Upload
dinhthu
View
224
Download
3
Embed Size (px)
Citation preview
ISSN: 2349-7300
ISO 9001:2008 Certified
International Journal of Innovative Research in Engineering & Multidisciplinary Physical Sciences
(IJIRMPS)
Volume 3, Issue 3, October 2015
1
A Unified Approach for the Transient Stability
Analysis for a Multi machine System Using
MatLab / Simulink Model Tefera Mekonnen, Dr HadadiSudheendra, Getnet_Zewde
School of Electrical and Computer Engineering, Jimma University, Jimma, Ethiopia
Abstract – Transient stability analysis has recently become a major issue in the operation of power systems due to the
increasing stress on power system networks specifically for a multi machine System. This problem requires evaluation of
a power system's ability to withstand disturbances while maintaining the quality of service. Many different techniques
have been proposed for transient stability analysis in power systems, especially for a multi machine system, these methods
include the time domain solutions, the extended equal area criteria, and the direct stability methods such as the transient
energy function. However, the most methods must transform from a multi-machine system to an equivalent machine and
infinite bus system. Transient stability well defined as the ability of a synchronous power system to return to stable
condition and maintain its synchronism following a relatively large disturbance arising from very general situations like
switching ‘on’ and ‘off’ of circuit elements viz the circuit breakers, relays or clearing of faults etc..More often than not,
the power generation systems are subjected to faults of this kind, and hence it’s extremely important for power engineers
to be well-versed with the stability conditions of the system without losing synchronism. Occurrence of fault in a power
system usually causes transients, which are due to sudden lightning, switching of lines etc, hence transient stability
analysis is extremely important for power engineers,. A classical model has been proposed for the study, for the faults
which are originating due to above said situations i.e. the ability of power system to deliver the power and maintain
synchronism when subjected to a severe transient disturbance is the Transient stability limit, such as a fault on
transmission facilitates the sudden loss of generation, or loss of a large load. In this research paper the transient model
of multi-machine power system is developed in MATLAB/SIMULINK using Simulator .A three–machine, six–bus power
system after subjected to a 3 Phase Short circuit (bolted fault) is studied. For studying the transient stability of this
system, the pre-fault load flow analysis, during fault and post fault analysis is calculated by using Kron’s elimination
method. For the simulation purpose, the Power System (SPS) set. Fault simulations at various clearing time is employed
to analyze for the critical clearing time. From the result obtained in the simulations for case study, the specific or the
exact fault clearing time for the system and the influence of fault clearing time is described.
Keywords: Multi machine, Transient stability, pre fault, during fault, post fault, Matlab/Simulink, Fault clearing
time (FCT), per unit value, Admittance parameter, Power angle, post fault admittance, Critical fault clearing time.
I. INTRODUCTION
Multi machine equations can be written similar to the one machine system connected to the infinite bus. In order
to reduce the complexity of the transient stability analysis, similar simplifying assumptions are made as follows.
A. Each synchronous machine is represented by a constant voltage source behind the direct axis transient
reactance. This representation Neglects the effect of saliency and assumes Constant flux linkages.
B. The governor’s action is neglected and the input powers are assumed to remain constant during the entire
period of simulation. -Using the prefault bus voltages.
The stability of power systems has been and continues to be of major concern in system
operation. Modern electrical power systems have grown to a large complexity due to
increasing interconnections, installation of large generating units and extra-high voltage tielines etc. Transient
stability is the ability of the power system to maintain synchronism when subjected to a severe transient
disturbance, such as a fault on transmission facilities, sudden loss of generation, or loss of a large load[1,2]. The
system response to such disturbances involves large excursions of generator rotor angles, power flows, bus
voltages, and other system variables. It is important that, while steady-state stability is a function only of
operating conditions, transient stability is a function of both the operating conditions and the disturbance(s).
This complicates the analysis of transient stability considerably. Repeated analysis is required for different
ISSN: 2349-7300
ISO 9001:2008 Certified
International Journal of Innovative Research in Engineering & Multidisciplinary Physical Sciences
(IJIRMPS)
Volume 3, Issue 3, October 2015
2
disturbances that are to be considered. In the transient stability studies, frequently considered disturbances are
the short circuits of different types. Out of these, normally the three-phase short circuit at the generator bus is
the most severe type, as it causes maximum acceleration of the connected machine.
Simulink is an interactive environment for modeling, analyzing, and simulating a wide variety of dynamic
systems. Simulink provides a graphical user interface for constructing block diagram models using ‘drag and
drop’ operations. A system is configured in terms of block diagram representation from a library of standard
components. A system in block diagram representation is built easily and the simulation results are displayed
quickly. Simulation algorithms and parameters can be changed in the middle of a simulation with intuitive
results, thus providing the user with a ready-access learning tool for simulating many of the operational
problems found in the real world. Simulink is particularly useful for studying the effects of non- linearity on the
behavior of the system, and as such, is also an ideal research tool. I have considered its parent software package
Simulink as a main tool in my present study.
Excitation systems, turbine and governor blocks from power system block set (PSB) can be readily used with
Simulink blocks as and when required. The user also has access to numerous design and analysis tools provided
in MATLAB and its toolboxes [3].
The classical model of a multi machine may be used to study the stability of a power system for a period of time
during which the system dynamic response is dependent largely on the kinetic energy in the rotating masses.
The classical three-machine six-bus system is the simplest model used in studies of power system dynamics and
requires of minimum amounts of data. Hence such studies can be connected in a relatively short time under
minimum cost. Among various method of load flow calculation Newton Raphson method by usin Matlab
programming is chosen for computing of load flow study.
II. METHODOLOGY USED
In the case study in Fig 1, The study related to with the three- machine, six-bus system and The system data are
given in table 1&2. The system has been simulated with a classical model for the generators. The disturbance
initiating the transient is a three-phase fault being most severe case, the study proposes the classical model of
simulation ,fault being near to bus 6 at the end of line 4– 6.The fault is cleared by opening CBs in line 4–6 . If
The system, being small , is large enough to be nontrivial and thus permits and enhances the illustration of a
number of stability concepts and results with clear technical approach.
Fig 1; one line diagram of a three machine 6 bus power system
ISSN: 2349-7300
ISO 9001:2008 Certified
International Journal of Innovative Research in Engineering & Multidisciplinary Physical Sciences
(IJIRMPS)
Volume 3, Issue 3, October 2015
3
Note; all values are given in Per unit
A . System modeling
The complete system has been represented in terms of Simulink blocks in a single integral model. It is self-
eplanatory with the mathematical model given below. One of the most important features of a model in
Simulink is its tremendous interactive capacity. It makes the display of a signal at any point readily available; all
one has to do is to add a Scope block or, alternatively, an output port. Giving a feedback signal is also as easy as
drawing a line. A parameter within any block can be controlled from a MATLAB command line or through an
m-file program. This is particularly useful for a transient stability study as the power system configurations
differ before, during and after fault. Loading conditions and control measures can also be implemented
accordingly.
From the given data in order to analyze the bus voltage across each bus, the power flow across the line and line
loss, formulation of Y bus matrix is the second step next to identification of the bus types. As it is indicated that
in the above figure 1, we have six buses
One Slack bus ( bus 1)
Two PV buses ( bus 2 &3)
Three load buses (bus 4,5 & 6)
After knowing the bus types it is possible to compute y bus matrixes.
B. Mathematical modeling
It is customary to have the following assumptions during our analysis for the Studies and the analysis made in
transient stability studies viz [1 - 4]:
1. The mechanical power input to each machine remains constant during the entire period of the swing curve
computation.
2. Damping power is negligible.
ISSN: 2349-7300
ISO 9001:2008 Certified
International Journal of Innovative Research in Engineering & Multidisciplinary Physical Sciences
(IJIRMPS)
Volume 3, Issue 3, October 2015
4
3. Each machine may be represented by a constant transient reactance in series with a constant transient internal
voltage.
4. The mechanical rotor angle of each machine coincides with the electrical phase angle of the transient internal
voltage.
5. All loads may be considered as shunt impedances to ground with values determined by conditions prevailing
immediately prior to the transient conditions. The system stability model based on the above assumptions is
called the classical stability model, which is used to study system disturbances originating from three-phase
faults, and studies which use this model are called classical stability studies. The system conditions before the
fault occurs, and the network configuration both during and after its occurrence, must be known in any transient
stability study. Consequently, in the multi-machine case ,two preliminary steps are required viz:
1. The steady-state pre-fault conditions for the system are calculated using a power-flow program.
2. The pre-fault network representation is determined and then modified to account for the fault and for the post-
fault conditions. From the first preliminary step I , I propose to calculate the values of power, reactive power,
and voltage at each generator terminal and load bus with all angles measured with respect to the slack bus. The
transient internal voltage of each generator is
Where; Vt is the corresponding terminal voltage and I is the output current.
Each load is converted into a constant admittance to ground at its bus using the equation
Where, PL + jQL is the load and VL is the magnitude of the corresponding bus voltage. The bus admittance
matrix which is used for the pre-fault power-flow calculation is now augmented to include the transient
reactance of each generators and the shunt admittance of each load. In the second preliminary step the bus
admittance matrix is modified to correspond to the faulted and post fault conditions.
Once the Y matrix for each network condition (pre-fault, during and after fault) is calculated, we can eliminate
all the nodes except for the internal generator nodes and obtain the Y matrix for the reduced network. The
reduction can be achieved by matrix operation with the fact in mind that all the nodes have zero injection
currents except for the internal generator nodes. In a power system with n generators, the nodal equation can be
written as[1,5].
Where the subscript n is used to denote generator nodes and the subscript r is used for the remaining nodes.
Expanding eqn. (3),
From which we eliminate Vr to find
Thus the desired reduced matrix can be written as follows:
It has dimensions (n x n) where n is the number of generators. Note that the network reduction illustrated by
eqns. (3)–(5) is a convenient analytical technique that can be used only when the loads are treated as constant
impedances. For the power system under study, the reduced matrices are calculated. The resultant matrices for
the pre fault, Instant of the fault and Post fault are given below.
ISSN: 2349-7300
ISO 9001:2008 Certified
International Journal of Innovative Research in Engineering & Multidisciplinary Physical Sciences
(IJIRMPS)
Volume 3, Issue 3, October 2015
5
The power into the network at node i, which is the electrical power output of machine i, is given by:
= negative of the transfer admittance between nodes i and j
= driving point admittance of node i
The equations of motion are then given by [7-,9]
And,
It should be noted that prior to the disturbance (t = 0) Pmi0 = Pei0; Thereby,
ISSN: 2349-7300
ISO 9001:2008 Certified
International Journal of Innovative Research in Engineering & Multidisciplinary Physical Sciences
(IJIRMPS)
Volume 3, Issue 3, October 2015
6
The subscript 0 is used to indicate the pre-transient conditions. As the network changes due to switching during
the fault, the corresponding values will be used in above equations.
C Simulink Models
Classical system model
The complete 3-generator system, given in Fig. 1, has been simulated as a single integral model in Simulink.
The mathematical model given above gives the transfer function of the different blocks. Fig. 2 shows the
complete block diagram of a classical system representation for transient stability study. The subsystems 1, 2
and 3 in Fig. 2 are meant to calculate the value of electrical power outputs for different generators; for example
Fig. 3 shows the computation of the power output of generator 1.
The model also facilitates the choice of simulation parameters, such as start and stop times, type of solver, step
sizes, tolerance and output options etc. The model can be run either directly or from the MATLAB command
line or from an m-file program. In the present study, the fault clearing time, the initial values of parameters as
well as the changes in network due to fault, are controlled through an m-file program in MATLAB.
Fig 2; complete classical model for transient stability analysis of three machines
ISSN: 2349-7300
ISO 9001:2008 Certified
International Journal of Innovative Research in Engineering & Multidisciplinary Physical Sciences
(IJIRMPS)
Volume 3, Issue 3, October 2015
7
Fig 3. Computation of electrical power output of generator # 1 by subsystem 1
Fig 4. Computation of electrical power output of generator # 2by subsystem 2
ISSN: 2349-7300
ISO 9001:2008 Certified
International Journal of Innovative Research in Engineering & Multidisciplinary Physical Sciences
(IJIRMPS)
Volume 3, Issue 3, October 2015
8
Fig 5. Computation of electrical power output of generator # 3by subsystem 3
III. SIMULATION RESULT AND DISCUSSION
In order to observe the transient behavior of a three–machine, six–bus power system after subjected to a three
phase bolted fault, Simulation studies are carried out under different values of fault clearing time (FCT). The
following cases are considered;
Case 1; fault cleared at 0.2 second.
In Figs 6(a), (b), (c) and (d):-The angular position of individual generators, the relative angular positions,
electrical power output of each generator and Accelerating power of each generator. This shows the rotor of the
machines becomes swing together. The accelerating power of each machine and their combined effect is going
to zero value. This implies that the system is stable and will come to some acceptable steady state value.
Fig 6(a); Angular position of individual generators for critical clearing time of 0.2 sec.
ISSN: 2349-7300
ISO 9001:2008 Certified
International Journal of Innovative Research in Engineering & Multidisciplinary Physical Sciences
(IJIRMPS)
Volume 3, Issue 3, October 2015
9
Fig 6(b); Relative angular position of δ21&δ31 of the machine with slack bus reference
Fig 6(c); plot of electrical power output of generator #1, 2&3 vs time
Fig 6 (d); plot of accelerating power of generator #1, 2 &3 vs time
Case 2; fault cleared at 0.41 second.
In Figs 7(a), (b) (c) and (d):- The system is unstable if the fault is cleared after 0.4 sec. from the critical fault
clearing time(0.4 sec.). The angular positions of the entire machines are increasing. This also shows that the
steady state operating power is greater than the maximum power output of the system during fault condition.
Therefore, the machines will be out of synchronism and the system is unstable during fault condition.
ISSN: 2349-7300
ISO 9001:2008 Certified
International Journal of Innovative Research in Engineering & Multidisciplinary Physical Sciences
(IJIRMPS)
Volume 3, Issue 3, October 2015
10
Fig7(a); Angular position of individual generators for clearing time of 0.41 sec
Fig 7(b) ; Relative angular position of δ21&δ31 of the machine with slack bus reference
Fig 7(c) ; plot of electrical power output of generator #1 , 2&3 vs time
Fig 7(d); plot of accelerating power of generator #1, 2&3 vs time.
IV. CONCLUSION
This paper presents the difference in response of the transient behavior of a three –machine ,six – bus power
system .For the case study, a three phase fault is placed on one of the transmission lines (near bus #6) at
different fault clearing time. A complete classical model for transient stability study of a multi-machine power
system was developed using Simulink. System responses are given for different values of fault clearing time
(FCT).
ISSN: 2349-7300
ISO 9001:2008 Certified
International Journal of Innovative Research in Engineering & Multidisciplinary Physical Sciences
(IJIRMPS)
Volume 3, Issue 3, October 2015
11
As it has been observed that the system response from the MATLAB model Simulink that, there is no stability
for clearing time of greater than 0.4seconds. Delaying the clearing time by few milli second make the system
out of synchronism or the system is not restored as before at steady state. Therefore It is proposed to have the
system fault clearing time to be 0.2 second. Accordingly the relay coordination setup is configured with this
fault clearing time.
REFERENCES [1] P. Kunder, ―Power system stability and control, EPRI Power system Engineering Series‖ (McGraw-Hill, New York,
1964).
[2] M. Anderson and A. A. Faud, Power System Control and Stability (Iowa State
University Press, Ames, IA, 1977).
[3] Simulink User’s Guide (The Math works, Natick, MA, 1999).
[4] Huynh ChauDuy, Transient stability analysis of a multi machine power system,HoChiMinh City University of
Technology, Vietnam, 2008.
[5] P. M. Anderson and A. A. Fouad, Power System Control and Stability (Iowa State University Press, USA,, IA, 1977).
[6] John J. Grainer, Willam D. Stevenson JR: Power System Analysis, McGraw-Hill International Editions, 1999.
AUTHORS PROFILE
Mr Tefera Mekonnen is the Head of the dept of School of Electrical and Computer engineering, Jimma University, JIT , Ethiopia, Having
vast experience in Electrical engineering teaching, Research, project guiding etc.,His main areas of research are Renewable energy, Power
systems, power Electronics,. Having good exposure to the simulation software applications, development and deployment as well power
system Stability studies. His main hobbies include Research, books, articles, writing, sports etc.
Dr Hadadi Sudheendra a senior member of IEEE having around 20 years of teaching and research experience .His main areas of Research
are Renewable energy, parallel processing, power systems, protection, stability analysis and spoof attack suppression by cryptography.. .
Mr. Getnet Zewde a senior Faculty member in the dept of ECE, JIT, Jimma Ethiopia, his main areas of interest are parallel computing,
power systems, having an experience of around 10 years in teaching and Research .