Importance of Trans Anatolian Natural Gas Pipeline Project
for Executing Southern Gas Corridor
2012 Frankfurt Gas ForumGermany
28 November 2012
Stand Points of the Project
• In December 2011, Turkey and
Azerbaijan have signed an agreement
for a new gas pipeline project that will
connect Turkey's east and west,
carrying Azerbaijani gas to Europe.
• The new pipeline, named the Trans-
Anatolian Natural Gas Pipeline, is
being designed by the Azerbaijani
state-owned oil company SOCAR
• The inter-governmental agreement between
the Government of the Republic of Turkey and
the Government of the Republic of Azerbaijan,
has been signed on Tuesday, June 26th 2012 in
Istanbul with broad participation.
Strategic Alliance Between Azerbaijan and Turkey
• Security Supply of Europe:
• Source, route and volume.
• Shahdeniz sources of Azerbaijan
• Shahdeniz 2, Upsheron, Ümid and Babek field
• Security Supply of Turkey:
• Source, volume and national network.
Stand Points of the Project
The Southern Gas Corridor
• Southern Gas Corridor is needed for
the independence of European
Union Energy Security.
• Decreased gas production and
increased demand pushes Europe to
pay more importance to develop
Southern Gas Corridor.
• For this reason, Trans Anatolian
Natural Gas Pipeline Project (TANAP)
is playing crucial role on the
European Energy Security.
• Diversification of energy supply
routes and provision of energy
security in the region and beyond are
closely interrelated, it is important to
move forward and achieve new
results in the implementation of plans
and projects that are drew up in the
last few years.
Natural Gas Supply-Demand Projections of Europe
Most possible scenario- Blue one- …
Jeroen de Joode, www.ecn.nl European gas market developments in different energy transition scenarios
Natural Gas Resources of Azerbaijan
• Reserves of Absheron, Umid, Babek, and
Nakhchivan: 1.25 tcm of gas and more
than 200 mln. tons of condensate*
• Shah-deniz Reserves: 1.2 tcm gas, 240
mln. Tons condensate
• Shah Deniz-1; Plateu production 9 bcma
• Shah Deniz-2; Plateu production 16 bcma
*Ilham Nasirov, Deputy General Manager Investment Division, SOCAR
Natural Gas Supply-Demand Projection of Turkey
High grow rates, no new contracts case.
Short Intro / Highlights of the Project
• Objective: Transport of Azeri and Regional Gas
Supplies to Turkey and to Europe
• Capacity: 16-31 BCM
• Shareholding: SOCAR-BOTAŞ-TPAO
(BP-Statoil-Total)
• Target Operation: 2018
• Target Markets: Turkey and Europe (TAP/NIC)
Initially Planned Corridor
Critical Milestones
• IGA 1- 25 Oct. 2011
• Gas SPA - 25 Oct. 2011
• MoU 26 Dec. 2011 (ratified)
• Project Company (TANAP Bv.) – June 2012
• IGA-HGA 26 June 2012 (pending ratification)
Current Activities/Status
• Preliminary/Conceptual Studies for:
• Routing and Route Verification
• ESIA / EIA
• Permitting
• Mapping
• Technical Feasibility ongoing (sensitivity analysis)
• Policy and Strategy setting ongoing
• Organizational Set-up ongoing
Way forward :Critical Milestones – Development Plan
• Technical Studies
• PMOE assigned
• Engineering Contractor
assigned
• ESIA/EIA
• Engineering
• Permitting
• Procurement of LLI
and EPC
• Land Acquisition and
Construction
• Commercial Framework:
• Project Entity set-up including
Shareholders Agreement
• Transportation Agreements
• Financing Arrangements
• Operation Agreements
Objective is to ensure commercial operation by 2018