Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Orange County Water District
Groundwater Replenishment System Addendum No. 2
Final Expansion Page 2 of 6
In accordance with Instructions to Bidders, we hereby issue Addendum No. 2, as indicated by the attached sheets. Acknowledge receipt of this Addendum by inserting its number and date on the Bid Form, Item 12, page P-6. This addendum forms a part of the Contract Documents and, with respect to the Contract Documents, this Addendum shall govern. The effort/cost of work included or excluded by this addendum shall be reflected in the Bidder’s Sealed Bid.
A. MODIFICATIONS TO THE FRONT END DOCUMENTS
1. NOTICE INVITING BIDS
DELETE: On Page N-1 in first paragraph, “Tuesday, July 9, 2019”.
ADD: In place of deleted, “Tuesday, July 23, 2019”.
2. INFORMATION FOR BIDDERS, Page I-6, Interpretations and Addenda.
ADD: To end of section, “Clarifications, interpretations, and questions must be received by the Project Manager no later than fourteen calendar days (14) prior to bid opening.”
B. MODIFICATIONS TO THE TECHNICAL SPECIFICATIONS
1. Section 02396, “1-1 The Requirement”
ADD: The following at end of section, “F. The Contractor or specialty contractor shall be responsible for supplying all power necessary for completion of the work in Section 02396 and in drawings 144-SM-010 thru 144-SM-070.”
2. Section 01640A, “Valve and Gate Schedule”
ADD: The following,
3. Section 01640A, “Valve and Gate Schedule”
Orange County Water District
Groundwater Replenishment System Addendum No. 2
Final Expansion Page 3 of 6
DELETE: On pages 1 and 2 the following valves in their entirety, 144-A05-IW-AVRV-0100, 144-A04-IW-AVRV-0100, 144-A03-IW-AVRV-0100, 144-A02-IW-AVRV-0100, and 144-A01-IW-AVRV-0100.
4. Section 01640A, “Valve and Gate Schedule”
REPLACE: On pages 1 and 2 the size of the valves 144-A05-SE-AVRV-0100, 144-A04-SE-AVRV-0100, 144-A03-SE-AVRV-0100, 144-A02-SE-AVRV-0100, and 144-A01-SE-AVRV-0100 from “1” to “2”.
5. Section 01640A, “Valve and Gate Schedule”
DELETE: On page 2 for valve 144-A01-SE-AVRV-0115, “144-I-012” and “1/2”.
ADD: In place of deleted the following respectively, “144-I-010” and “12”.
6. Section 01640A, “Valve and Gate Schedule”
DELETE: On page 2 for valves 144-A01-SE-NV-0140 and 144-A02-SE-NV-0140, the “NV” and “Needle”.
ADD: In place of deleted the following respectively, “PV” and “Plug”.
7. Section 11400, “Reverse Osmosis Treatment System”
DELETE: In Section 2-3 “Anticipated Water Quality” table in its entirety.
ADD: In place of delete the following new revised table.
Anticipated Water Quality (all units in mg/L unless stated otherwise)
Parameter Minimum
Value
Average
Value
Maximum
Value
Temperature (deg F) 67.1 74.7 80.6
pH 7.2 7.5 7.7
Ammonia Nitrogen (NH4-N) 3.0 6.8 13.1
Alkalinity 210 235 289
Hardness 239 267 352
TDS 1,102 1,442 1,925
Nitrate Nitrogen (NO3-N) 5.6 6.3 8.55
Total Nitrogen 12.1 18.3 29.4
Phosphate as PO4 0.13 0.67 1.6
Total Organic Carbon (TOC) 6.5 10.7 16.1
Aluminum (Al) 0.004 0.01 0.019
Calcium (Ca) 52 73 98
Magnesium (Mg) 16.8 20.3 26.3
Sodium (Na) 215 350 472
Potassium (K) 20.0 22.4 27.3
Barium (Ba) 0.0001 0.0001 0.0001
Orange County Water District
Groundwater Replenishment System Addendum No. 2
Final Expansion Page 4 of 6
Iron (Fe) 0.01 0.46 1.36
Manganese (Mn) 0.025 0.064 0.12
Bicarbonate (HCO3) 257 314 353
Sulfate (SO4) 124 173 245
Chloride (Cl) 329 434 618
Fluoride (F) 0.7 0.8 1.0
Silica (SiO2) 13.8 20.8 31.5
Strontium (Sr) 0.9 0.34 0.78
* Data for separate constituents listed were accumulated during multiple sample periods, reflecting conditions that may not simultaneously occur.
C. MODIFICATIONS TO THE PLANS (Note: Sheets not being re-issued for Addendum
unless noted)
1. Drawing No. 100-Y-259
DELETE: On Piping Plan, “235-P-015”.
ADD: In place of deleted, “210-P-015”.
2. Drawing No. 100-Y-290
DELETE: Drawing 100-Y-290.
ADD: In place of deleted, attached new Drawing 100-Y-290.
3. Drawing No. 100-Y-292
DELETE: Drawing 100-Y-292.
ADD: In place of deleted, attached new Drawing 100-Y-292.
4. Drawing No. 100-Y-293
DELETE: Drawing 100-Y-293.
ADD: In place of deleted, attached new Drawing 100-Y-293.
5. Drawing No. 100-Y-294
DELETE: Drawing 100-Y-294.
ADD: In place of deleted, attached new Drawing 100-Y-294.
6. Drawing No. 144-S-012, For 3’-9” x 3’-9” concrete equipment pad located
Orange County Water District
Groundwater Replenishment System Addendum No. 2
Final Expansion Page 5 of 6
west of transformer pad.
DELETE: One of the “3’-9”” dimensions.
ADD: In place of deleted “9’-9” (See Note 12)”
ADD: The following note, “12. The equipment shall be oriented such that service to the equipment panel(s) will occur atop the concrete pad not adjacent asphalt. Orientation to be coordinated with Owner.”
7. Drawing No. 235-P-009
DELETE: On Plan Note 1, “100-Y-259”.
ADD: In place of deleted, “210-D-011”.
8. Drawing No. 140-I-010
DELETE: Ball valve “140-BV-0136”.
ADD: In place of deleted, “140-PV-0136”.
9. Drawing No. 144-I-010
DELETE: Ball valve “A01-BV-0115”.
ADD: In place of deleted, “A01-PV-0115”.
10. Drawing Nos. 144-I-010, 144-I-011, and 144-I-012
REPLACE: Ball valves serving valves 144-A05-SE-AVRV-0100, 144-A04-SE-AVRV-0100, 144-A03-SE-AVRV-0100, 144-A02-SE-AVRV-0100, and 144-A01-SE-AVRV-0100 from “1” to “2”.
11. Drawing Nos. 144-I-010, 144-I-011, and 144-I-012
REPLACE: On IW feed to pump A05, A03, and A01, “3/4-STL-D” to “3/4-STL-IW”.
12. Drawing Nos. 210-I-080, 210-I-082, 210-I-084, 210-I-086, 210-I-102, 210-I-104,
210-I-106, 210-I-108, 210-I-130, 210-I-132, 210-I-134, and 210-I-136
DELETE: On 24” pipeline downstream of BFV-805 at three locations “STL/L” from 24-STL/L-BWW.
ADD: In place of deleted, “316SS”.
13. Drawing Nos. 210-I-081, 210-I-083, 210-I-085, 210-I-087, 210-I-103, 210-I-105,
210-I-107, 210-I-109, 210-I-131, 210-I-133, 210-I-135, and 210-I-137
Orange County Water District
Groundwater Replenishment System Addendum No. 2
Final Expansion Page 6 of 6
DELETE: On 24-STL/L-BWW pipeline, “STL/L”.
ADD: In place of deleted, “316SS”.
14. Drawing No. 510-I-720, 510-I-745, 510-I-765 and 510-I-785
DELETE: “316SS” from the “2-316SS-ROF” line after RO Bank 2.
ADD: In place of deleted “DSS”
D. OTHER
1. POTENTIAL BIDDER RFIs
A log of RFIs submitted and responded to has been included in Attachment 1.
2. RE-ISSUED DRAWINGS Re-issued drawings have been included in Attachment 2.
3. RE-ISSUED SPECIFICATIONS (NOT USED)
Attachment 1
Information Requests and Responses
Prebid Meeting 0 1 Is 6% a requirement or just a goal for MBD/DBE participation? The DBE participation of 6% is a goal not a requirement. 5/2/2019
Prebid Meeting 0 2 Have either of the previous GWRS Projects required AIS participation and goals?
Neither the original GWRS nor the GWRS Initial Expansion necessitated compliance with
the American Iron and Steel (AIS) requirement since the constructions of both phases of
the GWRS occurred before January 17, 2014, the date of enactment of the Consolidated
Appropriations Act (Public Law 113-76) which includes an AIS requirement.
5/2/2019
Prebid Meeting 0 3 If current projects at Plant 2 are not finished how can we complete the Expansion?All the project components in this bid contract can be completed and tested without the
OCSD Plant 2 projects.5/2/2019
Prebid Meeting 0 4 Where is the equipment access point for the MF basement?
Through the 8-ft square access hatches on MF deck and/or through the sawcut openings
in existing MF basement walls (to be completed as part of the work in this contract)
and/or through the existing freight elevator. An 8-ft square access hatch exists at Train
C and a new 8-ft square access hatch is to be installed as part of the Final Expansion near
Train F. See Drawing 210-S-042. See Addendum 1 for addtional requirement for use of
the existing freight elevator.
5/2/2019
Prebid Meeting 0 5Will the contractor have use of the bridge crane in the Final Product Water Pump
Station?
The contactor shall based bid on non-use of the bridge crane. However, Owner is open
to further discussion regarding bridge crane use during construction and may include
similar restrictions and requirements addressed in the addendum for use of the MF
elevator which includes cost for repair/maintenance.
5/2/2019
Prebid Meeting 0 6Are the various values and cost estimate from the Power point presentation accurate or
more up to date than what is in the Contract Documents?
The contractor is to use the values and estimates presented in the Contract Documents
unless changed by addendum. 5/2/2019
Shimmick 1 1
At the Pre-bid meeting, OCWD stated that Good Faith Effort documentation was to be
submitted by the apparent low bidder within 24 hours of the bid date. We are
requesting that that it be changed so that the Good Faith Effort documentation from the
lowest bidder be provided within 72 hours of the bid date.
OCWD will accept Good Faith Documentation to be submitted by the apparent lowest
bidder within 72 hours of the bid opening date.5/10/2019
Shimmick 1 2
According to Exhibit C – Guidelines for Meeting the California State Revolving Fund
(CASRF) Programs (Clean Water and Drinking Water SRF) Disadvantaged Business
Enterprise Requirements: Six Good Faith Efforts (GFE) Item 2. “Make information on
forthcoming opportunities available to DBEs. Posting solicitations for bids or proposals
for a minimum of 30 calendar days in a local newspaper, before the bid opening date.”
Provide clarification: Please confirm that the solicitation must be placed a minimum of
30 days prior to the bid opening, but does not need to be run for a minimum of 30 days
total.
OCWD confirms that the solicitations for bids or proposals from DBE subcontractors
must be placed a minimum of 30 calendar days prior to the bid opening date. Therefore,
the solicitations for bids or proposals must be posted for a period of, at least, 30
consecutive days in a local newspaper or trade journals or website or building exchange
or a combination hereof. For example, a prime contractor may post its solicitation for
DBE subcontractors in a local newspaper for 5 calendar days and in trade journals for
the remaining 25 calendar days, for a combined posting period of 30 calendar days.
5/10/2019
Shimmick 1 3 Please confirm if there is a mandatory DBE Goal for this project. The OCWD goal of 6% DBE participation is not a requirement for award of the project. 5/10/2019
ReceivedResponseContractor
Orange County Water DistrictGroundwater Replenishment System Final Expansion Project
Bid Period RFI Response Log
RFI No. Question#
Page 1 of 4
ReceivedResponseContractor
Orange County Water DistrictGroundwater Replenishment System Final Expansion Project
Bid Period RFI Response Log
RFI No. Question#
Lyles 1 1
In regards to Good Faith Effort, please clarify whether the posting of bid solicitations
needs to happen a minimum of 30 days before bid or for a 30 day duration before bid.
There has been confusion on previous projects as to how long the actualy advertisement
needs to run (1 day or 30 days).
OCWD confirms that the solicitations for bids or proposals from DBE subcontractors
must be placed a minimum of 30 calendar days prior to the bid opening date. Therefore,
the solicitations for bids or proposals must be posted for a period of, at least, 30
consecutive days in a local newspaper or trade journals or website or building exchange
or a combination hereof. For example, a prime contractor may post its solicitation for
DBE subcontractors in a local newspaper for 5 calendar days and in trade journals for
the remaining 25 calendar days, for a combined posting period of 30 calendar days.
5/28/2019
Lyles 1 2 Is there a cut off date for asking pre-bid questions? The cutoff date will be 14 calendar days prior to bid opening. See Addendum 2. 5/28/2019
Lyles 1 3Sheet 235-P-090 Plan Note 1 indicates that the new 2"-PVC-DW is to connect to an
exisitng 10"-PVC-DW. Please clarify.
The 10"-PVC-DW pipeline is located just east of the new containment structure. See
Drawing 210-D-011 for location of DW pipeline. Addendum 2 will revise note to cite 210-
D-011.
5/28/2019
Lyles 1 4DWG 100-Y-259 shows the 1"-CU-PA heading West to a note "For Continuation See
DWG 235-P-015." This DWG doesn't exist please clarify.Drawing 210-P-015 should have been referenced. See Addendum 2 for correction. 5/28/2019
DH Water Systems Section 11345- Will Blue-White Peristaltic pump be accepted as an approved equal?
OCWD will not pre-approve this pump as an “or equal” at this time. The appropriate
protocol is to submit all documentation through the general contractor (i.e. a specific
submittal for our application) that will be reviewed by the Engineer and OCWD to
determine if it is “equal” during the submittal process.
5/28/2019
DH Water Systems
Section 11727MF: Will the Rotho hose pump be accepted as an approved equal? This
pump is the updated version of the Siemens Chemtube that the district has been using
in a variety of chemical feed/transfer pump applications.
OCWD will not pre-approve this pump as an “or equal” at this time. The appropriate
protocol is to submit all documentation through the general contractor (i.e. a specific
submittal for our application) that will be reviewed by the Engineer and OCWD to
determine if it is “equal” during the submittal process.
5/28/2019
Shimmick 2 4
Due to the scope of this project that includes modifications to the existing
switchgear/MCC it is requested to be allowed access to this gear through a second job
walk where the Contractors have access to inspect this equipment. This is critical to be
able to properly price out the modifications to the switchgear and MCC.
A job walk is scheduled for June 13, 2019 from 9:00 AM to 11:00 AM. Access to
equipment will occur during this meeting. Equipment will be opened by OCWD staff.5/31/2019
Shea 1 1
In Specification Section 15092 - 2-1.03 the VBF-3 High Performance Butterfly valve listed
as Keystone, is not manufactured anymore in the USA, and Emerson has discontinued its
AIS valve line. Do you wish to use exclusively DeZurik and Pratt for these valves, do you
have an additional valve manufacture to list or will it be acceptable to use Keystone
even if they don’t meet the requirements of AIS?
Under review. To be addressed in Addendum 3. 6/4/2019
Page 2 of 4
ReceivedResponseContractor
Orange County Water DistrictGroundwater Replenishment System Final Expansion Project
Bid Period RFI Response Log
RFI No. Question#
Shea 1 2
In Specification Section 15092 - 2-1.05 the VBF-5 High Performance Butterfly valve listed
as Keystone, is not manufactured anymore in the USA, and Emerson has discontinued its
AIS valve line. Do you wish to use exclusively DeZurik and Pratt for these valves, do you
have an additional valve manufacture to list or will it be acceptable to use Keystone
even if they don’t meet the requirements of AIS?
Under review. To be addressed in Addendum 3. 6/4/2019
Shea 1 3
In Specification Section 15092 - 2-1.06 the VBF-6 Triple Offset Butterfly valve listed as
Vanesa, is not manufactured in the USA, but is exclusively made in Italy and will not
meet AIS requirements. Do you have an additional valve manufacture to list or will it be
acceptable to use Vanesa even if they don’t meet the requirements of AIS?
Under review. To be addressed in Addendum 3. 6/4/2019
Shea 1 4
In Specification Section 15092 - 2-1.07 the VBF-7 Butterfly valve tagged as 815-A05-BFV-
3405, listed as Tyco/Vanesa, is not manufactured in the USA, but is exclusively made in
Italy and will not meet AIS requirements. Do you have an additional valve manufacture
to list or will it be acceptable to use Vanesa even if they don’t meet the requirements of
AIS?
Under review. To be addressed in Addendum 3. 6/4/2019
Shea 1 5
In Specification Section 15101MF - 2-3. B the Type 2 Butterfly valve BFV-2, lists
Keystone, Crane, Jamesbury, Fisher and Masoneilon, none of which are manufactured in
the USA. Do you wish to use exclusively DeZurik for these valves, do you have additional
valve manufactures to list or will it be acceptable to use Keystone, Crane, Jamesbury,
Fisher or Masoneilon, even if they don’t meet the requirements of AIS.
Under review. To be addressed in Addendum 3. 6/4/2019
Shea 1 6
In Specification Section 01640A -Valve and Gate Schedule, page 2, the valve tagged 144-
A01- AVRV-0115, states that it is a 1/2" Air/Vac valve found drawing 144-I-012. We
cannot find this valve on the referenced drawing, but rather find this tag number on
drawing 144-I-010, where it is called out as a 12" valve. Please clarify this apparent
discrepancy.
The drawing referenced should be 144-I-010 and the size should be 12". See Addendum
2 for revisions.6/4/2019
Shea 1 7
In Specification Section 01640A -Valve and Gate Schedule, page 2, the valves tagged 144-
A01 & A02 -NV-0140, states that they are 6" Needle valves. We cannot find these valves
on the referenced drawing, but rather find two Plug Valves with the corresponding tag
numbers. Please clarify this apparent discrepancy.
The valves should be redesignated from Needle to Plug. See Addendum 2 for revision. 6/4/2019
Shea 1 8
On Drawing 210-I-080, the piping downstream of the waste valve BFV-E05-0805 is
depicted as changing to STL/L to the BWW flume. This is consistent on all BWW from all
trains. Yet on the drawing 210-M-013 the callout for the piping material downstream of
the referenced valves on all trains, is 316SS. Please clarify this apparent discrepancy.
The piping downstream of BFV-E05-0805 should be 316SS. See Addendum 2 for
revision.6/4/2019
Page 3 of 4
ReceivedResponseContractor
Orange County Water DistrictGroundwater Replenishment System Final Expansion Project
Bid Period RFI Response Log
RFI No. Question#
Flatiron 1 1
Due to the size and complexity of this project and the large number of water
infrastructure projects that are currently out for bid across Southern California, we
respectfully request a minimum three week bid extension. An extensionis needed in
order for Prime Contractors to have sufficient time to provide a complete and
competitive estimate.
Bid date will be extended to July 23, 2019. See Addendum 2 for revision. 6/4/2019
Shea 2 9Due to the complexity of this project and the multiple sites that the work will take place
on, we respectfully request that the bid date be extended by two weeks.Bid date will be extended to July 23, 2019. See Addendum 2 for revision. 6/5/2019
Lyles 2 5
Specification section 01025-2.2 - Bid Item No. 6, Microfiltration Membranes: states "
The owner expects to finalize the selection process by no later than December 31,
2020", please confirm this is a typo and should read "December 31, 2019".
December 2020 is correct. A decision by December 2019 is targeted however the
contractor should plan for the decision to be made by December 2020.6/6/2019
Lyles 2 6
Outage N in specification 01140 describes the Diversion Structure (Plant 2) work. The
points of isolation state "stop plate at OOBS (24GGAT104) and Stop plate for 36'' plant
water pipeline connection at LOFLO PS/PWPS Junction Structure". Please provide
details on where these stop plates are located. Does the contractor need to provide or
just set them in place? Please provide the estimated amount of water needed to
dewater from the pipeline or provide the locations of isolation.
The OOBS stop plate is existing and resides at OOBS. The plant water stop is being
constructed as part of another OCSD project. The plant water stop plate will be located
near OOBS. Both stop plates will be installed by the GWRSFE contractor not OCSD,
OCWD, or another projects contractor. Addendum 3 will show the location of the stop
plates.
6/6/2019
Midwestern
Fabricators1 1
I would like to to request that Midwestern Fabricators be listed as an acceptable
manufacturer for the FRP Tanks found in specification 11249 and 13190.
Midwestern Fabricators will be added as an acceptable manufacturer. Addendum 3 will
reflect revision.6/6/2019
Page 4 of 4
Attachment 2
Re-Issued Drawings
XX
XX
XXXXXX
100-Y-290
GROUNDWATER REPLENISHMENT SYSTEM FINAL EXPANSION
PLANT 1OVERALL YARD PIPING PLAN
06/07/2019
°
°
°
°
°
100-Y-292
GROUNDWATER REPLENISHMENT SYSTEM FINAL EXPANSION
PLANT 1YARD PIPING PLAN AND PROFILE 2 OF 2
06/07/2019
100-Y-293
GROUNDWATER REPLENISHMENT SYSTEM FINAL EXPANSION
PLANT 1GAP PIPING PLAN AND PROFILE
06/07/2019
100-Y-294
GROUNDWATER REPLENISHMENT SYSTEM FINAL EXPANSION
NORTH POC ENLARGED PLAN
06/07/2019