NORTHERN PROVINCE GICUMBI DISTRICT
IMIHIGO 2013-2014
IMIHIGO YADINDIYE IKENEYE UBUVUGIZI
15/01/2014
TOTAL IMIHIGO: 66
ECONOMIC PILLAR: 34 (=51,5%)
SOCIAL PILLAR: 17 (=25,7%)
GOOD GOVERNANCE & JUSTICE PILLAR: 15 (=22,7%)
SUMMARY
No ANNUAL TARGET PLANNED 1st SEM.
ACHIEVED 1 st SEM.
ADVOCACY
7.c)Gicumbi central town
space greened and
beautified (greening,
beautification, paved
paths, water shoot, …)
Tender for the
feasibility study &
Tender for works
execution
Tender process
for feasibility
study : draft
feasibility study
Gicumbi
District
7.d)2 Commercial buildings
constructed at 30% and
1 apartment building
constructed at 30%
Land acquisition
procedures, MoU
between District &
Stakeholders,
delivering
construction
permits, 3
buildings at 5%
MoU signed, Land
acquisition
procedures
finished,
construction
works started
(sites installation)
Gicumbi
District&
Northern
Province
7.e)New Gicumbi car taxi
park constructed at
50% (asphalt, offices)
Land acquisition
procedures
finished, MoU,
construction works
at 10%
Land acquisition
procedures
finished, MoU
signed
Gicumbi
District&
Northern
Province
.
No ANNUAL TARGET PLANNED
1st SEM.
ACHIEVED
1st SEM.
ADVOCACY
7.i) 2 bridges of Cyandaro and
Nyankokoma constructed
Tender
Process, &
Site
installation
Tender process
started but now
suspended
NB: Not
avaluable/ to be
removed
MINALOC
family
7.j) a) 2230 new people accessing to
clean water (to achieve 71.1 %)
AEPs of Ryaruganzu & Miliku II
water constructed and b) clean
water volume increased in
Gicumbi town ( 2500 m3/day)
Fund
mobilization&
Feasibility
study
Feasibility study
finished, Tender
for construction
material at
provisional
notification level,
funds obtained
Gicumbi
District&
Northern
Province
7.k 3500 new households accessed to
electricity in Gicumbi District (to
achieve 14.6%). (Construction of
Rukomo- Rutare- Bukure-
Rwesero- Gaseke new electrical
line)
500 HH
connected to
electricity
345 new HH have
access to
electricity
Prime
Minister
Office
No ANNUAL TARGET PLANNED
1st SEM.
ACHIEVED
1st SEM.
ADVOCACY
7.l) Construction of a
micro hydro power
plant on Kavumu river
at 35%
Feasibility
study, design,
Expropriation
and site
installation
Feasibility study
produced, design
done,
expropriation
finished, roads
terracing
Gicumbi
District&
Northern
Province
II. SOCIAL DEVELOPMENT PILLAR
No ANNUAL TARGET PLANNED 1st SEM.
ACHIEVED 1st SEM.
ADVOCACY
EDUCATION
19 2 existing VTCs upgraded
(Kibali and Rushaki) and 1
TSS equipped
(APEGIRUBUKI)
Tender process, 2
VTCs upgrading
works at 10%
Fields visits
done by WDA
Prime
Minister
Office
HEALTH
23 100% of Gicumbi
population covered by
health insurance
80% of population
with Health
insurance
71.9% of
population
have health
insurance
Gicumbi
District&
Northern
Province
No ANNUAL TARGET PLANNED
1st SEM.
ACHIEVED
1st SEM.
ADVOCACY
25.a) Constructing Mukarange
health center at 60%
Tender process, &
Construction works at
10%
Feasibility study:
draft report
available
Gicumbi
District
25.b) Byumba Hospital
extended at 15% and
Rutare Health Center
upgraded at 30%
Tender process,
Byumba Hospital
extension works at
5% and Rutare health
center upgrading
works at 5% also
Tender process
on going:
Notification
provisoire (Cfr
MoH)
Gicumbi
District&
Northern
Province
26b) 64,771,658 RwF of
financial services loans
(of other years than
2012-2013) recovered
(to achieve 85%)
Recovering 24,000,000
Frw of loans,
15.001.405 RwF
recovered
Gicumbi
District
III. GOOD GOVERNANCE AND JUSTICE
No ANNUAL TARGET PLANNED
1st SEM.
ACHIEVED
1st SEM.
ADVOCACY
29b) One TV installed
at each Cell office
(109 TV sets)
To identify and mobilize
the institutions where
to put the TVs Sets
Meetings in Sectors
organized for funds
mobilization
Gicumbi
District