Upload
evenso-ndlovu
View
218
Download
0
Embed Size (px)
Citation preview
8/13/2019 I Direct Burial & Plough in of of Cables
1/28
Direct Laying Of
Optical Fibre Cables
Surveying and planning of project Cable types
Installation methods
8/13/2019 I Direct Burial & Plough in of of Cables
2/28
Surveying and planning
Do feasibility study on most cost effective and
practical installation method
Obtain way leaves before final decision
Presence of services like crossings, power, water,
petrol pipelines will influence method Crossings may have to done with overhead routes
Directional boring can be used in special crossings
Soil conditions will influence depth and cost
Vegetation will be important as some are
indigenous
8/13/2019 I Direct Burial & Plough in of of Cables
3/28
Cable types
Only Corrugated Steel Tape (CST)
optical fibre cables can be directlyburied and ploughed in
8/13/2019 I Direct Burial & Plough in of of Cables
4/28
Installation methods
Plough in of cable with specialisedmachinery
Direct burial of cable
Directional boring
8/13/2019 I Direct Burial & Plough in of of Cables
5/28
Plough in method
Machinery
Route preparation
Plough in procedure
Reinstatement after plough in process
8/13/2019 I Direct Burial & Plough in of of Cables
6/28
Machinery required
Suitable machine to do pre-ripping of soil
Cable drum carrier
Excavator (TLB) to do small river and culvert
crossings Cable trailer for sub ducts if required
Plough in machine
8/13/2019 I Direct Burial & Plough in of of Cables
7/28
Plough in machine
Cable carrying attachment in front of machine
Hydraulic feeder system on drum with tensioncontrol
Rollers over roof of machine with bend radius
protection for cable and sub duct
Feeder system for marking/danger tape
Plough in attachment at back of machine suitableto lay multiple services
8/13/2019 I Direct Burial & Plough in of of Cables
8/28
Plough in machine
8/13/2019 I Direct Burial & Plough in of of Cables
9/28
Plough in machine
8/13/2019 I Direct Burial & Plough in of of Cables
10/28
Plough in machine
8/13/2019 I Direct Burial & Plough in of of Cables
11/28
Route preparation
Do road and railway crossings in advance
Remove all obstructions to plough in machinein advance provide temporary supports
Do pre-ripping if required at greater depth
Final pre-rip in same direction as plough in
Pre-trench creek and river crossings with TLB
8/13/2019 I Direct Burial & Plough in of of Cables
12/28
Plough in procedure
Excavate at least 5m at start of route
Position plough in machine over open trench
Load cable drum and feed cable through the chute
If sub duct must be laid in process, it can be fed
from cable trailer or laid out in front of plough inmachine
Load marker tape and feed through 300mm above
sub duct
8/13/2019 I Direct Burial & Plough in of of Cables
13/28
Plough in procedure (contd.)
Ensure correct sequence out of plough in chute
Provide sufficient cable slack for splicing
Start machine slowly and hold services by hand
in trench
Minimise stoppages during plough in process
Monitor marker tape at feeding system
Repeat same process at end of each length Plough in process can be stopped in middle of
length at night
8/13/2019 I Direct Burial & Plough in of of Cables
14/28
Inner ducts must be jointed with Plasson fittings
in trench Build manholes and jointing pits after plough in
process
Plough cable in as near as possible at end of
route and excavate trench as at start
Test all fibres after plough in process to verifyintegrity
Plough in procedure (contd.)
8/13/2019 I Direct Burial & Plough in of of Cables
15/28
Plough in machine
8/13/2019 I Direct Burial & Plough in of of Cables
16/28
Reinstatement after plough in process
No compaction of disturbed area is necessary
Back blading with plough machine
Level surface with TLB Repair all fences
Replace all stays and struts
8/13/2019 I Direct Burial & Plough in of of Cables
17/28
Direct burial
Applications
Installation method
8/13/2019 I Direct Burial & Plough in of of Cables
18/28
Applications
In rural areas where plough in can not be done
In urban areas where cables are buried underlayer of ducts which caters for future network
expansion
Road crossings and services that must be
crossed in urban areas will limit cable lengths
that can be ploughed in
8/13/2019 I Direct Burial & Plough in of of Cables
19/28
Installation method
Excavate trench as per normal requirements
Limit width to 370mm if only cable will be buried
Bedding and padding material river sand or
sieved material not greater than 5mm Bedding must be 150mm
Lay cable and cover with 150mm padding
8/13/2019 I Direct Burial & Plough in of of Cables
20/28
Installation method (contd.)
Install ducts if required on top of cable
Use same bedding and padding material forducts
Cover cable with 300mm backfill material
Use mechanical compaction to compact backfillin layers of 300mm
Build manholes and jointing pits for future
development after cable laying
8/13/2019 I Direct Burial & Plough in of of Cables
21/28
Directional boring
Description Applications
Machinery
Procedure
Advantages/Disadvantages
8/13/2019 I Direct Burial & Plough in of of Cables
22/28
Description
Directional boring is the drilling of a required
diameter hole between two points at a specific
depth to accommodate a cable or a duct without
disturbing or damaging any infrastructure
8/13/2019 I Direct Burial & Plough in of of Cables
23/28
Diagram
8/13/2019 I Direct Burial & Plough in of of Cables
24/28
Applications
Crossing streets, highways and railway lines Crossing foundations of buildings
Crossing rivers, pipelines and water drainage
systems
8/13/2019 I Direct Burial & Plough in of of Cables
25/28
Machinery
8/13/2019 I Direct Burial & Plough in of of Cables
26/28
Machinery
8/13/2019 I Direct Burial & Plough in of of Cables
27/28
Procedure Locate all services
Set up drilling rig Mix bentonite mix to suit soil formation
Drill pilot hole up to required position
Fit reamer to drill end and secure cable or duct
Pull cable/duct back while hole is reamed
Ensure sufficient slack
8/13/2019 I Direct Burial & Plough in of of Cables
28/28
Advantages / Disadvantages
Accurate
No trenching and reinstatement of surfaces Cost effective
Difficult crossings is possible and done safely
Only 300m is possible
Specialised equipment is needed
Too many deviations in hole will make haulingimpossible