In Partnership with Palangoy Gospel Chapel. ETWF Church and Training Centre. 50% Building = Second Storey + Roof Frame Structure 80% Building = Roof + Tiles + Painting Structure 100% Building = Fully Completed + TOP Structure. BAPTISMAL POOL - SIDE. BAPTISMAL POOL - FRONT. - PowerPoint PPT Presentation
Citation preview
In Partnership with Palangoy Gospel
Chapel
ETWF Church and Training Centre
50% Building = Second Storey + Roof FrameStructure
80% Building = Roof + Tiles + PaintingStructure
100% Building = Fully Completed + TOPStructure
EXPENSES - TAYUMAN PROJECT (August 2011 - )
Date Detail Ph Pesos Balance
30-Aug-11 Building Permit Fees 43,572.20 10,956,427.80
1-Sep-11 Claim Form 1 100,000.00 10,856,427.80
7-Sep-11 Claim Form 2 300,000.00 10,556,427.80
12-Sep-11 Claim Form 3 800,000.00 9,756,427.80
20-Sep-11 Claim Form 4 800,000.00 8,956,427.80
29-Sep-11 Claim Form 5 800,000.00 8,156,427.80
30-Sep-11 Edgar's Salary - September 2011 11,000.00 8,145,427.80
7-Oct-11 Claim Form 6 800,000.00 7,345,427.80
20-Oct-11 Claim Form 7 1,400,000.00 5,945,427.80
30-Oct-11 Edgar's Salary - October 2011 13,750.00 5,931,677.80
30-Nov-11 Edgar's Salary - November 2011 12,000.00 5,919,677.80
10-Dec-11 Claim Form 8 1,000,000.00 4,919,677.80
2-Jan-12 Edgar's Salary - December 2011 12,000.00 4,907,677.80
6-Jan-12 Claim Form 9 1,000,000.00 3,907,677.80
1-Feb-12 Edgar's Salary - January 2012 12,000.00 3,895,677.80
20-Feb-12 Claim Form 10 1,000,000.00 2,895,677.80
1-Mar-12 Edgar's Salary - February 2012 12,000.00 2,883,677.80
24-Mar-12 Claim Form 11 1,000,000.00 1,883,677.80
1-Apr-12 Edgar's Salary - March 2012 12,000.00 1,871,677.80
1-May-12 Edgar's Salary - April 2012 10,500.00 1,861,177.80
18-May-12 Viewtech Wall Screen 6,160.00 1,855,017.80
23-May-12 Claim Form 12 643,197.00 1,211,820.80
26-May-12 Import Permit for Chairs 15,000.00 1,196,820.80 Total 9,803,179.20 1,196,820.80
BUILDING FUND (April 2012 )Date Detail Sin $ Balance
14-Jan-12Philippines Building Fund (Target:
$350,000.00) 350,000.00
LESS REMITTANCES:
15-Aug-11 (1) Building Cost 85,964.89 264,035.11
22-Aug-11 (2) Building Cost 86,087.90 177,947.21
4-Nov-11 (3) Building Cost 88,893.89 89,053.32
20-Mar-12 (4) Building Cost 59,612.52 29,440.80
TBD (5) Furnishing Cost (PA System and Chairs) 29,440.80
PA System $23,508.00
Chairs $ 5,932.80
Total $29,440.80
BAPTISMAL POOL - SIDE
BAPTISMAL POOL - FRONT
FIRST FLOOR LADIES TOILET
FIRST FLOOR KITCHEN
SECOND FLOOR KITCHEN
MASTER ROOM WARDROBE
CONFERENCE ROOM 1 WARDROBE
MAIN SPEAKER LEFTMAIN SPEAKER RIGHT
CEILING MOUNT PROJECTOR
PULL DWN SCREEN
STAGE MONITOR LEFT STAGE MONITOR RIGHT
SUB-WOOFER
SANCTUARY STAGE
RAVI VICTOR
ETWF MEMBERS WITH
DEACON FRANCIS AND DEACONESS KATHY
CHECKING OUT THE AUDIO SYSTEM
CHECKING OUT THE AUDIO SYSTEM
PRAYER Items:1. Thanksgiving for providing
funds,2. Salvation of Construction
Workers ,3. Good Working Relationship,
4.Safe arrival of 300 Chairs,5. Built Within Budget,6.Smooth Handover,
7. Thanksgiving .