Upload
others
View
9
Download
0
Embed Size (px)
Citation preview
Hydro One’s Experience of Using State Estimation for Model
Validation
Yinhua Guo Jeff Penrice Vivian Cheuk
Ontario Grid Control Centre
Hydro One
1
Hydro One Power System
• Major Transmission Company in Ontario
– 29,000km High Voltage Transmission Grid
– Peak Load 27,000MW
– Interconnect with New York, Michigan, Minnesota, Manitoba, and Quebec (asynchronously)
• Largest Distribution Utility in Ontario
– 123,000kv Low Voltage Distribution Network
– Serving 1.3million Rural Customers
– Extensive Distributed Generation (Wind & Solar)
2
3
Courtesy of WorldAtlas
Hydro One EMS Applications
• State Estimation(SE): every 30sec.
• Thermal Limit Calculation: time limited ratings
• Contingency Analysis(CA): every 3min. ctg case redefinition, extensive SPS simulation
• Short Circuit Calculation: every 6min.
• Real Time and Study Environment
• Dispatcher Training Simulator(DTS)
4
SE Solution Validation
• What is a Valid/Good SE solution?
– Estimated value against measured values
– SE solution against power flow solution
– Power flow solution against CA solution
– Pre-outage CA solution against post-outage system state (real time or DTS Replay)
• Sources of Problem
– Data/Model errors, poor application tuning, software defects, inadequate theory.
5
6
Transformer/Phase Shifter
• Actual Physical Device:
– ULTC tap on HV or LV side
– DETC tap on HV or LV side
– Both ULTC & DETC taps: on different or same side
– Combined voltage transformer and phase shifter
• Typical Model Representation:
– ULTC tap on “from” side only
– Tap step size static (vs. function of DETC position)
7
Transformer/Phase Shifter…con
• Symptoms for Wrong Tap Model:
– MW circulation for parallel phase shifters
– MVAr circulation for parallel transformers
– Excessive MVAr/voltage
– Unrealistic estimated tap positions
• Problems with Impedance Parameters:
– Unbalanced flows on parallel transformers
– Too small value causing numerical difficulties
– Impedance variation with tap positions
8
Parallel Transformer/Phase Shifter
9
The first set is a voltage transformer & a separate phase shifter in series
The second set is one combined voltage and phase shifter transformer
10
T3 is a very different transformer model from the other 3 transformers
Transmission Circuit
• Typical Model and Assumptions
– π model per circuit, typical per kilometer value ranges available for data error check
– Balanced 3 phase assumed, mutual coupling between circuits ignored (small), but 500kv circuit rarely transposed
• Parameter Estimation
– Single scan vs. multiple scan solution
– Fluctuating results suggest other problems
11
Mutual Coupling Effect Example
12
Mutual Coupling Effect Modeled
13
Generator/Load Injection
• Generator Capability Limits
• Load Limits and DG impact (if modelled as negative load)
• Model Values (pseudo-meas) for Generator and Load Derived from Measurements.
• Injection Residue Distribution Between Generators and Loads
• Voltage Sensitive Load Model (at nominal kV)
14
Telemetry Model & Errors
• IEEE/ANSI C57.13 Defines Accuracy Classes
– Transformer correction factor(TCF) limits
– CT @100% rated current(+meter@10%, relay@20x)
– VT @90% and 110% rated voltage
• Transducer/IED:
– A/D bit length, digitizing error
– Scaling factor, resolution error
• Measurement/Device Mapping:
– Fixed in model, may be dynamic in field
15
16
VT location, multiple CT combined input
Measurement set up for normal configuration, switching operation may
make the mapping invalid
Weighting Factors
• Measurement Weighting in SE Relates to its Standard Deviation(Gauss Error Distribution)
– The product/ratio of 2 normal random variables is NOT a normal random variable
– Lack of source data and procedure
– Differ from ANSI Accuracy Class Definitions
• Impact to SE: Make or Break!
• Tuning: Science & Art or Trial & Error?
17
Performance Monitoring
• SE Solution Quality and Availability
– Large Residues/Biases by Measurement Types
– Bus Injection Residues
– Bad Voltage Solutions (too High or Low)
– Run every 30 seconds
• Monitoring Procedures and Tools
– Shift Control Engineer (7x24), issuing tickets
– Application Staff, 2nd level support
– Watchdog application, running in real time
18
19