2008-03-15 Matt Fleming
Hydroformed ReflectorTime & Materials Cost Estimate
SKA US TDP
Matt Fleming
2008-03-15
2008-03-15 Matt Fleming
Purpose• This presentation is intended to estimate the cost of a hydroformed
reflector system for use on a multi antenna radio telescope array.• The reflector system is composed of several parts and these parts
are different for various candidate technologies.• A typical system includes the reflector surface and some support
system that carries back to the elevation axis and drive attachment points.
• This exercise is structured in a way that will allow other candidate reflector manufacturing processes to be compared.
• It examines the process equipment, materials & tasks attempting to identify costs for each.
• The hydroforming process is well known in the metal forming industry. It uses a fluid, under pressure, to form metal sheet material onto or around a mold or pattern.
• Care has been taken not to disclose any information proprietary to any individual entity engaged in this business.
2008-03-15 Matt Fleming
Elements of Part Costs
• Any manufactured device has the following cost elements that need to appear somewhere in the analysis.– Facility cost ( often covered in labor rate )– Technology development cost.– Tooling or equipment cost ( per process )– Setup & adjustment costs ( per batch )– Material & Labor cost ( per part )– Storage & trasportation costs ( per batch )
2008-03-15 Matt Fleming
Surface Material
Diameter ( material used ) 12.2 meter
Thickness 0.25 inch
Weight ( 0.098 ) 4,439 lbs
Material price 2.40 $ / lb
Blank cost $10,654
Stiffener cost $2,273 614 lbs 0.188
So how thin can we make it ?
2008-03-15 Matt Fleming
FormingTasks Mtrl Labor Time Workers
Raw material & handling. 33 10 2
Metal cutting process. $20 100 60 1
Welding Process. $20 300 60 3
Surface texture process. $80 133 40 2
Blank installaton process. 67 10 4
Forming process. 150 45 2
Part removal process. 133 20 4
Inspection process. $20 100 60 1
Trim deburr. $10 67 20 2
Storage process. $40 50 15 2
Repeat prep & cleanup. 167 20 5
Total forming cost: $190 $1,300 6 hrs
2008-03-15 Matt Fleming
Tooling
Costs based oneducated guesses
Coil equip 15,000
Cutting equip 35,000
Welding equip 45,000
Texture equip 32,000
Press ( no mold ) 500,000
Custom Mold 1,420,000
Lifting fixtures 8,000
Inspection table 7,000
Transport carts 7,500
Storage racks 12,000
Shipping fixtures 26,000
Total forming equip $2,157,500
See separateslide
Really bigguess
2008-03-15 Matt Fleming
Mold Cost Estimateinputs are in green
cool units
AssumeImproved
design
this is thebig guess
ratio Diameter 6.1 12.0 m 1.97
Height 1.2 2.4 m 1.97
Cost 568,000 1,420,000 $ 2.50
Volume 140 1068 cu-m 7.61
Weight
47,000 188,000 lbs 4.00
Density
335 176 cu-m / lb 0.53
Rate 12.09 7.55 $ / lb 1.60
2008-03-15 Matt Fleming
Hydroformed ReflectorAssy Costs
Units Cost 12m = 452m^2
1 3,550,417 7,848.14
10 375,667 830.41
50 93,467 206.61
500 29,972 66.25
2500 24,328 53.78
5000 23,622 52.22