ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status ILCTA-MDB Status 1.3 GHz RF Power 1.3 GHz RF Power Meson Detector Building Meson Detector Building 3.9 GHz RF Power 3.9 GHz RF Power A0 Building A0 Building September 21, 2006 September 21, 2006 [John Reid]

ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John

Embed Size (px)

Citation preview

Page 1: ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John

ILCTA-MDB RF Power Status 9/21/06 Reid 1

ILCTA-MDB Status ILCTA-MDB Status 1.3 GHz RF Power 1.3 GHz RF Power

Meson Detector BuildingMeson Detector Building

3.9 GHz RF Power 3.9 GHz RF Power A0 BuildingA0 Building

September 21, 2006 September 21, 2006

[John Reid]

Page 2: ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John

ILCTA-MDB RF Power Status 9/21/06 Reid 2

1.3 GHz RF Update1.3 GHz RF Update

Capture Cavity II Status• Cavity warmed up on 9-11-06 to perform

scheduled repairs to tuner motor and address low frequency modes.

• Cryomodule end plates will be removed by the middle of next week. 18HZ and 180 HZ modes will be addressed by adding

intercepts on bellows. Failed Sanyo tuner motor will be replaced with a

Fpytron motor. Additional instrumentation will be added while

cryomodule is open. Estimate ~ 2 months to complete.

Page 3: ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John

ILCTA-MDB RF Power Status 9/21/06 Reid 3

1.3 GHz RF Update1.3 GHz RF Update

300 Kwatt Klystron Status

• On 4-1-06 installed one of two rebuilt YK-1240 klystrons to replace original power limited (~100 Kwatt) klystron. Conditioning took about 2 weeks to achieve full power

(300Kwatts @ 60Kv gun voltage) at 1.5 msec rf pulse. Ran without problems powering CC-II since installed. Only reason to remove it is to test the second rebuilt

YK-1240.

• The second rebuilt (YK-1240) tube will be installed next week. Conditioning will start 9-25-06. Dummy 50 ohm load has been installed on waveguide. If all goes as well, conditioning will take about 2 week.

Page 4: ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John

ILCTA-MDB RF Power Status 9/21/06 Reid 4

80 Kwatt Klystron80 Kwatt Klystron

Page 5: ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John

ILCTA-MDB RF Power Status 9/21/06 Reid 5

Work in ProgressWork in Progress

• 3.9 GHz 80 Kwatt Klystron Components assembled into relay rack.

• Water manifolds fabricated and installed in rack.• Filament transformer installed.• Solenoid power supply installed in rack.• Ready for installation at A0.

• 3.9 GHz waveguide components All components in house.

• Circulator installed at A0• Some WR-284 installed• Awaiting arrival of coupler test stand to finish

waveguide connections.

Page 6: ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John

ILCTA-MDB RF Power Status 9/21/06 Reid 6

ModulatorModulator

Page 7: ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John

ILCTA-MDB RF Power Status 9/21/06 Reid 7

Modulator – HV CompartmentModulator – HV Compartment

Page 8: ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John

ILCTA-MDB RF Power Status 9/21/06 Reid 8

70 KV Charging Supply70 KV Charging Supply

Page 9: ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John

ILCTA-MDB RF Power Status 9/21/06 Reid 9

Work in ProgressWork in Progress

• 60 KV modulators. Fabrication complete. Undergoing final electrical testing at MI-60. One will ship to A0 on 9-22-06

• 70 KV charging Supply. Fabrication complete. Undergoing final electrical testing at MI-60. Ship to A0 on 9-22-06.