Upload
lymien
View
225
Download
0
Embed Size (px)
Citation preview
Hunua Quarry
Management Plan
This Quarry Management Plan (QMP) is a non-statutory document that has voluntarily
been prepared by Winstone Aggregates in general accordance with the relevant provisions
of the Papakura District Plan.
Winstone Aggregates, September 2009
Hunua QMP September 2009
Preamble
(a) Quarrying is a permitted activity at Hunua Quarry under the Papakura District Plan
(referred to from herein as PDP), subject to a range of various development controls.
The site also has existing use rights for the quarrying activity.
(b) Winstone Aggregates (referred to as Winstone from herein) is not formerly required to
prepare a QMP for the Papakura District Council (referred to as PDC from herein).
Despite this, Winstone has developed this QMP in consultation with representatives of
the community and PDC to help provide an assurance to the community that potential
environmental effects associated with quarrying at the site are appropriately managed
and controlled.
(c) A Site Liaison Group (from herein referred to as SLG) has recently been established to
help facilitate improved communication and ongoing good relations between Hunua
Quarry management and the community.
(d) This QMP will address all the same matters required by rule 6.13.8.1 (d) of the PDP.
It will also address procedures for continued consultation and liaison with the
community, a description of the existing quarry operations and any proposed changes
to these.
(e) Winstone will operate its Hunua Quarry in accordance with this management plan.
(f) This QMP will be reviewed at least every five years by Winstone.
Revision
This revision of the QMP has been undertaken in April 2009, to better reflect operational
requirements at Hunua Quarry.
Hunua QMP September 2009
TABLE OF CONTENTS
1. GENERAL INTRODUCTION ............................................................................................................. 5
1.1 BACKGROUND TO THE QMP ....................................................................................................................... 5 1.2 CHANGES OR AMENDMENTS TO THE QMP .................................................................................................. 6
2. BACKGROUND TO THE QUARRY .................................................................................................. 6
2.1 LOCATION ................................................................................................................................................... 6 2.2 HISTORY AND OWNERSHIP ......................................................................................................................... 8 2.3 CURRENT SITE LAYOUT .............................................................................................................................. 8 2.4 GEOLOGY ................................................................................................................................................... 8 2.5 WATER RESOURCES .................................................................................................................................. 11 2.6 VEGETATION ............................................................................................................................................ 11 2.7 ARCHAEOLOGY ......................................................................................................................................... 11
3. REGULATORY FRAMEWORK ....................................................................................................... 12
3.1 RMA HIERARCHY .................................................................................................................................... 12 3.2 PAPAKURA DISTRICT PLAN (QUARRY ZONE AND ADJOINING ZONES) ...................................................... 13 3.3 REGIONAL COUNCIL CONSENTS ............................................................................................................... 15
3.3.1 Water permits ...................................................................................................................................... 15 3.3.2 Air permit ............................................................................................................................................ 15 3.3.3 Regional Landuse – Sediment Control ................................................................................................ 15
3.4 HASNO .................................................................................................................................................... 15
4. QUARRY OPERATIONS (CURRENT AND FUTURE) ................................................................. 16
4.1 OVERVIEW ................................................................................................................................................ 16 4.2 DESCRIPTION OF ACTIVITIES .................................................................................................................... 16
4.2.1 Vegetation removal and site preparation ............................................................................................ 16 4.2.2 Soil stripping and stockpiling .............................................................................................................. 16 4.2.3 Overburden stripping and disposal ..................................................................................................... 16 4.2.4 Rock removal ....................................................................................................................................... 17 4.2.5 Processing rock ................................................................................................................................... 17
4.3 STORAGE AND DISTRIBUTION .................................................................................................................... 17 4.4 WATER MANAGEMENT .............................................................................................................................. 18 4.5 REHABILITATION AND LANDSCAPE WORKS ............................................................................................... 18
5. QUARRY DEVELOPMENT .............................................................................................................. 18
5.1 QUARRY PIT DEVELOPMENT..................................................................................................................... 18 5.2 OVERBURDEN STRIPPING AND DISPOSAL .................................................................................................. 18
6. ENVIRONMENTAL OBJECTIVE AND MANAGEMENT MEASURES .................................... 22
6.1 GENERAL ENVIRONMENTAL OBJECTIVE ................................................................................................... 22 6.2 EXPLANATION .......................................................................................................................................... 22 6.3 MEASURES TO ACHIEVE THE GENERAL ENVIRONMENTAL OBJECTIVE ....................................................... 22
6.3.1 Resource management framework ...................................................................................................... 22 6.3.2 Management measures ........................................................................................................................ 22 6.3.3 Environmental policy .......................................................................................................................... 23 6.3.4 Environmental management system .................................................................................................... 23 6.3.5 Quarry design...................................................................................................................................... 24
7. ENVIRONMENTAL EFFECTS ......................................................................................................... 25
Hunua QMP September 2009
4
7.1 BACKGROUND .......................................................................................................................................... 25 7.2 NOISE ....................................................................................................................................................... 25
7.2.1 Noise effects ........................................................................................................................................ 25 7.2.2 Noise objective .................................................................................................................................... 25 7.2.3 Explanation of noise objective ............................................................................................................ 25 7.2.4 Noise performance standards .............................................................................................................. 25 7.2.5 Measures to implement noise objective ............................................................................................... 26
7.3 GROUND VIBRATION AND AIR OVERPRESSURE .......................................................................................... 29 7.3.1 Effects of Blasting ............................................................................................................................... 29 7.3.2 Vibration and Air Overpressure Objective.......................................................................................... 29 7.3.3 Explanation of Objective ..................................................................................................................... 29 7.3.4 Measures to Implement Vibration and Air Overpressure Objective : ................................................. 29 7.3.5 Blasting performance Standards ......................................................................................................... 31
7.4 TRAFFIC .................................................................................................................................................... 32 7.4.1 Background ......................................................................................................................................... 32 7.4.2 Traffic objective .................................................................................................................................. 32 7.4.3 Explanation of traffic objective ........................................................................................................... 32 7.4.4 Measures to implement the traffic objective ........................................................................................ 32
7.5 DUST (AIR QUALITY) ................................................................................................................................ 33 7.5.1 Air Quality objective ........................................................................................................................... 33 7.5.2 Explanation of air quality objective .................................................................................................... 33 7.5.3 Measures to implement air quality objective ....................................................................................... 34 7.5.4 Air Quality Performance standards .................................................................................................... 35
7.6 LANDSCAPE AND VISUAL .......................................................................................................................... 36 7.6.1 Landscape and visual objective ........................................................................................................... 36 7.6.2 Explanation of landscape and visual objective ................................................................................... 36 7.6.3 Performance standards ....................................................................................................................... 36 7.6.4 Measures to implement the landscape and visual objective ................................................................ 36
7.7 REHABILITATION AND END USE OPTIONS ................................................................................................. 37 7.7.1 Current Rehabilitation and End Use Objectives ................................................................................. 37 7.7.2 Explanation of Rehabilitation and End Use Objectives ...................................................................... 37
7.8 HAZARDOUS SUBSTANCES ........................................................................................................................ 37 7.8.1 Hazardous substances objective .......................................................................................................... 37 7.8.2 Measures to meet the Objective........................................................................................................... 38
7.9 TANGATA WHENUA .................................................................................................................................. 39 7.9.1 Measures to Implement Objective ....................................................................................................... 39
8. MONITORING..................................................................................................................................... 41
8.1 DUST ........................................................................................................................................................ 41 8.2 NOISE (EXCLUDING BLASTING) ................................................................................................................. 42 8.3 GROUND VIBRATION, AIR OVERPRESSURE (BLAST NOISE) AND FLY ROCK ................................................. 42
9. APPENDICES ...................................................................................................................................... 43
Hunua QMP September 2009
5
1. GENERAL INTRODUCTION
1.1 Background to the QMP
(a) Quarrying is a permitted activity at Hunua Quarry under the Papakura District Plan
(referred to from herein as PDP), subject to a range of various development controls.
The site also has existing use rights for the quarrying activity.
(b) Winstone is not formally required to prepare a QMP for PDC. Despite this, Winstone
has developed this QMP in consultation with representatives of the community and
PDC to help provide an assurance to the community that potential environmental
effects associated with quarrying at the site are appropriately managed and controlled.
(c) This QMP will address all the same matters required by rule 6.13.8.1 (d) of the PDP.
It will also address procedures for continued consultation and liaison with the
community, a description of the existing quarry operations and any proposed changes
to these.
(d) The Policy section for the Quarry Zone in the PDP (6.13.6) states:
“To require a Quarry Management Plan for all land within the zone and which outlines
operational matters and which gives and indication of the proposed end-state of the
land once quarrying has ceased”
The Rules section for the Quarry Zone in the PDP (6.13.8.1 (d)) states:
“All quarrying and restoration shall be carried out in accordance with the Quarry
Management Plan which shall include the following information in plan form and in
explanatory material:
(i) demarcation of the area to be quarried;
(ii) existing contours;
(iii) an indication of final contours and floor levels including the proposals for the
coordination of final levels of adjoining land;
(iv) proposed ultimate drainage of quarried lands and include any water consents
that it may be necessary to obtain;
(v) an indication of the period over which quarrying will continue, and of staged
development
(vi) provision for the disposal and/or stockpiling of overburden, waste and
quarried material, including the area to be used for stockpiling;
(vii) areas for stockpiling topsoil (where applicable);
(viii) provision for screening unsightly features from public view and fencing
dangerous or potentially dangerous features;
(ix) description of methods to be employed to prevent contamination of air or
natural water and to comply with the Noise and Vibration provisions of these
rules;
(x) an indication of the route by which quarried material is to be removed from the
lot;
Hunua QMP September 2009
6
(xi) provision for the progressive restoration of the lot such that the land will be
left in such condition as the Council considers suitable for the establishment of
those uses to which that land may subsequently be put; and
(xii) description of methods to be employed to avoid, remedy or mitigate any
adverse effects of quarrying operations on identified significant places and
areas.”
(j) The overall purpose of this quarry management plan is to set out objectives and
measures to maintain and enhance environmental performance of Winstone‟s Hunua
Quarry while avoiding, remedying and mitigating adverse environmental effects.
These objectives and measures will be set in accordance with the principles and
policies of Winstone‟s Environmental Policy. This document is attached in Appendix
1.
1.2 Changes or amendments to the QMP
(a) Amendments to the QMP may be made by Winstone at any time. The Hunua Quarry
CLG and PDC will be notified of any significant changes to the QMP that are likely to
impact on the effects of quarrying beyond the boundary.
(b) A complete review of the QMP shall be made every five years by Winstone. The
Hunua Quarry CLG and PDC will be notified of the changes to the QMP resulting
from any review. At the time of review Winstone will consider any changes suggested
by the Hunua Quarry CLG or other resident(s).
2. BACKGROUND TO THE QUARRY
2.1 Location
Hunua Quarry is located in the Hunua Ranges, some 6km east of Papakura Civic Centre,
adjacent to the Hunua Gorge.
Figure 1 shows the location of Hunua Quarry.
This Quarry Management Plan deals with some 105ha of Winstone land in the Hays
Stream catchment and which is in the current Quarry Zone of the PDP.
Hunua QMP September 2009
7
Figure 1 Location of the Site
Hunua Quarry
Papakura
Hunua QMP September 2009
8
2.2 History and Ownership
Quarrying commenced in the Hunua Gorge on the land currently owned by Winstone in
1934. In 1955 Winstone purchased the main block of the Hunua site comprising some 101
hectares. The Symonds Hill resource south of the Middleton Road ridge was purchased in
1958. Other blocks of land were subsequently purchased, when they became available, to
provide a buffer around the land which was intended to be quarried. Figure 2 shows land
owned by Winstone.
2.3 Current Site Layout
Figure 3 shows the existing layout of the Hunua Quarry site including features such as the
site buildings, entrance/exit and processing plant. Figure 2 shows the area to be quarried in
the Hays Stream catchment.
2.4 Geology
The basement rocks which comprise the aggregate resource at Hunua Quarry consist of
hard, slightly metamorphosed siltstone to sandstone loosely termed “greywacke”. These
rocks were formed by deep burial of clay, silt and sand deposited on the ocean floor some
150 million years ago. During and after formation the rock was greatly deformed by earth
movements to produce the highly faulted and locally veined rockmass currently exposed in
the quarry.
Weathering of this greywacke varies from complete reduction of the greywacke to soil, to
fresh hard rock with minor limonite staining confined to the major joints.
Apart from the currently excavated quarry pit area, the greywacke is generally overlain by
a variable thickness of soft sandstones and siltstones of the Waitemata Group and some
thin ash beds. This soft rock, along with weathered greywacke, comprises the overburden
which must be removed prior to extraction of the rock for aggregate use.
Hunua QMP September 2009
9
Figure 2 Land Owned by Winstone Aggregates at Hunua Quarry
Land Owned by Winstone Aggregates at Hunua Quarry
Indicative Area to be quarried in the Hays Stream Catchment
Hunua QMP September 2009
10
Figure 3 Current Site Layout
Fixed Plant
Site Entrance
Hunua QMP September 2009
11
2.5 Water Resources
The quarry property comprises approximately 251ha, of which 128ha is contained within
the Hays Stream catchment. The remainder lies within the Symonds Stream catchment.
All current quarry activities occur within the Hays Stream catchment. Hays Stream has a
catchment area, upstream of the quarry, of some 11.5 sq km, a little more than half of
which comprises the Papakura Water Supply dam catchment.
Hays Stream is identified in the Water Quality chapter of the Auckland Regional Policy
Statement as a water body with significantly degraded water quality. Adjacent land use
has impacted on the water quality within Hays Stream. This includes both rural and urban
runoff as well as reduced flows below the Papakura Water Supply dam.
The groundwater table within the greywacke rock in the quarry is at approximately
RL65m. To sustain quarry development, the pit will be excavated into the groundwater
table.
Adjacent to the quarry, Hays Stream is perched above the greywacke groundwater table.
Both the Waitemata cover sequence and greywacke rock mass generally have low to very
low permeabilities, although occasionally locally enhanced by faulting and fracturing.
Discontinuous and ephemeral perched water tables are present within the quarry area.
Currently all drainage within the quarry operational area has been modified. Water
resources within the quarry operational area are limited to stormwater runoff and minor
perched, ephemeral groundwater seepages.
Water for the washing of aggregate and dust suppression purposes is currently taken from
surface water storage ponds. The quarry has resource consents to take water directly from
Hays Stream and to pump groundwater from the pit. An agreement is in place to take
water from the Watercare pipeline from the Hays Stream dam.
2.6 Vegetation
A study of the entire development area and immediate surrounds has been carried out by
Bioresearches. The study shows that the vegetation within the Winstone Hunua property
forms a mosaic of highly variable habitats both in terms of their botanical value and their
value as wildlife habitats. The draft Vegetation and Landscape Management Plan (VLMP)
outlines in greater detail how the overall vegetation resource on site will be managed
overtime to maintain its integrity. A copy of the draft VLMP can be viewed by prior
arrangement with the Quarry Manager.
2.7 Archaeology
A survey of the entire Winstone Hunua Site and immediate surrounds was carried out R
Clough and Associates in 1999. During this survey, no archaeological features were
observed within Winstone Aggregates property boundaries. The topography of much of
the property suggests that the likelihood of archaeological sites relating to Maori
occupation is low. Even in the area of regenerating native vegetation sites are unlikely. In
Hunua QMP September 2009
12
general, the property is steep, and has been modified by past quarrying activities, with
large portions of the property‟s natural landscape obscured by quarrying activities.
The presence of a fortified pa (archaeological site R12/663) immediately to the west of the
property indicates that Maori used the area and suggests that the property‟s central
ridgeline was likely to be part of a network of tracks formed by Maori, providing access
for instance to Pukekiwiriki Pa c.2km to the northwest (archaeological site R12/4). It is
also highly likely that the occupants of archaeological site R12/663 harvested the forest
resources (birds, fibres and wood), in the general area. However, the pa sites are not
located on Winstones property and will not be affected by the quarrying activity.
3. REGULATORY FRAMEWORK
3.1 RMA Hierarchy
(a) Use of the quarry is primarily governed by the provisions of the Resource
Management Act 1991. Activities in the quarry which are not permitted activities or
existing uses require resource consents in terms of the District Plan and any relevant
Regional Plans of the Auckland Regional Council.
(b) At a national level the Resource Management Act 1991 deals with the management of
natural and physical resources and establishes a hierarchy of plans and policy
statements.
(c) At a regional level the Regional Policy Statement considers issues of significance to
the region and provides policies for the management of land, sea and air resources.
The Auckland Regional Policy Statement contains a section on minerals. This section
has two objectives:
1. To avoid, remedy or mitigate the adverse effects on the environment of
mineral prospecting, exploration, extraction, processing and transportation.
2. To ensure that mineral extraction activities and mineral deposits which are
presently or potentially valuable for development in the Region are not
unnecessarily compromised, and the region’s need for rock material continues
to be met.
(d) Regional Plans can be prepared for particular natural resources, however it is not
mandatory for Regional Councils to produce these plans, except for the Regional
Coastal Plan. Currently the Auckland Regional Council‟s Sediment Control Plan is
the only Regional Plan directly relevant to the Quarry‟s operation.
(e) At a territorial level District Plans deal with land use issues and the effects of activities
on the environment. The PDP contains objectives, policies and rules that control land
use activities in the Papakura District.
Hunua QMP September 2009
13
(f) Section 10 of the RMA also allows activities that have been legally established in the
past to continue operating in a similar way. Hunua Quarry maintains existing use
rights for quarrying activity.
3.2 Papakura District Plan (Quarry Zone and Adjoining zones)
Apart from an eastern block of land owned by Winstone, the zoning of the property is
Quarry Zone in the PDP. Figure 4 shows the zoning in the district plan. The eastern block
of Winstone land mentioned above is in the Rural Papakura zone and is not included in this
management plan.
The Quarry zone is intended to provide for the continuation of quarrying and associated
uses subject to environmental controls on the operation of the quarry and the ultimate use
of the land. The permitted activities in the Quarry zone are:
Any quarry activity or industrial activity and any activity ancillary to the
quarry activities.
Permitted activities are required to comply with district plan rules which affect:
Building height.
Quarrying within 30m of site boundaries.
Yards for industrial and commercial uses other than quarrying
Building coverage.
Quarry Management Plan for quarry extension outside previous quarry plans.
Noise received at or within 30m of dwellings.
Vibration and noise from blasting.
Dust control.
Waste and water pollution.
Topsoil removal.
In the Quarry Zone, individual native trees of listed species are protected. A resource
consent is required for irreparable damage to a tree such as tawa, taraire, miro, rewarewa,
puriri if the tree is higher than 6m or has a trunk circumference of more than 0.5m when
measured 0.5m from the ground.
Papakura District Council granted consent in November 1999 to clear an area of such trees
from the eastern side of the existing quarry pit for pit expansion. Vegetation management
on Winstone's land is comprehensively covered within the draft VLMP.
Hunua QMP September 2009
14
Figure 4 Land Zoning in the Papakura District Plan
Hunua QMP September 2009
15
3.3 Regional Council Consents
3.3.1 Water permits
Winstone holds consents for the following activities:
To take surface water from stored run-off for dust suppression and aggregates
washing in a quarry operation (Permit No. 938593, Auckland Regional Council)
To take surface water from Hays Stream for dust suppression and aggregate washing
in a quarry operation (Permit No. 936019, Auckland Regional Council)
To authorise the taking of groundwater for quarry dewatering and use in quarry
operations in accordance with Section 14 of the Resource Management Act 1991
(Permit No. 24893, Auckland Regional Council)
3.3.2 Air permit
Winstone Aggregates currently holds an air discharge permit (Permit No. 949046,
Auckland Regional Council).
3.3.3 Regional Landuse – Sediment Control
Winstone currently holds the following permits for sediment control;
To discharge groundwater and sediment-laden stormwater into Hays Stream at
discharge point J. (Permit No. 25032, Auckland Regional Council)
To discharge groundwater and sediment-laden stormwater into Hays Stream at
discharge point M. (Permit No. 25033, Auckland Regional Council)
To discharge groundwater and sediment-laden stormwater into Hays Stream at
discharge point C. (Permit No. 24908, Auckland Regional Council)
Winstone has developed a Sediment and Erosion Control Plan (January 2001) for the Hays
Stream Catchment area. This outlines site specific sediment control measures carried out
on site, in accordance with the company Environmental Management System. A copy of
the Sediment and Erosion Control Plan can be viewed by prior arrangement with the
Quarry Manager.
Winstone holds an additional permit (Permit No. 29408, Auckland Regional Council) for
Land Use Consent: Sediment Control, for the construction of an overburden disposal area
and access road at the „Hay Paddock‟. This permit applies to land within the quarry zone
and in the adjoining rurally zoned land owned by Winstone Aggregates located
immediately to the east of the quarry zone.
3.4 HASNO
In accordance with the Hazardous Substances and New Organisms Act 1996 Winstone
holds a Dangerous Goods Licence for Hunua Quarry. This licence authorises storage of
hazardous substances such as compressed gases and diesel required to be stored on site. A
copy of this licence is displayed in the quarry weighbridge office.
Hunua QMP September 2009
16
4. QUARRY OPERATIONS (CURRENT AND FUTURE)
4.1 Overview
The purpose of the quarry operation is to extract the rock from the ground and process it
for use as building, construction and roading aggregates. The process of transforming rock
from the ground into aggregate products comprises firstly the stripping of vegetation, soil
and low quality material overlying the rock resource. The next step is to loosen and
fragment the rock from the ground with the use of explosives and/or heavy machinery.
The rock is then excavated by heavy machinery and either stockpiled or transported to the
plant for further crushing and screening into various sizes and grades for sale. The
following sections are intended to provide a more detailed description of these activities.
4.2 Description of Activities
The methods used in future quarry operations on the site are likely to be generally similar
to those used at present. However it is expected that specific machinery and methods of
extraction will vary in the future as technology develops and machinery and quarrying
techniques are replaced. The following activities broadly summarise the current and
proposed quarry operational activities that occur on the site:
4.2.1 Vegetation removal and site preparation
This involves removal of vegetation and any structure.
4.2.2 Soil stripping and stockpiling
As the quarry pit expands, soils and subsoils are stripped, transported and stockpiled using
motor scrapers, bulldozers and/or excavators and trucks. These materials may be used in
the construction of bunds for landscape enhancement and noise control, stored for future
rehabilitation work.
4.2.3 Overburden stripping and disposal
As the quarry pit expands, overburden materials are stripped, transported and deposited.
Such materials have insignificant commercial value but are required to be removed to
facilitate extraction of the aggregate resources, employing a similar range of machinery as
used for soil/subsoil excavation.
Hunua QMP September 2009
17
4.2.4 Rock removal
The quarrying of softer aggregate resource types uses excavators and/or bulldozers and
loaders to excavate and load materials onto trucks for transport to the processing plant,
stockpiles or offsite. The quarrying of harder rock requires drilling and blasting with
explosives, followed by loading onto trucks using excavators or loaders for transport to the
processing plant, stockpiles or offsite.
Hunua Quarry uses drilling and blasting practices typical of New Zealand operations of a
similar scale. All blasts are designed and managed by trained and qualified personnel
taking into account a variety of factors including District Plan requirements. Typically at
Hunua blasting holes are drilled with 102mm diameter. These holes are loaded with either
bulk or bagged ANFO (Ammonium Nitrate and Fuel Oil) and are currently initiated with
non-electric detonators to reduce the potential for vibration and air blast.
4.2.5 Processing rock
Rock is processed into aggregate products, using crushing, screening, washing, blending
and conveying machinery. The products are moved by trucks, loaders or conveyor to
storage bins or stockpiles.
Winstone has a new aggregate processing plant that is capable of producing a full range of
aggregates. The plant has been specifically designed to maximise the Hunua rock resource
while at the same time minimising the potential for adverse environmental effects such as
noise and dust.
Special environmental controls include:
Housing the main processing plant to contain the potential effects of noise and dust.
Covering all potentially dust generating conveyors.
Spray bars at potentially dust generating material transfer points.
Mist sprays beneath all crushers.
The plant has been designed with the capability of washing semi-processed and finished
aggregate products and a water control and treatment system has been incorporated into the
plant to manage aggregate washings. This system is generally a closed circuit system with
only makeup water added to compensate for water lost through evaporation or soaked up
the aggregate products themselves.
From time to time depending on market conditions, mobile aggregate processing plants are
used at Hunua Quarry to supplement the fixed plant operation. These plants are subject to
the same environmental controls as all other operations on site and are typically located in
areas where adverse effects can best be avoided.
4.3 Storage and distribution
Aggregate products are transported around the site with the use of a range of mobile plant
and equipment. Wheel loaders are used to load customers trucks for distribution off site.
Hunua QMP September 2009
18
4.4 Water management
Water management is a term used to describe all activities carried out on site to control and
utilise surface water runoff, process water and groundwater resources. It includes a range
of activities such as the construction and maintenance of structures such as drains, ponds,
diversion channels and sumps through to the implementation of water monitoring
equipment and pumps. Hunua Quarry has a separate Sediment and Erosion Control Plan
(January 2001) that sets out the activities that will be carried out at the site over time.
4.5 Rehabilitation and landscape works
Where appropriate and practicable, excavated and disturbed areas are rehabilitated with the
placement of overburden and soils and then re-vegetated with suitable species. The site
has a separate VLMP that illustrates and describes how rehabilitation of different areas of
the quarry will occur over time as the quarry develops.
5. QUARRY DEVELOPMENT
5.1 Quarry Pit Development
Figure 5 shows the indicative short term staging of quarry development, and how Winstone
presently proposes to develop the quarry.
The staging of development at the quarry will ultimately be dependent on a number of
external factors outside Winstone‟s control e.g. the state of the market, the level of
knowledge of subsurface geology, the level of sales and production capacity limits. Figure
5 only illustrates how Winstone currently anticipates development to occur at the quarry.
The quarry pit design has been carried out by qualified mine design engineers with input
from registered geotechnical engineers to optimise quarry pit development and ensure the
safety of the cut slopes. Typically Hunua Quarry is developed with a series of 15 metre
high benches.
5.2 Overburden Stripping and Disposal
Overburden will continue to be removed from above the quarry faces as they advance
towards the east and south of the current quarry pit. These materials will be transported on
internal haul roads to overburden disposal areas where they will be placed and treated
according to the relevant design requirements.
Figure 6 details the location of the main Hunua overburden disposal area together with
potential future overburden disposal areas.
Hunua QMP September 2009
19
The overburden disposal areas will be designed to take into account the surrounding
topography, surface water drainage, geotechnical constraints and proposed end use. The
volume of material that can be contained in the site has been balanced with the stripping
requirements of the quarry pit.
The overburden disposal area immediately to the east of the quarry is known as the Hay
Paddock Area, see Figure 7. This area is partly within the quarry zone and partly within
the adjoining rural zone. Activities within this area the subject of a resource consent
application to Papakura District Council at the time of this December 2004 revision.
Figure 5 Quarry Pit Development showing Stage Outline
1998 Pit Extension
2001 Pit Extension
2004 /2005 Pit Extension
Hunua QMP September 2009
20
Figure 6 Quarry Pit Development Showing Overburden Disposal Areas
Overburden Contoured & Planted 1998 - 2001
Overburden Contoured & Planted 2001 - 2005
Other areas of site planted 1998 - 2001
Hunua QMP September 2009
21
Figure 7: Location of Hay Paddock Overburden Disposal Area
Hunua
Quarry
Hay
Paddock
Area
KEY Property Boundary Quarry Zone Boundary Hay Paddock Earthworks
Hunua QMP September 2009
22
6. ENVIRONMENTAL OBJECTIVE AND MANAGEMENT
MEASURES
6.1 General Environmental Objective
To manage the extraction and processing of a valuable aggregate resource while
avoiding, remedying or mitigating adverse effects on the environment and
enhancing environmental performance wherever practicable.
6.2 Explanation
(a) The continued and efficient extraction of aggregate resources in Auckland Region is
identified in the District Plan as an important resource issue. At the same time,
Winstone has an obligation to ensure that the environment is not detrimentally affected
by the continued operation of the quarry.
(b) Parts 3 and 4 of Winstone‟s Environmental Policy (see Appendix 1) call for
management to continuously improve activities and to lift standards and performance.
6.3 Measures to achieve the general environmental objective
6.3.1 Resource management framework
(a) To achieve the general environmental objective Winstone will also continue to
operate within the bounds of the legislative framework for resource
management in New Zealand as summarised above.
6.3.2 Management measures
(a) Winstone‟s management measures are provided here to give an insight into
how Winstone intends to manage this quarry. It can be expected that these
management measures will change over time as Winstone strives to achieve
continuous improvement in environmental performance.
(b) The current management measures and procedures are explained in sections
6.3.4 - 6.3.5 below. The company recognises the effects its operations may
have on the environment and is continually searching for ways in which these
effects can be avoided, remedied or mitigated against.
Hunua QMP September 2009
23
6.3.3 Environmental policy
(a) Winstone‟s Environmental Policy (see Appendix 1) sets out the overall goals
for the company‟s environmental performance. The environmental policy is
used in the following ways to make staff and visitors on site aware of the
importance of good environmental performance;
displayed to personnel on site
displayed to the public in reception areas
referred to when setting annual objectives and targets
6.3.4 Environmental management system
(a) Winstone Aggregates has in place an Environmental Management System
(EMS) that is based upon the framework established by ISO 14001-
Environmental Management Systems - Specification with Guidance for Use.
(b) The EMS is a tool that ensures accountability for environmental performance,
providing a management framework that encourages openness and
environmental improvement at all operational sites.
(c) Winstone‟s Environmental Management Manual (EMM) documents the EMS
and ensures that the Environmental Policy is implemented at operational sites.
The Manual covers such things as:
legal requirements that each site must adhere to;
setting environmental targets and objectives for individual quarries;
procedures for management of effects on the environment;
management structure and responsibilities;
record keeping of each quarry‟s environmental effects;
communication including environmental reporting and information sharing;
review of the EMS and Environmental Policy.
(d) Environmental Record and Procedures Manuals (ERPMs) are kept at each site
and contain environmental diaries that are used to record the results of
compliance monitoring, complaints, objectives and targets. Regular reporting
of compliance to senior management enables appropriate action to be taken.
Monthly environmental reports are forwarded to the General Manager, the
Business Unit Manager and the Environmental Coordinator by each site
manager.
(e) Records of all verbal and written complaints will be maintained in the site
ERPM. The records will be kept for no less than five years and will include:
name and details of complainant;
description of complaint;
any follow-up action.
Hunua QMP September 2009
24
(f) Internal site inspections by senior management are made regularly for each
quarry site. The purpose of these inspections is to reinforce the importance of
good environmental performance and continual improvement.
6.3.5 Quarry design
(a) To achieve the general environmental objective Winstone will design the
quarry in a way that maximises the extraction of the aggregate resource within
the property boundary in accordance with resource consents, district and
regional plans and geotechnical constraints.
(b) The operation of the quarry is regulated under the Health and Safety in
Employment (HSE) Act 1992 and more specifically the Mining Administration
Regulations 1996. These regulations are administered by The Ministry of
Labour through Occupational Safety and Health (OSH).
Hunua QMP September 2009
25
7. ENVIRONMENTAL EFFECTS
7.1 Background
Quarrying has the potential to have a range of adverse environmental effects. This section
identifies these effects and sets out the relevant environmental standards that the quarry has
to achieve and the measures and methods for how it will achieve these standards.
The standards taken from the District Plan provisions are shown in italics below.
7.2 Noise
7.2.1 Noise effects
(a) Noise is generated by a number of different activities carried out at the quarry
including: drilling; rock breaking; crushing; extraction; trucks; machinery and
blasting. If noise is not controlled at the quarry there is the potential for noise to
cause a nuisance to people who live near the quarry.
(b) It is important to note that blast vibration and noise generated by blasting (air blast
overpressure) are treated as separate effects within this document.
7.2.2 Noise objective
To avoid, remedy or mitigate adverse effects of noise generated by on-site activity
on the residents of dwellings and on business activities in the vicinity of the
quarry.
7.2.3 Explanation of noise objective
Excessive noise of sufficient duration or continuity can be detrimental to public health and
to the amenity of adjacent land. The noise objective is an intention by Winstone to keep
noise levels from the quarry site at an acceptable level and to provide the community with
an assurance on the level of noise that they can expect from the quarry and its operations.
7.2.4 Noise performance standards
Except for the Hunua Quarry Aggregate Resource Protection Area, the L10 noise level as
measured at or within 30 metres from any dwelling shall not exceed the following limits:
Monday to Friday between the hours of 0700 – 1800 and Saturday between the hours of 0700 –
1700.
Hunua QMP September 2009
26
55dBA
Al all other times including Sundays and Public Holidays – 45 dBA.
Noise – Hunua Quarry Aggregate Resource Protection Area
The L10 noise level measured at or within 30 metres from any occupied dwelling existing at 1
January 2001 shall not exceed the limits above.
The L10 noise levels as measured at any point on the Quarry Effects Line as shown on figure [8]
shall not exceed the following limits:
Monday to Friday between the hours of 0700-1800 and Saturday between the hours of 0700-
1600.
65dBA
At all other times including Sundays and Public Holidays - 45 dBA.
The noise levels shall be measured and assessed in accordance with the requirements of New
Zealand Standard NZS 6801: 1991 Measurement of Sound and New Zealand Standard NZS
6802: 1991 Assessment of Environmental Sound.
The noise shall be measured with a sound level meter complying with the International Standard
IEC 651 (1979): Sound Level Meters, Type 1.
Any construction work on site will be carried out in compliance with the New Zealand Standard
for Construction Noise NZS 6803: 1999.
7.2.5 Measures to implement noise objective
To comply with the District Plan and to keep noise to an acceptable level Winstone implements a
range of operational practices that include the following measures;
(a) Managing the time and location of particularly noisy operations around the site to
ensure compliance with the performance standards.
(b) While the company prefers to avoid operations on Sundays, work which complies
with the noise levels for Sunday permitted by the District Plan may be necessary to
meet particular contract obligations.
(c) The majority of fixed processing plant, excluding conveyors will be housed within
structures that reduce the noise level at the boundary of the quarry.
(d) Machinery will be regularly maintained to ensure that noise produced from
machinery is kept to a practicable minimum.
Hunua QMP September 2009
27
(e) Bunds have been constructed where appropriate on quarry boundaries to reduce the
effects of noise beyond the boundary of the quarry.
(f) To ensure that the noise performance standards set in the District Plan are met,
monitoring on representative occasions will be carried out using appropriate
equipment, methods and personnel.
Hunua QMP September 2009
28
Figure 8 Quarry Effects Line Map
Hunua QMP September 2009
29
7.3 Ground vibration and air overpressure
7.3.1 Effects of Blasting
Blasting is used in the quarry as a means of fragmenting rocks prior to processing.
Blasting causes noise, vibration and air overpressure (air blast noise). These effects have
the potential to have a “startling effect” on people, especially when people are not
expecting the blast. Other potential effects of blasting are dealt with in the section on
discharges to air.
Ground vibration and air overpressure from blasting also have the potential, if not
controlled, to adversely affect the structural stability of buildings and potential to adversely
affect the amenity value of land in the vicinity of the quarry.
7.3.2 Vibration and Air Overpressure Objective
To avoid, remedy or mitigate adverse effects of vibration and air overpressure (blast
noise) from blasting on neighbouring people and buildings.
7.3.3 Explanation of Objective
The uncontrolled use of explosives in terms of noise, intensity and duration would have an
unacceptable effect on the amenity values of adjoining residential land. This vibration and
air over pressure objective is an intention by Winstone to keep the effects of vibration and
air overpressure to an acceptable level using best practicable means and therefore provide
an assurance to the community that the effects of blasting are being controlled.
7.3.4 Measures to Implement Vibration and Air Overpressure Objective :
To keep vibration and air overpressure to an acceptable level Winstone implements a range
of operational practices that include the following :
(a) Blasting shall only be carried out between 9:00am - 5:00pm Monday to Friday and
will be restricted to two times per day except where necessary for emergency or
safety reasons. Typically blasting is carried out between 10:00 – 10:30, 2:00 – 2:30
and 4:30 – 5:00.
(b) If blasting is to occur at an irregular time or for emergency or safety reasons,
potentially affected neighbours will be notified whenever possible.
Hunua QMP September 2009
30
(c) Records will be maintained for each blast including:
the time of the blast;
location of the blast;
weather conditions;
total charge weight;
maximum instantaneous charge;
volume of rock blasted;
position of any monitoring; and
distance from blast to monitoring positions.
(d) Winstone will undertake monitoring of representative blasts by reliable and
appropriate methods to ensure the set limits for vibration and air overpressure are not
exceeded. These records shall be made available to Papakura District Council on
request.
(e) Removing rock, where practicable, with an excavator by free digging or ripping
instead of blasting.
(f) Each blast will be designed and supervised by an appropriately qualified person and
shall take into account:
general geological conditions;
cavities and fissures;
distance to the boundary;
maximum instantaneous charge;
direction of initiation;
orientation of the face; and
weather conditions.
(g) The effects of air overpressure are controlled by:
use of good quality stemming material;
maintenance of correct stemming height;
maintenance of adequate burden on all free faces;
optimisation of drill patterns to reflect good geometrical design;
optimisation of the delay sequence to maintain adequate relief;
minimisation of secondary blasting; and
close examination of the face for weak seams and clay bands where
explosive products may vent to free air.
All the factors above individually or in conjunction with each other can influence the level
of effects produced by any one blast. Ensuring that all these factors are taken into
consideration when designing a blast will increase the level of certainty into what the
potential vibration and air overpressure effects will be.
(h) Records will be maintained of all complaints relating to blasting including:
name and details of complainant;
description of complaint; and
any follow-up action.
Hunua QMP September 2009
31
7.3.5 Blasting performance Standards
Vibration and Airblast
(a) For the Hunua Quarry Aggregate Resource Protection Area, the noise created by
the use of explosives measured at a notional boundary of 20m from any occupied
dwelling existing as at 1 January 2001 shall not exceed a peak overall sound
pressure of 128dBL peak.
(b) For the Hunua Quarry Aggregate Resource Protection Area, the noise created by
the use of explosives measured at any point on the Quarry Effects Line as shown
on figure [8] shall also not exceed a peak overall sound pressure of 133dBL peak
(97.5% compliance) and a maximum of 140 dBL peak (99% compliance).
(c) All blasting shall be restricted to between 9.00 am and 5.00pm Monday to Friday
except where necessary because of safety reasons.
(d) Blasting shall be confined to two occasions per day except where necessary for
safety reasons.
(e) Where because of irregular or infrequent nature of blasting startling of
neighbouring tenants is likely than adequate public notification shall be given to
those affected by this.
(f) For the Hunua Quarry Aggregate Resource Protection Area, when blasting the
limit of particle velocity (peak particle velocity) shall not exceed the following
limits:
when measured on any foundation of an adjacent building not connected
with the quarry site existing at 1 January 2001; 20 mm/s for commercial
buildings (97.5% compliance), or 5 mm/s for dwellings and buildings
intended for domestic use (97.5% compliance), and a maximum of 10 mm/s
(99% compliance).
when measured at any point on the Quarry Effects Line as shown on Figure
[8 ] 20 mm/s (97.5% compliance).
Peak particle velocity means the maximum particle velocity in any of three
mutually perpendicular directions. The units are millimetres per second (mm/s).
Explanatory Note
The above standard, requires the peak particle velocity on any foundation of an
adjacent building outside the ARPA Area to meet the compliance level at that
point. It is recognised that the person carrying out the monitoring might not
have the right of access or the ability to monitor directly on the foundation.
Measurement should normally be carried at a suitable point(s) representative of
Hunua QMP September 2009
32
the adjacent building and demonstrate that ground vibrations are below the
levels required in the Rule at the building foundation.
(g) Monitoring vibrations and air overpressure (air blast).
(h) Instruments to measure vibrations and air overpressure and methods of
measurement shall comply with the Australian Standard AS2187.2 1993 applying
measurement and assessment in a statistical manner.
(i) Monitoring shall be sufficient to assess compliance with the Rule at all likely
affected sites.
7.4 Traffic
7.4.1 Background
The effects of traffic on public roads outside the quarry site are generally beyond the
control of Winstone and outside the scope of the District Plan. Winstone will however
take any practicable steps to reduce the effects of traffic directly related to the quarry
operation. These effects are associated with noise, dust, safety and congestion.
7.4.2 Traffic objective
To minimise the adverse effects of traffic, directly generated by quarrying
activity, on the environment, where practicable.
7.4.3 Explanation of traffic objective
(a) This objective is an intention by Winstone to avoid, remedy or mitigate the
adverse effects associated with quarry traffic. The performance standards
associated with achieving this traffic objective are inclusive in those standards
dealing with the specific effects of noise and dust. The traffic objective is an
assurance to the community that Winstone will control the effects of traffic
within its site and where practicable outside the quarry site.
7.4.4 Measures to implement the traffic objective
(a) Hunua Quarry is authorised to operate on a 24 hours basis, subject to meeting
relevant performance criteria specific in Papakura District Plan (as at 6 August
2008 as referred to by Certificate of Compliance ref 9354) such as limits
relating to operational noise. This means that operational activities associated
with product dispatch will occur at Hunua Quarry during night time hours.
These night time operations are a critical component of the quarry‟s activities
and are necessary to meet the demand for aggregate throughout the region.
Hunua QMP September 2009
33
(b) While the opening of the quarry for general sales will generally be restricted to
the hours set out below, large contract jobs and cartage by Winstone‟s own
fleet may take place at all times.
Monday to Friday 6:00am – 5:30pm
Saturday 6:00am – 4:00pm
All other times As described above
Hours may occasionally vary depending on customers‟ requirements.
(c) All Winstone owned and operated vehicles will be regularly maintained and
checked to ensure that appropriate noise suppression devices are installed and
operating effectively.
(d) Any customer whose vehicle is noted as having excessive emissions due to
lack of maintenance will be requested to rectify the problem and warned that
they may be refused products on their next visit if the problem persists.
(e) Winstone loader drivers will be appropriately trained to help ensure that
customers trucks are loaded securely. All trucks leaving the quarry with loads
of quarry products will be checked for insecure loads. This will also help
reduce the risk of quarry products being spilled on public roads. It is however
ultimately the responsibility of the individual truck drivers to make sure their
load is secure before they drive on a public road.
(f) A wheel wash will be used to spray truck wheels as they leave the quarry site.
This will help reduce the risk of dust being carried onto public roads by trucks.
7.5 Dust (Air quality)
(a) Dust can be generated by a variety of different activities that are carried out at the
quarry site including: drilling; rock breaking; crushing; extraction; trucks; machinery
and blasting.
7.5.1 Air Quality objective
To avoid, remedy or mitigate adverse nuisance or amenity effects of dust from
quarry operations beyond the boundaries of the quarry site.
7.5.2 Explanation of air quality objective
Of the potential discharges to air, particulate emissions of dust have the greatest potential
for off-site effects. However, provided the operation site is well controlled and the
Hunua QMP September 2009
34
activities well managed, particulate emissions can be reduced to a level where any adverse
health or nuisance effects, or damage to vegetation will not occur.
7.5.3 Measures to implement air quality objective
(a) Locating the fixed processing plant away from quarry boundaries (Figure 3).
(b) The fixed processing plant is clad in areas where dust generation could become a
nuisance.
(c) Potential dust generating conveyors are covered where practicable to contain dust.
(d) Fitting exposed transfer points with fixed water sprays to suppress dust emissions
wherever practicable.
(e) Large volumes of water are maintained on site and are available for dust suppression
purposes.
(f) Areas of exposed material with dust generating potential (e.g. clay banks) are kept to
a practicable minimum.
(g) A water tanker is used to spray water on working areas during dry and windy
weather conditions.
(h) Potentially dusty activities are not carried out when weather conditions give rise to
offsite dust emissions.
(i) Blasting will be restricted if windy conditions are likely to carry visible dust
emissions beyond the quarry boundary where they could create a nuisance.
(j) Minimising dust emissions from blasting by sequential firing and using minimum
force.
(k) Revegetating areas that will not be further disturbed as soon as possible.
(l) Efficient extraction of dust on drilling equipment.
(m) Proper maintenance and tuning of the vehicles and equipment also assists in avoiding
any off-site effects.
(n) A wheel washing facility is used at the exit to reduce the potential of material from
trucks wheels to be deposited on the roadway outside the site.
(o) Good blasting practice, including using waterproof explosives in areas where
groundwater levels are high, to avoid the degradation of the explosive, will minimise
incomplete combustion and any associated NOx emissions.
(p) The quarry manager or his or her nominee shall record daily:
Hunua QMP September 2009
35
visual emission of dust;
sources of visual emission of dust;
measures initiated in response to visual emission of dust to prevent recurrence
or mitigate effects;
water cart use (yes/no);
weather conditions (wind strength and direction, rainfall).
7.5.4 Air Quality Performance standards
The air permit for the site states:
(a) That the processes shall be operated by the Consent Holder in such a manner and
the operations supervised and the plant maintained so as to ensure that discharges of
contaminants to air are kept to a practicable minimum.
(b) That beyond the boundary of the site there shall be no odour, dust or fume caused by
discharges from the site which, in the opinion of an enforcement officer, is noxious,
offensive or objectionable.
(c) That no discharges from any activity shall give rise to visible emissions, other than
water vapour and steam, to an extent which, in the opinion of an enforcement officer,
is noxious, offensive or objectionable.
(d) That over the period 1 November to 30 April each year the consent holder shall
undertake monitoring of total suspended particulate in ambient air in the vicinity of
the site.
(e) That without prejudice to the generality of Conditions 4 and 6, if the monitoring
shows that the total suspended particulate in ambient air at or beyond the boundary
of the site, as measured in accordance with Condition 17, exceeds 100 micrograms
per cubic metre as a 24 hour average, an investigation shall be initiated by the
Consent Holder as to the probable causes of the exceedence.
(f) That, if the cause of the elevated levels of total suspended particulate is identified as
being an activity undertaken on the Consent Holder’s site, then as far as practicable,
action shall be taken by the Consent Holder to reduce those discharges to the
satisfaction of the Manager.
(g) That any results of total suspended particulate in ambient air tests showing
exceedences of the prompt given in Condition 18 shall be reported by facsimile to the
Manager as soon as practicable. A summary of all monitoring results, including
references to wind and rainfall data, and any remedial action taken shall be
submitted to the Manager by 1 June each year.
Hunua QMP September 2009
36
(h) The Consent Holder shall continuously record and be able to make available wind
speed, wind direction and rainfall data.
The District Plan provisions states that:
(i) Quarry owners and operators must ensure that adequate measures are taken to
control the emission of dust from all parts of the site.
7.6 Landscape and visual
(a) Quarrying can change the landscape and subsequently affect the visual amenity of an
area. Activities carried out within the quarry can also have visual effects on
neighbouring residents.
7.6.1 Landscape and visual objective
To minimise adverse landscape and visual effects of the quarry operations on the
surrounding community.
7.6.2 Explanation of landscape and visual objective
The quarry has been an existing activity on the site for a considerable length of time. It is
Winstone‟s intention to minimise the landscape and visual effects of the quarry operations
on the surrounding community and provide an assurance to neighbours that Winstone will
take practicable steps to carry this out.
7.6.3 Performance standards
(a) The District Plan states the following with regard to yard in the Quarry Zone:
No quarrying shall be carried out within 30 metres of each site boundary unless the
appropriate resource(s) consent is obtained.
7.6.4 Measures to implement the landscape and visual objective
Hunua QMP September 2009
37
(a) A VLMP is being developed for the site which sets out how the vegetation and
landscape will be managed over time at the quarry. This document should be referred
to for a comprehensive description of all measures that will be taken on site to achieve
the landscape and visual objective.
(b) Where appropriate and practicable new buildings will be designed in a way that
minimises the visual impact on neighbouring sites. For example colour, height,
screening and relationship to the topography of the surrounding area.
(c) Install and manage operational and access lights to avoid unnecessary light spill in the
locality.
(d) Provide earth mounding and vegetation screening to mitigate visual effects of quarry
operations and on-site truck routes where practical.
7.7 Rehabilitation and End Use Options
There are many options available for progressive rehabilitation and for end use once
quarrying has been completed at the site. Winstone does not know what the end use for the
quarry will be at this stage.
7.7.1 Current Rehabilitation and End Use Objectives
To design and develop landforms which enable effective short-term rehabilitation
during the operation of the quarry and to consider practicable options for end use of
the quarry site.
7.7.2 Explanation of Rehabilitation and End Use Objectives
The completion of quarrying is currently predicted to be more than 50 years away. This
fact makes it very difficult and impracticable to make a final decision on how rehabilitation
should take place and what the end use shall be.
7.8 Hazardous Substances
This section of the management plan deals with issues relating to the release of hazardous
substances from storage facilities or during their use, transport or disposal within the
quarry site. The relevant objective is:
7.8.1 Hazardous substances objective
To avoid, remedy or mitigate the potential for adverse effects on the environment of
the storage, use, disposal and transportation of hazardous substances such as fuels,
oils or materials used for blasting.
Hunua QMP September 2009
38
The significant hazardous substances that are currently stored on the site are diesel, oils,
compressed gasses and explosives.
7.8.2 Measures to meet the Objective
(a) The storage and/or the production of only the necessary quantities of material for
the operation of the quarry.
(b) Based on experience at other quarries, the storage requirements have been
determined such that inventory control and “just in time” delivery will ensure that
only the imminent operational requirements are stored on the site.
(c) All transport, storage and operating conditions meet the requirements of licences
under the Hazardous Substances and New Organisms legislation and the relevant
standard for the transportation of hazardous substances NZS 5433.
(d) Until regulations are developed under the HSNO Act, the transitional regulations
stemming from the Explosives Act 1957 and the Dangerous Goods Act 1974 will
be applicable. The relevant requirements will be complied with to the satisfaction
of inspectors from the Department of Labour and Papakura District Council.
(e) Explosives and detonators are generally not stored on site.
(f) Fuel, lubricant and waste oil storage, dispensing and operating facilities are
designed and operated in such a way that contamination of soil and water is
avoided as far as practicable.
(g) All bulk liquid storage tanks will be in or adjacent to the Workshop. Heavy tyred
vehicles are refuelled on a concrete pad adjacent to the diesel bulk storage tank.
Heavy tracked vehicles are refuelled in place in the pit. Rain falling on this
refuelling pad is directed to an oil separator before entering the stormwater
drainage system. Oil separators are cleaned out on a regular basis.
(h) Drums and smaller containers are stored on bunded pads in the workshop., Drip
trays are provided for any in use, in and around the workshop.
(i) Compressed gases in the workshop are stored in racks and are suitably restrained
when in use.
Hunua QMP September 2009
39
7.9 Tangata Whenua
Objective
To operate the quarry in a manner which recognises and provides for the
relationship of Maori and their culture and traditions with their ancestral lands,
water, sites, wahi tapu and other taonga.
7.9.1 Measures to Implement Objective
Tangata whenua will be identified and consultation will be undertaken to agree on a
procedure to deal with any discovery of koiwi and taonga.
Procedures such as the following would be followed should evidence or indications of
koiwi or taonga be discovered :
Immediately koiwi or taonga have been discovered, activity around the area of
the discovery will cease;
An archaeologist will immediately arrange to secure the area to ensure that the
suspected koiwi or taonga remain untouched;
Tangata whenua and the Historic Places Trust will be advised that it is
suspected that koiwi or taonga have been uncovered on the site;
A representative of tangata whenua will be asked to contact relevant kaumatua
who are to guide and advise Winstone as to the course of action to be followed
and to immediately advise the archaeologist of the identity of the kaumatua and
such other details as may be appropriate in the circumstances;
The archaeologist will arrange staff/Papakura District Council to meet and
guide kaumatua, police, DOC or Historic Places Trust representatives to the
site, and assist with any requests that they may make;
If the kaumatua are satisfied that the koiwi or taonga are of Maori origin the
kaumatua will implement appropriate procedures and will communicate this to
Winstone, NZ Police and other relevant parties;
Winstone will ensure that the kaumatua are given the opportunity to perform
karakia and other religious or cultural ceremonies and activities considered
appropriate in accordance with tikanga Maori (Maori custom and protocol);
and
Winstone will make available on their property other suitable, secure non
working areas for the reburial of koiwi or taonga if tangata whenua so wish.
Hunua QMP September 2009
40
Definitions
“Koiwi” means human remains such as skeletal material.
“Taonga” refers to cultural artefacts such as implements, weapons or decorations
traditionally and historically utilised by tangata whenua and includes parts and remains
thereof.
Hunua QMP September 2009
41
8. MONITORING
(a) The site Environmental Records and Procedures Manual (ERPM) contains all
relevant details relating to the carrying out of all required monitoring including:
when it has been carried out;
where it is has been carried out;
how it has been carried out; and
the monitored results.
(b) The ERPM shall also contain records of all complaints received relating to
environmental effects associated with the quarry operation:
The record shall include the following information:
name and details of complainant;
description of complaint; and
any follow-up action.
(c) The ERPM is available for inspection only at the quarry site, following prior
arrangement with the quarry manager.
8.1 Dust
(a) The quarry manager or his nominee shall record daily:
› visual emission of dust,
› sources of visual emission of dust;
› measures initiated in response to visual emission of dust to prevent recurrence or
mitigate effects.
› water cart use (yes/no); and
› weather conditions (wind strength and direction, rainfall).
(b) That over the period 1 November to 30 April each year the consent holder shall
undertake monitoring of total suspended particulate in ambient air in the vicinity of
the site.
(c) That without prejudice to the generality of Conditions 4 and 6, if the monitoring
shows that the total suspended particulate in ambient air at or beyond the boundary
of the site, as measured in accordance with Condition 17, exceeds 100 micrograms
per cubic metre as a 24 hour average, an investigation shall be initiated by the
Consent Holder as to the probable causes of the exceedence.
Hunua QMP September 2009
42
(d) That, if the cause of the elevated levels of total suspended particulate is identified as
being an activity undertaken on the Consent Holder‟s site, then as far as practicable,
action shall be taken by the Consent Holder to reduce those discharges to the
satisfaction of the Manager.
(e) That any results of total suspended particulate in ambient air tests showing
exceedences of the prompt given in Condition 18 shall be reported by facsimile to
the Manager as soon as practicable. A summary of all monitoring results, including
references to wind and rainfall data, and any remedial action taken shall be submitted
to the Manager by 1 June each year.
(f) The Consent Holder shall continuously record and be able to make available wind
speed, wind direction and rainfall data.
8.2 Noise (excluding blasting)
(a) To ensure that the noise performance standards set in the District Plan are met,
monitoring will be carried out using appropriate equipment, methods and personnel.
The noise monitoring regime will include:
Monitoring on representative occasions.
Prior to any change in the quarry operations occurring that could result in
greater noise effects beyond the boundary, a reassessment of the noise from
quarry operations shall be carried out, if the changes have not already been
predicted or modelled.
8.3 Ground vibration, air overpressure (blast noise) and fly rock
(a) Records will be maintained for each blast including:
the time of the blast;
location of the blast;
total charge weight; and
maximum instantaneous charge.
(b) Winstone will undertake monitoring on representative occasions by reliable and
appropriate methods as set out in the District Plan to ensure the set limits for
vibration and air overpressure are not exceeded. These records shall be made
available to Council on request. Vibration monitoring does not necessarily have to
be undertaken on the foundation of adjacent buildings provided that the quarry
operator can safely extrapolate the measurements taken from the chosen monitoring
point to the foundation of adjacent buildings.
Hunua QMP September 2009
9. APPENDICES