@ODOT_Akron ODOTD4 Real Time Traffic Updates: OHGO.com or App Questions 330-786-2208 I-680/SR 164 Project IN BEAVER TOWNSHIP March 2018 I-680 under SR 164 will be reduced to one lane in each direction for roadway widening and drainage improvements. Work will begin on the new interchange. Construction of temporary pavement on SR 164 between I-680 and just south of the SR 164 bridge over the Ohio Turnpike. During this time, SR 164 will be reduced to one lane maintained by flaggers. Mid-April 2018 SR 164 will be shifted, one lane of traffic maintained in each direction between I-680 and just south of the SR 164 bridge over the Ohio Turnpike through late October 2019. Work will begin on the SR 164 and SR 626 roundabout and continue through October 2018. The Ohio Turnpike will have various daily lane restrictions through late October 2018. Mid- August 2018 SR 626 north of SR 164 will be closed for 30 days for roundabout construction. The detour will be SR 164 to SR 7 to US 224 to I-680. Early October 2018 Seven day closure of the south leg of SR 626/164 interchange. The detour will be SR 626 to SR 165 to SR 164. 680 626 164 164 626 2018 Work will begin in mid- March 2018 on a $11.6 million project to construct a new interchange at I-680 and SR 164.The project also includes the addition of a southbound lane on SR 164 between I-680 and SR 626, the addition of a southbound left turn lane on SR 164 at the SR 626 southbound junction, conversion of the SR 626 north junction to a single lane roundabout and the widening and replacement of the SR 164 bridge over I-76/Ohio Turnpike. The entire project is scheduled to be completed in November 2019.

I-680/SR 164 Project - Ohio Department of Transportation€¦ · I-680 and SR 626, the addition of a southbound left turn lane on SR 164 at the SR 626 southbound junction, conversion

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: I-680/SR 164 Project - Ohio Department of Transportation€¦ · I-680 and SR 626, the addition of a southbound left turn lane on SR 164 at the SR 626 southbound junction, conversion

@ODOT_Akron ODOTD4 Real Time Traffic Updates: OHGO.com or AppQuestions 330-786-2208

I-680/SR 164 ProjectI N B E A V E R T O W N S H I P

March 2018• I-680 under SR 164 will be reduced to one lane in each direction for roadway widening and drainage improvements. Work will begin on the new interchange.• Construction of temporary pavement on SR 164 between I-680 and just south of the SR 164 bridge over the Ohio Turnpike. During this time, SR 164 will be reduced to one lane maintained by flaggers.

Mid-April 2018• SR 164 will be shifted, one lane of traffic maintained in each direction between I-680 and just south of the SR 164 bridge over the Ohio Turnpike through late October 2019.• Work will begin on the SR 164 and SR 626 roundabout and continue through October 2018.• The Ohio Turnpike will have various daily lane restrictions through late October 2018.

Mid- August 2018SR 626 north of SR 164 will be closed for 30 days for roundabout construction. The detour will be SR 164 to SR 7 to US 224 to I-680.

Early October 2018Seven day closure of the south leg of SR 626/164 interchange. The detour will be SR 626 to SR 165 to SR 164.

680

626

164

164

626

2018Work will begin in mid- March 2018 on a $11.6 million project to construct a new interchange at I-680 and SR 164.The project also includes the addition of a southbound lane on SR 164 between I-680 and SR 626, the addition of a southbound left turn lane on SR 164 at the SR 626 southbound junction, conversion of the SR 626 north junction to a single lane roundabout and the widening and replacement of the SR 164 bridge over I-76/Ohio Turnpike. The entire project is scheduled to be completed in November 2019.

Page 2: I-680/SR 164 Project - Ohio Department of Transportation€¦ · I-680 and SR 626, the addition of a southbound left turn lane on SR 164 at the SR 626 southbound junction, conversion

@ODOT_Akron ODOTD4 Real Time Traffic Updates: OHGO.com or AppQuestions 330-786-2208

I-680/SR 164 ProjectI N B E A V E R T O W N S H I P

2019164

626

April 2019• The Ohio Turnpike will have various daily lane restrictions through late October 2019• SR 164 will be shifted, one lane of traffic maintained in each direction between I-680 and just south of the SR 164 bridge over the Ohio Turnpike through late October 2019.

June 2019Weekend closures of SR 164 just south of the roundabout to I-680. The detour will be US 224 to SR 7 to SR 164.

November 2019• New Entrance and exit ramps and entrance on SR 164 and I-680 will open.• The new roundabout at SR 164 and SR 626 will be fully functional. • The new park and ride will open.

626

164

680

Coming in early April www.ohgo.com/mah is your one stop destination for up to date information about the

project. Specific closure dates, project renderings, and roundabout video will be included. You can also sign up to receive weekly email updates and construction

updates.