Upload
jlla86
View
218
Download
0
Embed Size (px)
DESCRIPTION
modelo de gantt
Citation preview
Id EDT Nombre de tarea Duracin
1 1 CERCO DE ALBAILERIA 50 das
2 inicio 0 das
3 1.1 OBRAS PROVISIONALES 2 das
4 1.1.1 INSTALACIONES Y CONSTRUCCIONES PROVISIONALES
2 das
5 1.2 TRABAJOS PRELIMINARES 3 das
6 1.2.1 LIMPIEZA DE TERRENO 2 das
7 1.2.2 TRAZO Y REPLANTEO 1 da
8 1.3 MOVIMIENTO DE TIERRA 21 das
9 1.3.1 EXCAVACION DE ZANJAS 6 das
10 1.3.2 RELLENO COMPACTADO CON MATERIAL PROPIO 3 das
11 1.3.3 ELIMINACION DE MATERIAL EXCEDENTE 2 das
12 1.4 CONCRETO CICLOPEO 4 das
13 1.4.1 CIMIENTO CORRIDO fc = 210 kg/cm2 4 das
14 1.5 SOBRECIMIENTO 6 das
15 1.5.1 CONCRETO fc = 210 kg/cm2 2 das
16 1.5.2 ENCOFRADO Y DESENCOFRADO 6 das
17 1.6 CONCRETO ARMADO 45 das
18 1.6.1 COLUMNAS 39 das
19 1.6.1.1 CONCRETO f'c = 210 kg/cm2 2 das
20 1.6.1.2 ENCOFRADO Y DESENCOFRADO 8 das
21 1.6.1.3 ACERO fy = 4200 kg/cm2 6 das
22 1.6.2 VIGAS 39 das
23 1.6.2.1 CONCRETO f'c = 210 kg/cm2 2 das
24 1.6.2.2 ENCOFRADO Y DESENCOFRADO 6 das
25 1.6.2.3 ACERO fy = 4200 kg/cm2 4 das
26 1.7 MURO DE ALBAILERIA 10 das
27 1.7.1 MURO DE LADRILLOS CORRIENTES (6X12X23) cm ENAPARAJEO DE SOGA
10 das
28 fin 0 das
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 1
Proyecto: imprimir diagrama ga
Fecha: mi 19/11/14
Comienzo Fin Predecesoras
lun 12/01/15 mar 10/03/15
lun 12/01/15 lun 12/01/15
lun 12/01/15 mar 13/01/15
lun 12/01/15 mar 13/01/15 2
mi 14/01/15 vie 16/01/15
mi 14/01/15 jue 15/01/15 4
vie 16/01/15 vie 16/01/15 6
sb 17/01/15 mar 10/02/15
sb 17/01/15 vie 23/01/15 7
jue 05/02/15 sb 07/02/15 15,16
lun 09/02/15 mar 10/02/15 10
sb 24/01/15 mi 28/01/15
sb 24/01/15 mi 28/01/15 9
jue 29/01/15 mi 04/02/15
sb 31/01/15 lun 02/02/15 16FC-4 das
jue 29/01/15 mi 04/02/15 13
sb 17/01/15 mar 10/03/15
sb 17/01/15 mar 03/03/15
mi 25/02/15 jue 26/02/15 20FC-6 das
lun 23/02/15 mar 03/03/15 27,21
sb 17/01/15 vie 23/01/15 7
sb 24/01/15 mar 10/03/15
vie 06/03/15 sb 07/03/15 24FC-4 das
mi 04/03/15 mar 10/03/15 19,20,25
sb 24/01/15 mi 28/01/15 21
mi 11/02/15 sb 21/02/15
mi 11/02/15 sb 21/02/15 11
mar 10/03/15 mar 10/03/15 24,23
12/01
S D L M X J V S D L M X J V S D L M X J V S D L
05 ene '15 12 ene '15 19 ene '15 26 ene '15 02 feb '15
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 2
Proyecto: imprimir diagrama ga
Fecha: mi 19/11/14
12/01
10/03
L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S
02 feb '15 09 feb '15 16 feb '15 23 feb '15 02 mar '15 09 mar '15
Tarea
Divisin
Hito
Resumen
Resumen del proyecto
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
solo duracin
Informe de resumen manual
Resumen manual
solo el comienzo
solo fin
Tareas externas
Hito externo
Fecha lmite
Tareas crticas
Divisin crtica
Progreso
Progreso manual
Pgina 3
Proyecto: imprimir diagrama ga
Fecha: mi 19/11/14