Upload
others
View
9
Download
0
Embed Size (px)
Citation preview
STAR REFINERY REFINERY FIREFIGHTING SYSTEM IMPROVEMENT
PROJECT
CONTRACT Nº STR-PRM-CTR-016
UNIT Nº 000
CONTRACTOR DOC No: 920858-FI-011-001
SH/OF 1/7
STAR DOCUMENT No. 000-A-ZE-0040001-015
REV 0
HYDRAULIC CALCULATION FOR 1 x 12” + 2 x 6” FIRE WATER MANIFOLD
0 26-Nov-19 Issue for Review ESS ESS OS
REV. ISSUE DATE REASON FOR ISSUE PREPARED
BY CHECKED
BY APPROVED
BY
STAR REFINERY REFINERY FIREFIGHTING SYSTEM IMPROVEMENT
PROJECT
CONTRACT Nº STR-PRM-CTR-016
UNIT Nº 000
CONTRACTOR DOC No: 920858-FI-011-001
SH/OF 2/7
STAR DOCUMENT No. 000-A-ZE-0040001-015
REV 0
TABLE OF CONTENTS
1 GENERAL .............................................................................................................................................3
1.1 PURPOSE ................................................................................................................................................... 3
1.2 OBJECTIVES .............................................................................................................................................. 3
2 REFERENCES ......................................................................................................................................3
2.1 PROJECT DOCUMENTS ............................................................................................................................ 3
2.1.1 Project Specifications ................................................................................................................................ 3
2.1.2 Basis of Design and Project Documents ................................................................................................. 3
2.2 INTERNATIONAL STANDARDS AND CODES .......................................................................................... 4
3 ABBREVIATIONS .................................................................................................................................4
4 DEFINITIONS ........................................................................................................................................5
4.1 GENERAL DEFINITIONS ............................................................................................................................ 5
5 REQUIREMENTS ..................................................................................................................................5
6 FORMULA AND CALCULATION DATA ..............................................................................................5
6.1 GENERAL CRITERIA .................................................................................................................................. 5
6.2 FORMULA ................................................................................................................................................... 6
7 ATTACHMENT ......................................................................................................................................7
STAR REFINERY REFINERY FIREFIGHTING SYSTEM IMPROVEMENT
PROJECT
CONTRACT Nº STR-PRM-CTR-016
UNIT Nº 000
CONTRACTOR DOC No: 920858-FI-011-001
SH/OF 3/7
STAR DOCUMENT No. 000-A-ZE-0040001-015
REV 0
1 GENERAL
1.1 PURPOSE
The scope of this document is the Fire Water Hydraulic Calculation of 1x 12” Fire Water
Manifolds within Oil Storage Tanks Area (Unit 620 and Unit 640) and Process Units (U-100, U-
110, U-120, U-130, U-140, U-150, U-160, U-190, U-430, U-450, U-662) according to design
specification and standards used in the AEGEAN REFINERY project.
1.2 OBJECTIVES
The purpose of this document is to define and present the guidelines and requirements of fire
water hydraulic calculation for fire protection systems of plant, in conjunction with relevant
project specifications, which will be supplied for DHI QAR Combined Cycle Power Plant Project.
The following values are determined by means of hydraulic calculation within document;
Flow rates
Simultaneous system actuation
Friction losses
System pressures available
Velocities and line sizes
2 REFERENCES
The fire protection system shall be designed and installed in accordance with the following
referenced Codes, Standards and Technical Specifications. The editions of the listed codes are
the current revisions at the date of Contract signature.
2.1 PROJECT DOCUMENTS
2.1.1 Project Specifications
STGPS-S4 FIRE PROTECTION AND SAFETY FACILITIES
2.1.2 Basis of Design and Project Documents
920858-PC-105-001 FIRE PROTECTION SYSTEMS DESIGN BASIS
100-A-EB-050250-001 P&ID CDU-VDU (U-100)
110-A-EB-050320-001 P&ID 110/410 SGP/SRCT (SECTION 300)
120-A-EB-050901-001 P&ID NHT/CCR UNIT (U-120/160620TK-001B/C)
130-A-EB-050901-001 P&ID KEROSENE HYDROTREATING UNIT (U-130)
140-A-EB-050901-001 P&ID UNIT 140 (SECTION 200)
150-A-EB-050156-001 P&ID UNICRACKING PROCESS UNIT (U-150) SECTION 300
STAR REFINERY REFINERY FIREFIGHTING SYSTEM IMPROVEMENT
PROJECT
CONTRACT Nº STR-PRM-CTR-016
UNIT Nº 000
CONTRACTOR DOC No: 920858-FI-011-001
SH/OF 4/7
STAR DOCUMENT No. 000-A-ZE-0040001-015
REV 0
420-A-EB-050901-001 P&ID ARU/SRU/SWS UNIT (U-420/421/430/440/441/442)
450-A-EB-050034-001 P&ID UNIT 450 (SECTION 400)
620-A-EB-050903-001 P&ID CRUDE OIL STORAGE TANK (620TK-001B/C)
640-A-EB-050902-001 P&ID DIESEL EN590 STORAGE AREA (640TK-007A/B)
640-A-EB-050903-001 P&ID DIESEL EN590 STORAGE AREA (640TK-007C/D)
660-A-EB-050902-001 P&ID FLARE AREA B (U660B/661B)
662-A-EB-050011-001 P&ID U-662 (SECTION 100)
2.2 INTERNATIONAL STANDARDS AND CODES
NFPA 13 STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS
NFPA 14 STANDARD FOR THE INSTALLATION OF STANDPIPE AND HOSE SYSTEMS
NFPA 24 STANDARD FOR THE INSTALLATION OF PRIVATE FIRE SERVICE MAINS AND THEIR APPURTENANCES
API 2001 FIRE PROTECTION IN REFINERIES
API 2021 MANAGEMENT OF ATMOSPHERIC STORAGE TANK FIRES
3 ABBREVIATIONS
Lengths (L) Meters (m)
Time (T) Minutes (m)
Pipe Diameter (ø) Inch or mm
Pressure (P) Bar
Pressure loss (P) Bar/m
Flow Meter cubic per hour (m3/h) or gallon per minute (gpm)
Discharge Density Liters per minute and square meter (l/min/m2)
Velocity Meters per second (m/sec)
Temperature Degree centigrade (ºC)
Height elevate Meters (m)
C-factor Friction loss coefficient
STAR REFINERY REFINERY FIREFIGHTING SYSTEM IMPROVEMENT
PROJECT
CONTRACT Nº STR-PRM-CTR-016
UNIT Nº 000
CONTRACTOR DOC No: 920858-FI-011-001
SH/OF 5/7
STAR DOCUMENT No. 000-A-ZE-0040001-015
REV 0
4 DEFINITIONS
4.1 GENERAL DEFINITIONS
The following words and expressions used in the Specification have the following meanings:
OWNER shall mean STAR Refinery A.Ş. (STAR)
ENGINEER means ÇİMTAŞ.
VENDOR shall mean any part who delivers equipment and materials for
FACILITIES/UNITS
PROJECT means Fixed Fire Fighting system rehabilitation and U-630/640 LPG unit &
Impounding basin area Fire Fighting system rehabilitation of STAR Refinery A.Ş.(STAR) at
Aliağa, TURKEY
FACILITIES/UNITS shall mean the entire facilities, units, and plants where fire fighting
systems to be rehabilitated in conformity with the PROJECT requirements and scope that
ENGINEER meet its liabilities as defined in the agreement on, under, in or through
OWNER’s JOBSITE.
JOBSITE shall mean OWNER’s property land at IZMIR – ALIAĞA, TURKEY on, under, in
or through which the required FACILITIES for rehabilitation of fire fighting systems.
5 REQUIREMENTS
The Hydraulic calculation shall be performed considering the minimum pressure at hose connection points on the fire water manifolds.The minimum pressure at hose connections most remote nozzle is 7 bar (NFPA 24). The pressure and flow required by the system at the point of connection to the water supply system have been verified by Omnicadd HCS 2.3.The results are shown in Calculation Report table. For hydraulic calculation, the following general data has been considered for all calculation: • Minimum Pressure at Hose Connection = 7 bar
• Values “C” for Carbon Steel Pipe = 120 (Table 23.4.4.8.1 of NFPA 13)
• Maximum velocity allowable for Fire Water Mains = 3.5 m/sec.
6 FORMULA AND CALCULATION DATA
6.1 GENERAL CRITERIA
The calculations are performed by a hydraulic calculation software, the procedures described
on NFPA 13 and NFPA 24.
STAR REFINERY REFINERY FIREFIGHTING SYSTEM IMPROVEMENT
PROJECT
CONTRACT Nº STR-PRM-CTR-016
UNIT Nº 000
CONTRACTOR DOC No: 920858-FI-011-001
SH/OF 6/7
STAR DOCUMENT No. 000-A-ZE-0040001-015
REV 0
ASME-B36.10 ASTM A106 Grade B Seamless pipes shall be installed for aboveground fire
protection systems. Equivalent lengths of the used fittings as given in NFPA 13, are added to
the actual length of each pipe pathway for input into the pressure drop calculation. Pressure
drop due to friction is calculated for each pathway by using the Hazen-Williams pressure drop
method. All pressure drops through each critical pathway leading to a system are added for a
total pressure drop due to friction.
6.2 FORMULA
Friction loss formula is described in item 23.4.2.1.1 of NFPA 13
𝑃𝑚 = 6.05 × (𝑄𝑚
1.85
𝐶1.85 × 𝑑𝑚4.87) × 105
where: Pm = frictional resistance (bar/m of pipe)
Qm = flow (L/min)
C = friction loss coefficient
dm = actual internal diameter (mm)
Input Data
The following requirements has been considered as input to OmniCADD Software.
1. Assumed Terminal Point head is 22712 45424 lpm (126.000 gpm) at 8 bar. In case of fire one
Ambassador Mobile Monitor (6.000 gpm) and 2 (two) Fire Fighting Truck ( 2x 3.000 gpm) shall
be connected to 1 x 12” + 2 x 6” Fire Water Manifold.
2. Maximum velocity in the underground fire water network is 3.5 m/s
3. Hose Streams for one (1) outlet is required flow and pressure 22712 lpm (6.000 gpm) at 7
bar. Two (2) outlets are required flow and pressure 2 x 11356 lpm ( 2 x 3.000 gpm) at 7
bar.Hose Streams for one (1) outlet (12”) is required flow and pressure 11356 lpm (3.000 gpm)
at 7 bar, for two (2) outlets (6”) are required flow and pressure 5678 lpm (1.500 gpm) at 7 bar
Output Data
The following requirements has been considered as input output to OmniCADD Software.
1. Calculated head is 22712 45424 lpm (612.000 gpm) at 7.2 bar.
2. Calculated maximum velocity in the manifold pipes is 5.110.2 m/s
STAR REFINERY REFINERY FIREFIGHTING SYSTEM IMPROVEMENT
PROJECT
CONTRACT Nº STR-PRM-CTR-016
UNIT Nº 000
CONTRACTOR DOC No: 920858-FI-011-001
SH/OF 7/7
STAR DOCUMENT No. 000-A-ZE-0040001-015
REV 0
7 ATTACHMENT
Hydraulic Calculation Report is indicated in attached.
HYDRAULIC CALCULATIONS
for
1 x 12" + 2 x 6" Fire Water Manifold
Contract No.
Date November 26, 2019
Design Data:
Remote Area Location Units (U-100, U-110, U-120, U-130, U-140, U-150, U-160, U-190, U-430, U-450)
Occupancy Classification
Density 0.00 lpm/sq.m
Remote Area Size 0.0 sq.m
Coverage per Sprinkler 0.0 sq.m
Sprinkler K-Factor varies
No. of Sprinkler Calculated 0
In-Rack Demand 0.0 lpm
Source Hose Demand 0.0 lpm
Total Water Including Hose 45424.0 lpm
Name of Contractor
Name of Designer Çimtas Boru Imalatlari ve Ticaret Ltd. Sti.
Address Ata Sb. Mah. Müge Cad. 16600, No: 17 Gemlik / Bursa, Turkey,
Authority Having Jurisdiction 920858-PC-105-001 - Design Basis
Manifold flow rate and required pressure were assumed as 2 x 3.000 gpm and 6.000 gpm @7bar in accordance with Owner Requirements
OmniCADD Hydraulic Calculation Software v. 2.3
November 26, 2019 03:32 PM STR-PRM-CTR-016 Page: 2
GENERAL RESULTS
Total Water Including Hose 45424.0 lpm
Additional Allowances 45424.0 lpm
Discharge from Sprinklers 0.0 lpm
Source Hose Demand 0.0 lpm
Average Imbalance 0.004 lpm
Maximum Imbalance 0.2 lpm
Maximum Velocity @ Pipe: bl1 10.2 m/s
Maximum Fr. Loss @ Pipe: bl1 0.061 bar/m
Average Density -
Remote Area was not Peaked
Velocity pressures have been used for information only, and are not valid for balancing the system.
SOURCE : s1Static Pressure 9.0 barResidual Pressure 8.0 barFlow 45424.0 lpmHose Allowance 0.0 lpmAvailable Pressure 8.0 barRequired Pressure 7.2 barSafety Factor 9.8%, 0.8 barWater Flowing 45424.0 lpm
OmniCADD Hydraulic Calculation Software v. 2.3
November 26, 2019 03:32 PM STR-PRM-CTR-016 Page: 3
Water Curves for Src : s1
End Head Pressure Responce 0 @ 0 - D : 0 @ 45424Demand Curve @ Src : s1 0.1 @ 0 - C : 7.2 @ 45424Supply Curve @ Src : s1 A : 9 @ 0 - B : 8 @ 45424
Curve Values - X : bar @ lpm
0
0
7000
7000
13500
13500
18500
18500
22500
22500
26000
26000
29500
29500
32500
32500
35500
35500
38000
38000
40500
40500
43000
43000
45500
45500
0 0
1 1
2 2
3 3
4 4
5 5
6 6
7 7
8 8
9 9
10 10
BAR
LPM
A
B
C
D
OmniCADD Hydraulic Calculation Software v. 2.3
November 26, 2019 03:32 PM STR-PRM-CTR-016 Page: 4
NODES
# Type Value Elevationm
Xm
Ym
Res. Pres.bar
Dischargelpm
s1 Src [...] 0.0 0.0 0.0 7.2 0.0o2 Hose 11356.0 1.5 -0.5 0.6 6.4 11356.0o5 Hose 22712.0 1.5 -0.5 0.1 6.9 22712.0o3 Hose 11356.0 1.5 -0.5 -0.6 6.4 11356.0n4 Node - 1.5 0.0 0.6 7.1 -n6 Node - 1.5 0.0 0.1 7.1 -n1 Node - 1.5 0.0 0.0 7.1 -n5 Node - 1.5 0.0 -0.6 7.1 -
OmniCADD Hydraulic Calculation Software v. 2.3
November 26, 2019 03:32 PM STR-PRM-CTR-016 Page: 5
PIPES
## Type Value Elevation
m
Res.Pres.
bar
Discharge
lpm
MaterialHWC
Fittings
SizeNom.Diam.Int.Diam.
LengthEq.Length
Total Lengthm
Fr.Loss
bar/m
Pres.Fr.LossPres.Elev.LossPres.Vel.Loss
bar
Flow
lpm
Velocity
m/s
TypeStart/End Nodes
bl2 o2 Hose 11356.0 1.5 6.4 11356.0 Sch40 6 0.5 0.061 0.637 -11356.0 10.2 Branch Linen4 Node - 1.5 7.1 - 120 152.284 10.0 0.000
TG 153.934 10.5 0.514 bl1 o3 Hose 11356.0 1.5 6.4 11356.0 Sch40 6 0.5 0.061 0.637 -11356.0 10.2 Branch Line
n5 Node - 1.5 7.1 - 120 152.284 10.0 0.000 TG 153.934 10.5 0.514
bl5 o5 Hose 22712.0 1.5 6.9 22712.0 Sch40 12 0.5 0.007 0.150 -22712.0 5.0 Branch Linen6 Node - 1.5 7.1 - 120 304.569 20.1 0.000
TG 309.645 20.6 0.126 fm1 n1 Node - 1.5 7.1 - Sch40 16 1.5 0.010 0.014 -45424.0 6.6 Feed Main
s1 Src [...] 0.0 7.2 0.0 120 406.802 0.0 0.147 TG 381.000 1.5 0.219
fm4 n4 Node - 1.5 7.1 - Sch40 16 0.5 0.001 0.000 -11356.0 1.7 Feed Mainn6 Node - 1.5 7.1 - 120 406.802 0.0 0.000
T 381.000 0.5 0.014 fm6 n6 Node - 1.5 7.1 - Sch40 16 0.1 0.006 0.001 -34068.0 5.0 Feed Main
n1 Node - 1.5 7.1 - 120 406.802 0.0 0.000 T 381.000 0.1 0.123
fm5 n5 Node - 1.5 7.1 - Sch40 16 0.6 0.001 0.000 -11356.0 1.7 Feed Mainn1 Node - 1.5 7.1 - 120 406.802 0.0 0.000
T 381.000 0.6 0.014
OmniCADD Hydraulic Calculation Software v. 2.3
November 26, 2019 03:32 PM STR-PRM-CTR-016 Page: 6
FLOW DIAGRAM
n4
n6
n1
n5
s1
o2
o5
o3
OmniCADD Hydraulic Calculation Software v. 2.3