I Direct Burial & Plough in of of Cables

Embed Size (px)

Citation preview

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    1/28

    Direct Laying Of

    Optical Fibre Cables

    Surveying and planning of project Cable types

    Installation methods

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    2/28

    Surveying and planning

    Do feasibility study on most cost effective and

    practical installation method

    Obtain way leaves before final decision

    Presence of services like crossings, power, water,

    petrol pipelines will influence method Crossings may have to done with overhead routes

    Directional boring can be used in special crossings

    Soil conditions will influence depth and cost

    Vegetation will be important as some are

    indigenous

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    3/28

    Cable types

    Only Corrugated Steel Tape (CST)

    optical fibre cables can be directlyburied and ploughed in

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    4/28

    Installation methods

    Plough in of cable with specialisedmachinery

    Direct burial of cable

    Directional boring

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    5/28

    Plough in method

    Machinery

    Route preparation

    Plough in procedure

    Reinstatement after plough in process

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    6/28

    Machinery required

    Suitable machine to do pre-ripping of soil

    Cable drum carrier

    Excavator (TLB) to do small river and culvert

    crossings Cable trailer for sub ducts if required

    Plough in machine

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    7/28

    Plough in machine

    Cable carrying attachment in front of machine

    Hydraulic feeder system on drum with tensioncontrol

    Rollers over roof of machine with bend radius

    protection for cable and sub duct

    Feeder system for marking/danger tape

    Plough in attachment at back of machine suitableto lay multiple services

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    8/28

    Plough in machine

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    9/28

    Plough in machine

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    10/28

    Plough in machine

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    11/28

    Route preparation

    Do road and railway crossings in advance

    Remove all obstructions to plough in machinein advance provide temporary supports

    Do pre-ripping if required at greater depth

    Final pre-rip in same direction as plough in

    Pre-trench creek and river crossings with TLB

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    12/28

    Plough in procedure

    Excavate at least 5m at start of route

    Position plough in machine over open trench

    Load cable drum and feed cable through the chute

    If sub duct must be laid in process, it can be fed

    from cable trailer or laid out in front of plough inmachine

    Load marker tape and feed through 300mm above

    sub duct

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    13/28

    Plough in procedure (contd.)

    Ensure correct sequence out of plough in chute

    Provide sufficient cable slack for splicing

    Start machine slowly and hold services by hand

    in trench

    Minimise stoppages during plough in process

    Monitor marker tape at feeding system

    Repeat same process at end of each length Plough in process can be stopped in middle of

    length at night

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    14/28

    Inner ducts must be jointed with Plasson fittings

    in trench Build manholes and jointing pits after plough in

    process

    Plough cable in as near as possible at end of

    route and excavate trench as at start

    Test all fibres after plough in process to verifyintegrity

    Plough in procedure (contd.)

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    15/28

    Plough in machine

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    16/28

    Reinstatement after plough in process

    No compaction of disturbed area is necessary

    Back blading with plough machine

    Level surface with TLB Repair all fences

    Replace all stays and struts

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    17/28

    Direct burial

    Applications

    Installation method

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    18/28

    Applications

    In rural areas where plough in can not be done

    In urban areas where cables are buried underlayer of ducts which caters for future network

    expansion

    Road crossings and services that must be

    crossed in urban areas will limit cable lengths

    that can be ploughed in

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    19/28

    Installation method

    Excavate trench as per normal requirements

    Limit width to 370mm if only cable will be buried

    Bedding and padding material river sand or

    sieved material not greater than 5mm Bedding must be 150mm

    Lay cable and cover with 150mm padding

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    20/28

    Installation method (contd.)

    Install ducts if required on top of cable

    Use same bedding and padding material forducts

    Cover cable with 300mm backfill material

    Use mechanical compaction to compact backfillin layers of 300mm

    Build manholes and jointing pits for future

    development after cable laying

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    21/28

    Directional boring

    Description Applications

    Machinery

    Procedure

    Advantages/Disadvantages

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    22/28

    Description

    Directional boring is the drilling of a required

    diameter hole between two points at a specific

    depth to accommodate a cable or a duct without

    disturbing or damaging any infrastructure

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    23/28

    Diagram

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    24/28

    Applications

    Crossing streets, highways and railway lines Crossing foundations of buildings

    Crossing rivers, pipelines and water drainage

    systems

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    25/28

    Machinery

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    26/28

    Machinery

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    27/28

    Procedure Locate all services

    Set up drilling rig Mix bentonite mix to suit soil formation

    Drill pilot hole up to required position

    Fit reamer to drill end and secure cable or duct

    Pull cable/duct back while hole is reamed

    Ensure sufficient slack

  • 8/13/2019 I Direct Burial & Plough in of of Cables

    28/28

    Advantages / Disadvantages

    Accurate

    No trenching and reinstatement of surfaces Cost effective

    Difficult crossings is possible and done safely

    Only 300m is possible

    Specialised equipment is needed

    Too many deviations in hole will make haulingimpossible