PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
LUZON CAR Apayao CabugaoPan Pacific Renewable Power
Phils., corp.Apayao-Abulog For Contract negotiation
600.00
Conner Sierra Madre Water Corporation NabaungganFor submision of lacking documentary
requirements. 0.00
Benguet AtokBenguet Electric Cooperative,
Inc.Lok-o for financial evalaution
0.00
Baguio CityBenguet Electric Cooperative,
Inc.Bued River
For evaluation of financial
requirements 0.00
Bokod Hedcor, Inc. Bokod 1 For Contract negotiation 14.70
Bokod 2 For Contract negotiation 10.00
Itogon SN-Aboitiz Power-Benguet Binga For Contract negotiation 100.00
Kabayan Hedcor, Inc. Eddet For Contract negotiation 5.00
Sabangan Hedcor Sabangan, Inc. Sabangan For Contract negotiation 13.20
Tuba AV Garcia Power System, Inc. Bacayao River
Prepared letter for submission of
lacking documentary requirements
within 30-days. 0.00
Keyte River
Prepared letter for submission of
lacking documentary requirements
within 30-days. 0.00
Hedcor, Inc. Irisan 1 For Contract negotiation 3.80
Tuba 1 For Contract negotiation 4.20
Tuba 2 For Contract negotiation 18.90
Solutions UsingRenewable
Energy (SURE), Inc,.Pellmell
For submission of lacking
documentary requirements within
the 30-day period. With letter dated
February 18, 2011. 0.00
Tublay Hedcor, Inc. Tublay For Contract negotiation 9.80
Ambukao Sn Aboitiz Power-Benguet, Inc. Ambuklao For Contract negotiation105.00
Ifugao Asipolo Hedcor, Inc. Cadaclan For Contract negotiation 16.20
Kiangan ENERHIGHLANDS Corp. Asin RiverFor final evaluation , such as legal and
financial requirements 4.00
Hungduan For legal and financial evaluation 4.40
Ibulao River 1 For legal and financial evaluation 6.00
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
LUZON CAR Ifugao Kiangan PNOC- Renewables Corporation Bangbang
Prepared letter for submission of
lacking documentary requirements
within 30-days. 8.60
Tinoc Sta. Clara Power Corporation Tinoc 5 (Lower Luhong) For Contract negotiation6.00
Tinoc 6 (Wangwang) For Contract negotiation 6.00
Lamut ENERHIGHLANDS Corp. Ibulao River 2 For legal and financial evaluation 8.00
Lamut River For legal and financial evaluation9.00
Lagawe &
Mayoyao
Sn Aboitiz Power-Niueva Ecija,
Inc.Alimit For legal and financial evaluation
100.00
Kalinga Pinukpuk Sierra Madre Water Corporation Babaca For payment of processing fee35.00
Tabuk DPJ Engineers & Consultants BulanaoFor submission of lacking
documentary requirements 0.30
BuloFor submission of lacking
documentary requirements 0.30
Hydrotec Renewables, Inc. Chico RIS 1
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 0.68
Chico RIS 2
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 0.83
TinglayanPan Pacific Renewable Power
Phils., corp.Tinglayan For Contract negotiation
4.30
Mountain
ProvinceBarlig
Asiapac Green Renewable
Energy Corp.Tanudan For Contract negotiation
4.00
MabungaoSoutheast Asia Renewable Power
Corp.Mabungao For payment of processing fee
5.70
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
LUZON CARMountain
ProvinceMalecom
Southeast Asia Renewable Power
Corp.Malecom For payment of processing fee
1.50
MaligSoutheast Asia Renewable Power
Corp.Malig For payment of processing fee
0.80
NatoninSoutheast Asia Renewable Power
Corp.Pantor For payment of processing fee
1.20
ParacelisAsiapac Green Renewable
Energy Corp.Siffu (Lower) For Contract negotiation
8.00
Siffu (Upper) For Contract negotiation 8.00
(blank)Asiapac Green Renewable
Energy Corp.Dicapan
For evaluation of financial
requirements 3.00
I Ilocos Norte Solsona Sierra Madre Water Corporation Labugaon For payment of processing fee20.00
Sigay Hedcor, Inc. Marcos For payment of processing fee 7.80
Ilocos Sur Alilem Sta. Clara Power Corporation Alilem For Contract negotiation 4.50
Quirino Sta. Clara Power Corporation Quirino For Contract negotiation 10.00
Sugpon Sta. Clara Power Corporation Danac For Contract negotiation 3.00
Marcos Hedcor, Inc. Sigay For payment of processing fee 7.50
La Union San Gabriel Hedcor, Inc. San Gabriel For Contract negotiation 2.60
Tubao LGU of Tubao Tubao For Contract negotiation 1.00
Pangasinan Asingan Hydrotec Renewables, Inc. Agno 1 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 3.70
San Manuel Hydrotec Renewables, Inc. Agno 2 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 0.42
II Cagayan GonzagaPan Pacific Renewable Power
Phils., corp.Baua 1 River For Contract negotiation
4.44
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
LUZON II Isabela Cordon PhilCarbon, Inc. Magat F
For submission of lacking
documentary requirements. ( MOA
with NIA) 0.60
JonesGreenPower Resources
corporationDibuluan For Contract negotiation
17.00
Ramon Hydrotec Renewables, Inc.2.16 MW Magat Hydro
Project
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 2.16
6.93 MW Magat Hydro
Project
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 6.93
Magat Baligatan 3 For Contract negotiation 7.39
SN-Aboitiz Power-Benguet 360 MW Magat Hydro For Contract negotiation360.00
Roxas Hydrotec Renewables, Inc. Magat C RIS 1
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 2.30
Magat D RIS 2
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 0.69
San AgustinGreenPower Resources
corporationDabubu For Contract negotiation
10.00
San Mariano ENERHIGHLANDS Corp. Catalangan 1 Legal evaualution on-going 5.50
Catalangan 2 Legal evaualution on-going 2.70
First Isabela Renewable Energy
CorporationCalumangan For legal and financial evaluation
1.20
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
LUZON II Isabela San MarianoGreenPower Resources
corporationDisabungan For Contract negotiation
9.00
Isabela Power Corporation Ilaguen 2For submission of lacking
documentary requirements 10.00
San Mariano &
San GuillermoIsabela Power Corporation Ilaguen on-going financial evaluation
25.00
Dinapigue Isabela Power Corporation Ilaguen 3For submission of lacking
documentary requirements 7.00
Ilaguen 4For submission of lacking
documentary requirements 6.00
Quirino CabbaroguisGreen Energy Management
HoldingsDiduyon For Contract negotiation
332.00
(blank)First Pacific Renewable Energy
CorporationCabarvan For legal and financial evaluation
1.50
Conwap For legal and financial evaluation
Manglad For legal and financial evaluation 2.80
Nueva Vizcaya Quezon SN Aboitiz -Nueva Ecija, Inc. Lower Magat For legal and financial evaluation 26.00
KayapaFirst Pacific Renewable Energy
CorporationPandang For legal and financial evaluation
2.40
DupaxFirst Pacific Renewable Energy
CorporationBiduk For legal and financial evaluation
2.50
III Aurora CasiguranAlternergy Viento Partners
CorporationAmro River For Contract negotiation
3.00
Bataan MarivelesSoutheast Asia Renewable Power
Corp.Mariveles For payment of processing fee
1.10
Bulacan Angat Hydrotec Renewables, Inc. Bayabas River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 1.23
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
LUZON III Bulacan Bustos Hydrotec Renewables, Inc. Angat River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 5.54
Norzagaray First Gen Premier Energy Corp. Angat For Contract negotiation300.00
San Agustin Hydrotec Renewables, Inc. San Miguel River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 0.44
(blank)Metropolitan Waterworks and
sewerage SystemAngat -Umiray
For evaluation of legal and financial
requirements 1.50
Nueva Ecija General Tiño First Gen Luzon Power Corp. Balintingon For Contract negotiation 30.00
Masiway Hydrotec Renewables, Inc. Casecnan
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 7.70
Palayan Hydrotec Renewables, Inc. Pampanga 1 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 2.72
Pampanga 2 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 0.37
Pantabangan First Gen Prime Energy Corp.Pantabangan Pump
Storage PlantFor Contract negotiation
300.00
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
LUZON III Nueva Ecija Penaranda Hydrotec Renewables, Inc. Peñaranda River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 1.91
KayapaFirst Pacific Renewable Energy
CorporationNasignan For legal and financial evaluation
1.80
Pampamga San Juan Bano Hydrotec Renewables, Inc. Pampanga RIS River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 3.70
IV-A Laguna Majayjay Majayjay Hydro Power Co., Inc. MajayjayFor evaluation of legal and financial
requirements 2.00
Sinilioan Sierra Madre Water CorporationLlano and Lagunlan
Multi RiverFor payment of processing fee
6.00
Siniloan Sierra Madre Water Corporation
Siniloan Multi River
Hydro Power/Bulk
Water ( Co-Product)
For evaluation of legal and financial
requirements.35.00
Quezon General Nakar Kanan Hydroelectric PowerCorp. Kanan River For Contract negotiation150.00
Rizal Antipolo Hydrotec Renewables, Inc. Hinulugang River For Contract negotiation 2.24
Marikina Hydrotec Renewables, Inc. Marikina 1 River For Contract negotiation 1.89
Marikina 2 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 2.17
Nangka 1 River For Contract negotiation 1.85
Nangka 2 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 2.16
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
LUZON IV-A Rizal Marikina Hydrotec Renewables, Inc. Nangka 3 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 2.70
Nangka 4 River For Contract negotiation 1.08
Montalban Hydrotec Renewables, Inc. Montalban 1 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 5.78
Montalban 2 River For Contract negotiation 1.85
Morong Hydrotec Renewables, Inc. Uugong River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 0.96
Rodriguez Hydrotec Renewables, Inc. Marikina Upper 1 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 3.47
Marikina Upper 2 River For Contract negotiation6.87
San Mateo Hydrotec Renewables, Inc. Marikina 3 River For Contract negotiation 2.46
IV-B Oriental Mindoro NaujanPhilippine Hybrid Energy System,
Inc.Mag-asawang Tubig A
0.00
Mag-asawang Tubig B 0.00
San Teodoro Mindoro Grid Corporation Baltan River
For submission of lacking
documentary requirmenst with 30-
day period 0.00
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
LUZON IV-B Oriental Mindoro Victoria Century Peak Energy Corporation Aglubang
For submission of lacking
documentary requirmenst with 30-
day period 0.00
Palawan El NidoAlternegy Viento Partners
CorporationNagcalicalit For Contract negotiation
0.12
Alternergy Viento Partners
CorporationBatacalan For Contract negotiation
0.15
Bulalakao-1 North
RiverFor Contract negotiation
0.34
Bulalakao-2 South
RiverFor Contract negotiation
0.44
Romblon RomblonRomblon Electric Cooperative,
Inc.Cantingas on-going financial evaluation
0.90
San AgustinSunwest Water & Eletrcic Co.,
Inc.Hinugasan
For submission of lacking
documentary requirmenst with 30-
day period 0.60
NCR Metro Manila Marikina Hydrotec Renewables, Inc. Marikina 4 River For Contract negotiation 2.59
Marikina 5 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 1.89
Marikina 6 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 1.24
Pasig Hydrotec Renewables, Inc. Pasig River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 4.07
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
LUZON NCR Metro Manila Quezon Hydrotec Renewables, Inc. San Juan 1 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 0.55
Quezon City Hydrotec Renewables, Inc. San Juan 2, river
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 0.68
Sta. Mesa Hydrotec Renewables, Inc. San Juan 3 River
Submitted documents are under
evaluation. For Payment of
processing Fee with letter dated
February 2, 2011. No payment yet
made. 1.04
V Camarines Sur GoaClean and Green Energy
Solutions, Inc.Ranggas on-going legal evaluation
1.80
Sorsogon SorsogonSunwest Water & Electric Co.,
Inc.
Lower Cawayan
(Cawayan 2)
For submission of lacking
documentary requirmenst with 30-
day period 0.99
Catanduanes Caramoran Sunwest Water & Electric Co.,
Inc.
Gigmoto
For submission of lacking
documentary requirmenst with 30-
day period 0.55
Hitoma 2
For submission of lacking
documentary requirmenst with 30-
day period 1.35
Pangaldawan Sunwest Water & Electric Co.,
Inc.
Upper Hinipaan River
(Hinipaan River 2)
For submission of lacking
documentary requirmenst with 30-
day period 1.20
LUZON Sum 2,942.03
VISAYAS VI Aklan IbajaySunwest Water & Electric Co.,
Inc.Ibajay 1
For submission of lacking
documentary requirmenst with 30-
day period 1.00
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
VISAYAS VI Aklan IbajaySunwest Water & Electric Co.,
Inc.Ibajay 2
For submission of lacking
documentary requirmenst with 30-
day period 2.00
VIII Northern Samar Victoria PNOC- Renewables Corporation MaouFor submission of list and names of
technical consultants 3.00
VII Bohol AntequeraSolutions UsingRenewable
Energy (SURE), Inc,.Inambacan
For submission of lacking
documentary requirements within
the 30-day period. With letter dated
February 18, 2011. 0.00
VISAYAS Sum 6.00
MINDANAO ARMM Lanao del Norte BacolodProvincial Government of Lanao
delNorteLiangan
For submission of lacking
documentary requirements12.00
Iligan CityEuro Hydro Power (Asia)
Holdings, Inc.Bayug River For Contract negotiation 1.00
KolamboganEuro Hydro Power (Asia)
Holdings, Inc.Titunod River For Contract negotiation 1.00
Lanao del Norte &
Lanao del Sur(blank) Agus 3 Hydropower Corporation Agus 3
Prepared letter informing Agus 3
Corp that the applied site is under
OCSP.
240.00
Lanao del Sur KapaiEuro Hydro Power (Asia)
Holdings, Inc.Kapai River For Contract negotiation 0.30
IXZamboanga del
NorteLeon Postigo
Euro Hydro Power (Asia)
Holdings, Inc.Polandoc River For legal and financial evaluation 2.00
MutiaEuro Hydro Power (Asia)
Holdings, Inc.Dapitan River (Middle) For legal and financial evaluation 4.40
SindanganZamboanga delNorte Electric
CooperativeIngin
With letter for submission of lacking
documentary requirements within 30-
days dated Janaury 27, 2011. No
reply yet.
3.00
(blank) Epower Technologies Corp. Sindangan River
For submission of docuemntary
requirements. Withletter dated April
28, 2011.
7.00
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
MINDANAO IXZamboanga del
NortePiñan
Epower Technologies Corp.
Polako River
For submission of docuemntary
requirements. Withletter dated April
28, 2011.
2.00
Zamboanga del
SurJosefina PG of Zamboanga del Sur Salug Daku River 2
For submission of
lackingdocuemnetary requirements
within the 30-day period. With letter
of march 28, 2011.
6.00
Salug Daku River 1
For submission of
lackingdocuemnetary requirements
within the 30-day period. With letter
of march 28, 2011.
6.00
Salug Daku River 3
For submission of
lackingdocuemnetary requirements
within the 30-day period. With letter
of march 28, 2011.
4.00
Salug Daku River 4
For submission of
lackingdocuemnetary requirements
within the 30-day period. With letter
of march 28, 2011.
2.50
Lakewwod Hedcor, Inc. Lakewood
For submission of
lackingdocuemnetary requirements
within the 30-day period.
7.50
Zambonga del
NorteMutia
Euro Hydro Power (Asia)
Holdings, Inc.Dapitan River (Upper) For legal and financial evaluation 3.60
Manukan Epower Technologies Corp. Dohinong
For submission of docuemntary
requirements. Withletter dated April
28, 2011.
3.00
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
MINDANAO IXZambonga del
NorteManukan Epower Technologies Corp. Pian River
For submission of docuemntary
requirements. Withletter dated April
28, 2011.
1.40
Katipunan
Epower Technologies Corp.
Tookan River
For submission of docuemntary
requirements. Withletter dated April
28, 2011.
0.90
X BukidnonBaungon and
LibonanBubunawan Power Company Bubunawan For Contract negotiation 8.00
ImpasugongEuro Hydro Power (Asia)
Holdings, Inc.Atugan
For submission of lacking
documentary requirements0.80
MalaybalayEuro Hydro Power (Asia)
Holdings, Inc.Sawaga For legal and financial evaluation 1.20
MalitbogEuro Hydro Power (Asia)
Holdings, Inc.2.5 MWSiloo For legal and financial evaluation 2.50
Sta. Clara Power Corporation Malitbog For Contract negotiation 5.00
Silo-o For Contract negotiation 4.50
Manolo Fortich Sta. Clara Power Corporation Mangima For Contract negotiation 10.00
MaramagEuro Hydro Power (Asia)
Holdings, Inc.Nabatantungan
For submission of lacking
documentray requirements.1.60
First Bukidnon Electric
Cooperative, Inc.Maramag For payment of processing fee 2.00
Moleta For payment of processing fee 2.00
Santiago Hedcor, Inc. Amusig For financial evaluation 15.40
Malagaong For financial evaluation 11.20
TalakagFirst Gen Mindanao Hydro Power
Corp.Cagayan River 1 For Contract negotiation 8.00
Cagayan River 2 For Contract negotiation 10.00
Guihian Hedcor, Inc. Guihian For financial evaluation 6.10
ValenciaBukidnon II Electric Cooperative,
Inc.Upper Manupali For legal and financial evaluation 2.00
Misamis
OccidentalCalamba
Misamis Occidental 1 Electric
Cooperative Inc.Langaran River For Contract negotiation 3.64
Misamis OrientalCagayan de Oro
citySta. Clara Power Corporation Mat-i 2 For Contract negotiation 4.00
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
MINDANAO X Misamis Oriental Cagayan de Oro Sta. Clara Power Corporation Mat-i 3 For Contract negotiation 4.00
Turbines Resources &
Development Corp.Limbatangon For Contract negotiation 10.00
Jasaan Minergy Energy Systems, Inc. Lower Cabulig
Fo submission of lacking
documentary requirements within 30-
day period
10.00
XICompostela
ValleyNew Bataan
Euro Hydro Power (Asia)
Holdings, Inc.New Bataan River For Contract negotiation 1.00
(blank)Euro Hydro Power (Asia)
Holdings, Inc.Lapaz (Cawayan River) For Contract negotiation 1.20
Hedcor, Inc. Camanlangan For Contract negotiation 7.20
Tandik For Contract negotiation 7.00
Davao del Sur Davao City Hedcor Bukidnon, Inc. Simod For Contract negotiation 11.80
Sita For Contract negotiation 16.40
Hedcor, Inc. Tamugan For Contract negotiation 12.00
Malita LGU of Malita Malita River For legal and financial evaluation 2.50
Sta. Cruz HEDCOR Sibulan, Inc. Sibulan Plant A For Contract negotiation 16.50
Sibulan Plant B For Contract negotiation 26.00
Hedcor Tudaya, Inc. Tudaya 1 For Contract negotiation 6.60
Tudaya 2 For Contract negotiation 7.00
Davao Oriental Caraga Hedcor, Inc. Caraga (lower) For financial evaluation 22.90
Caraga (middle) For financial evaluation 19.50
Caraga (Upper) For financial evaluation 7.10
Cateel Hedcor, Inc. Aliwagwag For financial evaluation 9.70
Manurigao Hedcor, Inc. Manurigao For financial evaluation 12.20
Tauantauan Hedcor, Inc. Tauantauan For payment of processing fee 10.00
Davao del Norte TalaingodHedcor, Inc.
Talaingod For payment of processing fee 8.50
XII North Cotabato AlamadaEuro Hydro Power (Asia)
Holdings, Inc.Alamada River For Contract negotiation 1.00
Malitubog River For Contract negotiation 3.00
Sarangani MaasimAlsons energy Development
CorporationSiguil 1 For financial evaluation 8.70
Siguil 2 For financial evaluation 3.20
PENDING HYDROPOWER PROJECTS
ISLAND /
GRIDREGION PROVINCE
CITY /
MUNICIPALITYCOMPANY NAME PROJECT NAME STATUS
POTENTIAL
CAPACITY
(MW)
MINDANAO XII Sarangani Maasim Alsons energy Development Siguil 3 For financial evaluation 4.80
Saranggani MaitumAlsons energy Development
CorporationKalaong 1 For payment of processing fee 12.00
Kalaong 2 For payment of processing fee 6.00
Kalaong 3 For payment of processing fee 4.00
Euro Hydro Power (Asia)
Holdings, Inc.
Pangi
For submission of lacking
docuemnetary requirements within
the 30-day period.
1.20
South Cotabato Lake Sebu Euro Hydro Power (Asia)
Holdings, Inc.
Pitol Kalabaw 1
For submission of lacking
docuemnetary requirements within
the 30-day period.
0.50
Pitol Kalabaw 2
For submission of lacking
docuemnetary requirements within
the 30-day period.
0.40
Sultan Kudarat Isulan Sta. Clara Power Corporation Kabulnan 2 For Contract negotiation 110.00
XIII Agusan del Norte Butuan Equi-Parco Cosntruction Co. Taguibo 1 For Contract negotiation 2.00
Taguibo 2 For Contract negotiation 2.40
Jabonga Agusan Power Corporation Lake Mainit On-going technical evaluation 25.00
(blank) Equi-Parco Cosntruction Co. Asiga For Contract negotiation 5.00
MINDANAO Sum 823.84
Grand Total 3,771.87