10

Click here to load reader

Hydraulic Calculation of Sprinkler System(Rev.c)

Embed Size (px)

DESCRIPTION

for information

Citation preview

  • SOUTH ASIA PAKISTAN TERMINALS LIMITED (SAPT)

    PAKISTAN DEEP WATER CONTAINER PORT

    BUILDINGS PHASE-1

    HYDRAULIC CALCULATION OF SPRINKLER SYSTEM

    - GROUND FLOOR PLAN OF CRANE WORKSHOP

    Date: Dec. 2014

    Rev:C

    Document No. Prepared by Checked by Approved by

    Liu Yi Mao Xiaofang Zhong Liangsheng

  • SOUTH ASIA PAKISTAN TERMINALS LIMITED (SAPT)

    CONTENTS

    1. BRIEF INTRODUCTION ...................................................................................... 1

    1.1. General ....................................................................................................... 1

    1.2. Codes and Standards ................................................................................. 1

    2. HYDRAULIC CALCULATION OF SPRINKLER SYSTEM .................................. 2

    2.1. The Extreme Pressure Point ....................................................................... 2

    2.2. Flow of Node .............................................................................................. 2

    2.3. Flow Rate ................................................................................................... 2

    2.4. Frictional Resistance .................................................................................. 2

    2.5. Difference of Pressure ................................................................................ 2

    2.6. The Results ................................................................................................ 3

    ANNEX A. DETAIL HYDRAULIC CALCULATION OF SPRINKLER SYSTEM ...... 5

    ANNEX B. FIGURE OF SPRINKLER SYSTEM ...................................................... 8

  • SOUTH ASIA PAKISTAN TERMINALS LIMITED (SAPT)

    1

    1. BRIEF INTRODUCTION

    1.1. General

    1) This hydraulic calculation of sprinkler system is for crane workshop of Pakistan Deep Water Container Port.

    2) Galvanized steel pipe (meets the requirements of ASME B36.10M-2004 Welded and Seamless Wrought Steel Pipe) is adopted as the sprinkler system of this design. Standard (STD) wall thickness is adopted as the wall thickness of the pipe in this design.

    3) HDPE pipe (meets the requirements of BS EN 12201-1-2003 Plastics Piping Systems for Water Supply-Polyethylene (PE) ) is adopted as the buried pipe in fire fighting system.

    1.2. Codes and Standards

    1) NFPA 13-2007 Standard for the Installation of Sprinkler Systems

    2) ASME B36.10M-2004 Welded and Seamless Wrought Steel Pipe.

    3) BS EN 12201-1-2003 Plastics Piping Systems for Water Supply-Polyethylene (PE)

  • SOUTH ASIA PAKISTAN TERMINALS LIMITED (SAPT)

    2

    2. HYDRAULIC CALCULATION OF SPRINKLER SYSTEM

    2.1. The Extreme Pressure Point

    According to requirements of NFPA 13-2007. 1.0 bar will be adopt as the extreme pressure point at the remotest of the pipe in this design.

    2.2. Flow of Node

    Pressure balancing shall be permitted through the use of a K-factor developed for branch lines or portions of systems using:

    0.5/ ( )pK q p (1)

    So the equation can change as:

    0.5( )pq K p (2)

    Where:

    q= flow of node in L/min;

    Kp= K-factor, for this project, Kp=80;

    p=pressure of point in bar.

    2.3. Flow Rate

    21000 / / 0.785 / 60iv Q D (3)

    Where:

    V=flow rate in m/s;

    Q= flow of pipe in L/min;

    Di= internal diameter in mm;

    2.4. Frictional Resistance

    Pipe friction losses shall be determined on the basis of the Hazen-Williams formula, as follows:

    1.855

    1.85 4.87

    Q6.05( )10m

    m

    pC d

    (4)

    Where:

    pm= frictional resistance in bar per meter of pipe;

    Q= flow in L/min;

    C= friction loss coefficient, for galvanized steel pipe of this project, C=120;

    dm= actual internal diameter in mm.

    2.5. Difference of Pressure

    ( ) /10m eP p L L H (5)

  • SOUTH ASIA PAKISTAN TERMINALS LIMITED (SAPT)

    3

    Where:

    P= difference of pressure in bar;

    pm= frictional resistance in bar per meter of pipe;

    L= length of Pipe in m;

    Le = equivalent length in m;

    H= difference of level in m.

    The figure of density/Area Cruves is as follow:

    Figure 1 Density/Area Curves

    2.6. The Results

    Table 1 The results of the hydraulic calculation for crane workshop

    Hydraulic Calculations

    for

    CRANE WORKSHOP GROUND FLOOR

    Date: 9-12-2014

    Design

    Occupancy classification Ordinary Hazard Group II

    Density 9.45 mm/min

    Area of application 254 m2

    Coverage per sprinkler 7.12 m2

    Special sprinklers -----------

    No. of sprinklers calculated 34

  • SOUTH ASIA PAKISTAN TERMINALS LIMITED (SAPT)

    4

    In-rack demand -----------

    Hose streams 250 gpm (946 L/m)

    Total water required including hose streams 883 gpm (3346 L/m)

    According to the NFPA 13, the sprinkling density of this building is ordinary hazard

    Group 2.In figure 1, When the calculated area is 254 m2, the average sprinkling density is not less than 7.2 mm/min. So the design parameters can meet the requirements of the standard, and it is acceptable.

    For the detailed hydraulic calculation of sprinkler system refer to Annex A.

    For the figure of sprinkler system refer to Annex B.

  • 5

    ANNEX A. DETAIL HYDRAULIC CALCULATION OF SPRINKLER SYSTEM

    Table 2 Hydraulic calculation of sprinkler system

    Node Pressure of

    Node(p) Flow of Node(q)

    Pipe Section Number

    Flow of Pipe(Q)

    Flow Rate(v)

    Nominal Diameter

    (Dn)

    Internal Diameter

    (Di)

    Length of

    Pipe(L)

    Equivalent Pipe

    Length (Le)

    Friction Loss Coefficient

    ( C )

    Difference of Level

    (H)

    Difference of Pressure

    (P)

    (bar) (L/min) (L/min) (m/s) (mm) (mm) (m) (m) (m) (bar)

    1 0.5350 58.515 1~2 58.515 1.751 25 26.64 2.8 0.0 120 0.0 0.0512

    2 0.5862 61.253 2~3 119.767 2.066 32 35.08 2.8 0.0 120 0.0 0.0505

    3 0.6367 63.834 3~4 183.602 2.326 40 40.94 2.8 0.0 120 0.0 0.0524

    4 0.6891 66.410 4~5 250.011 1.927 50 52.48 2.8 0.0 120 0.0 0.0277

    5 0.7168 67.731 5~6 317.742 2.449 50 52.48 0.8 0.0 120 0.0 0.0118

    6 0.7285 0.000 6~12 317.742 2.449 50 52.48 2.95 1.5 120 0.0 0.0686

    12 0.7971 0.000

    7 0.5850 61.188 7~8 61.188 1.831 25 26.64 2.8 0.0 120 0.0 0.0556

    8 0.6406 64.032 8~9 125.220 2.160 32 35.08 2.8 0.0 120 0.0 0.0548

    9 0.6954 66.714 9~10 191.934 2.431 40 40.94 2.8 0.0 120 0.0 0.0569

    10 0.7523 69.390 10~11 261.324 2.015 50 52.48 2.8 0.0 120 0.0 0.0300

    11 0.7824 70.762 11~12 332.086 2.560 50 52.48 0.8 0.0 120 0.0 0.0128

    12 0.7951 0.000 12~18 649.827 3.512 65 62.68 3.3 3.7 120 0.0 0.1706

    18 0.9658 0.000

    13 0.7100 67.409 13~14 67.409 2.017 25 26.64 2.8 0.0 120 0.0 0.0666

    14 0.7766 70.498 14~15 137.907 2.379 32 35.08 2.8 0.0 120 0.0 0.0655

    15 0.8421 73.411 15~16 211.318 2.677 40 40.94 2.8 0.0 120 0.0 0.0680

    16 0.9100 76.317 16~17 287.635 2.217 50 52.48 2.8 0.0 120 0.0 0.0359

    17 0.9459 77.807 17~18 365.442 2.817 50 52.48 0.8 0.0 120 0.0 0.0152

    18 0.9612 0.000 18~24 1015.269 3.496 80 78.52 3.3 4.6 120 0.0 0.1467

    24 1.1079 0.000

  • 6

    19 0.8280 72.796 19~20 72.796 2.178 25 26.64 2.8 0.0 120 0.0 0.0767

    20 0.9047 76.094 20~21 148.889 2.569 32 35.08 2.8 0.0 120 0.0 0.0755

    21 0.9802 79.204 21~22 228.094 2.889 40 40.94 2.8 0.0 120 0.0 0.0783

    22 1.0585 82.307 22~23 310.401 2.393 50 52.48 2.8 0.0 120 0.0 0.0413

    23 1.0998 83.898 23~24 394.299 3.040 50 52.48 0.8 0.0 120 0.0 0.0175

    24 1.1173 0.000 24~41 1409.568 2.862 100 102.26 1.65 6.1 120 0.0 0.0730

    41 1.1903 0.000

    25 0.7950 71.330 25~26 71.330 2.134 25 26.64 2.8 0.0 120 0.0 0.0739

    26 0.8689 74.572 26~27 145.902 2.517 32 35.08 2.8 0.0 120 0.0 0.0727

    27 0.9416 77.629 27~28 223.531 2.832 40 40.94 2.8 0.0 120 0.0 0.0754

    28 1.0170 80.678 28~29 304.209 2.345 50 52.48 2.8 0.0 120 0.0 0.0398

    29 1.0568 82.242 29~30 386.450 2.979 50 52.48 0.8 0.0 120 0.0 0.0177

    30 1.0745 0.000 30~41 991.110 3.413 80 78.52 1.65 4.6 120 0.0 0.1110

    41 1.1856 0.000

    31 0.7000 66.933 31~32 66.933 2.002 25 26.64 2.8 0.0 120 0.0 0.0657

    32 0.7657 70.003 31~33 136.936 2.363 32 35.08 2.8 0.0 120 0.0 0.0646

    33 0.8303 72.898 31~34 209.834 2.658 40 40.94 2.8 0.0 120 0.0 0.0671

    34 0.8974 75.787 31~35 285.621 2.202 50 52.48 2.8 0.0 120 0.0 0.0354

    35 0.9329 77.268 31~36 362.889 2.797 50 52.48 0.8 0.0 120 0.0 0.0158

    36 0.9486 0.000 31~37 604.660 3.268 65 62.68 2.3 3.7 120 0.0 0.1280

    30 1.0766 0.000

    37 0.5000 56.569 37~38 56.569 1.692 25 26.64 2.8 0.0 120 0.0 0.0481

    38 0.5481 59.228 38~39 115.797 1.998 32 35.08 2.8 0.0 120 0.0 0.0474

    39 0.5955 61.736 39~40 177.533 2.249 40 40.94 2.8 0.0 120 0.0 0.0493

    40 0.6448 64.239 40~36 241.772 3.063 40 40.94 6.0 3.6 120 0.0 0.2990

    36 0.9438 0.000

  • 7

    41 1.1903 0.000 41~42 2400.678 4.874 100 102.26 2.3 13.5 120 5.0 0.8984

    42 2.0887 0.000 42~43 2400.678 2.147 150 154.08 44.0 17.2 120 10.0 1.2096

    43 3.2982 0.000 43~44 2400.678 2.979 160 130.8 25.0 8.6 150 0.0 0.1691

    44 3.4673 0.000

    Remark: The difference of level for pipe section number 41~42 (5 m) is the loss of the zone control valve. This calculation sheets indicate that the flow of this system is 2400.678L/min(40.01 L/s), the pressure of node 44 which is connected with underground fire fighting pipe is 3.4673 bar (34.67 mH2O).

  • 8

    ANNEX B. FIGURE OF SPRINKLER SYSTEM

    Figure 2 Sprinkler system

    Remark:The calculated area of this building is 254 m2.