Samir Boukhalfa Director – Local Energy Agency of the Lyon Urban Area (ALE) RENAISSANCE International Conference Milan – 31 st May 2011 Importance of the Construction Phase

Importance of the Construction Phase - Renaissance Project fileSamir Boukhalfa Director – Local Energy Agency of the Lyon Urban Area (ALE) RENAISSANCE International Conference Milan

  • Upload
    lykiet

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Importance of the Construction Phase - Renaissance Project fileSamir Boukhalfa Director – Local Energy Agency of the Lyon Urban Area (ALE) RENAISSANCE International Conference Milan

Samir Boukhalfa Director – Local Energy Agency of the Lyon Urban Area (ALE)

RENAISSANCE International Conference Milan – 31st May 2011

Importance of the Construction Phase

Page 2: Importance of the Construction Phase - Renaissance Project fileSamir Boukhalfa Director – Local Energy Agency of the Lyon Urban Area (ALE) RENAISSANCE International Conference Milan

RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework programme

Plan of intervention

1) Consortium, a technical support 2)  About on-site trainings 3) What remains to be done ? 4) Conclusion

1

Page 3: Importance of the Construction Phase - Renaissance Project fileSamir Boukhalfa Director – Local Energy Agency of the Lyon Urban Area (ALE) RENAISSANCE International Conference Milan

RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework programme

1) Consortium, a technical support

2

A pluridisciplinary team : - ENERTECH, INSA-CETHIL, HESPUL, ALE

Objectives : - Offer aid during each phase of construction (including engineering phase) - Technical assistance for promoters and their teams - Review the Concerto-Renaissance objectives

Means : - Read and analyze all projects data (for each phase) - Make proposals on improving projects

Page 4: Importance of the Construction Phase - Renaissance Project fileSamir Boukhalfa Director – Local Energy Agency of the Lyon Urban Area (ALE) RENAISSANCE International Conference Milan

RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework programme

2)  About on-site trainings

3

Developping on-site trainings : - For Workers, - For Training Officers

Topics was : -  Quality of works -  Interactions between building trades -  External insulation -  Airthightness

Page 5: Importance of the Construction Phase - Renaissance Project fileSamir Boukhalfa Director – Local Energy Agency of the Lyon Urban Area (ALE) RENAISSANCE International Conference Milan

RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework programme 4

Return of experiences - Feedback - Writing guidelines about the experiences (maintenance, create wood boiler in urban area)

Trainings -  Complete tools for trainers -  develop contents and trainings (new topics)

3)  What remains to be done ?

Page 6: Importance of the Construction Phase - Renaissance Project fileSamir Boukhalfa Director – Local Energy Agency of the Lyon Urban Area (ALE) RENAISSANCE International Conference Milan

RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework programme

Assistance to the promoters: - Importance of the communication - specific tools will be done (management, best practices,…)

5

4)  Conclusions & Recommendations

Trainings: - Make mandatory the training (integrate to the contract)

Page 7: Importance of the Construction Phase - Renaissance Project fileSamir Boukhalfa Director – Local Energy Agency of the Lyon Urban Area (ALE) RENAISSANCE International Conference Milan

RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework programme

French Partner Spanish Partners Italian partners

6

Contact [email protected]

ALE

Thank you for your attention !