ICARUS transfer from LNGS to CERN

Jean-Louis GRENARD & Ingo RÜHL (on behalf of Caterina BERTONE)

EN-HE

Page 2: ICARUS transfer from LNGS to  CERN

Agenda

Present situation I. Rühl 10 min

Dismantling works JL. Grenard 20 min

Cost estimates I. Rühl 10 min

Page 3: ICARUS transfer from LNGS to  CERN

Present situation ICARUS experiment and annexed equipment was transferred via

TIR tunnel and installed in EMPTY ‘B’ room of LNGS laboratory about 10 years ago.

Since then major modifications in TIR tunnel

Installation of fire resistant doors, which reduced clearance height from 4.75 to 4.6m

Installation of ventilation ducts, which reduces the overall height clearance along the tunnel to 4.6m

Installation of cryo-box restricting the clearance width to 4.3m in a curve B room

Installation of WARP experimental complex Installation of OPERA control rooms Installation of concrete step of 25cm height in center parallel to TIR gallery Increase of height floor by 30cm (expect TIR area)

Page 4: ICARUS transfer from LNGS to  CERN

Result of modifications

Free net passage at the door for a long, non tilted item is only about 4.05m

Installation procedure

Removal procedure

Page 5: ICARUS transfer from LNGS to  CERN

Objects to be transferred

2 cryostats containing wire and tube chambers (ext. dimensions 3970x4403mm by 20’209mm of length) with unit weight of 48,5t

Structures and equipment for a total volume of ~1’800mc (26mx11mx10m – 2 tanks) composed of: 2 STEARLING tanks 3 pumping groups 96 electrical cupboards (racks) Cryogenic material (tanks, pipes, filters

etc), metallic structure, bulk material

Page 6: ICARUS transfer from LNGS to  CERN

Dismantling and removal works

Presented by JL. Grenard

Page 7: ICARUS transfer from LNGS to  CERN

Cost estimates

Preparation works (mainly civil engineering works)

Dismantling works (mainly handling works)

Tooling

Transport costs

Summary

Page 8: ICARUS transfer from LNGS to  CERN

Cost estimates – Preparation works

Preparation works Removing concrete step Removing OPERA CS2 Evacuation of all stored equipment Removal of the ‘neon’ part Removal of cryo-tank from TIR tunnel

Additional works for complete cryostat evacuation Removal of added 30cm concrete floor of about

20m length into the cavern Removal of doors and air duct

Costs to be evaluated by

INFN!

Page 9: ICARUS transfer from LNGS to  CERN

Dismantling works

Based on CERN experience the dismantling work of items that shall be transferred to CERN will require 1 crane drivers 2 handlers 1 mechanic 1 foreman / supervisor

for a period of up to 2 months.

These people must have many years of experience to work in confined underground areas.

CERN supervision of dismantling and handling activities is subject to approval by the CERN management.

15’000 SFr/2 months30’000 SFr/2 months15’000 SFr/2 months20’000 SFr/2 months

80’000 SFr

Cost estimates based on CERN contract prices with

the French company AltéAD - displacement costs to be

added!

Page 10: ICARUS transfer from LNGS to  CERN

Tooling

Mobile crane and forklift rental 10-20 kSFr In case that cryostat will be removed

Consumables (slings, hooks, etc.) 10-20 kSFr

Air pads 15 kSFr Compressor unit 10 kSFr

Repair, modify, certify transport tools 15kSfr

Contingencies (storage costs, etc.) 20 kSFr

Costs estimate varies between 60 and

100kSFr

Page 11: ICARUS transfer from LNGS to  CERN

Transport costs

Two exceptional transport convoys from LNGS to CERN120 kSFr

Standard cargo truck 2 kSFR Estimated 20 travels 40

kSFrCost estimates provided by French company AltéAD!

Page 12: ICARUS transfer from LNGS to  CERN

Summary

Cost estimate in SFr

Remarks

Preparation works INFN

Dismantling works 80’000

Tooling 80’000 Cost estimate between 60 and 100 kSFr

Transport costs 160’000 2 exceptional and 20 standard transports

Installation costs at CERN

Depends on building infrastructure

Total 320’000