Upload
mahesh-s
View
212
Download
0
Embed Size (px)
Citation preview
In-situ Reconfiguration for Flexible Distribution of
Energy and Storage Resources
Ajit A. Renjit
Student Member, IEEE
The Ohio State University
Electrical and Computer Engineering
Columbus, OH 43210, USA
Mahesh S. Illindala
Senior Member, IEEE
The Ohio State University
Electrical and Computer Engineering
Columbus, OH 43210, USA
Abstract—Flexible Distribution of EneRgy and Storage
Resources (FDERS) is a new framework recently proposed for
integrating various distributed resources in a power system. It
provides flexibility in rearranging the interconnected system
resources into formations in order to achieve greater
sustainability as observed in the V-shape formation of a bird
flock or peloton formation of a cycling racing team. One of the
characteristic features of FDERS is in enabling distributed
resources reconfiguration in-situ, i.e., the resources
demonstrate a different dynamic behavior relative to each
other than their (original) physical ‘electrical’ location
otherwise would suggest. This paper presents various schemes
for in-situ reconfiguration along with their advantages. It is
achieved by means of developing novel techniques employing
special functions of compensating reactances. These techniques
help in achieving greater sustainability goals like optimal
energy storage deployment, enhanced controllability, improved
system robustness and increased lifetime of the distributed
energy and storage resources. In-situ reconfiguration is
demonstrated for within-parallel, parallel-to-series and series-
to-parallel connections. Finally, a comparison is also presented between physical and in-situ and reconfigurations.
I. INTRODUCTION
Distributed Energy Resources (DERs) and microgrids
have been proposed in the recent past to improve the power
quality and reliability for critical and sensitive loads [1].
However, the integration techniques developed thus far
relied to a large extent on the traditional power systems
approach that assumes large DERs providing power to
numerous smaller-rated loads. In this case, the individual
load dynamics get smoothed out and there is seldom a need
to make any large and sudden changes in generation. Such
systems are ill-prepared for challenging scenarios of large
and fluctuating demands – as observed when multiple smaller-rated DERs need to supply significant-sized loads,
especially when there is no power from the main (utility)
grid.
A typical example of challenging load scenario is the
crusher load commonly found in metal industries, mining
sites or cement plants [2]. A network of small-rated DERs
needs very detailed and thorough design for reliably
supplying without breakdown any large and fluctuating
loads, especially in the islanded mode of operation. This is
because the dynamic behaviors of such DERs are highly
dependent on their ‘electrical’ locational placement within
the microgrid [3-5]. As a solution, a new framework known
as Flexible Distribution of EneRgy and Storage Resources
(FDERS) was proposed in [6].
FDERS was inspired by the V-shape formation of a bird
flock and peloton/echelon formation of a cycling racing team
where the team members cooperate for deriving greater
shared benefits [6]. It claims to offer several benefits like optimal energy storage deployment, enhanced controllability,
improved system robustness and increased lifetime of all
power system resources. One of the key features enabling the
flexibility is the reconfiguration in-situ, where the distributed
resources demonstrate a different dynamic behavior relative
to each other than their (original) physical ‘electrical’
location otherwise would suggest. This paper presents
various schemes for in-situ reconfiguration along with their
advantages.
The organization of this paper is as follows: Section II
describes the synthesization of virtual reactance that is the
essential first step in realizing in-situ reconfiguration. Also
the simple case of within-parallel in-situ reconfiguration is
explained in this section. In Section III, an in-situ
reconfiguration scheme parallel-to-series is described.
Section IV covers the series-parallel in-situ reconfiguration.
Finally, Section V concludes the paper.
II. SYNTHESIZATION OF VIRTUAL REACTANCE FOR WITHIN-PARALLEL IN-SITU RECONFIGURATION
This section discusses briefly how to realize synthesized
virtual reactances in power electronics based DERs that are
connected parallelly to supply a load [6]. Consider an n-
DER parallel network. In order to realize FDERS, it is
required to achieve relative drafting between two DERs in
the network. This is only possible with a variation in their
2378978-1-4799-0336-8/13/$31.00 ©2013 IEEE
Fig. 1. Synthesis of ‘virtual’ reactance Xk-add in producing inner loop voltage controller reference for each DER in a parallel network
individual interface reactances.
A practical concern over the use of a large physical
reactance in interfacing any DER to the network is its size
and the fact that it cannot be easily varied in the existing
equipment. Therefore, using the method of synthesized
‘virtual’ reactances as shown in Fig. 1 any value of
additional reactance can be built within the DER’s
controller, and thereby changing its voltage reference
from �⃗�𝑘∗ (𝑡) to �⃗�𝑘
′∗(𝑡). It is to be noted that, for the purposes
of simulation, the inner voltage regulator has been
approximated as a first-order lag function whose time-
constant is assumed as (Tv = 5 ms) based on the controller
bandwidth for a PWM inverter operating at 4-kHz switching
frequency [5].
Fig. 2 illustrates a parallel configuration where the
physical reactances X1o=X2o=X30…=Xno=10%, and the
additional reactances Xk-add (where k = 1, 2, .., n) for each
DER are synthesized within its controller card. The value of
the synthesized reactance Xk-add can then be programmed
corresponding to the pecking order of DERs in the
formation – similar to the bird flock/V-formation [7, 8] or
cycling team/peloton formation [9-11]. The pecking order
can be modified based on preferred criteria such as energy
resource availability, prime-mover response characteristics
and lifecycle costs. Thus the method of synthesized
reactances helps the DERs to reconfigure in-situ while their
physical electrical location remains unaltered.
Time-domain simulations were carried out in
Matlab/Simulink/SimPowerSystems for the parallel
DER system. Fig. 3 shows the observed dynamic response
of a parallel-connected 3-phase, 480-V, 60-Hz, 4-DER
islanded system for a large block load change from 80-kW
to 160-kW.
Fig. 2. Single line diagram of parallel configuration of multiple (n > 2) DER system with synthesized reactances.
Act
ive
po
wer
(k
W)
Time (s)
Fig. 3. Response of a 4-parallel-DER system obtained using within-
parallel in-situ reconfiguration to a step change in a large block load from
80kW to 160kW
As anticipated based on the net reactance values (Xko+Xk-
add), the DER1 that is electrically closest to the load
3-phase
space
vector
(synchr. frame)
+
Vk∗
ωk∗
ikd
From “DERk
power
controller”
(inset of this
picture)
From DERk output current measurements
ikq
-1
𝑖𝑘(𝑡)= 𝑖𝑘𝑑 + 𝑗𝑖𝑘𝑞
𝑗𝑖𝑘(𝑡)= −𝑖𝑘𝑞 + 𝑗𝑖𝑘𝑑
+
𝑣𝑘𝑞
∗
Xk-add
�⃗�𝑘′∗(𝑡)
= 𝑣𝑘𝑑′∗ + 𝑗𝑣𝑘𝑞
′∗
�⃗�𝑘′∗(𝑡) = �⃗�𝑘
∗(𝑡) − j𝑋k−add 𝑖𝑘(𝑡)
𝑣𝑘𝑑∗
𝑣𝑘𝑞′∗
𝑣𝑘𝑑′∗
ωk∗
�⃗�𝑘∗(𝑡)
= 𝑣𝑘𝑑∗ + 𝑗𝑣𝑘𝑞
∗ dq/abc
transform. (Effect of
inner voltage controller)
1
1 + 𝑠𝑇𝑣
�⃗�𝑘
′ (𝑡)= 𝑣𝑘𝑑
′ + 𝑗𝑣𝑘𝑞′
𝑣𝑘𝑞′
𝑣𝑘𝑑′
𝑣𝑘𝑎′
𝑣𝑘𝑏′
𝑣𝑘𝑐′
ikd
ikq
nom
+ 1
Dqk
+
+
+
+
+
Vk∗
ωk∗
Vno
m Q
k
Pk
To the inner
loop voltage regulators
1
Mks + Dk
∆Vk∗
∆ωk∗
Qk∗
V /Q
Controller
/P
Controller
Pk∗
1 + 𝑠𝑇𝑎
1 + 𝑠𝑇𝑏
X2o
𝑖2
PL
X1o
DER
1
𝑖1
DER
2
X1-add
X2-add
DER
n
�⃗�1𝑝= V1𝑝ej1pt
�⃗�𝑛𝑝= V𝑛𝑝ejnpt
�⃗�2𝑝= V2𝑝ej2pt
�⃗�1𝑝′ = V1𝑝
′ ej1pt
�⃗�2𝑝′ = V2𝑝
′ ej2pt
�⃗�𝑛𝑝′ = V𝑛𝑝
′ ejnpt
Xn-add
𝑖𝑛
X3o
X1-add
< X2-add
< ••• < Xn-add
X1o
= X2o
= ••• = Xno
= 10%
X1-add = -10%
X2-add = 0%
X3-add = 10%
X4-add = 20%
X1o
= X2o
= X3o
= X4o
=10%
Leading
DER1
Drafting
DER4
2379
DERn
X1o
=0
�⃗�1𝑠= V1𝑠ej1st
X2o
Xno
�⃗�2𝑠= V2𝑠e
j2st
�⃗�𝑛𝑠= V𝑛𝑠ejnst
DER2
DER1
𝑖1
𝑖2
𝑖𝑛 P
L
𝑖2 + 𝑖3 … + 𝑖𝑛
X2o
= X3o
= ••• = Xno
contributes a major share in the transient power flow while the remaining DERs show drafting characteristics.
III. PARALLEL - SERIES IN-SITU RECONFIGURATION
It was earlier reported that the series connection of DERs facilitated a greater amount of drafting than a parallel connection [6]. Consequently, the parallel system in Fig. 4a was reconfigured into an n-DER series connected system in Fig. 4b using the conventional methods of physical reconfiguration using sectionalizers/switchgears. Fig. 6.a illustrates the response of a 4-DER series connected system for a block load change from 80kW to 160kW. Although by such a physical reconfiguration, enhanced drafting could be achieved, a major concern over this kind of reconfiguration technique is that it is not practically feasible to change interconnections to all the DERs that are distributed over long distances in a network. This would require a significant investment due to greater installation costs, communication overhead. Moreover, it also complicates the protection and control strategies. As a solution, the in-situ reconfiguration technique introduced in this paper, helps in reconfiguring the systems between parallel and series configurations and vice versa without any kind of physical interconnection between the DERs.
Fig. 4.a Single line diagram of a parallel configuration for multiple (n > 2)
DER system for equal steady-state sharing of a large block load (PL)
Fig. 4.b Single line diagram of series configuration for multiple (n > 2)
DER system for equal steady-state sharing of a large block load (PL)
For the parallel and series connected n-DER systems in Fig. 4a and Fig. 4b, the network equations are shown in Table I.
TABLE I. NETWORK EQUATIONS FOR THE PARALLEL AND SERIES
CONFIGURATIONS
Comparing the network equations of both the parallel and
series configurations in Table I, it is observed that
reconfiguring in-situ a parallel network to series form requires recreating all the additional voltage drops that are
absent in the parallel configuration’s network equations. In
the previous section, for a within-parallel in-situ
reconfiguration, the additional voltage drops required to
generate drafting characteristics in the parallel network were
built using synthesized reactances Xk-add and their
corresponding branch currents, 𝑖𝑘. However, in the parallel-
to-series case the network equations in Table-I suggest that
in order to achieve an in-situ parallel - series
reconfiguration, it would necessitate each DER to use its
neighbors’ branch currents too. A detailed step-by-step
procedure to realize this in-situ reconfiguration technique is explained below:
Step 1: Recreating the additional voltage drops using the
virtual reactances.
As a first step, the additional voltage drops in the
network equations of the (final state) series configuration
are added to the (initial state) parallel network equations in
Table I. However in a parallel configuration, since the DERs
are tied directly to the point of common coupling (PCC)
through their individual physical reactances Xko the
remaining voltage drops for Xm,o (m = 2, 3, …, k) are
constructed using corresponding virtual reactance Xm-add = Xm,o (m = 2, 3, …, k). Accordingly, the reconfigured
network equations can be represented as:
�⃗�1𝑝∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 )
�⃗�2𝑝∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 ) + (𝑖2 ∗ 𝑗𝑋2𝑜) + (∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋2−𝑎𝑑𝑑)
�⃗�3𝑝∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 ) + (𝑖3 ∗ 𝑗𝑋3𝑜) + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑) +
(∑ 𝑖𝑘𝑛𝑘=3 ∗ 𝑗𝑋3−𝑎𝑑𝑑)
�⃗�4𝑝∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) + (𝑖𝑛 ∗ 𝑗𝑋𝑛𝑜) + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑)
+(∑ 𝑖𝑘𝑛𝑘=3 ∗ 𝑗𝑋3−𝑎𝑑𝑑) ……. + (∑ 𝑖𝑘
𝑛𝑘=𝑛−1 ∗ 𝑗𝑋(𝑛−1)−𝑎𝑑𝑑)
DER
No
Parallel configuration
(Fig. 4a) Series configuration (Fig. 4b)
1 �⃗�1𝑝∗ = 𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 �⃗�1𝑠
∗ = (𝑃𝐿/ ∑ 𝑖𝑘𝑛𝑘=1 )
2
�⃗�2𝑝∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 ) +
(𝑖2 ∗ 𝑗𝑋2𝑜)
�⃗�2𝑠∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) +
(∑ 𝑖𝑘𝑛𝑘=2 ∗ 𝑗𝑋2𝑜)
3 �⃗�3𝑝
∗ = (𝑃𝐿/ ∑ 𝑖𝑘𝑛𝑘=1 ) +
(𝑖3 ∗ 𝑗𝑋3𝑜 )
�⃗�3𝑠∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) +
(∑ 𝑖𝑘𝑛𝑘=2 ∗ 𝑗𝑋2𝑜) + (∑ 𝑖𝑘
𝑛𝑘=3 ∗
𝑗𝑋3𝑜)
4
�⃗�4𝑝∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) +
(𝑖4 ∗ 𝑗𝑋4𝑜)
�⃗�4𝑠∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) +
(∑ 𝑖𝑘𝑛𝑘=2 ∗ 𝑗𝑋2𝑜) + (∑ 𝑖𝑘
𝑛𝑘=3 ∗
𝑗𝑋3𝑜) + (∑ 𝑖𝑘𝑛𝑘=4 ∗ 𝑗𝑋4𝑜)
n
�⃗�𝑛𝑝∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 ) +
(𝑖𝑛 ∗ 𝑗𝑋𝑛𝑜)
�⃗�𝑛𝑠∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) +
(∑ 𝑖𝑘𝑛𝑘=2 ∗ 𝑗𝑋2𝑜) + (∑ 𝑖𝑘
𝑛𝑘=3 ∗
𝑗𝑋3𝑜) +… … . + (∑ 𝑖𝑘𝑛𝑘=𝑛 ∗ 𝑗𝑋𝑛𝑜)
X1o
=0
�⃗�𝑛𝑝= V𝑛𝑝ejnt
DERn
�⃗�1𝑝= V1𝑝ej1pt
X2o
�⃗�2𝑝= V2𝑝ej2pt
DER2
DER1 𝑖1
𝑖2
𝑖𝑛 PL
X2o
= X3o
= ••• = Xno
Xno
Vpcc
ejpcct
Vpcc
ejpcct
2380
A typical equivalent circuit corresponding to the above
equations is shown in Fig. 5.a for n=3, DER3.
Fig. 5.a Equivalent circuits showing the transformation of the actual DER3
network in the parallel configuration of Fig. 4.a into a reconfigured
network with the additional voltage drops created using the virtual (Xk-add)
reactances between the source and the PCC.
Step 2: Modifying the virtual reactance drops into
dependent voltage sources to be built inside the DER’s controller card:
Next, all the additional terms depicting voltage drops
(across virtual reactances) are built inside each DER’s
controller as dependent voltage sources, and thereby its
voltage reference is modified from �⃗�𝑘𝑝∗ (𝑡) to �⃗�𝑘𝑝
′∗ (𝑡), as shown
in Fig. 5.c.
�⃗�1𝑝′∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 )
�⃗�2𝑝′∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 ) + (𝑖2 ∗ 𝑗𝑋2𝑜)
= �⃗�2𝑝∗ − (∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋2−𝑎𝑑𝑑)
�⃗�3𝑝′∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 ) + (𝑖3 ∗ 𝑗𝑋3𝑜)
= �⃗�3𝑝∗ − (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑)−(∑ 𝑖𝑘
𝑛𝑘=4 ∗ 𝑗𝑋3−𝑎𝑑𝑑)
�⃗�𝑛𝑝′∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 ) + (𝑖𝑛 ∗ 𝑗𝑋𝑛𝑜)
= �⃗�𝑛𝑝∗ − (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑) −(∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋3−𝑎𝑑𝑑)…….
− (∑ 𝑖𝑘𝑛𝑘=𝑛−1 ∗ 𝑗𝑋(𝑛−1)−𝑎𝑑𝑑)
A simplified equivalent circuit corresponding to the
above equations is shown in Fig. 5.b for k=3, DER3.
The dynamic behavior of a parallel-to-series in-situ reconfigured 4-DER system for an 80-kW load change was
evaluated through a time-domain simulation performed
using MATLAB/Simulink/SimPowerSystems, and the results obtained are displayed in Fig. 6.b. It was
observed that the reconfiguration results matched
reasonably well with the physical series configuration
results displayed in Fig. 6.a. Minor discrepancies are
observed because of the unaccounted resistive drops in the
simulation model (that also exist in real-life). It is to be
noted that the PWM inverter-based DER inner-voltage
regulator controls were approximated as a first-order lag
function whose time-constant is assumed to be (Tv = 5 ms)
based on the controller bandwidth (cf. Fig. 1) typical with a
4-kHz switching frequency [5].
Fig. 5.b Equivalent circuit of the reconfigured network for DER3 with
dependent voltage sources to modify the terminal voltage from �⃗�3𝑝 to �⃗�3𝑝′ .
Fig. 5.c The complete reconfigured parallel-to-series equivalent circuit with
dependent voltage sources implemented inside each DER controller to
modify its voltage reference from �⃗�𝑘𝑝∗ (𝑡) to �⃗�𝑘𝑝
′∗ (𝑡)
IV. SERIES - PARALLEL IN-SITU RECONFIGURATION
Another kind of reconfiguration that may be also of
interest to power engineers is the reverse transformation of
that described in the previous section, viz., a series-to-
parallel reconfiguration. As such, the in-situ reconfiguration
technique was once again employed to reverse reconfigure
the n-DER series network (X1=0, X2 = X3 =... = Xn) in Fig.
4.b into a parallel one (X1=0, X2 = X3 =... = Xn) in Fig. 4.a. The network equations of both the parallel and series
connected n-DER systems are the same as shown before in
Table I. Relating both the system equations, it is observed
�⃗�3𝑝= V3𝑝ej3pt
X2-add
PL
X3o
𝑖3 DER
3
X3-add
𝑖2 + 𝑖3 … +𝑖𝑛
𝑖4 + 𝑖5 … +𝑖𝑛
−𝑖3 + 𝑖4 𝑖5 … + 𝑖𝑛
𝑖2
�⃗�3𝑝∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 ) + (𝑖3 ∗ 𝑗𝑋3𝑜) + (∑ 𝑖𝑘
𝑛𝑘=4 ∗ 𝑗𝑋3−𝑎𝑑𝑑)
+(∑ 𝑖𝑘𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑 )
DER3
�⃗�3𝑝= V3𝑝ej3pt
X3o
𝑖3
PL
(R-Load)
𝑖3
Vpcc
ejpcct
Vpcc
ejpcct
𝑗𝑋2−𝑎𝑑𝑑 ∗ (𝑖2 +𝑖3 … . . +𝑖𝑛) �⃗�3𝑝
𝑗𝑋3−𝑎𝑑𝑑 ∗ (𝑖4 +𝑖5 … . . +𝑖𝑛)
PL
X3o
�⃗�3𝑝′ = V3𝑝
′ ej3pt
DER3
𝑖3
�⃗�3𝑝′∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 ) + (𝑖3 ∗ 𝑗𝑋3𝑜)
= �⃗�3𝑝∗ − (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑)−(∑ 𝑖𝑘
𝑛𝑘=4 ∗ 𝑗𝑋3−𝑎𝑑𝑑)
Vpcc
ejpcct
X2o
DER
2
DERn
DER3
DER1
X3o
Xno
Vpcc
ejpcct
�⃗�2𝑝′ = V2𝑝
′ ej2pt
�⃗�1𝑝′ = V1𝑝
′ ej1pt
PL
𝑖1
𝑖2
𝑖3
𝑖𝑛
𝑗𝑋2−𝑎𝑑𝑑 ∗ (𝑖3 +𝑖4 … . . +𝑖𝑛)
𝑗𝑋2−𝑎𝑑𝑑 ∗ (𝑖2 +𝑖3 … . . +𝑖𝑛)
𝑗𝑋(𝑛−1)−𝑎𝑑𝑑 ∗
(𝑖𝑛−1 + 𝑖𝑛) 𝑗𝑋2−𝑎𝑑𝑑 ∗ (𝑖2 +𝑖3 … . . +𝑖𝑛)
𝑗𝑋3−𝑎𝑑𝑑 ∗ (𝑖4 +𝑖5 … . . +𝑖𝑛) �⃗�3𝑝
′ = V3𝑝′ e
j3pt
�⃗�𝑛𝑝′ = V𝑛𝑝
′ ejnpt
�⃗�2𝑝
�⃗�𝑛𝑝
�⃗�3𝑝
2381
A
ctiv
e p
ow
er (
kW
)
Act
ive
po
wer
(k
W)
Time (s) Time (s)
(a) (b)
Figure 6.a Response of a 4-DER physical series network to a step change in a large block load from 80kW to 160kW
Figure 6.b Response of a 4-DER series network (obtained using parallel-to-series in-situ reconfiguration) to a step change in a large block load from 80kW to 160kW
that reconfiguring in-situ a series system into a parallel form
requires getting rid of all the additional voltage drops that
are present in the network equations of the series
configuration. Following a similar procedure as the previous
section on parallel-to-series reconfiguration, a detailed step-
by-step procedure to realize in-situ series-to-parallel
reconfiguration is explained below:
Step 1: Compensating the additional voltage drops using the
virtual reactances.
Identifying that the (final state) parallel configuration
should be devoid of all the additional voltage drops that are
present in the network equations of the (initial state) series
configuration, their effect is nullified by using compensating
virtual reactances. (Note: The respective network equations
are given in Table I.)
In a series configuration, since the DERs are
interconnected through their individual physical reactances
Xko, the compensating voltage drops for Xm,o (m = 2, 3, …,
k) are constructed using corresponding virtual reactance Xm-
add = Xm,o (m = 2, 3, …, k). Accordingly, the reconfigured network equations can be represented as:
�⃗�1𝑠∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 )
�⃗�2𝑠∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2𝑜) -(∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋2−𝑎𝑑𝑑)
�⃗�3𝑠∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2𝑜) + (∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋3𝑜)-
(∑ 𝑖𝑘𝑛𝑘=4 ∗ 𝑗𝑋3−𝑎𝑑𝑑) -(∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑)
�⃗�𝑛𝑠∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2𝑜)+(∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋3𝑜) +
… … + (∑ 𝑖𝑘𝑛𝑘=𝑛 ∗ 𝑗𝑋𝑛𝑜) −(∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑)-(∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋3−𝑎𝑑𝑑)-
… … − (∑ 𝑖𝑘𝑛𝑘=𝑛−1 ∗ 𝑗𝑋(𝑛−1)−𝑎𝑑𝑑)
A typical equivalent circuit corresponding to the above
equations is shown in Fig. 7.a for n=3, DER3.
Step 2: Modifying the virtual reactance drops into
dependent voltage sources to be built inside the DER’s
controller card:
As a next step, all the additional terms depicting voltage
drops (across virtual reactances) are built inside each DER’s
controller as dependent voltage sources, and thereby its
voltage reference is modified from �⃗�𝑘𝑠∗ (𝑡) to �⃗�𝑘𝑠
′∗ (𝑡), as shown
in Fig. 7.c.
�⃗�1𝑠′∗ = (𝑃𝐿/ ∑ 𝑖𝑘
𝑛𝑘=1 )
Fig. 7.a Equivalent circuits showing the transformation of the actual DER3
network in the series configuration of Fig. 3.b into a reconfigured network
with the compensating voltage drops created using the virtual (Xm-add)
reactances.
�⃗�2𝑠′∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2𝑜)
= �⃗�2𝑠∗ + (∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋2−𝑎𝑑𝑑)
�⃗�3𝑠′∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2𝑜) + (∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋3𝑜)
= �⃗�3𝑠∗ + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑)+(∑ 𝑖𝑘
𝑛𝑘=4 ∗ 𝑗𝑋3−𝑎𝑑𝑑)
X2o
�⃗�3𝑠= V3𝑠ej3st
DER3
X3o
𝑖4 + 𝑖5 … + 𝑖𝑛
𝑖3
𝑖2
DER3
𝑖4 + 𝑖5 … + 𝑖𝑛
𝑖2 + 𝑖3
𝑖2 + 𝑖3 + ⋯ 𝑖𝑛
X2o
�⃗�3𝑠= V3𝑠ej3st
X3o
𝑖2 + 𝑖3 … + 𝑖𝑛
𝑖3 + 𝑖4 … + 𝑖𝑛
𝑖4 + 𝑖5 … + 𝑖𝑛
𝑖3
𝑖2
X3-add
X2-add
�⃗�3𝑠∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2𝑜) + (∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋3𝑜)-
(∑ 𝑖𝑘𝑛𝑘=4 ∗ 𝑗𝑋3−𝑎𝑑𝑑) -(∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑)
𝑖3 + 𝑖4 … + 𝑖𝑛
PL
PL
𝑖2 + 𝑖3 … + 𝑖𝑛
Vpcc
ejpcct
Vpcc
ejpcct
X2o = X3o = X4o
=10%
X2o = X3o = X4o
=10%
X2-add = X3-add = X4-add
=10%
Leading
DER1
Drafting
DER4
Leading
DER1
Drafting
DER4
2382
�⃗�𝑛𝑠′∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2𝑜) + (∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋3𝑜 ) +… ….
+ (∑ 𝑖𝑘𝑛𝑘=𝑛 ∗ 𝑗𝑋𝑛𝑜)
= �⃗�𝑛𝑠∗ + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑) +(∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋3−𝑎𝑑𝑑)…….
+ (∑ 𝑖𝑘𝑛𝑘=𝑛−1 ∗ 𝑗𝑋(𝑛−1)−𝑎𝑑𝑑)
A simplified equivalent circuit corresponding to the
above equations is shown in Fig. 7.b for k=3, DER3. Note the presence of the dependent voltage sources in the
network and their polarity. They are represented in such a
way that they cancel out the additional voltage drops in the
series configuration’s network equation.
Fig. 7.b Equivalent circuit of the reconfigured network for DER3 with
dependent voltage sources to modify the voltage reference from �⃗�𝑘𝑠∗ (𝑡)
to �⃗�𝑘𝑠′∗ (𝑡)
The dynamic behavior of a series to parallel in-situ
reconfigured 4-DER system for a 80kW to 160kW load
change was evaluated through a time-domain simulation in
MATLAB/Simulink/SimPowerSystems, and the results obtained are displayed in Fig. 8.b. For comparison
purposes, the dynamic response of the 4-DER physical
parallel network (of Fig. 4.a) is illustrated in Fig. 8.a for the same block load change from 80kW to 160kW. It was
observed that the in-situ reconfigured system results
matched reasonably well with the physical parallel
configuration results. As observed in the earlier case, minor
discrepancies are observed in this case also because of the
unaccounted resistive drops in the simulation model (that
also exist in real-life). It is to be noted that the PWM
inverter-based DER inner-voltage regulator controls were
approximated as a first-order lag function whose time-constant is assumed to be (Tv = 5 ms) based on the controller
bandwidth (cf. Fig. 1) typical with a 4-kHz switching
frequency [5].
Fig. 7.c The complete reconfigured parallel-to-series equivalent circuit with
dependent voltage sources implemented inside each DER controller to
modify its voltage reference from �⃗�𝑘𝑠∗ (𝑡) to �⃗�𝑘𝑠
′∗ (𝑡).
Act
ive
po
wer
(k
W)
Act
ive
po
wer
(k
W)
Time (s) Time (s)
(a) (b)
Figure 8.a Response of a 4-DER physical parallel network to a step change in a large block load from 80kW to 160kW
Figure 8.b Response of a 4-DER parallel network (obtained using series-to-parallel in-situ reconfiguration) to a step change in a large block load from 80kW to 160kW
𝑗𝑋3−𝑎𝑑𝑑 ∗ (𝑖4 +𝑖5 … . . +𝑖𝑛) �⃗�3𝑠
𝑗𝑋2−𝑎𝑑𝑑 ∗ (𝑖2 +𝑖3 … . . +𝑖𝑛)
PL
�⃗�3𝑠′ = V3𝑠
′ ej3pt
DER3
�⃗�3𝑠′∗ = (𝑃𝐿 / ∑ 𝑖𝑘
𝑛𝑘=1 ) + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2𝑜) + (∑ 𝑖𝑘
𝑛𝑘=3 ∗ 𝑗𝑋3𝑜)
= �⃗�3𝑠∗ + (∑ 𝑖𝑘
𝑛𝑘=2 ∗ 𝑗𝑋2−𝑎𝑑𝑑)+(∑ 𝑖𝑘
𝑛𝑘=4 ∗ 𝑗𝑋3−𝑎𝑑𝑑)
X2o
X3o
𝑖2
+ 𝑖3 …+ 𝑖𝑛
𝑖3
+ 𝑖4 …+ 𝑖𝑛
𝑖2
+ 𝑖3 …+ 𝑖𝑛
𝑖3
+ 𝑖4 …+ 𝑖𝑛
𝑖2 + 𝑖3 … + 𝑖𝑛
𝑖3 + 𝑖4 … + 𝑖𝑛
𝑖2
𝑖4 + 𝑖5 … + 𝑖𝑛
Vpcc
ejpcct
Xno
�⃗�𝑛𝑠′ = V𝑛𝑠
′ ejnt
X1o
=0
�⃗�1𝑠= V1𝑠ej1st
X2o
DER1
𝑖2
𝑖2 + 𝑖3 … + 𝑖𝑛
𝑗𝑋3−𝑎𝑑𝑑 ∗ (𝑖4 +𝑖5 … . . +𝑖𝑛) �⃗�3𝑠
𝑗𝑋2−𝑎𝑑𝑑 ∗ (𝑖2 +𝑖3 … . . +𝑖𝑛)
𝑗𝑋2−𝑎𝑑𝑑 ∗ (𝑖3 +𝑖45 … . . +𝑖𝑛) �⃗�2𝑠
𝑗𝑋(𝑛−1)−𝑎𝑑𝑑 ∗ (𝑖(𝑛−1) + 𝑖𝑛) �⃗�𝑛𝑠
𝑗𝑋2−𝑎𝑑𝑑 ∗ (𝑖2 +𝑖3 … . . +𝑖𝑛)
𝑖3 + 𝑖4 … + 𝑖𝑛
𝑖3
𝑖𝑛
X3o
�⃗�3𝑠′ = V3𝑠
′ ejnt
�⃗�2𝑠′ = V2𝑠
′ ejnt
DER2
DERn
DER3 P
L
Vpcc
ejpcct
X2o = X3o = X4o
=10%
X2o = X3o = X4o
=10%
X2-add = X3-add = X4-add
=10%
Leading
DER1
Drafting DER2,
DER3 and DER4
Leading
DER1
Drafting
DER4
2383
V. CONCLUSIONS
This paper has presented the various in-situ reconfiguration schemes that are possible in Flexible Distribution of EneRgy and Storage Resources (FDERS). It facilitates the flexibility in rearranging and teaming up the interconnected power system resources into cooperative formations like the V-shape formation of a bird flock or peloton formation of a cycling racing team. By the methods presented in this paper, the various distributed resources are made to demonstrate a different dynamic behavior relative to each other than their (original) physical ‘electrical’ location otherwise would suggest. It has been achieved by means of developing novel techniques employing special functions of synthesized virtual reactances. A comparative analysis between the physical and in-situ reconfiguration schemes has been also presented. It was observed that the in-situ reconfiguration results match reasonably well with those of physical reconfiguration. The in-situ reconfiguration can be a viable alternative to the physical reconfiguration as it offers the benefits of saving installation cost, reducing communication overhead and simplifying the protection and control strategies. The proposed methods are particularly helpful in sustainably dealing with the large and fluctuating loads that are typically found in the metal industries, mining sites and cement plants. They help in achieving the greater sustainability goals of FDERS including optimal energy storage deployment, enhanced controllability, improved system robustness and increased lifetime of the distributed energy and storage resources.
REFERENCES
[1] G. Venkataramanan, M. S. Illindala, “Microgrids and Sensitive
Loads,” in Proc. IEEE Power Eng. Soc. Winter Meeting, Jan 2002, Vol. 1, pp. 315-322.
[2] V. B. Bohorquez, "Fast Varying Loads," 9th Intl. Conf. on Electrical
Power Quality and Utilisation, EPQU 2007, pp.1-6, 9-11 Oct. 2007.
[3] R. H. Lasseter, “Smart Distribution: Coupled Microgrids,”
Proceedings of the IEEE , vol.99, no.6, pp.1074-1082, June 2011.
[4] A. J. Wood, B. F. Wollenberg, Power Generation Operation and Control, 2nd Edition, John Wiley & Sons, 1996.
[5] M. S. Illindala, Vector Control of PWM-VSI Based Distributed
Resources in a Microgrid, Ph.D. Dissertation, University of Wisconsin-Madison, 2005.
[6] M. S. Illindala, "Flexible Distribution of Energy and Storage
Resources," in Proc. of IEEE Energy Conversion Congress and Exposition (ECCE), 2012, pp.4069-4076, 15-20 Sept. 2012.
[7] P. B. S. Lissaman, C. A. Schollenberger, “Formation Flight of Birds,”
Science, Vol. 168, 1970, pp. 1003–1005. doi:10.1126/science.168.3934.1003.
[8] H. Weimerskirch, J. Martin, Y. Clerquin, P. Alexandre, S. Jiraskova,
“Energy Saving in Flight Formation,” Nature, Vol. 413, 2001, pp. 697–698. doi:10.1038/35099670.
[9] C. R. Kyle, “Reduction of wind resistance and power output of racing cyclists and runners traveling in groups,” Ergonomics, 1979, Vol. 22:
pp. 387–397.
[10] A. G. Edwards, W. C. Byrnes, “Aerodynamic characteristics as determinants of the drafting effect in cycling,” Journal of Medical
Science Sports Exercise, Jan 2007, Vol. 39, No. 1, pp. 170-176.
[11] J. Brisswalter, C. Hausswirth, “Consequences of Drafting on Human Locomotion: Benefits on Sports Performance,” International Journal
of Sports Physiology and Performance, Apr 2008, Vol. 3, No. 1, pp. 3-15.
2384