Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Research ArticleImplementation of Distributed Generation with Solar Plants in a132kV Grid Station at Layyah Using ETAP
Ghulam Mujtaba,1 Zeeshan Rashid ,1 Farhana Umer,1 Shadi Khan Baloch ,2
G. Amjad Hussain,3 and Muhammad Usman Haider4
1Department of Electrical Engineering, The Islamia University of Bahawalpur, 63100 Bahawalpur, Pakistan2Department of Mechatronics Engineering, Mehran University of Engineering and Technology, 76062 Jamshoro, Pakistan3Department of Electrical Engineering, College of Arts and Sciences, American University of Kuwait, Safat, Kuwait4Department of Electrical Engineering, Electrobuild Engineering Private Limited, 39350 Sheikhupura, Pakistan
Correspondence should be addressed to Zeeshan Rashid; [email protected]
Received 11 January 2020; Revised 16 May 2020; Accepted 6 June 2020; Published 25 June 2020
Academic Editor: Raúl Gregor
Copyright © 2020 Ghulam Mujtaba et al. This is an open access article distributed under the Creative Commons AttributionLicense, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work isproperly cited.
Decentralized power generation efficaciously merges technological advances in a rapidly changing face of power networksintroducing new power system components, advanced control, renewable sources, elegant communication, and web technologypaving the way for the so called smart grids. Distributed generation technology lies at the intersection point of power systems,power electronics, control engineering, renewable energy, and communication systems which are not mutually exclusivesubjects. Key features of renewable integration in a distribution network include loss minimization, voltage stability, powerquality improvement, and low-cost consumption resulting from abundant natural resources such as solar or wind energy. In thisresearch work, a case study has been carried out at a 132 kV grid station of Layyah, Pakistan, which has active losses, reactivelosses, low power factor, low voltage on the demand side, and overloaded transformers and distribution lines. As a result, poweroutage issue is frequent on the consumer side. To overcome this issue, a simulation of load flow of this system is performedusing the Newton-Raphson method due to its less computational time, fewer iterations, fast convergence, and independencefrom slack bus selection. It finds the harsh condition in which there were 23 overloaded transformers, 38 overloadeddistribution lines, poor voltage profile, and low power factor at the demand side. There is a deficit of 24MW in the wholesystem along with 4.58MW active and 12.30MVAR reactive power losses. To remove power deficiency, distributed generationusing solar plants is introduced to an 11 kV distribution system with a total of 24 units with each unit having a capacity of1MW. Consequently, active and reactive power losses are reduced to 0.548MW and 0.834MVAR, respectively. Furthermore,the voltage profile improves, the power factor enhances, and the line losses reduce to a great extent. Finally, overloadedtransformers and distribution lines also return to normal working conditions.
1. Introduction
The global emerging trend of deregulated electricity markethas underpinned a remarkable stride in the paradigm ofdistributed or dispersed generation (DG) by the use ofsmall photovoltaic or wind plants to cope with the inevita-ble shortcomings such as power outage, poor quality, volt-age regulation, and increased component losses incommercial and domestic infrastructure [1, 2]. These smallpower plants installed at subsequent stations not only pro-
vide better services to the consumers as backup sourcesbut also eliminate pollution, greenhouse gas emission, andglobal warming [3]. DG ranging from a few kW to MW isnow part of distributed energy resources which includesresponsive loads and energy storage [4]. It also reduces theneed for the distribution and transmission expansion withthe essential requirements of huge power plants [5]. Themost attractive prospect lies in the fact that DG is installedaround the network that is close to the consumer’s side tominimize power losses and voltage drops [6].
HindawiInternational Journal of PhotoenergyVolume 2020, Article ID 6574659, 14 pageshttps://doi.org/10.1155/2020/6574659
https://orcid.org/0000-0002-5592-4126https://orcid.org/0000-0002-7318-4715https://creativecommons.org/licenses/by/4.0/https://creativecommons.org/licenses/by/4.0/https://doi.org/10.1155/2020/6574659
The implementation of DG by renewable energyresources is advantageous in rural areas specifically to stabi-lize the power grid and ensure reliability at reduced cost ofgeneration and distribution [7, 8]. In order to exploit the fullpotential of DG, versatile and competent work force isrequired to cope with the broad spectrum of technical chal-lenges. Few of the associated issues hindering the robustoperation are the requirements of decentralized control [9],optimal placement of plants [3, 10], fault location [11], distri-bution system protection [12], reconfiguration [13], andintegration [14].
The last decade has been dedicated to the implementa-tion of the DG framework to furnish its overwhelmingfeatures to the power system community such as voltagestability and loss minimization [15]. Injeti and Kumaranalytically determined the placement and sizing of DGfor planning and operation of active distribution networksusing fuzzy logic [16]. They carried out a detailed perfor-mance analysis on 12-bus, 33-bus, and 69-bus radial distri-bution networks to conclude an enhanced voltage stabilityfactor at minimum losses. Mehta et al. proposed a selec-tion scheme of the best type of DG unit and its optimallocation by analyzing the voltage sensitivity index andbus participation factors using a power flow algorithmand modal analysis technique [17]. With these protocols,they were able to enhance the voltage stability of the distribu-tion network with simultaneous improvement in the voltageprofile for the 33- and 136-node radial distribution network.Onlam et al. proposed a novel optimization technique calledthe adaptive shuffled frog-leaping algorithm to solve the net-work reconfiguration and DG placement problems in IEEE33- and 69-bus distribution systems [18]. They definedspecific objective functions taking into account power lossminimization and voltage stability index improvement(VSI) and concluded that the power loss and VSI providedby this algorithm were better than all other protocols inboth 33- and 69-bus systems. Rudresha et al. presented amethod to determine the proper size and location of DGin a distribution system to reduce the losses and improvethe voltage stability for different loading conditions [19].They considered the IEEE 33-bus system to simulate thevoltage profile and losses in the system and concluded thatproper placement and sizing of DG potentially reduce thelosses, improve the voltage profile, and thereby improvethe voltage stability.
This paper deals with a comprehensive investigation of a132 kV grid station in Layyah, a backward city surrounded bydeserts in the southern part of Punjab Province in Pakistan.Due to the growing population, inevitable electricity needs,and negligence from the country’s policy makers, the powerinfrastructure in Layyah is facing adverse stress to providereliable, continuous, and quality services to the consumers.On the brighter side, the considered district holds the mostfavourable climatic conditions because sun shines for longerduration and there are extremely low chances of cloudy orrainy weather throughout the year implying maximumpotential for solar energy. In the first part of the research,the whole grid station of Layyah including three zones con-sisting of 24 distribution transformers each is simulated on
an Electrical Transient Analysis Program (ETAP) power flowsolver using the Newton-Raphson algorithm. The Newton-Raphson method provides a fast load flow solution withoutcomputing the superior order of derivatives for solving thesmall-, medium-, and large-scale distribution system andgives efficient results for computational cost minimization[20, 21]. Moreover, the results from the Newton-Raphsonmethod are more reliable with a higher success rate ofconvergence as compared to those from the other powerflow algorithms [22]. In this regard, the ETAP softwareis excellent for system planning and it has a positive effecton the test feeder so it can be employed for optimum sizeand location of DG in the substation [23]. Simulationresults performed on this platform reliably predict thesuperiority and effectiveness of the proposed methods[24]. The network layout, component ratings, and all oper-ating values considered in the simulation are based on theactual data of the region [25].
As a result of the computation, certain overloadedtransformers and distribution lines of the existing networkare identified causing load shedding, voltage deterioration,enhanced losses, and low power factor. In the second partof the research, the simulated power network of Layyah isupgraded to a DG network by the installation of distrib-uted solar power plants of 1MW each at subsequent inter-vals along the 11 kV bus in all the zones of the gridstation. Moreover, the underrated transformers and distribu-tion lines are replaced with new higher rated components tocircumvent overloading and failure issues. As suggested bythe results, all components of the network operate under nor-mal loading conditions, and the voltage profile and powerfactor at each load side improved substantially with a consid-erable reduction in the losses across each transformer anddistribution line.
Figure 1 shows a single-line diagram of a 132 kV gridstation of Layyah in which three isolators (81-1, 82-1,and 83-1) at three legs leading to zones A-C are connectedto the main 132 kV bus. There is one current transformerspecified by symbol “E” which has two available currenttransformation ratios of 100/5 A and 200/5 A. Subse-quently, each leg has an SF-6-type circuit breaker andlightening arrestor (LA) followed by a primary distributiontransformer (132/11.5 kV) of 20/26 MVA rating. There isone more current transformer with transformation ratiosof 1600/5 A and 800/5 A followed by a potential trans-former (11500/35V).
The grid of 132 kV shown in Figure 1 splits into threeprimary distribution networks which are categorized intothree zones: zone A, zone B, and zone C. The schematicdiagram of the individual zone of the distribution networkis shown in Figure 2. Each zone consists of further two11.5 kV branches with each branch having 12 transformersconnected to it for secondary distribution to the con-sumers. In this way, each zone is fulfilling demand to 24regions of consumers. The simulation results of the exist-ing system indicate that there are 23 transformers and38 distribution lines in total which are overloaded andare represented by red colors. The voltage profile is foundout to be around 300V which is much smaller than the
2 International Journal of Photoenergy
nominal value of 380V. The power factor across all the zonesis fluctuating around 0.7, and there are considerable lossesacross the transformers and distribution lines. In the newdesigned system, firstly, these transformers and distributionlines are replaced by highly rated components. In the secondstep, eight solar plants (Suntech, monocrystalline) of 1MWpower each are connected to the grid such that each branchis assisted with four units as shown in Figure 2. Each solarplant consists of 80 cells in series and 80 cells in parallel witheach cell having the rating of 180W. After solving the newsystem, it is established that the voltage level returns toaround 380V with a power factor of unity in the system.All losses in the system also reduce considerably.
This paper is organized as follows. Section 2 deals withcurrent and future trends of electricity needs, power genera-tion, annual demand factor, and power losses in the wholecountry. Section 3 discusses the Newton-Raphson powerflow algorithm. In Section 4, the implementations of theexisting system and new system are described in detail alongwith the discussion of results. Finally, conclusions are drawnin Section 5.
2. Current and Future Trends in Pakistan
In Pakistan, National Transmission & Despatch Company(NTDC) has designed a future load forecasting from 2017to 2040 in which installed capacity and peak demands arehighlighted at the end of each year. Although installedcapacity was more than the total demand of electricityeven in the past, the shortage of electricity is due to highlosses and plants not running at full capacity. In 2017,the installed capacity was 137328GWh, but the demandwas 25717MW. Future generation capacity and peakdemand are shown in Figure 3. In 2040, the total installedcapacity will reach 630529GWh and the peak demand willreach up to 110736MW [27]. Pakistan cannot fulfil itspeak demand because most of the generating power plantsare not running at rated capacity causing shortage ofpower in each state. The Quaid-e-Azam solar power planthas been installed in Bahawalpur, Pakistan, which has1000MW generation capacity but 400MW is in operationand 600MW is under progress. Some more projectsincluding hydro and renewable energy sources like solar,wind, biomass, and geothermal energy sources are underdiscussion for the expansion.
The demand factor of load varies from month to monthdepending on the daily activities of the population and theseason. In the month of February, it has a minimum valueof 0.58. The maximum demand is unity in the month of Junesince it is the hottest working month of the year before sum-mer vacations in institutes [27]. A month-wise graph of thedemand factor is shown in Figure 4.
In Pakistan, transmission and distribution losses varyfrom year to year which are plotted in Figure 5 from theactual data taken from NTDC [28]. The transmission anddistribution in Pakistan are not yet reliable which can beobserved from the data taken from the fiscal years 1981 to2018. In 1981, losses were 29.5% which were reduced to someextent after every year [28]. In 2017, the lowest losses of19.4% were recorded in the system which again surged to20% in 2018.
At the proposed site, power generation is less and powerconsumption is more due to which the system has increasedlosses, load fluctuations, and higher possibility of instrumentinterruption. A case study has been taken for solving theproblem of load shedding, active and reactive losses, andlow power factor and for improving the voltage profile. Thedata has been taken from the 132 kV grid station at Layyah,Pakistan. There is a problem of load shedding and a lowpower factor which has a minimum value of 0.69 and anaverage value of 0.84 in all the three zones. Minimum farend consumers’ voltage is 283V which is very less than the
81–1 82–1 83–1
Grid
132 kV
100,200/5 ALEH-81AEG (SF-6)
100,200/5 ALEH-82AEG (SF-6)
100,200/5 ALEH-83CHINA (SF-6)
E
E E E
E E
LA LA LA
LALALA
T-1 = 20/26 MVA132/11.5 kV(PEL)20/12/12
T-2 = 20/26 MVA132/11.5 kV(HEC)30/02/08
T-3 = 20/26 MVA132/11.5 kV(Elprom)01/02/18
1600,800/5 A 800, 1600/5 A 800, 1600/5 A
P.T P.T P.T11500/35 V 11500/35 V 11500/35 V
Incoming
11.5 kV 11.5 kV 11.5 kV
To zone A To zone B To zone C
IncomingIncoming
Figure 1: 132 kV grid station installed at Layyah, Pakistan [26].
Load 12Load 2Load 1
Load 13 Load 14 Load 24
11.5
kV
11.5
kV
11.5 kV/220 V
Sola
r cel
ls
Zones A, B, C
& co
nver
tor
Figure 2: DG in different zones with overloaded transformers anddistribution lines.
3International Journal of Photoenergy
transmitted value of 380V. There was also a deficit of 24MWpower compared to the total demand at the grid. There arethree zones in the 132 kV grid where each zone has an almost8MW energy deficit. So consumer energy demand cannot befulfilled, and daily 6- to 8-hour load shedding is a routine.
To solve this problem, two techniques are valuable: thefirst one is to inject a DG to the load side and the second isthat the grid station should be upgraded to 220 kV whichnecessitates higher upgradation cost. Here, DG injectioncan solve this issue with minimal cost and flexibility in thechoice of the installation venue. The ETAP software is usedto simulate the existing system and the new system. The oldsystem has more losses than the new system. Power deficitis also removed by injection of the solar system which has atotal of 24MW rated output in which each unit has 1MWgeneration capacity.
3. Power Flow Analysis
Power flow studies are of paramount importance for powersystem planning and upgradation and for determining thebest operation of existing systems. The power flow problemcan be solved by considering the admittance matrices of thenetwork incorporating all the buses and feeders using asingle-line diagram. All the buses are categorized as eithervoltage-controlled bus (or PV bus), load bus (or PQ bus)and slack bus (mostly bus 1). The Newton-Raphson methodbeing the most efficient method in all aspects is used for solv-ing power flow problems which also eliminates the need toexplicitly specify the slack bus. The Taylor series expansionup to two initial terms is the basis for solving a multivariablenonlinear equation in a polar form with equal number ofunknowns. The Newton-Raphson method is used for analy-sis of the 132 kV grid station at Layyah because of its conver-gence which is very fast and independent of size of buses, andlittle number of iterations is required for the solution of loadflow. The convergence process of the multivariable Newton-
204020352030Fiscal year
2025202020150
20
40
60
80
Peak
dem
and
(MW
) ×10
4
Pow
er g
ener
atio
n (G
Wh)
×10
4
100
0
20
40
60
80
100
Peak demand Power generation
Figure 3: Future load forecasting of the peak demand and installedcapacity.
0.5
July
Augu
stSe
ptem
ber
Oct
ober
Nov
embe
rD
ecem
ber
Janu
ary
Febr
uary
Mar
chAp
rilM
ayJu
ne
0.6
0.7
0.8
Dem
and
fact
or
0.9
1.0
Figure 4: Year-wise demand factor of load in Pakistan.
181980 1990 2000
Fiscal year2010 2020
20
22
24
26
Pow
er lo
sses
(%)
28
30
Figure 5: Power losses at transmission and distribution from 1981to 2018.
132 kV
Grid
Zone A
20 M
VA
20 M
VA
20 M
VA
Zone
A tr
ansfo
rmer
Zone
B tr
ansfo
rmer
Zone
C tr
ansfo
rmer
Zone B Zone C
Figure 6: Simulation diagram of a 132 kV grid connected to three20MVA transformers.
4 International Journal of Photoenergy
Raphson method is explained below.
Si = Pi + jQi =Vi 〠n
k=1Y∗ikV
∗k = 〠
n
k=1ViVkYike
j δi−δk−δikð Þ,
Pi = 〠n
k=1ViVkYik cos δi − δk − δikð Þ,
Qi = 〠n
k=1ViVkYik sin δi − δk − δikð Þ:
ð1Þ
Pi and Qi are the active and reactive powers, respectively.
f =Pi
Qi
" #,
x =δi
∣Vi∣
" #:
ð2Þ
When more variables are involved, f ′ is replaced by thepartial derivates of Pi and Qi with respect to the two entriesin column vector x. The resultant matrix f ′ shown in Equa-tion (3) is also called the Jacobian matrix.
f ′ =
∂Pi∂δi
∂Pi∂ ∣Vi ∣
∂Qi∂δi
∂Qi∂ ∣Vi ∣
26664
37775, ð3Þ
ΔPi
ΔQi
" #=
Pi schð Þ
Qi schð Þ
24
35 − Pi calð Þ
Qi calð Þ
24
35
= f ′Δδi
Δ∣Vi∣
" #,
ð4Þ
Δδi
Δ∣Vi∣
" #= f ′h i−1 ΔPi
ΔQi
" #: ð5Þ
The subscript cal denotes the calculated value and schrepresents the scheduled values. The iterative process stops
00
400
800
1200
1600
Tran
sform
er ra
ting
(kV
A) 2000
5 10 15 20Transformer #
250
5
10
15
20
25
Dist
ance
from
load
(km
)
(a)
00
400
800
1200
1600
Tran
sform
er ra
ting
(kV
A) 2000
5 10 15 20Transformer #
250
5
10
15
Dist
ance
from
load
(km
)
20
25
(b)
00
400
800
1200
1600Tr
ansfo
rmer
ratin
g (k
VA
) 2000
5 10 15 20Transformer #
250
5
10
15
Dist
ance
from
load
(km
)
20
25
(c)
Figure 7: Transformer ratings and route lengths in (a) zone A, (b) zone B, and (c) zone C.
Table 1: Specifications of the existing system.
Name of parameters Assumptions for parameter
System type Three-phase AC system
Type of distribution line Overhead line conductors
Type of load Constant load
Standard frequency 50Hz
Standard voltage 380V (L-L)
Type of conductorsAluminium conductorsteel reinforced (ASCR)
Voltage limits
Critical over voltage > 105%,critical under voltage < 95%,marginal over voltage > 102%,marginal under voltage < 97
Bus 1 Reference bus or slack bus
5International Journal of Photoenergy
when the mismatches become smaller than the specifiedtolerance ϵ, i.e.,
ΔPi
ΔQi
" #≤ ϵ: ð6Þ
It should be noted that the entries in the calculationprocess exclude the slack bus so there will be n − 1 busesfor which the computation will be carried out.
4. Results and Discussion
A case study of the 132 kV grid station at Layyah has beensimulated on ETAP. The grid station is divided into threezones, namely, zone A, zone B, and zone C. At the distribu-tion level, 72 distribution transformers are connected to theload. There are 24 transformers in each zone and a mainpower transformer connected to the grid having the ratingof 20MW. After simulating the system, it appears that afew transformers are overloaded which can be observed fromtheir highlighted red color in the simulation in Figure 6. Thethree main transformers of zone A, zone B, and zone C arealso overloaded. In addition, the loads are located at suffi-
ciently large distance from the transformers. As a result, thesystem has transmission line losses, low power factor, andpoor voltage regulation due to overloading which are themain issues in the grid. In particular, during the peak hours,the power demand is higher than the generation, so the over-all system is not healthy to fulfil power demands to the con-sumers. The ratings of all transformers along with theirdistance from the load side in the three zones are plotted inFigure 7.
4.1. Existing System Implementation on ETAP. In order toanalyze the power flow of the three zones, implementationof the grid is done on the ETAP software. The specificationsof the existing system are shown in Table 1, and the same areconsidered in the simulation settings.
A 132 kV grid is implemented on the ETAP softwarewhose layout is shown in Figures 6 and 8–10. When the pro-gram runs on ETAP, the following results are obtained. Thethree main transformers of individual zones having ratingsof 20MVA each are overloaded as shown in Figure 6 by theirred colors. Moreover, in zone A, 11 transformers are over-loaded which are connected to the sugar mill colony, theemployees’ colony, Noorabad, Chandiawala, the Q.H.scheme, the lawyers’ colony, Qadeerabad, Laskaniwala,
Zone A
L1
L27 L47
L28
L26
L25
11.5
kV
800
kVA
400
kVA
1200
kVA
300
kVA
1200
kVA
1600
kVA
750
kVA
800
kVA
950
kVA
300
kVA
600
kVA
431
kW
642
kW
665
kW
707
kW
972
kW
253
kW
842
kW
560
kW
628
kW
932
kW
278
kW
800
kW
L48
296
V
293
V
296
V
320
V
306
V
304
V
314
V
Din
pur
Tibb
i khu
rdN
ashe
eb
Qad
eera
bed
Koro
nas
heeb
312
V
321
V
317
V
297
V
321
V
Shah
pur
�al
Mau
j gar
h
Sirg
ani t
hal
Shan
iwal
a
Moc
hiw
ala
Kach
iBh
arsh
ah
Lask
aniw
ala
Karo
r tha
l
300
V
Law
yers
'co
lony
Q.H
. sch
eme
Chan
diaw
ala
Basti
shee
kJa
lu
Noo
raba
d
TDA
colo
ny
Man
di to
wn
Empl
oyee
s'co
lony
Hou
sing
colo
ny
Man
zoor
abad
Cana
lco
lony
Suga
r mill
colo
ny
305
V
305
V
311
V
325
V
326
V
302
V
309
V
310
V
310
V
315
V
320
V
456
kW
242
kW
728
kW
515
kW
498
kW
1012
kW
806
kW
838
kW
258
kW
L4L2 851
kW
319
kW
664
kW 130
0 kV
A
800
kVA
200
kVA
1200
kVA
1000
kVA
750
kVA
1000
kVA
300
kVA
1500
kVA
1000
kVA
800
kVA
750
kVA
500
kVA
L3 L23
L24
Load 1 Load 2 Load 3 Load 4 Load 5 Load 6 Load 7 Load 8 Load 9 Load 10 Load 11 Load 12
Load 13 Load 14 Load 15 Load 16 Load 17 Load 18 Load 19 Load 20 Load 21 Load 12 Load 23 Load 24
650 k
VA
330 k
VA
1030
kVA
800 k
VA
770 k
VA
1600
kVA
1300
kVA
1300
kVA
1200
kVA
400 k
VA
850 k
VA
300 k
VA
850 k
VA
200 k
VA
1200
kVA
1000
kVA
750 k
VA
1100
kVA
1000
kVA
880 k
VA
800 k
VA
550 k
VA
500 k
VA
500 k
VA
Figure 8: Implementation of zone A of the existing system on ETAP.
6 International Journal of Photoenergy
Sirgani Thal, Maujgarh, and Shahpur Thal. In zone A, 18 dis-tribution lines are overloaded which are L1, L9, L10, L15,L16, L20, L21, L22, L23, L24, L36, L41, L43, L44, L45, L46,L47, and L48. For the sake of saving space, numbers are onlymentioned for the first four and last two lines. The marginallyand fully overloaded transformers are shown in pink and redcolors, respectively, and the overloaded distribution lines areshown in red colors in Figure 8.
In zone B, eight transformers and twelve lines are over-loaded. The overloaded transformers are connected toLohachthal, Zard, Jhoralnashib, Jakharpacca, Kharal Azeem,Khokharwala, Rakh, and Shahwala. Lines which are over-loaded include L59, L83, L84, L86, L88, L90, L91, L92, L93,L94, L95, and L96.
Finally, in zone C, four transformers are overloaded.These transformers are connected to Saeed Nasheeb, Lad-hana, Jamanshah, and Awanwala. There are eight lines whichare overloaded. These distribution lines are L97, L109, L131,
L132, L133, L139, L140, and L142. As a result of overloading,there is an observed deficit of 24MW resulting into 6 to 8hours of load shedding every day.
4.2. New Design of the 132 kV Grid Station. At the distribu-tion side, solar cell modules are installed at uniform intervalsafter each third distribution line to overcome the problems ofpower shortage, voltage regulation, and low power factor.There is a deficit of 8MW in each zone, so eight solar panelsof 1MW rating each are installed in each zone. The solarpanel is installed at the distribution end or close to the userend to balance deficit and reduce line losses. The single-linediagram of the grid and all the three zones of the new systemare shown in Figures 11–14, respectively.
After the installation of distributed solar panels in eachzone, considerable power is extracted from the DG sets whichcauses less burden on each zonal transformer (20MVA).Hence, all three zonal transformers return to their normal
500
kVA
250
kVA
1000
kVA
1000
kVA
800
kVA
660
kVA
1400
kVA
750
kVA
800
kVA
1200
kVA
200
kVA
400
kVA
Load 25 Load 26 Load 27 Load 28 Load 29 Load 30 Load 31 Load 32 Load 33 Load 34 Load 35 Load 36
Load 37 Load 38 Load 39 Load 40 Load 41 Load 42 Load 43 Load 44 Load 45 Load 46 Load 47 Load 4844
0 kVA
200 k
VA
1200
kVA
800 k
VA
750 k
VA
1400
kVA
600 k
VA
800 k
VA
1000
kVA
1000
kVA
250 k
VA
500 k
VA73
1 kW
324
kW
1028
kW
376
kW
937
kW
1193
kW
1229
kW
614
kW
578
kW
838
kW
222
kW
465
kW
L71
11.5 kV
Zone B
L49
L73
L75 L95
L51L5
2
L72
750
kVA
545
kW32
0 V
323
V
316
V
320
V
332
V
328
V
335
V
340
V
326
V
336
V
342
V
330
VG
ochi
Gad
di
Bait
Was
saw
a
Balo
ch k
han
Chaj
ra
Jakh
arpa
cca
Jhor
alna
shib
Kha
nwal
a
Rakh
Shah
wal
a
Kho
khar
wal
a
Kha
ral a
zeem
L96
285
kW
822
kW
569
kW
1222
kW
302
kW
966
kW
671
kW
316
kW
1034
kW
L76
L74 36
0 kW
1360
kW 40
0 kV
A
1100
kVA
700
kVA
1600
kVA
350
kVA
1200
kVA
900
kVA
250
kVA
1300
kVA
350
kVA
1200
kVA
L50
299
V
283
V
318
V
321
V
321
V
323
V
Jhor
alth
al
340
V
320
V
347
V
333
V
319
V
335
V
Am
ircla
sra
Pana
hK
hara
l
Pirja
gi
Was
aya
Soha
nra
Sohi
atha
l
Shar
if A
raye
n
Dub
ali
Loha
chth
al
Weh
niw
alth
al
Karlo
Zard
800 k
VA
440 k
VA
1200
kVA
750 k
VA
1600
kVA
380 k
VA
1300
kVA
900 k
VA
250 k
VA
1300
kVA
350 k
VA
1200
kVA
Figure 9: Implementation of zone B of the existing system on ETAP.
7International Journal of Photoenergy
operating regimes despite having the same power rating asbefore. In addition, the overloaded transformers and distri-bution lines are replaced with higher rating componentsdue to which their overloading problems are also eliminated.These facts can be observed from Figures 12–14 for zone A,
zone B, and zone C, respectively. Finally, all the problemsof low power factor, voltage regulation, and power losses intransformers and transmission lines occurring in the systemare resolved. The comparison of results between the existingsystem and the new simulated system is done in the nextsection.
4.3. Zone A: Transformer, Distribution Lines, and LoadAnalysis. In zone A of the existing system, 11 transformersare overloaded. Due to the overloaded transformers, the sys-tem is unbalanced. To overcome this problem, new trans-formers of higher rating are connected to replace the oldones and avoid overheating of transformers. As a result, thesystem reliability is increased and transformer losses are alsoreduced. A comparison between old and new ratings isshown in Figure 15.
DG at the load side has reduced losses to a great extent. Ithas increased cost for replacing new transformers but ful-filled the demand of customers. Transformer losses reachup to 18 kW in the old case which remain below 6kW forthe DG-injected system. Losses across each transformer inthe old system and the new system are plotted inFigure 16(a).
Zone C
L123 L143Load 49
800 k
VA
400 k
VA
400 k
VA
1100
kVA
1200
kVA
1200
kVA
1000
kVA
800 k
VA
800 k
VA
1200
kVA
330 k
VA
550 k
VA
1700
kVA
500 k
VA
1000
kVA
700 k
VA
1300
kVA
800 k
VA
380 k
VA
1800
kVA
800 k
VA
1300
kVA
450 k
VA
650 k
VA
Load 50 Load 51 Load 52 Load 53 Load 54 Load 55 Load 56 Load 57 Load 58 Load 59 Load 60
Load 61 Load 62 Load 63 Load 64 Load 65 Load 66 Load 67 Load 68 Load 69 Load 70 Load 71 Load 72
L97
11.5
kV
1700
kVA
�al
kala
n
�al
jand
i
Baitd
ewan
Jam
rid
Jam
ansh
ah
Basti
nano
Sum
rans
hib
Shad
okha
n
Kapb
ali
Awan
wal
a
337
V
319
V
333
V
338
V
334
V
316
V
322
V
322
V
313
V
311
V
315
V
305
V
Jaisa
lnas
eeb
Mad
niTo
wn
500
kVA
1000
kVA
700
kVA
1300
kVA
800
kVA
350
kVA
1800
kVA
800
kVA
1300
kVA
450
kVA
600
kVA
L121
L122
L124 650
kW
1040
kW
359
kW
696
kW
911
kW
311
kW
1219
kW
568
kW
445
kW
258
kW
L144
852
kW
1463
kW
800
kVA
400
kVA
400
kVA
1100
kVA
1200
kVA
1200
kVA
1200
kVA
300
kVA
500
kVA
1000
kVA
800
kVA
800
kVA
L98
L100
Bairo
onKu
nal
333
V
330
V
340
V
340
V
324
V
321
V
307
V
316
V
313
V
Loha
ncht
hal
310
V
305
V
298
V
Saee
dN
ashe
eb
Ladh
ana
Loha
nchw
ala
Mirr
anip
acca
Nag
gilo
hanc
h
Said
otha
l
Kotla
qazi
Sam
tiath
al
Gut
thal
Kunn
alna
shib72
8 kW
351
kW
1107
kW
356
kW
948
kW
922
kW
1107
kW
581k
W
558
kW
800
kW
246
kW
L120
456
kW
L99 L119
Figure 10: Implementation of zone C of the existing system on ETAP.
132 kV
Grid
Zone A
20 M
VA
20 M
VA
20 M
VA
Zone
A tr
ansfo
rmer
Zone
B tr
ansfo
rmer
Zone
C tr
ansfo
rmer
Zone B Zone C
Figure 11: Simulation diagram of a 132 kV grid after DG injection.
8 International Journal of Photoenergy
Lines losses are also reduced when DG is injected to theload side by replacing lines with proper ratings. The existing17 distribution lines having the capacity of 267MW are over-loaded, and they are replaced with new lines with a rating of500MW. Line losses reach up to 110 kW in the existing sys-tem which remain below 11kW for the proposed system. Agraph is shown in Figure 16(b) which compares line lossesin the old and new systems.
The power factor of load is improved when DG isinjected at the load side. So the new power factor is slightlyless than unity which is a good sign for a robust power sys-tem. A high power factor also reduces the cost of equipmentbecause equipment cost under a low power factor is high dueto high current ratings. A high power factor reduces the cop-per losses because the phase component of the current isreduced. It has also decreased the losses and voltage regula-tion which were occurring due to the low power factor. Thegraph of power factors and voltage profiles at the load sidefor zone A is shown in Figures 17(a) and 17(b).
The power factor for specific loads is better (>0.9) in theexisting system; however, it stays below 0.85 for most of theconnected loads. In the simulated system, the power factorhas improved drastically to around unity. Voltage, on theother hand, has sufficiently small values at the load sidewhich vary mostly between 300V and 320V. The desiredvalue of voltage is 380V (3 −Φ line-to-line voltage) whichis successfully achieved by photovoltaic installation.
4.4. Zone B: Transformer, Distribution Lines, and LoadAnalysis. Zone B consists of 24 transformers, 24 loads, and48 lines. In the existing system, 4 transformers are overloadedrequiring new transformers of better ratings to be installed. Acomparison between old and new ratings is shown inFigure 18.
After replacing old transformers with those of better rat-ings, losses are reduced considerably as in the previous case.Transformer losses which were reaching 38 kW are nowreduced to smaller values with maximum approaching
Zone C
1000
kVA
500 k
VA
1500
kVA
500 k
VA
1500
kVA
1500
kVA
2000
kVA
1000
kVA
1000
kVA
1500
kVA
500 k
VA
1000
kVA
1500
kVA
500 k
VA
1500
kVA
1000
kVA
1000
kVA
1500
kVA
500 k
VA
2000
kVA
1000
kVA
1500
kVA
1500
kVA
1000
kVA
Load 1 Load 2 Load 3 Load 4 Load 5 Load 6 Load 7 Load 8 Load 9 Load 10 Load 11 Load 12
Load 13 Load 14 Load 15 Load 16 Load 17 Load 18 Load 19 Load 20 Load 21 Load 22 Load 23 Load 24
11.5 kVSu
gar m
illco
lony
Cana
l col
ony
Man
zoor
abad
Hou
sing
colo
ny
Empl
oyee
s'co
lony
378
V37
8 V
378
V
377
V
377
V
377
V
375
V
375
V
374
V
374
V
374
V96
8 kW
1453
kW
1454
kW
971
kW
1948
kW
488
kW
1473
kW
977
kW
982
kW
1483
kW
493
kW
1492
kW1
500
kVA
1500
kVA
1000
kVA
1000
kVA
1500
kVA
500
kVA
2000
kVA
1000
kVA
1500
kVA
1500
kVA
1000
kVA
Shah
pur �
al
Mau
jgar
h
Sirg
ani �
al
Karo
r �al
Shan
iwal
a
Moc
hiw
ala
Lask
aniw
ala
Kach
iBa
hars
hah
Din
pur
Koro
Nas
heeb
Tibb
i Khu
rdN
ashe
eb
Qad
eera
bad
500
kVA
376
V
379
V
378
V
379
V
375
V
377
V
377
V
375
V
375
V
376
V
376
V
376
V
375
V
Man
di T
own
TDA
colo
ny
Noo
raba
d
Basti
She
ekJa
lu
Chan
diaw
ala
Q.H
. sch
eme
Law
yers
'co
lony
987
kW
494
kW
1488
kW
485
kW
1469
kW
1471
kW
1949
kW
977
kW
976
kW
1457
kW
488
kW
973
kW100
0 kV
A
500
kVA
1500
kVA
500
kVA
1500
kVA
1500
kVA
2000
kVA
1000
kVA
1000
kVA
1500
kVA
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
500
kVA
1000
kVA
Figure 12: Implementation of zone A of the new system on ETAP.
9International Journal of Photoenergy
11 kW. Old transformer losses and new transformer lossesfor zone B are plotted in Figure 19(a).
Line losses are also reduced after the installation of DGand by replacing distribution lines of proper ratings. Sevendistribution lines (267 A) are overloaded and are replacedwith 500 A lines. Consequently, line losses reduce and staybelow 12kW which were approaching 120 kW in the existingsystem. A graph is shown in Figure 19(a) that compares oldsystem line losses and new system line losses.
The power factor of load is improved when DG isinjected at the load side. So the new power factor is close tounity as in the previous case. It also reduces the losses andimproves voltage regulation. The power factor in the old sys-
tem fluctuates and reaches up to a minimum of 0.73 which isimproved to around unity with DG injection. The voltagealso stays below 350V; however, it stays higher than 375Vfor the new system. The graphs of the power factor and volt-age profiles are shown in Figures 20(a) and 20(b),respectively.
4.5. Zone C: Transformer, Distribution Lines, and LoadAnalysis. Zone C consists of 24 transformers, 24 loads, and48 lines. In the existing system, 8 transformers are over-loaded. To overcome this problem, new transformers areconnected to the load. A comparison between old and newratings for zone C is shown in Figure 21.
Load 25 Load 26 Load 27 Load 28 Load 29 Load 30 Load 31
11.5 kV
11.5 kV
Zone B
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
Load 32 Load 33 Load 34 Load 35 Load 36
Load 37 Load 38 Load 39 Load 40 Load 41 Load 42 Load 43 Load 44 Load 45 Load 46 Load 47 Load 48
2000
kVA
500 k
VA
2000
kVA
1000
kVA
500 k
VA
1500
kVA
1000
kVA
1500
kVA
1500
kVA
1000
kVA
500 k
VA
500 k
VA
1000
kVA
500 k
VA
1000
kVA
1000
kVA
1500
kVA
1500
kVA
1500
kVA
1500
kVA
1500
kVA
1000
kVA
1500
kVA
1000
kVA
379
V37
6 V
376
V
377
V
377
V
377
V
376
V
377
V
375
V
375
V
375
V
377
V
374
V
378
V
378
V
378
V
377
V
377
V
377
V
374
V
376
V
375
V
375
V
375
V
2000
kVA
500
kVA
1500
kVA
1000
kVA
1500
kVA
500
kVA
500
kVA
1500
kVA
1000
kVA
1000
kVA
2000
kVA
500
kVA
1000
kVA
500
kVA
1500
kVA
1500
kVA
1500
kVA
1500
kVA
1500
kVA
1500
kVA
1000
kVA
1000
kVA
1000
kVA
1000
kVA
1985
kW
494
kW
494
kW
981
kW
1473
kW
490
kW
1924
kW
972
kW
1458
kW
488
kW
975
kW
1480
kW
981
kW
490
kW
1472
kW
930
kW
1473
kW
1468
kW
1473
kW
973
kW
972
kW
1473
kW
1480
kW
967
kW
Gad
di
Balo
ch K
han
Bait
Was
awa
Kha
nwal
a
jhor
alna
shib
Jakh
arpa
cca
Chaj
ra
Kha
ral A
zeem
Kho
khar
wal
a
Rakh
Shah
wal
a
Goc
hiA
mir
Clas
ra
Pana
h kh
aral
Pirja
gi
Shar
if A
raye
n
Soha
nra
Was
aya
Sohi
atha
l
Jhor
alth
al
Weh
niw
alth
al
Loha
chth
al
Dub
ali
Karlo
Zard
Figure 13: Implementation of zone B of the new system on ETAP.
10 International Journal of Photoenergy
When transformers of proper ratings are used, lossesreduce to a great extent. In the old system, transformer losseswere reaching 30 kW and they reach up to 6.5 kW for the newsystem. The graph of transformer losses is shown inFigure 22(a).
Line losses are reduced when DG is injected and byreplacing lines of proper ratings. Twelve distribution linesare overloaded and are replaced with 500MW lines in thesystem. In zone C too, line losses are approaching 120 kWwhich reduces to around 6 kW for the new system. A graphis shown in Figure 22(b) showing the line losses in the exist-ing and updated systems. The power factor of the load isimproved when DG is injected at the load side. Again forzone C, the new power factor is nearly unity. For the existingsystem, the power factor reduced to as low as 0.68 whichimproved after the DG injection. The graph between oldand new power factors is shown in Figure 23(a).
The voltage profile is also improved as a result of DGinjection. For the old system, the voltage level varied between
11.5
kV
Zone C
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
1 M
W
Load 49 Load 50 Load 51 Load 52 Load 53 Load 54 Load 55 Load 56 Load 57 Load 58 Load 59 Load 60
Load 61
2000
kVA
2000
kVA
500 k
VA
2000
kVA
1000
kVA
500 k
VA
1500
kVA
1500
kVA
1500
kVA
1500
kVA
1000
kVA
500 k
VA
1000
kVA
1000
kVA
500 k
VA
1000
kVA
1000
kVA
2000
kVA
1500
kVA
1500
kVA
1500
kVA
1500
kVA
1000
kVA
500 k
VA
500 k
VA
500
kVA
1985
kW
495
kW
1484
kW
975
kW
1470
kW
1474
kW
490
kW
1952
kW
971
kW
1456
kW
489
kW
970
kW
379
V
378
V37
9 V
378
V37
9 V
378
V
377
V
377
V
377
V
377
V
376
V
376
V
375
V
375
V
375
V
376
V
374
V
377
V
377
V
376
V
376
V
375
V
375
V
375
V
1500
kVA
1500
kVA
1500
kVA
500
kVA
500
kVA
1500
kVA
1000
kVA
1000
kVA
2000
kVA
1000
kVA
1000
kVA
500
kVA
1500
kVA
1500
kVA
1500
kVA
2000
kVA
500
kVA
1500
kVA
1000
kVA
1000
kVA
1000
kVA
500
kVA
Load 62 Load 63 Load 64 Load 65 Load 66 Load 67 Load 68 Load 69 Load 70 Load 71 Load 72
968
kW
488
kW
1459
kW
970
kW
971
kW
1951
kW
1468
kW
1471
kW
470
kW
492
kW
993
kW
1476
kW
�al
kala
n
Bairo
onku
nal
Gut
thal
Kunn
alna
shib
Loha
nchw
ala
Mirr
anip
acca
Nag
gilo
hanc
h
Said
otha
l
Kotla
qazi
Sam
tiath
al
Loha
ncht
hal
Saee
dN
ashe
eb
Ladh
ana
Mad
ni T
own
�al
jand
i
Baitd
ewan
Jam
rid
Jaisa
lnas
eeb
Jam
ansh
ah
Basti
nano
Sum
rana
shib
Shad
okha
n
Kapb
li
Awan
wal
a
Figure 14: Implementation of zone C of the new system on ETAP.
00
500
1000
1500
Tran
sform
er ra
ting
(kVA
)
2000
2500
5 10 15Total no. of transformers
20 25
Actual ratingNew rating
Figure 15: Actual and new rating of transformers in zone A.
11International Journal of Photoenergy
300V and 340V which improved substantially to around378V after photovoltaic injection. Old and new voltage levelsare shown in Figure 23(b).
5. Conclusion
Pakistan is an underdeveloped country where energy crisesare more and the overall economy is low. A case study has
been taken to observe load flow from the 132 kV grid stationat Layyah. There are issues of power losses, poor voltage pro-file, low power factor, and overloaded transformers. To solvethese issues, two techniques are available: one is to upgradethe grid to 220 kV and the other is to inject a DG system tofulfil the needs of the demand side. The second approach isadopted for the solution of problems. Three zones weredesigned on ETAP to simulate a power flow algorithm usingthe Newton-Raphson method and discussed one by one.Each zone consists of 24 transformers, 24 constant loads,and 48 cables.
Zone A has 24 transformers in which 11 transformers areoverloaded and 18 distribution lines are overloaded. The loadpower factor is 0.71 at Shahpur Thal, and the lower voltage atMaujgarh was 293V. When DG is injected in all trans-formers, distribution lines started working properly withminimum losses. Shahpur Thal’s load power factor becomes0.9975, and Maujgarh’s voltage profile is improved from293V to 374V. Similarly, losses reduced in every element,and also the power factor improvement is noticeable. ZoneB has 24 transformers in which 8 transformers are over-loaded, 12 distribution lines are overloaded, and the lowestpower factor is 0.69 at Awanwala. The lowest voltage at Lad-hana is 298V. When DG is injected to all transformers, dis-tribution lines started working in a proper way withminimum losses. Awanwala’s power factor of loads became0.9973. Ladhana’s voltage profile improved from 298V to
25Total no. of transformers
20151050
25
20
Tran
sform
er lo
sses
(kW
)
15
10
5
0
A�er DG injectionExisting system
(a)
50
A�er DG injection
Total no. of lines403020100
Line
loss
es (k
W)
0
30
60
90
120
Existing system
(b)
Figure 16: (a) Transformer losses and (b) line losses before and after DG in zone A.
00.6
0.7
0.8
Load
pow
er fa
ctor
0.9
1.0
5 10 15 20 25Total no. of loads
A�er DG injectionExisting system
(a)
VR (
V)
0280300320340360380400
5 10 15 20 25Total no. of loads
A�er DG injectionExisting system
(b)
Figure 17: (a) Power factor and (b) voltage at the receiving end in zone A.
00
500
1000
1500
Tran
sform
er ra
ting
(kVA
)
2000
2500
5 10 15Total no. of transformers
20 25
Actual ratingNew rating
Figure 18: Actual and new rating of transformers in zone B.
12 International Journal of Photoenergy
374V. Zone C has 24 transformers in which 4 transformersare overloaded, 8 distributions lines are overloaded, and thelowest power factor is 0.75 at Zard. The lowest voltage atKarlo is 283V. When DG is injected, distribution linesstarted working properly with minimum losses. The powerfactor of loads in the Zard region becomes 0.9862. The volt-age profile in the Karlo region improved from 283V to
375V. Initially, total losses were 4.58MW and 12.30MVARwhich were then reduced in the newly implemented systemup to 0.548MW and 0.834MVAR. Load forecasting is donein this case study where more power is needed. In this design,old transformers were replaced by new transformers to savethe consumer side from outages of power. Every zone needs8MW power, so 24 solar panels of 1MW each were installedat the consumer side. This method has the potential to over-come the problem of load shedding as well, which is about 6to 8 hours in the region.
Data Availability
The data used to support the findings of this study areincluded within the article. The data is cited at relevant placeswithin the text as references.
Conflicts of Interest
The authors declare that there is no conflict of interestregarding the publication of this paper.
References
[1] J. Miret, J. L. G. de Vicuña, R. Guzmán, A. Camacho, andM. M. Ghahderijani, “A flexible experimental laboratory for
25Total no. of transformers
20151050
Tran
sform
er lo
sses
(kW
)
0
10
20
30
40
A�er DG injectionExisting system
(a)
50
A�er DG injection
Total no. of lines403020100
Line
loss
es (k
W)
0
30
60
90
120
150
Existing system
(b)
Figure 19: (a) Transformer losses and (b) line losses before andafter DG in zone B.
060
70
80
Load
pow
er fa
ctor
90
100
5 10 15 20 25Total no. of loads
A�er DG injectionExisting system
(a)
0200
250
300
VR (
V)
350
400
5 10 15 20 25Total no. of loads
A�er DG injectionExisting system
(b)
Figure 20: (a) Power factor and (b) voltage at the receiving end inzone B.
00
500
1000
1500
Tran
sform
er ra
ting
(kVA
)
2000
2500
5 10 15Total no. of transformers
20 25
Actual ratingNew rating
Figure 21: Actual and new ratings of transformers in zone C.
25Total no. of transformers
20151050
Tran
sform
er lo
sses
(kW
)
0
10
20
30
40
A�er DG injectionExisting system
(a)
50
A�er DG injection
Total no. of lines403020100
Line
loss
es (k
W)
0
30
60
90
120
150
Existing system
(b)
Figure 22: (a) Transformer losses and (b) line losses before andafter DG in zone C.
00.6
0.7
0.8Lo
ad p
ower
fact
or
0.9
1.0
5 10 15 20 25Total no. of loads
A�er DG injectionExisting system
(a)
VR (
V)
0280
300
320
340
360
380
5 10 15 20 25Total no. of loads
A�er DG injectionExisting system
(b)
Figure 23: (a) Power factor and (b) voltage at the receiving end inzone C.
13International Journal of Photoenergy
distributed generation networks based on power inverters,”Energies, vol. 10, no. 10, p. 1589, 2017.
[2] M. Kumar, C. Samuel, and A. Jaiswal, “An overview of distrib-uted generation in power sector,” International Journal of Sci-ence, Technology & Management, vol. 4, no. 1, pp. 3239–3326,2015.
[3] P. S. Georgilakis and N. D. Hatziargyriou, “Optimal distrib-uted generation placement in power distribution networks:models, methods, and future research,” IEEE Transactions onPower Apparatus and Systems, vol. 28, no. 3, pp. 3420–3428,2013.
[4] K. Doğanşahin, B. Kekezoğlu, R. Yumurtacı, O. Erdinç, andJ. Catalão, “Maximum permissible integration capacity ofrenewable DG units based on system loads,” Energies, vol. 11,no. 1, p. 255, 2018.
[5] S. Singh, J. Østergaard, and N. Jain, “Distributed generation inpower systems: an overview and key issues,” in 24rth IndianEngineering Congress, p. 8, Surathkal, Kerala, 2009.
[6] A. Saini, “Distributed system and its role in healthcare sys-tem,” International Journal of Computer Science and MobileComputing, vol. 4, no. 4, pp. 302–308, 2015.
[7] Z. A. Arfeen, A. B. Khairuddin, R. M. Larik, and M. S. Saeed,“Control of distributed generation systems for microgridapplications: a technological review,” International Transac-tions on Electrical Energy Systems, vol. 29, no. 9, pp. 1–26,2019.
[8] E. S. Elmubarak and A. M. Ali, “Distributed generation: defini-tions, benefits, technologies & challenges,” International Jour-nal of Science and Research (IJSR), vol. 5, no. 7, pp. 1941–1948,2016.
[9] W. Lin and E. Bitar, “Decentralized stochastic control of dis-tributed energy resources,” IEEE Transactions on Power Appa-ratus and Systems, vol. 33, no. 1, pp. 888–900, 2018.
[10] C. Zhang, J. Li, Y. J. Zhang, and Z. Xu, “Optimal location plan-ning of renewable distributed generation units in distributionnetworks: an analytical approach,” IEEE Transactions onPower Apparatus and Systems, vol. 33, no. 3, pp. 2742–2753,2018.
[11] R. Perez, C. Vasquez, and A. Viloria, “An intelligent strategyfor faults location in distribution networks with distributedgeneration,” Journal of Intelligent & Fuzzy Systems, vol. 36,no. 2, pp. 1627–1637, 2019.
[12] S.-E. Razavi, E. Rahimi, M. S. Javadi et al., “Impact of distrib-uted generation on protection and voltage regulation of distri-bution systems: a review,” Renewable and Sustainable EnergyReviews, vol. 105, pp. 157–167, 2019.
[13] D. Šošić and P. Stefanov, “Reconfiguration of distribution sys-tem with distributed generation using an adaptive loopapproach,” Journal of Electrical Engineering, vol. 70, no. 5,pp. 345–357, 2019.
[14] G. Xu, W. Yu, D. Griffith, N. Golmie, and P. Moulema,“Towards integrating distributed energy resources and storagedevices in smart grid,” IEEE Internet of Things Journal, vol. 4,no. 1, pp. 192–204, 2016.
[15] M. Firdhous, “Implementation of security in distributed sys-tems - a comparative study,” International Journal of Com-puter Information Systems, vol. 2, no. 2, pp. 1–6, 2012.
[16] S. Kumar Injeti and N. P. Kumar, “Optimal planning of dis-tributed generation for improved voltage stability and lossreduction,” International Journal of Computers and Applica-tions, vol. 15, no. 1, pp. 40–46, 2011.
[17] P. Mehta, P. Bhatt, and V. Pandya, “Optimal selection of dis-tributed generating units and its placement for voltage stabilityenhancement and energy loss minimization,” Ain Shams Engi-neering Journal, vol. 9, no. 2, pp. 187–201, 2018.
[18] A. Onlam, D. Yodphet, R. Chatthaworn, C. Surawanitkun,A. Siritaratiwat, and P. Khunkitti, “Power loss minimizationand voltage stability improvement in electrical distributionsystem via network reconfiguration and distributed generationplacement using novel adaptive shuffled frogs leaping algo-rithm,” Energies, vol. 12, no. 3, p. 553, 2019.
[19] S. J. Rudresha, S. G. Ankaliki, and T. Ananthapadmanabha,“Impact of DG integration in distribution system on voltagestability and loss reduction for different loading conditions,”International Journal of Recent Technology and Engineering,vol. 8, no. 5, pp. 2177–2181, 2020.
[20] S. A. Kumar, M. S. S. Narayana, B. A. Naidu, and G. V. S.Reddy, “Optimal power flow for IEEE -9 bus system usingETAP,” International Journal of Recent Technology and Engi-neering, vol. 6, pp. 368–370, 2019.
[21] S. Khan, S. U. Rehman, A. U. Rehman, and H. Khan, “Optimalplacement of distributed generation in power system for powersystem loss reduction using ETAP,” International Journal ofEngineering and Technologies, vol. 16, pp. 7–19, 2019.
[22] O. A. Afolabi, W. H. Ali, P. Cofie, J. Fuller, P. Obiomon, andE. S. Kolawole, “Analysis of the load flow problem in powersystem planning studies,” Energy and Power Engineering,vol. 7, no. 10, pp. 509–523, 2015.
[23] U. Farooq, S. Qureshi, S. Ahmad, I. National, and F. Wahab,“Load flow analysis of 11 kV test feeder with and without theinjection of DG,” International Journal of Computer Scienceand Information Security, vol. 15, no. 3, pp. 1–5, 2017.
[24] M. Tostado, S. Kamel, and F. Jurado, “Developed Newton-Raphson based predictor-corrector load flow approach withhigh convergence rate,” International Journal of ElectricalPower & Energy Systems., vol. 105, pp. 785–792, 2019.
[25] “National Electric Power Regulatory Authority Notification,”https://nepra.org.pk/Legislation/2-Rules/2.7%20NEPRA%20Performance%20Standards%20(Transmission)%20Rules,%202005/Performance%20Standards%20(Transmission)%20Rules%202005.pdf.
[26] “132KV Projects,” http://www.emco.com.pk/index.php/about-emco/our-projects/132kv-projects.
[27] G. Manager, Indicative Generation Capacity Expansion Plan(IGCEP) 2018-40, National Transmission and Dispatch Com-pany (NTDC), 2019.
[28] K. R. Hassan, Power system statistics, National Transmissionand Despatch Company (NTDC), 43rd edition, 2018.
14 International Journal of Photoenergy
https://nepra.org.pk/Legislation/2-Rules/2.7%20NEPRA%20Performance%20Standards%20(Transmission)%20Rules,%202005/Performance%20Standards%20(Transmission)%20Rules%202005.pdfhttps://nepra.org.pk/Legislation/2-Rules/2.7%20NEPRA%20Performance%20Standards%20(Transmission)%20Rules,%202005/Performance%20Standards%20(Transmission)%20Rules%202005.pdfhttps://nepra.org.pk/Legislation/2-Rules/2.7%20NEPRA%20Performance%20Standards%20(Transmission)%20Rules,%202005/Performance%20Standards%20(Transmission)%20Rules%202005.pdfhttps://nepra.org.pk/Legislation/2-Rules/2.7%20NEPRA%20Performance%20Standards%20(Transmission)%20Rules,%202005/Performance%20Standards%20(Transmission)%20Rules%202005.pdfhttp://www.emco.com.pk/index.php/about-emco/our-projects/132kv-projectshttp://www.emco.com.pk/index.php/about-emco/our-projects/132kv-projects
Implementation of Distributed Generation with Solar Plants in a 132 kV Grid Station at Layyah Using ETAP1. Introduction2. Current and Future Trends in Pakistan3. Power Flow Analysis4. Results and Discussion4.1. Existing System Implementation on ETAP4.2. New Design of the 132 kV Grid Station4.3. Zone A: Transformer, Distribution Lines, and Load Analysis4.4. Zone B: Transformer, Distribution Lines, and Load Analysis4.5. Zone C: Transformer, Distribution Lines, and Load Analysis
5. ConclusionData AvailabilityConflicts of Interest