC Access LS1 evolutions

• “Small” project workpackage

• E.g. SUSI Access Control (or Fire detection works)

• plan.cern.ch was essential

• Permitted to identify tens of coming requests

• Should come asap for LS2

• Identify and analyze proposed evolutions asap (ECR)

• Point 7 Collimation: September 2012

• Preparatory phase organized by EN-MEF well appreciated

• Integration (3D) laser scans, studies and conflict detections to pursue and reinforce

• Early detection of conflicts between key projects (and “big” items)

• E.g. PS Access & PS Cooling and Ventilation

• Develop and simplify publication and approval of 3D views

• Keep the notion of “LS1 mode” (Access Safety System “in reduced mode”)

• To be planned with BE DSO

Page 16: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

16

Access Systems – Lessons learnt

• Access conditions & Safety training

• A lot of newcomers – how to practice ? Safety Training Center ?

• Safety trainings (&DBs) must be in place much before the start of the LS

• CSA (guards) involvement

• Clear need: the integrity of the envelop

• MAD remote operation very useful to handle difficult cases

• Dedicated and trained “ZORA team”

• Coordination in LHC & injectors well appreciated

• Coordination in Meyrin Experimental areas – room for improvement

• Planning and stakeholders especially in commissioning phase

• Identification of the actors to operate infrastructure

• DSO tests are essential

• Allocate and “protect” the slots – huge commitment of several teams

• Works on some EIS-beam just before these tests

• Keep in mind the specific maintenance requirements of these equipment

• Validation, traceability, etc.Ch. Delamare GS-ASE

Page 17: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

17

Access Systems – Improvements

• Maintenance during runs

• Maintenance of the lifts during run

• New PZ65 Access point

• MAD personnel detection

• Ventilation WG impact ?

• SPS Access – key LS2 GS-ASE project

• As transparent as possible

• Notes de coupure

• Improve the understanding of the consequences

• “Swap” between the access points

• Automatic process via IMPACT ?Ch. Delamare GS-ASE

Page 18: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

18

Alarm Systems (GS-ASE)Fire Brigade

Ch. Delamare GS-ASE

Page 19: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

19

Alarm Systems – LS1 LHC key changes

• LHC ASD detectors replaced

• 700 LHC evacuation/BIW sirens replaced

• R2E relocations (LHC4, LHC5, LHC7)

• Point 7 Collimation – Fire Detection

• New ODH/gas centrals USA15 & UX15

• New ODH central CMS

• LHC ODH detectors accessibility

• Portable ODH detectors

• Replacement of SPS Fire detection centrals

• PS Evacuation/BIW renovated

• Fire detection

• PS HIE-Isolde, ELENA, EAR nTOF, LINAC4

• CSAM powering

• And many other works everywhereCh. Delamare GS-ASE

Page 20: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

20

Alarm Systems – Lessons learnt

• Maintenance slots are correct

• Coordination warmly thanked

• Xmas break: prepare plan B in case of Access problem

• Much more IS37

• Obvious needs – Anticipate the resources

• Training and information sessions to avoid forgotten IS37

• IS37 process evolution (IMPACT)

• Reduce the number of “false alarms”

• Announce the “alarms” work packages asap

• non standard gas detection => 9 months

IS37 year #2015 (24th March) 2782014 15082013 16102012 9442011 7342010 484

Ch. Delamare GS-ASE

Page 21: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

Ch. Delamare GS-ASE 21

GS-FB – Lessons learnt

• Operational activity/Interventions

• Emergency: moderated increase

• Non-emergency: significant increase (confined spaces, VIP visits, CERN events)

• Emergency preparedness

• Accelerators are “open” = unique opportunity

• Wish: major crisis drill involving all partners

• CERN Experiment or Underground sector

• CMT, HSE, GS-ME, GS-ASE, etc.

• HUG, 144, SIS, SSA, SDIS

Page 22: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

22

Logistics,Storesand other site services (GS-IS)

Ch. Delamare GS-ASE

Page 23: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

23

GS-IS areas

• Logistics (Shipping/Reception/Distribution)

• Storage areas

• Waste

• Cleaning

• Mobility (Car fleet, Shuttles and Buses)

• Stores

• Hostels

Ch. Delamare GS-ASE

Page 24: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

24

Logistics Shipping/Reception/Distribution

« LS1 bump » for logistics-related services

2/2

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

5,000

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

# of shipping documents / receptions / distributions and removals by quarter Jan 2010 - Sep 2014

Distribution / Removal Reception Shipping (secondary axis)

Ch. Delamare GS-ASE

Page 25: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

25

Stores

LS1 generated a turnover increase

- 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000

10,000

Turnover by quarter,Jan 2011 to Aug 2014 (in kCHF)

1/2

Ch. Delamare GS-ASE

Page 26: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

26

Cleaning

• LS1 cleaning activities include:

• Barracks / Bases de vie

• Tunnels and experimental caverns

• Lessons learnt:

• Cleaning methods to be reviewed to avoid dust in the tunnels (action: GS)

• Search for vacuum cleaners (large models) that are adapted for work in controlled areas (RP)

Ch. Delamare GS-ASE

Page 27: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

27

Mobility car fleet

• 167 additional LS1 cars

• 55 cars still in use as of end March

• CERN-wide fleet management required

• Anticipation of the needs

• Contractual solution(s)

• E.g. leased cars (but higher cost + VAT fuel)

1/2

Ch. Delamare GS-ASE

Page 28: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

GS-IS LS2 forecasts• Forecasts are needed for almost all GI-IS areas

• Budgets, service contracts

• Inform on quantity and quality change versus LS1

• E.g through plan.cern.ch enhance activity details with data such as

• Required storage space

• Material needs

• Cleaning request

• Generated waste

• CERN Stores standard items

• Anticipate project needs to identify the best suppliers, prepare supply contracts, stock only the necessary level of material (no dead stock), respond at the right time to material demands.

• Infrastructure: New building for radioactive storage

• On-going process. Can take up to 3 years

• Please answer to the corresponding surveys (+regular updates)

Ch. Delamare GS-ASE

Page 29: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

29

Civil Engineering (GS-SE)

Ch. Delamare GS-ASE

Page 30: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

Civil Engineering - LS1 - Activities(1/3)

• The works are structured in three types of activities:(34 plan items - 76 group contributions – 25 big, 42 medium, 45 small)

• Large civil engineering works for the realisation of new buildings, roads and shielding structures (for example, the works for increasing the radiation shielding on the PS extraction region, New building and shaft EAR2 in nTOF, etc.)

• Maintenance of the infrastructures only accessible during the long shutdowns (for example: tunnel floors and drains, underground sanitary equipment, roofs of operational buildings, etc.)

• Civil engineering works required by equipment groups in their activities during the long shutdown (for example: creation of slabs, excavation of trenches, concrete coring, shielding walls, etc.).

30Ch. Delamare GS-ASE

Page 31: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

Civil Engineering - LS1 - Activities(2/3)

• Large civil engineering works (1/2):• New buildings

• HIE – ISOLDE cooling : New building and related facitilies 198-199

• New building and shaft EAR2 in nTOF

• ELENA - Extension of blg 193

• New LHCb control room and data center

• CMS SL53 (new offices, conference room, visitors gallery)

• LIU-SPS 200 MHz RF Upgrade, New RF Building BAF3 - New building construction follow-up

• Construction of blg 774

• New building 107

31Ch. Delamare GS-ASE

Page 32: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

Civil Engineering - LS1 - Activities(3/3)

• Large civil engineering works (2/2):• Extensions/Renovations

• CCC repowering - CE work package bdg 874

• PS access - CE works for the new access system for the PS

• ISOLDE - extension of target storage area (bdg 179)

• Renovation of blg 192

• Facade carbonatation treatment - 168-20-21; 30-112

• Roads/Shieldings• Civil Engineering for Increasing the Radiation Shielding on the

Route Goward Passage over the PS

• Civil Engineering for Increasing the Radiation Shielding on the PS extraction region

32Ch. Delamare GS-ASE

Page 33: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

Civil Engineering - LS1 - Shielding Septum

33Ch. Delamare GS-ASE

Page 34: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

Civil Engineering - LS1 - works PS access

34Ch. Delamare GS-ASE

Page 35: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

35

Civil Engineering - LS1 – R2E

P7- Wall demolition and ducts dismantling• 2x217 m dismantled ducts

• total length of cuts: 3600 m

• 34720 kg of steel evacuated

• 235 m wall demolition (125 m3 of concrete)

• 5 days with some “lift out of order” issues

• From 14h to 22h: 7 weeks … 3 in advance!

• 1200 m2 painting

Page 36: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

36

Civil Engineering - LS1 - preparation

• LS1 activities started well before the shutdown

• Task force for the space requirements

• Involved long negotiations – time consuming

• Implied construction and transformation works before LS1 period started

• Identification of the support to be provided to equipment groups

• Plan tool as a starter

• Involved long discussions with equipment groups to anticipate requirements for CONTRACTS, RESOURCES and BUDGETS

Ch. Delamare GS-ASE

Page 37: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

LS1 – dedicated organization

37Ch. Delamare GS-ASE

Page 38: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

38

Civil Engineering – Lessons learnt

• Allow sufficient time for preparation

• Many things GS-SE does are needed well before the beginning of the shutdown.

• Additional resources need to be on board well in anticipation (1 year!).

• Strategy of support contracts needs to be finalized NOW.

• Note that Civil Engineering large works require ~2-3 years from the decision to the realization (contract for design, design, building permits, contracts for works, works)

• Huge list already collected (e.g. Chamonix)

• Communicate at all level (internal/external to the group)

• Management of priorities (machine/tertiary)

• Quick decisions are needed to shift personnel from the standard services (e.g. leaking roof) to tunnel services (e.g. equipment supports)

• Time consuming participation to coordination meetings.Ch. Delamare GS-ASE

Page 39: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

GS feedback summarywhat I - keep II - improve III - change

List the different aspects in the management of the work carried out during the LS1

Define what should be kept and was an added value during the LS1

Define what you propose to improve in order to better manage the LS2

Define what was a bottleneck to carry out the work during the LS1 and needs to be changed for LS2

3D Integration Essential for Access projects (“big” items)

To be reinforced (e.g. 3D scans, viewers, etc.)

Civil Engineering needs Large works require ~2-3 years. Contact GS-SE asap

plan.cern.ch Essential to identify the “small” WP

Collect needs about storage, material, cleaning, waste

Complex changes must be ECRed ~1 year before

Stores & al. Anticipate project needs. Contact Stores and reply to surveys

Space requirements Long negotiations

Safety Training Trainings defined much before the start of the LS.Consider IS37.

How to deal with newcomers (training center)

Access Safety “LS Mode” To be planned with DSO.This avoids spurious BIW

“Swap” between the access points

Flexibility necessary to handle incidents

Automatic procedure via IMPACT

Ch. Delamare GS-ASE

Page 40: Http://indico.cern.ch/event/373053/ GS activities during LS1 Christophe Delamare GS-ASE EDMS 1499839

GS feedback summarywhat I - keep II - improve III - change

List the different aspects in the management of the work carried out during the LS1

Define what should be kept and was an added value during the LS1

Define what you propose to improve in order to better manage the LS2

Define what was a bottleneck to carry out the work during the LS1 and needs to be changed for LS2

MAD personnel detection Improve/revisit the system

Notes de coupure Improve the understanding of the consequences (e.g. links between functional positions)

CSA involvement Dedicated team. The integrity of the envelope must be respected

Emergency preparedness Plan major drill involving all partners

Coordination in LHC & injectors

compulsory

Coordination in Meyrin Experimental areas

Planning commissioning. Stakeholders info

Who can operate the infrastructure

DSO tests Essential (and mandatory) Protect the slotsAvoid works on EIS just before the tests

Ch. Delamare GS-ASE