Upload
phungdieu
View
217
Download
3
Embed Size (px)
Citation preview
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 02ND
DAY OF DECEMBER, 2015
BEFORE:
THE HON’BLE MR. JUSTICE ANAND BYRAREDDY
WRIT PETITION No.41561 OF 2015 (GM-RES)
CONNECTED WITH
WRIT PETITION No.44658 OF 2015,
WRIT PETITION No.43244 OF 2015 AND
WRIT PETITION No.47497 OF 2015 (GM-RES)
In W.P.No.41561/2015:
BETWEEN:
AUTOGRADE INTERNATIONAL PRIVATE LIMITED,
(Formerly Aasma Techno Products Private Limited),
35/334, Mamangalam Church Road,
Kochi-682 025.
Kerala State, Represented by its
Authorised signatory
Mr. T. Mohammed Ashraf.
…PETITIONER
(By Shri N. Khetty, Advocate)
AND:
1. The State of Karnataka,
By its Secretary for Transport,
M.S. Building, Bangalore-1.
2
2. The Commissioner for Transport
And Road Safety,
M.S. Building,
Dr. B.R. Ambedkar Veedhi,
Bangalore-1.
3. Rosmerta Autotech Pvt. Ltd.,
Formerly known as Multispeed Gears Pvt. Ltd.,
Having its registered office at
Khasra No.19/28, Kapashera,
New Delhi-122 016.
And Corporate office at
137, Udyog Vihar Phase-I,
Gurgaon-122 016.
Haryana, Represented by its
General Manager
Mr. Joy Joseph.
… RESPONDENTS
(By Shri A.S. Ponnanna, Additional Advocate General for Shri
M.I. Arun, Additional Government Advocate for Respondents 1
and 2,
Shri Jayakumar S. Patil, Senior Advocate for Shri Joseph
Anthony, Advocate for Respondent No.3)
*****
W.P.41561/2015 is filed under Articles 226 and 227 of the
Constitution of India, praying to quash the impugned public notice
dated 29.8.2015 at Annexure-B published in the newspaper on
5.9.2015, and etc.
3
In W.P.No.44658/2015:
BETWEEN:
DIGILA DEVICES INDIA (PVT) LTD.
NH 212, Industrial Layout,
Near Government Technical School,
Sulthan Bathery, North Kerala,
Represented by its Managing Director
Mr. Biju Polouse.
…PETITIONER
(By Shri N. Khetty, Advocate)
AND:
1. The State of Karnataka,
By its Secretary for Transport,
M.S. Building, Bangalore-1.
2. The Commissioner for Transport
And Road Safety,
M.S. Building,
Dr. B.R. Ambedkar Veedhi,
Bangalore-1.
3. Rosmerta Autotech Pvt. Ltd.,
Formerly known as Multispeed Gears Pvt. Ltd.,
Having its registered office at
Khasra No.19/28, Kapashera,
New Delhi-122 016.
And Corporate office at
137, Udyog Vihar Phase-I,
Gurgaon-122 016.
Haryana, Represented by its
4
Authorised Signatory and General Manager
Mr. Joy Joseph.
… RESPONDENTS
(By Shri A.S. Ponnanna, Additional Advocate General for Shri
M.I. Arun, Additional Government Advocate for Respondents 1
and 2,
Shri Jayakumar S. Patil, Senior Advocate for Shri Joseph
Anthony, Advocate for Respondent No.3)
*****
W.P.44658/2015 is filed under Articles 226 and 227 of the
Constitution of India, praying to quash the impugned public notice
dated 29.8.2015 at Annexure-B published in the Times of India
newspaper on 5.9.2015, and etc.
In W.P.No.43244/2015:
BETWEEN:
CRAYSOL TECHNOLOGIES (INDIA) PVT. LTD.
Craysol Building, XVIII / 498,
Cochin University Road,
Cusot P.O., Kalamassery,
Kochi-682 022, Kerala,
Represented by its
Managing Director
Mr. Noby E.A. …PETITIONER
(By Shri N. Khetty, Advocate)
AND:
1. The State of Karnataka,
By its Secretary for Transport,
5
M.S. Building, Bangalore-1.
2. The Commissioner for Transport
And Road Safety,
M.S. Building,
Dr. B.R. Ambedkar Veedhi,
Bangalore-1.
3. Rosmerta Autotech Pvt. Ltd.,
Formerly known as Multispeed Gears Pvt. Ltd.,
Having its registered office at
Khasra No.19/28, Kapashera,
New Delhi-122 016.
And Corporate office at
137, Udyog Vihar Phase-I,
Gurgaon-122 016.
Haryana, Represented by its
Authorised Signatory & General Manager
Mr. Joy Joseph.
… RESPONDENTS
(By Shri A.S. Ponnanna, Additional Advocate General for Shri
M.I. Arun, Additional Government Advocate for Respondents 1
and 2,
Shri Jayakumar S. Patil, Senior Advocate for Shri Joseph
Anthony, Advocate for Respondent No.3)
*****
W.P.43244/2015 is filed under Articles 226 and 227 of the
Constitution of India, praying to quash the impugned public notice
dated 29.8.2015 at Annexure-B published in the Times of India
newspaper on 5.9.2015, and etc.
6
In W.P.No.47497/2015:
BETWEEN:
M/s. Sriyash Technologies Pvt. Ltd.,
6th
Floor, Poddar Point, 113,
Park Street,
Kolkata-700 016,
Represented by its
Director, Anil Kishorepuria. …PETITIONER
(By Smt. Kavitha H.C., Advocate)
AND:
1. The State of Karnataka,
Represented by its
Under Secretary to Government,
Department of Transport,
M.S. Buildings,
Bangalore-560 001.
2. The Commissioner for Transport
And Road Safety,
Government of Karnataka,
M.S. Building,
Dr. B.R. Ambedkar Veedhi,
Bangalore-1.
… RESPONDENTS
(By Shri A.S. Ponnanna, Additional Advocate General for Shri
M.I. Arun, Additional Government Advocate for Respondents 1
and 2)
*****
7
W.P.47497/2015 is filed under Articles 226 and 227 of the
Constitution of India, praying to quash the checklist / eligibility
criterion at Annexure-C, prescribed by the respondents and etc.
These Writ Petitions having been heard and reserved on
25/11/2015 and coming on for pronouncement of Orders this day,
the Court delivered the following:-
O R D E R
These petitions are heard and disposed of by this common
order.
2. The petitioner in the first of these petitions in WP
41561/2015, M/s Autograde International Private Limited, is said
to be a private limited company engaged in the manufacture of
Speed Limiting Devices, also known as Speed Governors. The
said devices are intended to confine the maximum speed of the
motor vehicle, to which it is fitted, to the speed limit set on the
device. The speed limit so set is as notified by the Central
Government under the Motor Vehicles Act, 1988. (Hereinafter
referred to as ‘the MV Act, for brevity)
8
The installation of the speed governors is made mandatory
under Rule 118 of the Central Motor Vehicle Rules, 1989
(Hereinafter referred to as ‘the CMV Rules’, for brevity). Though
it was in vogue since the year 2003, the State of Karnataka had
issued a notification in March, 2005 for the installation of speed
governors for specified vehicles. The actual installation was
however, postponed from time to time. This extension being
granted indefinitely, was challenged in public interest before this
court. By a judgment dated 30.6.2008, in the case of Y. N.
Nanjappa v. State of Karnataka in W.P.10416/2007, this court
had quashed the extension orders and directed the respondents to
strictly implement the rule. The said order having been
challenged by the State itself, in a special leave petition before the
Apex Court, the said petition was ultimately dismissed as on
18.8.2011, on an undertaking by the State that a notification
would be issued to implement the rule for installation of speed
governors.
9
On 15.4.2015, the amended Rule 118 of the CMV Rules
was notified, making it mandatory for every transport vehicle, as
notified by the Central Government, under Section 4 of the MV
Act, to be equipped, by the manufacturer of those vehicles - even
at the dealership stage, with a speed governor - with effect from
1.10.2015. The pre-set speed limit was to be 80 kilometres per
hour (kmph). The devices were to conform to the Standard AIS
(Automotive Industry Standard ) 018/2001.
The said amended Rule 118 reads as follows :
“118. Speed Governor – (1) Every transport vehicle
notified by the Central Government under sub-section (4)
of Section 41 of the Motor Vehicles Act, 1988 (59 of
1988), save as provided herein, and manufactured on or
after the 1st October, 2015 shall be equipped or fitted by the
vehicle manufacturer, either in the manufacturing stage or
at the dealership stage, with a speed governor (speed
limiting device or speed limiting function) having
maximum pre-set speed of 80 kilometres per hour
conforming to the Standard AIS 018/2001, as amended
from time to time:
Provided further that the transport vehicles that
are—
(i) Two wheelers;
10
(ii) Three wheelers;
(iii) Quadricycles;
(iv) Four wheeled and used for carriage of
passengers and their luggage, with seating capacity not
exceeding eight passengers in addition to driver seat (M1
Category) and not exceeding 3500 kilogram gross vehicle
weight;
(v) Fire tenders;
(vi) Ambulances;
(vii) Police vehicles;
(viii) Verified and certified by a testing agency
specified in rule 126 to have maximum rated speed of not
more than 80 kilometre per hour, shall not be required to be
equipped or fitted with speed governor (speed limiting
device or speed limiting function);
Provided further that the transport vehicles
manufactured on or after 1st of October, 2015 that are
dumpers, tankers, school buses, those carrying hazardous
goods or any other category or vehicle, as may be specified
by the Central Government by notification in the Official
Gazette from time to time, shall be equipped or fitted by the
vehicle manufacturer, either in the manufacturing stage or
at the dealership stage, with a speed governor (speed
limiting device or speed limiting function) having
maximum speed of 60 kilometre per hour conforming to
the Standard AIS 018/2001, as amended from time to time.
11
(2) The State Government shall, by notification in
the Official Gazette, specify on or before 1st October 2015,
the categories of transport vehicles registered prior to the
1st October, 2015 which are not already fitted with a speed
governor (speed limiting device or speed limiting function),
and are not covered under the first proviso to sub-rule 1
above, that such transport vehicles shall be equipped or
fitted by the operators of those vehicles on or before 1st
April, 2016 with a speed governor (speed limiting device or
speed limiting function), having maximum pre-set speed of
80 kilometres per hour or such lower speed limit as
specified by the State Government from time to time,
conforming to the Standard AIS: 018/2001, as amended
from time to time;
Provided that the categories of transport vehicles
carrying hazardous goods and those transport vehicles that
are dumpers, tankers or school buses, registered prior to the
1st October, 2015 and not already fitted with a speed
governor (speed limiting device or speed limiting function),
shall be equipped or fitted by the operator of such vehicle,
with a speed governor (speed limiting device or speed
limiting function) having maximum pre-set speed of 60
kilometres per hour or such other lower speed limit as may
be specified by the State Government, conforming to the
Standard AIS: 018/2001, as amended from time to time.”
12
In terms of Sub-rule (2) above, the State Government had
issued a notification dated 11.8.2015, specifying the categories of
vehicles to be fitted with the devices. Thereafter, the
Commissioner for Road Safety and Transport, the second
respondent herein, is said to have invited applications from
manufacturers of speed governors - possessing the requisite Type
Approval Certificates and Conformity of Production - which were
in compliance with the AIS 018/2001 norms and certified by the
testing agencies as required under Rule 126 of the CMV Rules, to
be considered for fitment of the devices to the specified categories
of vehicles. The notice indicated a checklist of documents that
were to be submitted along with the details of eligibility and other
criteria.
The petitioner claims that on having studied the check list,
it was found that the conditions prescribed were in the nature of an
invitation to tender for supply of goods to a government or its
undertakings. And that such conditions were out of place in
respect of devices to be sold in the open market, which have the
13
requisite approval under the MV Act and the CMV Rules. And
that the conditions had no nexus with the object sought to be
achieved - in terms of ensuring the quality of the speed governors.
The petitioner had hence, by a letter dated 18.9.2015,
questioned the authority of the second respondent to issue a
checklist prescribing the several eligibility criteria and is said to
have called upon the authority to withdraw the same. It is said
that there was no response to the same.
However, the second respondent is said to have passed an
order dated 26.9.2015 permitting two manufacturers, exclusively,
to sell their products in the entire State of Karnataka on the ground
that they are the only ones who qualify in terms of the checklist.
The said manufacturers are said to have been chosen from
amongst seven, including the petitioner. It is said that though the
petitioner had not filed any application to be considered, he is
shown as one of the contenders. The first of these petitions is thus
filed questioning the propriety and legality of the actions of the
respondents.
14
3. The petitioners in the writ petitions in WP 44658/2015,
WP 43244/2015 and WP 47497/2015 are all by other
manufacturers of speed governors, who are similarly aggrieved.
4. Shri N. Khetty, the learned counsel appearing for three of
the petitioners would contend as follows:
That the second respondent has no authority to impose
eligibility criteria in the form of a check list seeking documents
from manufacturers of speed governors as a pre-requisite for them
to be registered and to sell their products in Karnataka State.
Neither the notification issued by the Central Government dated
15.4.2015, nor the notification issued by the State Government
dated 11.8.2015 mention any eligibility criteria for registration.
The second respondent has, by imposing such a check list,
negated the CMV Rules and has travelled beyond the scope of the
said Rules and has exceeded the role envisaged therein for the
State Government. By such an administrative Order, even the
Notification issued by the State Government is overshadowed.
15
It is emphasized that the only requirement of law is that the
speed governors must be approved by the four competent
authorities mentioned in Rule 126 of the CMV Rules, including
the ARAI.
The prohibition of multiple manufacturers to freely compete
in the open market and freely conduct their business in any place
in India by imposing artificial barriers created in the form of
checklist, which is not sanctioned in law, blatantly violates the
fundamental right under Article 19 of the Constitution of India to
carry on their business in accordance with law. The impugned
check list carries conditions to arrive at the eligibility, which are
of a business nature, where as the conditions imposed by the
Central Government’s requirements are purely technical in nature.
The impugned Check list is apparently tailored to ensure a
monopoly for select manufacturers in the business and to
eliminate manufacturers such as the petitioners who are not in a
position to meet the high financial turnover and other such
16
conditions or criteria - prescribed in the checklist. It is pointed out
that the rule being implemented throughout the country only at
this point of time, all manufacturers being expected to have a large
turnover and volume of sales, is an illogical pre-requisite.
That in a federal set up, if the mandate of Rule 118 of the
CMV Rules is complied with, then no separate registrations
should be required in the State based on further extraneous
conditions, because it would create an anomalous situation
whereby a Central law and its mandate would be obviated by an
administrative order of a departmental head. Besides, an
incongruous situation of the same speed governor being a valid
item for sale in one State, yet would not be permitted to be sold in
another State.
By fixing a time frame for the registration of manufacturers
of speed governors, is again an ingenious manner of eliminating
the several manufacturers situated all over the country, every one
of whom may not even have been aware of the notice issued by
the second respondent in a local newspaper, of the unusual
17
procedure adopted, is another aspect that would vividly disclose
the mala fides and the evil designs of the second respondent.
The learned counsel hence seeks that the petitions be
allowed as prayed for.
5. The learned Additional Advocate General, Shri
A.S.Ponanna, appearing for respondents nos.1 and 2, would on
the other hand, contend that it is indeed a fact that pursuant to the
amendment to Rule 118 of the CMV Rules, the State Government
had issued the notification dated 11.8.2015, specifying the
category of vehicles which are registered before 1.10.2015 and are
not already fitted with speed governors shall be equipped with the
same, with a pre-set speed limit of 80 kmph, confirming to the
Standard AIS 018.
It is stated that the provisions of the MV Act, which
provides for limits of speed, does grant powers to the respondent -
State Government to frame Rules for the purpose of carrying into
effect the said provisions. Fixing the eligibility criteria for
18
registration of manufacturers for supply and installation of speed
governors was a step in aid of ensuring the effective
implementation of the same. It is further claimed that the Ministry
of Road Transport and Highways, had by a communication dated
21.8.2009, issued directions to all the State Governments, inter-
alia, as hereunder :
“4. The whole issue has been examined in this
Ministry and it is felt that the fitment of speed governors
can take place in an effective manner if the following steps
are taken:-
a) That the adequate numbers are made available
uniformly all over the State.
b) That the good quality product is available for the
vehicle owners as directed by Hon’ble High Court.
c) That fly by night operators and sub-standard
manufacturers are avoided.
d) That consistent and uninterrupted supply is
maintained.
e) That full system of transparency is maintained by
incorporation of efficient MIS system.
f) That the vehicle so selected can be made
obligated to meet the requirement failing which a stiff
penalty can be imposed on the vendor which will safeguard
the State Government obligations.
19
g) That the accountability will thus increase and the
State Government can focus on the effective monitoring
and enforcement of the legislation for public safety.
h) That MIS data / reports can be generated for
effective implementation of the speed governors through
software to be provided by the selected vendors.
i) Tampering issues are curtained with proper
technological developments and implementation.
j) That AMC is properly undertaken.
5. The above process can take place, if a suitable
tender is invited with suitable eligibility criteria keeping in
view the above mentioned points.”
In the absence of a mechanism or other guidelines to
implement the speed governor regime, the State Government
having taken the initiative to prescribe criteria for the selection of
eligible manufacturers, is in line with the above directions of the
Ministry.
The petitioners had all obtained check lists prescribing the
criteria and conditions, including the petitioner in the first of the
petitions. It transpires except two of them, the rest had submitted
particulars. It was found that only two entities met all the
20
requirements. The result of the verification carried out by the
second respondent is disclosed in a tabular form thus:
Sl.No. Name & address of
the Company /
Organisation
Whether the
conditions of
check list
have been
fulfilled?
If not, which
are the
conditions
not fulfilled
Whether
eligible to
permit for
fitment of
speed
governors as
per the check
list?
1) M/s. Hovel Scale &
Systems E/1,
Maharani Plaza,
102, Hari Nagar,
Ashram,
New Delhi
-110 014.
No Sl.No.1(a)
(b) (f), 2, 3,
4, 8, 9, 10,
11 & 12
No
2) M/s. Micro Autotech,
31, FIE, Patpargunj
Indl. Area, Delhi-110
092.
No Sl.No.1(a)
(b)(f), 2, 3, 4,
8, 10, 11, 13,
14 & 15
No
3) M/s. CONVERTZ
Technologies (I) Pvt.
Ltd., Plot 794, 37-
18/28, Rajyalakshmi
Complex, 1st Floor,
Defence Colony,
Sainikpuri,
Secunderabad.
No Sl.No.1(f), 2,
3, 8, 10 and
11
No
4) M/s. PRICOL
Limited, Plant No.1,
Perianaickenapalyam,
Coimbatore.
Yes -- Yes
5) M/s. Rosmerta
Autotech Pvt. Ltd.,
Khasara, No.19/28,
Kapshera, New
Delhi-110 037.
Yes -- Yes
21
6) M/s. Ecogas Impex
Pvt. Ltd., Factory
Address: Shop No.5,
Plot No.43, DLF
Indl. Area, Phase-I,
Faridabad, Haryana –
121 003.
No Sl.No.1(f), 2,
3, 4, 5(a), 8,
10 & 11
No
7) M/s. Autograde
International Pvt.
Ltd., 35/334,
Mamangalam,
Church Road,
Palarivattom, Kochi-
682 025, Kerala.
No
documents
have been
submitted.
No No
Accordingly, the companies named at serial nos.4 and 5
above were identified as being eligible for fitment of speed
governors to transport vehicles in the State of Karnataka.
It is further stated that the following issues were to be
addressed in the wisdom of the State by putting in place a fool
proof mechanism to strictly implement the Rule regarding speed
limit.
To ensure road safety and keeping in view the issues faced
in the past, during implementation of Speed Governors in various
States where Speed Governors were already mandatory, namely:
22
1) Non fitment and Issue of Fake Fitment Certificates:
Speed Governors were fitted only with a view to obtain
registration and fitness certification. As there was no proper
checking for want of personnel at the RTO level to ensure that the
Speed Governors were really fitted, many were found engaged in
issuing fake fitment certificates based on which vehicles were
registered or fitness certified.
2) Tampering and Removal of Speed Governors after
Registration: After registration/fitness certification, the Speed
Governors fitted were either tampered or disconnected. With lack
of enforcement, the operators of such vehicles who had either
tampered or disconnected the Speed Governors went unnoticed
and unaccounted for.
3) Recycling of Speed Governors already fitted: Speed
Governors fitted on one vehicle would be removed and fitted on
another vehicle to enable registration and to obtain a fitness
certificate. There was no control and monitoring mechanism to
23
link the Serial No. of the Speed Governor to the Registration No.
of the Vehicle.
4) Improper and Incomplete Fitment of Speed Governors:
As the vehicles fitted with Speed Governors were not subject to
any functional tests, “Fly by Night” manufacturers of Speed
Governors involved in fitting incomplete and non functional
Speed Governors had mushroomed. Road side mechanics and
untrained people were found installing the Speed Governors
eventually resulting in the Speed Governors not functioning
properly. There was no control mechanism to ensure that the
fitment was done only at Authorised Fitment Centres which
would maintain the records of Fitment and Servicing which could
be made subject to inspection.
5. Fitment of Speed Governors Models different from the
Type Approved Model: As per AIS 037, only a Type Approved
Speed Governor was allowed for fitment. Many unscrupulous
operators would obtain a particular speed governor type approved
24
and manufacture a wholly different version of the same
compromising on the quality of the components which was
critical to quality, like the sensor, solenoid valves, motor actuators
etc. and the same were sold. The changes made in the product
was neither communicated nor validated by the Testing Agencies.
There was no mechanism to ensure that only the Type Approved
Speed Governors were made available in the market.
6. Fitment of Non Approved Speed Governors: According
to AIS-018, a particular make and model of Speed Governors that
had been tested and approved by an authorized testing agency on
a particular make and model of the vehicle at a pre-set speed was
only allowed for fitment of that specific make and model of
vehicle for that pre-set speed. As there was no proper mechanism
for the implementing agencies to check if a particular
manufacturer had the requisite approval, non approved speed
governors were routinely fitted on vehicles by unscrupulous
manufacturers. This defeated the whole purpose of the Speed
25
Governors legislation which required that the Speed Governors
must conform to AIS 018 Standard amended from time to time.
7. Lack of Stringent Type Approval & COP norms: While
the testing agencies issue the type approval certificates based on
testing the samples for the provisions in AIS-018, the lack of
proper pre-qualification criteria allowed any company to obtain a
type approval. In many cases, the companies that had secured the
Type Approval did not even have a proper design and
manufacturing facility. This lead to manufacture and supply of
sub standard speed governors. The COP period was 2 years and
did not consider the number of Speed Governors manufactured.
There was no provision or empowerment for the Testing Agencies
to collect samples from the market or do surprise inspections on
suspect manufactures, based on market feedback to ensure that
only the Type Approved Products were manufactured and
supplied.
26
8. Lack of After-sales Warranty and Service Support:
Manufacturers selling sub standard Speed Governors to the
vehicle operators at low costs did not provide any after-sales
service support nor did provide a warranty. Because of this, the
Vehicle Operators suffered, sometimes to the extent of their
vehicle becoming inoperable. There was no mechanism to ensure
that servicing was undertaken by authorized service centers of the
manufacturer and no service records were maintained. Moreover,
there was no mechanism or guideline to ensure that maintenance
was undertaken and honoured to ensure that the speed governors
fitted on vehicles remained operational.
9. No Centralised Data base: There was no integration of
the Speed Governors information with the National Data base of
vehicles (VAHAN) and there was also no mechanism to capture
and integrate the vehicle data base and the Speed Governors
information at State Levels. In such a scenario, when the rule
was applicable all over the country, it was essential to have a
27
centralized database for enabling better enforcement and
implementation.
10. Loss of Revenue to the Governments 1and non
accountability of the manufacturers: Many of the manufacturers
involved sold Speed Governors without any proper invoices or
bills, to avoid taxation. Such vendors were also not registered for
purposes of taxation and did not provide any information about
their dealer network and service and maintenance network. This
had resulted in loss of revenue to the Governments and
additionally the manufacturer was totally unaccountable as there
was no documentary evidence of the sales.
In the light of the above , it is contended that the action of
the State was prompted by the best of intentions to ensure road
safety and effective enforcement of the law.
It is also pointed out that the first of the petitioners had not
furnished any particulars as to its eligibility. However, from the
28
material now brought on record would indicate that the said
petitioner does not even meet the minimum requirement of
specification relating to the speed governors required and
admittedly cannot match the other criteria prescribed.
Hence, the learned Additional Advocate General seeks the
dismissal of the petitions.
6. The learned Senior Advocate, Shri Udaya Holla,
appearing for the counsel for the third respondent contends as
follows.
That the speed governors manufactured by the third
Respondent are tested and approved by the International Centre
for Automotive Technology, Manesar, which is one of the testing
agencies approved by the Central Government under Rule 126 of
the Central Motor Vehicle Rules, 1989.
Further, it is contended that pursuant to the order dated 26th
September 2015, the third Respondent has submitted a bank
guarantee of Rs.50 Lakh to the Transport Department. The third
29
Respondent has also appointed distributors and dealers in the
entire State of Karnataka and has provided such distributors and
dealers with sufficient stock of speed governors to ensure smooth
supply and fitment of speed Governors in the State.
On having come to know of the filing of this petition, it is
stated that the third Respondent filed an impleading application
dated 5th October 2015, which came to be allowed on 9
th
November 2015.
Further, it is contended that the State of Karnataka has laid
down fifteen mandatory eligibility criteria and terms and
conditions for selecting speed governor manufacturers in
pursuance of the Central Government Notification dated 15th April
2015 and that the said eligibility criteria has been duly followed
by all the manufacturers except the petitioners herein. The
petitioners have failed to submit any documents and are presently
seeking the indulgence of this Court to allow their entry, in
30
violation of the eligibility criteria laid down by the second
Respondent.
Further, it is contended that the petitioners herein are
attempting to gain a backdoor entry into the selection process after
having admittedly failed to submit any documents as mandated
under the checklist. Hence, if the petitions are allowed, the same
would lead to denudation of the third Respondent’s rights that
were vested and concluded pursuant to the selection process and
would lead to discrimination between other manufacturers, since
the third respondent along with the other selected manufacturer
had followed the mandates of the checklist, whereas the
petitioners have admittedly failed to comply with the checklist
conditions.
It is pointed out that it is settled law that if the Court is
satisfied that there is nothing arbitrary or unfair in a selection
process, it cannot substitute its wisdom to a technical committee
and find out whether the act of the State is within the regulatory
31
framework, when such regulation is towards proper
implementation of the Notification. After all, the object of
eligibility criteria in a selection process in most matters is to
satisfy the implementing authority that persons who undertake to
execute the work would be really competent to implement the
work, to the best of their ability. In view of the aforesaid reasons,
it is contended that the petitioners have filed the instant writ
petitions with the mala fide intention of gaining ulterior advantage
of the jurisdiction of this Court into interfering with first and
second Respondent’s valid and legitimate selection process and
thereby illegally paving way into being selected as one of the
manufacturers.
Further, it is contended that it is also settled law in India
that if a decision relating to a selection process is bona fide and is
in public interest, courts will not, in exercise of power of judicial
review, interfere even if a procedural aberration or error in
assessment or prejudice to a manufacturer is made out and that
32
power of judicial review should not be permitted to be invoked to
protect private interest at the cost of public interest.
Further, it is contended that the petitioners have failed to
fulfill the requirements of the eligibility criteria. The Petitioners,
only to make good the financial loss that they may incur due to
their failure to submit the requisite documents, have approached
this Court to satisfy their private interest at the cost of the public
and other eligible manufacturers, thereby delaying the
implementation of the Notification dated 11th
August 2015
bearing No.SARIE 107 SAESE 2014. Thus, it is clear that the
Petitioners have approached this Court with unclean hands and the
petitions are a pedestal of mala fide intention.
Further it is contended that it is the settled position of law
that the Government and its undertakings must have a free hand in
setting terms of a selection procedure and the jurisdiction of the
courts ought not be invoked to interfere with the terms of the
33
selection prescribed by the Government. The first and second
Respondents, as implementing authorities, are required to ensure
that the scheme of fitment of speed governors is effectively
implemented. It is with this sole objective that the State had
issued a check-list with eligibility criteria for registration of
manufacturers for supply and installation of speed governors in
the State of Karnataka. The right of the State to choose the most
competent manufacturer is its prerogative. Further, that for
effective implementation of the Rule, the manufacturer must
inter-alia possess sound financial and technical capacity. And
that the conditions are prescribed by the State only to adjudge the
capability of a particular manufacturer who can provide fail-safe
and sustainable delivery capacity.
Hence, it is contended that the power of judicial review of
the courts must not be permitted to be invoked to protect private
interest, at the cost of public interest. And that the present
petitions are a clear attempt by unsuccessful manufacturers with
34
an imaginary grievance and business rivalry to persuade this
Court to interfere with the terms of the selection procedure by
exercising the power of judicial review. Such interference should
be resisted, as the ultimatum of such an action would result in
holding up public works for years, or delay relief and aid to
thousands and millions and may increase the project cost
manifold.
Lastly, it is contended that where the State is dealing with
the public, the same has to be conducted by way of a prescribed
set of rules and procedures which are required to be satisfied by
every interested manufacturer and where a manufacturer is unable
to satisfy the prescribed requirements, they cannot approach the
courts as a last resort, with the mala fide intent of obtaining a
backdoor entry into the already concluded selection process, to
interfere with the procedure determined by the implementing
authority. As a result, the interest of the public at large is at stake
and also that of the other qualified manufacturers who are
discriminatorily affected to their detriment.
35
Shri Holla would support the arguments on behalf of the
State and seek dismissal of the petitions.
7. By way of reply, Shri Khetty would contend that the
contention of respondents nos. 1 and 2 that they trace their power
to fix the eligibility criteria for registration of manufacturers for
supply and installation of speed governors, to the provisions of the
MV Act and the CMV Rules, it is pointed out is not tenable. On
the other hand, by virtue of Section 111(1), the power of the State
Government is specifically excluded with regard to Section 110(1)
of the Act. Besides, the notification issued by the second
respondent was an administrative Order and not even a rule.
It is contended that it is also misleading that the criteria has
been fixed pursuant to directions issued by the Ministry of Road
Transport as per circular dated 21.8.2009. The said Circular has
been superceded by a further communication dated 6.4.2011, to
particularly clarify that it was advisory in nature. And in any
36
event, the said guidelines did not contain conditions such as the
requirement of a minimum turnover of the manufacturer to be a
minimum of Rs.50 Crore, nor did it contemplate the minimum net
worth of the entity to be a certain amount. These and other such
conditions introduced by the second respondent as if imposing
conditions which may have been relevant even while inviting
tenders, which again would have been questionable, were totally
out of place.
It is sought to be demonstrated that in so far as the third
respondent is concerned, with reference to its Balance Sheet for
the year 2013-14 that it has sold speed governors of a value of
Rs.24.23 crore and going by the price of its speed governors, at
approximately Rs.10,000/- each, it had produced and sold a little
over 24,000 units in the entire year. This is only one month’s
production as stipulated in the Check list issued by the second
respondent. In that, it is contended, that the production capacity
being a criterion is hardly met by the third respondent. And
37
further, for a private sale in the open market the production
capacity of a manufacturer of speed governors duly approved
under AIS 018/2001 is of no concern to the Respondent nos. 1
and 2, as it has no bearing on the quality of the product.
It is emphasized that one important feature, namely, the
price of the speed governor is not at all a consideration in the
check list that is provided by the second respondent. In the result,
the two manufacturers that are now chosen by the said respondent
have a free rein on the market and have been enabled to dictate a
price at which every transport operator, who is required to install a
speed governor, is compelled to pay whatever the price is.
As regards the several factors named by respondent nos.1
and 2 as regards the need for stringent conditions being imposed
in the selection of manufacturers, it is argued that the same are
either the making of the office of the second respondent or are
trivial in nature which could be addressed with minimal effort.
38
8. On a consideration of the rival contentions, the points for
consideration are:
1. Whether the second respondent had the authority
sanctioned by law, to invite applications for registration of
manufacturers to exclusively supply and install speed governors
on the vehicles specified in terms of Rule 118 of the CMV Rules
and notifications issued pursuant thereto.
2. Whether the conditions and criteria prescribed in the
Check list issued by the Commissioner for Transport & Road
Safety, had any nexus with the object sought to be achieved in
terms of ensuring the quality of speed governors.
3. Whether the said exercise has resulted in the petitioners
being deprived of their fundamental right to carry on their
business in the State of Karnataka.
4. Whether the respondents 1 and 2 have created artificial
barriers to eliminate the petitioners from selling their products in
Karnataka.
39
5. Whether it could be said that there is any apparent intent
on the part of the second respondent to appease and favour
selected manufacturers.
9. In so far as the relevant provisions of the Act and Rules
are concerned, it is to be noticed that on 15.4.2015, the Central
Government notified in the Gazette the amended Rule 118 of the
CMV Rules. By virtue of the same, it was made mandatory, after
1.10.2015 for every transport vehicle, notified by the Central
Government under Section 41(4) of the MV Act, to be equipped
or fitted with a speed governor by the manufacturer of the vehicle,
having a pre-set speed limit of 80 kmph, conforming to the
Standard AIS 018/ 2001.
Certain transport vehicles namely, two wheelers, three
wheelers, quadricycles, four wheeled passenger vehicles with a
gross weight below 3500 kg, fire tenders, ambulances and police
vehicles, were exempted and were not required to be so fitted with
a speed governor.
40
Certain transport vehicles, manufactured after 1.10.2015,
namely, dumpers, tankers, school buses and vehicles carrying
hazardous goods, were to be fitted with a speed governor by the
manufacturer of the vehicle, with a pre-set speed limit of 60 kmph.
The State Government was required to notify in the Official
Gazette, on or before 1.10.2015, the categories of vehicles - other
than the exempted vehicles mentioned above, which shall be fitted
with a speed governor, on or before 1.4.2016, with a pre-set speed
limit of 80 kmph.
Transport vehicles carrying hazardous goods, dumpers,
tankers or school buses, registered prior to 1.10.2015 and not
already fitted with a speed governor, were required to be fitted
with one, by the operator of the vehicle, with a pre-set speed limit
of 60 kmph.
The State government was thus required to specify the
categories of vehicles registered prior to 1.10.2015, which were
required to be fitted with a speed governor.
41
By a notification dated 11.8.2015, the Karnataka State has
specified the transport vehicles, registered before 1.10.2015,
which were to be fitted with a speed governor by the operator of
the vehicle, before 1.4.2016.
At the hearing, the learned Additional Advocate General
has furnished the following particulars of the number of vehicles
(as on 31.8.2015) in each category so notified which would
require to be fitted with a speed governor.
Sl.No. Class of Vehicles No. of vehicles
1. Omni Buses 125121
2. Multi Axled Articulated Vehicles 62743
3. Trucks and Lorries 218536
4. Stage Carriages 39837
5. Contract Carriages 2594
6. Private Service Vehicles 15245
7. Educational Institution Buses 17352
8. Other Buses 8981
9. Maxi Cab 78221
10. LMV – Goods Vehicles 4 wheeler 217721
TOTAL 786351
Thereafter, a public notice dated 19.8.2015 was issued by
the Commissioner of Transport, also published in a daily
newspaper dated 5.9.2015, inviting speed governor manufacturers
42
holding Type Approval Certificates and Conformity of
Production, complying with AIS 018/2001 norms. The applicants
were required to meet conditions and eligibility criteria as per a
Check list prescribed by the said authority.
The said check list is reproduced hereunder for ready
reference.
ELIGIBILITY CRITERIA FOR REGISTRATION OF
MANUFACTURERS FOR SUPPLY AND INSTALLATION OF SPEED
GOVERNORS IN THE STATE OF KARNATAKA.
Sl.
No. Eligibility Criteria
1. The Manufacturer must be an Indian Company and registered with the
Registrar of Companies as per Companies Act, 1956.
1. Copy of Company Incorporation
2. Copy of Memorandum of Association.
3. Copy of PAN Card.
4. Copy of Sales Tax / VAT Registration of the Manufacturing
Plant and Karnataka Branch
5. Manufacturing Address
6. Copy of Excise Registration
2. TURNOVER OF THE COMPANY – Rs. 50 Crores in the last three
financial years from the business of manufacturing, sales and service
of Speed Governors.
1. Details of Turn-over from the business of manufacturing and
selling Speed Governors.
2. Copy of Audited Balance Sheet and IT Returns for 2 years for
2012-13 and 2013-14 and statement of accounts certified by Auditor
for 2014-15.
3. NET WORTH OF THE MANUFACTURER: Net Worth of the
Manufacturer must not be less than Rs.20 Crores as on the financial
year ending March 2015.
1. Certificate from Chartered Accountant certifying the net worth.
43
2. The Manufacturer who on being selected in the State of
Karnataka for supply of Speed Governors must provide a bank
guarantee (Any National Bank) for Rs.50 Lakhs.
4. The Company be an ISO /TS 16949 Company
5. SALES & SERVICE NETWORK IN KARNATAKA: The Company
must have sales, Fitment and Service Network in Karnataka.
1. Details of Branch Address with Contact person
2. Details of Dealer Network with contact details
6. Type Approval as per AIS 018: Manufacturers should have Speed
Governors models suitable for fitment in mechanically and
electronically controlled engines and different fuel types.
1. Type Approval Certificates for the different models of Speed
Governors manufactured by the Company.
2. Suitability needs to be demonstrated to the Department of
Transport (if required).
7. Type Approval as per AIS 037:
1. Valid COP Certificates for the Type Approved Speed Governors
to be furnished.
8. Experience Certificate for award of Tender by STU / Govt.
Department excluding Public Sector Undertakings: The Manufacturer
must have supplied and fitted Speed Governors to at least one STU /
Govt. Department by means of tender directly or through its
authorized dealer for a minimum quantity of 1000 Nos.
1. Copy of the Purchase Orders along with Sales Invoices as Proof
of supply to be submitted.
9. Installed Production Capacity: Minimum 25,000 Nos. / Month.
1. Declaration regarding installed Production capacity to be
furnished.
10. Proof of Sales – Sales Statement Certificate for a minimum of 50,000
Speed Governors sold in India in the last 3 financial years (2012-13,
2013-14 and 2014-15) certified by Auditor.
11. List of Vehicle Based Approvals for Speed Governors for Vehicles
covered under the MORTH Notification dated 15th
April 2015.
1. Minimum 125 base approvals for speed limits of 60 / 80 Kmph
out of which minimum 50 Base Model Approvals required for a speed
limit of 80 Kmph.
12. Sample of Speed Governors: The manufacturer has to submit the
samples of different models of Speed Governors intended for fitment
in the State of Karnataka.
44
13. Any manufacturer whose approval / operations with respect to Speed
Governors have been suspended / cancelled / black listed by any State
Government / Central Government would not be considered in the
registration process.
14. The Manufacturer must not have been prosecuted or convicted and no
investigation should be pending against such manufacturer for
infringement of Intellectual Property Rights of any third party or entity
under the provisions of Patent Act, Copyright Act and / or Trademark
Act, as the case may be with regard to Speed Governor being
manufactured by it.
1. An undertaking in the form of an affidavit to this effect to be
submitted.
15. The Transport Department reserves the right to cancel / suspend the
approval / permission granted to the manufacturer for supply and
fitment of Speed Governors in the state if the details / information
provided by the manufacturer at the time of registration is found to be
false, misrepresented or suppressed and the selected manufacturer does
not meet the terms and conditions of the registration.
It is noticed that the petitioner in the first of these petitions
was earlier known as, M/s Aasma Techno Products Private
Limited. And during the year 2011, the very second respondent is
said to have specified eligibility criteria and a checklist to be met
with by manufacturers of speed governors to be registered as
vendors and the petitioner had submitted his particulars against
such criteria. However, the petitioner had challenged the action of
the second respondent in seeking certain additional information,
other than was prescribed. The writ petition was disposed of with
45
appropriate directions to the respondent. But the fact remains that
the petitioner had acquiesced in the modality adopted by the
second respondent in identifying the most suitable manufacturers,
with regard to many criteria apart from the quality of the speed
governor manufactured by that entity. This may not strictly be
construed as being an arbitrary action or being an overreach by
the second respondent.
The second respondent has also been prompted to proceed
in the most prudent fashion in formulating a modality of selection
of vendors of speed governors by virtue of the tenor of the
communication dated 21.8.2009, which has been cited by the State
and produced as Annexure R-3 to the Statement of Objections.
Though the learned counsel for the petitioner has alleged
that it was fraudulent on the part of the State to place reliance on
the said communication in view of the same having been
superceded by a further communication dated 6.4.2011, a copy of
which is produced as Annexure AF-1.
46
The relevant portion of the said communication reads as
follows :
“As far as the contents of the letter are concerned,
the matter has been reconsidered in this Ministry. In this
regard it may be clarified that the letter issued by this
Ministry in August, 2009 was only to express the concern
of this Ministry regarding non-implementation of law by
the States. Besides, certain suggestions were also tendered
such as ensuring the quality of the product, availability of
adequate number of speed governors for the States,
selection of a vendor capable of producing speed governors
of specified standard, fixing the responsibility and
accountability of the vendor, tamper proof installation of
speed governor and upkeep of proper record etc.
It may be further noted that the letter dated 21.8.09,
issued by the Ministry was only advisory in nature and
certainly not binding on any State. It is always the
prerogative of the States to decide the manner in which
they would like to implement the provision in the Central
Motor Vehicles Rules, 1989. In case any State decides to
go for a tender, they may decide the terms and conditions
of the tender, as they deem appropriate.”
This would indicate that the State and its Departments were
given a free hand to effectively implement the Rule while still
47
bearing in view the concern of the Ministry and its advise.
Viewed in that light, the prescription of eligibility criteria and the
invitation for applications from manufacturers of speed governors
by the second respondent cannot be termed as illegal or
unauthorized.
Incidentally, the petitioner in the first of these petitions had
not submitted any application against the public notice issued by
the second respondent. On the other hand, it was only to protest
against the modality adopted the petitioner had written to the
second respondent questioning his authority to do so.
Insofar as the time limit prescribed by the second
respondent, in the public notice, for the manufacturers to furnish
particulars is concerned, the contention that the same may not
have received wide publicity for many manufacturers to
participate, is not tenable as it is seen that manufacturers from
Delhi, Haryana, Secunderabad, Coimbatore and Kochi have
responded. And they have not found it difficult to furnish
particulars in time.
48
In considering the question whether there is a nexus
between the eligibility criteria prescribed and the object sought to
be achieved, it would be unwise for this court to substitute its
wisdom for that of the competent authority, who would have the
benefit of technical and financial advisors as to the most effective
manner of implementation of a Rule. When under a regulatory
frame work, the action of an authority is questioned, and when the
action complained of is purportedly aimed at better
implementation of the Rule, this court would refrain from
interfering with such action. The insistence of the State to search
for an experienced manufacturer with sound financial and
technical capacity cannot be misunderstood.
Even otherwise, it is seen that the petitioners are not in a
position to claim that they are on par with the selected
manufacturers. It is noticed that the petitioners do not appear to
be manufacturing speed governors, duly certified, with a pre-set
speed limit of 80 kmph. They would therefore be ineligible even
on a primary technical requirement, even if the check list was
49
restricted to address the quality and specifications of the speed
governors manufactured by the petitioners.
Having regard to the above circumstances, it cannot be said
that there is any willful denial of the right of the petitioners to
carry on their business in the State of Karnataka. Such a situation
is a fall out of the modality that is adopted by the respondents in
identifying the more eligible manufacturer to meet the
requirement. In the process, the petitioners having been found
less qualified, cannot be a ground to claim mala fides on the part
of the respondents. The second respondent cannot also be accused
of creating artificial barriers to eliminate the petitioners from
carrying on business in Karnataka State.
There are no apparent circumstances to indicate that there is
an unholy nexus between the second respondent and the selected
manufacturers.
50
The writ petitions are accordingly dismissed as being
devoid of merit.
Sd/-
JUDGE
KS *