Implementation & Migration Working
Group18th January 2006
Kevin Young
Interconnect & Numbering Services
The information in this presentation relates to plans currently under development and subject to consultation, and may be subject to change. Detailed implementation depends upon a number of factors including the capabilities of suppliers and the final 21CN network design.
NGS Capacity Check Request Process
CP Requires Change of Target NGS for 21CN DLE Migration
BT Assesses
And Agrees
Change of Target NGS
BT Internal Process To Implement
Change
NGS Capacity Check Process Completed
CP Decides To Use Original Target NGS
Original Target NGS Used
Alternative Target NGS
Used
CP Instigates SIA Contract Dispute
Procedure
No
No
Yes
A A
Yes
BT Accepts Check Request
For Assessment?
Yes
No
CP Submits NGS Capacity Check
Request
CP Escalates to BAU BT Disparity Resolution Team
NGS Capacity Check Request
Process Flowchart
NGS Capacity Check Request Process Milestones
• DSAN Issued
• NGS Capacity CR Forms submitted to BT by CPs cut-off
– DSAN Issue + 1 week
• NGS Capacity CR Assessment start
– DSAN Issue + 2 weeks (1 week allowed for iteration between BT and CP to ensure CR is accepted for assessment)
• NGS Capacity CR Assessment complete & CP notified of result
– DSAN Issue + 4 weeks
• NGS Capacity CR Assessment result accepted by CP or escalated to BT Disparity Resolution Team
– DSAN + 5 weeks
• NGS Capacity CR Assessment result escalation to BT Disparity Resolution Team considered and result communicated to CP
– DSAN + 6 weeks
NGS Capacity Check Request Process Milestones
• NGS Capacity Check Request Form:
Will be a Pro-Forma
Should be submitted separately for each DLE in the tranche covered by the DSAN where a change is required
Should contain description of change required
Should contain detailed reason for request and justification, including diagrammatic representation and ramifications of CR rejection
Should be submitted by the cut-off date for the tranche
Should contain BT assessment result, including reasons for rejection where appropriate
• NGS Capacity Check Requests:
Will be assessed as a batch for all CPs for a tranche
Will be assessed by the BT team responsible for managing NGS Capacity within the 21CN Programme.
• NGS Capacity Check is managed through the existing TAM/CP relationship