1 SIMON FRASER PPP Transaction Manager – Inland Rail IAQ Qld Infrastructure Summit 14 September 2018 The Australian Government is delivering Inland Rail through the Australian Rail Track Corporation (ARTC), in partnership with the private sector.

IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

1

SIMON FRASERPPP Transaction Manager – Inland Rail

IAQ Qld Infrastructure Summit14 September 2018

The Australian Government is delivering Inland Rail through the Australian Rail Track Corporation

(ARTC), in partnership with the private sector.

Page 2: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

2

AGENDA Why Inland Rail?

Rationale for PPP

Indicative timeline for PPP

Inland Rail PPP Team

Current status of ‘Whole of Programme’ opportunities

Questions

What is Inland Rail?

2

Page 3: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

ENHANCING THE NATIONALSUPPLY CHAIN

inlandrail.com.au3

Page 4: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

4

KEY OUTCOMES OF INLAND RAIL

FASTStraight and flat

NOW33hrs

BENEFICIAL30%

CONNECTED

FUTURE

24<MELBOURNE

TO BRISBANE

16,000 JOBS

BILLION IN ECONOMIC ACTIVITY$16

COST REDUCTION

COMPARED TO TRUCKS

RELIABLE98%

4

Page 5: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

5

The 126km section from Toowoomba to Kagaru, including large scale tunneling, will be delivered through a Public Private Partnership (PPP)

PPP – GEOGRAPHICAL CONTEXT

5

Page 6: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

artc.com.au | Simon Thomas, Programme Delivery Director – Inland Rail |

artc.com.au

PPP – GEOGRAPHICAL CONTEXT

6

Page 7: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

7

Cut to Fill -

11,700,000m3 cut

to 10,400,000m3

fill Formation

(capping) layer –

194,327m3

131 culverts of

various sizes

51 bridges

totalling 3.94km

in length

11 viaducts totalling

8.07km in length

6 road over

rail grade

separations

Active – 10

Passive – 11

8.51km in

length

PPP – INNOVATION WHERE IT MATTERS THE MOST

133.6km of new dual gauge

track, 11 passing loops to

cater for 1.8km trains

Local road realignment

4.7km

New road access 7.3km

Page 8: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

8

RATIONALE FOR PPP

COMMONWEALTH GOVERNMENT ANNOUNCED IN 2017 GOWRIE TO KAGARU SECTION TO BE DELIVERED AS A PPP.

Commonwealth Government analysis

Technical Complexities and desire for smart, innovative solutions from private sector

Value for Money

Risk Optimisation

8

Page 9: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

9

PPP – INDICATIVE TIMELINE

9

Page 10: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

10

PPP – INLAND RAIL TEAM – INTERNAL

Also supported by specialists and support resources within the organisation

Approximately 40 people dedicated to the PPP Project

Projected to grow

10

Page 11: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

11

PPP – INLAND RAIL TEAM – EXTERNAL Technical

and Approvals Consultants

Future Freight JV (AECOM +

Aurecon)

Technical Advisors

SMEC + Arup JV

Probity Advisor

BDO

Commercial and Financial

Advisors

KPMG

Legal Advisors

KWM

Transaction Advisor

Calcutta Group

Geotechnical Advisors

TBC

11

Page 12: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

12

MARKET TESTING TIMING (NON PPP)

12

Page 13: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

13

‘WHOLE OF PROGRAMME’ OPPORTUNITIES

inlandrail.com.au/register

13

Page 14: IAQ Infrastructure Summit Inland Rail presentation · IAQ Infrastructure Summit Inland Rail presentation Author: Simon Fraser Created Date: 9/21/2018 1:45:48 PM

14

THANK YOU

QUESTIONS?

14