8/16/2019 IKL Project Bsline
1/2
ID Task Name Duration Start Finish
1 FABRICATION 7 UNITS of STORAGE TANK 54 days Tue 5/17/16 Sun 7/3/16
2 Project Award 1 day Tue 5/17/16 Tue 5/17/16
3 Kick of meeting 1 day Thu 5/19/16 Fri 5/20/16
4 Engineering 17 days Sat 5/21/16 Sun 6/5/16
5 Reference drawing for MTO 1 day Sat 5/21/16 Sat 5/21/16
6 AFC drawing 17 days Sat 5/21/16 Sun 6/5/16
7 Cutting plan 2 days Sun 5/22/16 Tue 5/24/16
8 Procurement 17 days Sat 5/21/16 Sun 6/5/16
9 Make MTO 2 days Sat 5/21/16 Mon 5/23/16
10 Make PR 1 day Sun 5/22/16 Mon 5/23/16
11 Issued P.O 2 days Mon 5/23/16 Tue 5/24/16
12 Receive Stainless steel materials 15 days Mon 5/23/16 Sun 6/5/16
13 Receive Carbon steel materials (structure materials) 7 days Mon 5/23/16 Sun 5/29/16
14 Receive Rolling & Forming parts 15 days Mon 5/23/16 Sun 6/5/16
15 Receive Equipment from IKL (free issued) 0 days Sun 5/29/16 Sun 5/29/16
16 FABRICATION 46 days Tue 5/24/16 Sun 7/3/16
17 Skids of 7 units Storage Tank 35 days Tue 5/24/16 Fri 6/24/16
18 Marking, Cutting & Grinding frame 4 days Tue 5/24/16 Fri 5/27/16
19 Marking & Cutting check by QC 4 days Wed 5/25/16 Sat 5/28/16
20 Fit-up Main Frame 7 days Wed 5/25/16 Tue 5/31/16
21 Fit-up check by QC 7 days Wed 5/25/16 Wed 6/1/16
22 Welding Main Frame 14 days Thu 5/26/16 Wed 6/8/16
23 Visual check, dimensional & NDE by QC 13 days Sat 5/28/16 Thu 6/9/16
24 Marking & Cutting 2nd frame & accessories 4 days Sat 5/28/16 Wed 6/1/16
25 Marking & Cutting check by QC 4 days Mon 5/30/16 Thu 6/2/16
26 Fit-up 2nd Frame & Accessories 7 days Wed 6/1/16 Tue 6/7/16
27 Fit-up check by QC 7 days Wed 6/1/16 Tue 6/7/16
28 Welding 2nd Frame & Accessories 15 days Thu 6/2/16 Thu 6/16/16
29 Visual check, dimensional & NDE by QC 15 days Fri 6/3/16 Fri 6/17/1630 Blasting & Painting SKIDS 7 days Sat 6/18/16 Fri 6/24/16
31 Spool of 7 units Storage Tanks 26 days Tue 5/24/16 Thu 6/16/16
32 Marking & Cutting Pipes 5 days Tue 5/24/16 Sat 5/28/16
33 Marking & Cutting check by QC 5 days Wed 5/25/16 Sun 5/29/16
34 Grinding Pipes & Flanges 5 days Tue 5/24/16 Sat 5/28/16
35 Fit-up Spool 10 days Wed 5/25/16 Fri 6/3/16
36 Fit-up check by QC 10 days Wed 5/25/16 Fri 6/3/16
37 Welding Spools 12 days Thu 5/26/16 Mon 6/6/16
38 Visual check & Dimensional by QC 12 days Fri 5/27/16 Tue 6/7/16
39 NDE Test 4 days Tue 6/7/16 Fri 6/10/16
40 Hydrotest Spool 2 days Fri 6/10/16 Sun 6/12/16
41 Pickling & Passivation Spools 5 days Sat 6/11/16 Thu 6/16/16
42 7 units Storage Tanks 45 days Tue 5/24/16 Sun 7/3/16
43 Marking & Cutting Pipes 3 days Tue 5/24/16 Thu 5/26/16
44 Fit-up Pipe to Flange (Nnozzles) 4 days Wed 5/25/16 Sat 5/28/16
45 Check Fit-up Nozzles by QC 3 days Wed 5/25/16 Sat 5/28/16
46 Welding Pipe to Flange (Nozzles) 7 days Thu 5/26/16 Wed 6/1/1647 Check welded Nozzles by QC 5 days Sat 5/28/16 Wed 6/1/16
48 Fit-up LS#1 (shell) & LS#2 (heads) 2 days Mon 6/6/16 Wed 6/8/16
49 Fit-up check by QC 1 day Tue 6/7/16 Wed 6/8/16
50 Welding LS#1 & LS#2 3 days Tue 6/7/16 Thu 6/9/16
51 Welding check by QC 3 days Wed 6/8/16 Fri 6/10/16
52 Fit-up & welding CS#1 4 days Thu 6/9/16 Sun 6/12/16
53 Visual check by QC 4 days Thu 6/9/16 Sun 6/12/16
4%
100%
100%
29%
100%
20%
69%
15%
100%
100%
44%
6%
13%
6%
5/29
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W Ty 15, '16
May 22, '16 May 29, '16 Jun 5, '16 Jun 12, '16 Jun 19, '16 Jun 26, '16 Jul 3, '16
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Baseline Split
Milestone
Summary Progress
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
PROGRESS REPORT
FABRICATION of 7 UNITS STORAGE TANK
Page 1
Project: IKL Project bslineDate: Tue 5/24/16
8/16/2019 IKL Project Bsline
2/2
ID Task Name Duration Start Finish
54 Marking & Cutting Holes for Nozzles on Tanks 3 days Fri 6/10/16 Mon 6/13/16
55 Check Marking & Cutting holes by QC 3 days Fri 6/10/16 Mon 6/13/16
56 Fitup Nozzles to Shell 5 days Fri 6/10/16 Wed 6/15/16
57 Fit-up checked by QC 5 days Fri 6/10/16 Wed 6/15/16
58 Welding Nozzles on Tanks 7 days Sun 6/12/16 Sat 6/18/16
59 Fit-up Legs & External structure to Tanks 4 days Thu 6/16/16 Sun 6/19/16
60 Fit-up Check Legs & External structure by QC 3 days Sat 6/18/16 Mon 6/20/16
61 Welding Legs & External Structure 5 days Sat 6/18/16 Thu 6/23/16
62 Final Visual & Dimensional by QC 3 days Thu 6/23/16 Sat 6/25/16
63 Hydrotest Spool 2 days Mon 6/27/16 Wed 6/29/16
64 Pickling & Passivation the Tanks 5 days Tue 6/28/16 Sun 7/3/16
65 Installation Equipment 3 days Fri 6/24/16 Sun 6/26/16
66 Installation/Assembly of Spools 3 days Sat 6/25/16 Mon 6/27/16
67 Installation & Hook up Instrument Cable (E&I) 3 days Sun 6/26/16 Tue 6/28/16
68 Touch up Painting 2 days Tue 6/28/16 Thu 6/30/16
69 Shipment 3 days Fri 7/1/16 Sun 7/3/16
70 Packing & Preservation the goods 2 days Fri 7/1/16 Sun 7/3/16
71 Load Out 1 day Sun 7/3/16 Sun 7/3/16
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W Ty 15, '16
May 22, '16 May 29, '16 Jun 5, '16 Jun 12, '16 Jun 19, '16 Jun 26, '16 Jul 3, '16
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Baseline Split
Milestone
Summary Progress
Summary
Project Summary
External Tasks
External Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
PROGRESS REPORT
FABRICATION of 7 UNITS STORAGE TANK
Page 2
Project: IKL Project bslineDate: Tue 5/24/16