Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
IN THE HIGH COURT OF SOUTH AFRICA (TRANSVAAL PROVINCIAL DIVISION)
Case no. 27415/2008 ROYAL NORTHLANS GOLF AND COUNTRY
ESTATE (PTY) LTD (REG NO 1997/01748/07) APPLICANT
And
BELA BELA LOCAL MUNICIPALITY RESPONDENT
JUDGMENT
MAVUNDLA J.
[1] The applicant has approached this Court by way of an urgent application
seeking an order in the following terms:
" 1 . That the application be dealt with in accordance with the provisions
of Rule 6(12) of the Uniform Rules of Court this dispensing with the
t ime limits and forms;
2. The respondent be ordered to reinstate the Applicant's electricity
supply in relation to account 102499/003943 on Portion 56 (a
Portion of Portion 25) of the farm Het ad 465;
3 The Responent be ordered to pay the costs of this application on a
scale as between attorney and client
4 Further and /or alternative relief."
[2] In its founding affidavit the applicant states that the purpose of the
application involves an order against the respondent for the reconnection/
reinstatement of the electricity service supply to the applicant pursuant to
an agreement in relation to alleged arrears of same and payment thereof
by the applicant to the respondent, thus settlement of the electricity
account in full 0. Respondent, contrary to the agreement without any
reason thereof, bluntly refuses to reinstate the applicant's electricity
services under circumstances which renders the application urgent.
[3] The applicant is the registered owner of Portion 56 (a Portion of Portion
25) of the farm Het Bad 465situated within the boundaries. The applicant
is since 1996 in the process of developing a golf and country estate in the
said property. Towards this end the applicant states that the parties
entered into an agreement which deals with bulk electrical services to be
supplied by the respondent to the applicant. It is further averred that its
common cause between the parties the applicant had access to electricity
supply against payment to the respondent of its prescribed tariffs(levies)
and consumption.
[4] The applicant states that the electricity supply to itself was disconnected
by the respondent on 26 February 2008, the applicant not having paid its
account. A variety of visits to the respondent's offices and subsequent
negotiations between itself and the respondent as well as the applicant's
attorneys, which related not only to the electricity supply, but to further
unrelated disputes not relevant for purposes of this application.
[5] The applicant further avers that during the course of negotiations since
March 2008, the applicant endured not having electricity supply to its
premises. The applicant further avers that during April and again in May
2008 it received very disturbing electricity accounts on its municipal
account. The electricity average consumed by the applicant in rand value
averaged approximately R20, 000,00 Per month. The April and May
account however indicated approximately R99 000,00 added to the
electricity consumption at the applicant's premises It avers that the
respondent was clearly wrong in this regard.
[6] According to the applicant the dispute pertaining to the electricity, together
with certain other disputes, unrelated to the present application but to the
development as a whole, including property rates and taxes and but
services installed on behalf of the respondent by the applicant. Culminated
in the applicant's decision to call a meeting with duly authorised
representatives of the respondent with a view to air all possible disputes
between the parties and in an attempt to finalise same.
[7] The applicant further avers that the reason why during the early parts of
May 2008 it decided to endeavour to settle all outstanding issues between
itself and the respondent resulting from the applicant's endeavours is that:
7.1 During April 2008 the applicant for reasons unrelated to this
application, settled all monetary issues outstanding between the parties
ant the appl icants professional team, causing the contractual relationship
that existed between the applicant and its professional team, causing the
contractual relationship that existed between the applicant and its
professionals to cease.
7.2 The applicant successfully negotiated and concluded a service and
construction agreement with a Malasian company, AL-AMBIA SDN.
BHD.to
7.2.1 rectify and complete the installation of the internal services; and
7.2.2 construct 460 golf and residential villas on the Royal Northland &
Golf Estate proclaimed township; and
7.2.3 redesign (with Gary Players's assistance) and upgrade the
Warmbaths Golf course and club (forming part of the development as a
whole)
7.2.4 The agreement as stated above, was reached after two visits from
the foreign contingent and executors of the financier (EXIM BANK
(MALASIA); The date of the company's representatives' arrival and
subsequent planning and construction process is set for 20 June 2008.
The 'time line" planning involved careful consideration and recruitment of
local contractors and sourcing of materials for the construction process.;
the applicant had as a matter of urgency to f inalise (if possible) the
outstanding disputes as between itself and the respondent. With the
construct ion date in mind, the applicant thus caused upon its attorneys to
arrange a meeting with all relevant role-players from the respondent at
their earliest convenience.
[8] The applicant further al leges in its affidavit that there was a meeting
between the parties with their respective representatives on 21 May 2008.
The applicant further avers that after some serious debate between the
parties it was agreed that the respondent shall investigate the dispute
regarding electricity account, and the respondent would revert to the
applicant within 24 hours. The applicant shall record all other issues and
its view on such issues and that the respondent shall after investigating
and reschedule a meeting for bon f ide negotiat ions to finalise all
outstanding matters. It was further impressed on the respondent 's
representat ives that due to the arrival of the Malasian construction team
during mid-June 2008 dispute should and must be finalised as a matter of
extreme urgency to determine the applicant's indebtedness in respect of
the electricity account so as to enable the applicant to settle its inbtedness
to the respondent. The applicant further state that the electricity account
was dealt with separately due to the fact that the other issues were
unrelated to the electricity bill and this was confirmed by its attorneys on
26 May 2008 which letter is marked annexure E. On 29 May 2008
(attached and marked annexure F) the respondent furnish it with a
breakdown of the electricity account and advised that as per its "Credit
Control policy, the outstanding balance must be settled in full before
services can be reinstated "
[9] The applicant further state that on 30 May 2008 it caused a payment in the
amount of R45684, 00 to be made, which is the amount on the
respondent's version is the applicant's current indebtedness in relation to
the electricity consumption and charges. The applicant has however
stated that annexure "F" indicates a credit for electricity consumption that
amounts to R97 609, 34. On the 30 May 2008 the respondent through Ms
Baartman bluntly stated that there was no agreement existing in terms of
which the respondent is obliged to "switch on the electricity again." The
respondent subsequently stopped in dismay of the response of Ms
Baartman stopped payment of the aforementioned payment. The
respondent further states that it would serve no purpose to settle the
electricity account, if other disputes, relating to approximately R6.8 million
cannot be resolved prior to 20 June 2008. The applicant further states that
there is no legal nor factual basis for the respondent to renege on the
agreement to reactivate the electrical services at the property of the
applicant. It is however the applicant's view that it has settled the
electricity account.
[10] With regard to urgency the applicant states that should the matter not be
heard before 20 June 2008 the applicant's contractors will lose faith in the
development process, with an international embarrassment and this in
turn might cause the applicant irreparable monitory damage. It further
states that the consequences of respondents action resulting in no
electricity available to the applicant to pursue its construction, is self
evident. Ultimately the respondent stands to gain 460.
[11] The respondent is opposing this application. In its opposing affidavit its is
stated inter alia that its common cause that the applicant and the
respondent have entered onto a service agreement on or about 20
August 1998. In terms if the agreement , the applicant was responsible for
the payment of property tax at the prevailing tariffs and the applicant had
access to electricity supply against payment to the respondent of the
prescribed tariff (levies) and consumption.
[12] It is stated further by the respondent that as far back as the 20 September
2007 the applicant and the respondent had a meeting regarding the
applicant's outstanding balance owing to the respondent in the amount of
R1 700 000, 00, The respondent indicated to the applicant that it was
willing to accept R1 100 000, 00 payable immediate payment of an
amount of R550 000, 00 thereafter upon payment of a further amount of
R550, 000, 00 Payable in three equal instalment. The respondent set out
this position in two separate letters dated 27 September 2007 and 30
October 2007. The respondent further informed that applicant that its
water and lights must be paid to date since its credit control measures will
be taken on the payment of this account and that failure to honour this
agreement would lead to the respondent reversing the whole agreement.
The respondent adopted a credit and debt collection policy in terms of
section 96 of the Municipal System Act, Act 32 of 2000, The respondent
further states that it informed the applicant on various occasions in writing
of the fact that non-compliance with the aforesaid agreement would lead
to the respondent implementing its credit control policy on the applicant's
accounts with itself. Save for the payment of only R550 000,00 the
applicant failed to honour the agreement by not paying the rest of the
outstanding amount of approximately R1 200 000, 00 on time. On 22
January 2008 the respondent informed the applicant that due to the
applicant's dishonouring of the agreement the applicant was reversing the
whole of the agreement and the full outstanding amount would be due
and that the respondent had no alternative but to introduce its credit
control policy. The respondent further informed the applicant that it will
therefore be disconnecting the electricity supply to the applicant as from
22 January 2008. Apart of the payment of the amount of R550 000,00 the
respondent did not receive further payment between October 2007 and
January 2008 Subsequently the respondent terminated the electricity
supply in February 2008. On 11 March 2008 the respondent informed the
applicant that due to the applicant's dishonouring the previous agreements
the respondent had no alternative but to implement its credit control policy,
notwithstanding the receipt of payment of an amount of R 106 815, 09
which was received on 31 January 2008
[13] With regard to urgency the respondent points out that the electricity was
terminated on 26 February 2008 and was fully aware of the respondent's
credit control policy regarding reconnection. The respondent further states
that the application is premature.
[14] Counsel for the applicant has referred me to, inter alia, to the Mandarina
Trading 488 CC v Bela Bela Local Municipality unreported judgment of
Br. Justice Van Der Merwe which dealt with the aspect of property tax
levied by the Local Authorities on properties. I am of the view that the
relevant case is not apposite to this particular case which relates to the
issue of reconnection of the electricity supply to the applicant. The
submission made on behalf of the applicant is, inter alia, that the accounts
issued by the respondent not only for the 13 individual erven, but also for
portion 56, in the absence of a lawful entitlement thereto, cannot create a
right to receive such taxes or an obligation to pay same. This submission,
in my view goes against the very application of the applicant who primarily
seeks an order compelling the respondent to reconnect the supply of
electricity to the applicant. The effect of such an order would result in a
situation in terms of which the applicant is supplied with electricity which in
turn it consumes but refuses to pay towards such supplied electricity
because, according to it, the respondent does not have a lawful
entitlement thereto and can therefore not demand for the payment of such
supplied electricity.
[15] In the letter of the applicant's attorneys of record dated 26 May 2008
(annexure E) it is conceded that the applicant has not had electricity
supplied to it since from 26 February 2008. It therefore is common cause
that the electricity supply to the applicant was disconnected since about
26 February 2008. It is common cause that this application was only
launched on 6 June 2008. Approximately more than 15 weeks after such
termination. Once the applicant decided to embark on the cause of
settlement, the applicant lost out its right to approach this Court on urgent
basis for reconnection of the supply of electricity. Besides the applicant
concedes that there still remain issues in dispute between the parties. I
therefore hold the view that the application is not urgent and it must be
dismissed for this reason.
[16] In the matter ZULU v MINISTER OF WORKS KWAZULU, AND OTHERS
1992 (1) SA 181 (D &CLD) at 190F-H at Thirion said that:
"I am of the view that since the appl icants use the water did not
constitute the use of a servitutal right and since any right which the
applicant might have had to have water supplied to him did not
constitute an incident of his possession or control of a corporeal
thing (i.e. his dwelling house), it would not be competent to grant a
spoliation order ordering the respondents to resume supplying the
applicant with water. To hold otherwise would in effect mean that
the Court would grant an order for specific performance of a
contractual obligation in proceedings the respondent is precluded
from adducing evidence to disprove the existence of the obligation.
If a spoliation order were to be competent in the present case and
were to be granted, the respondent would have to Court and obtain
judgment author sing them to terminate the supply of the water. If
they fail to convince the Court that they have a right to terminate
the water supply they would presumably be compelled to pump
water free of charge to the appl icants house for ever." Vide also
TELKOM SA Ltd v XSINET (Pty) LTD 2003 (5) SA 309 at 314G
paragraph [14].
[17] I am of the view that what is said by Thirion J I in the above quoted
paragraph is apposite to this matter The applicant has conceded that
there is a dispute about the electricity account and the parties have not
settled such dispute. To order the applicant to reconnect the supply of the
electricity supply would be ordering the respondent to perform specific
performance of a contractual obligation, which obligation I am not satisfied
that the applicant has acquitted the onus resting upon it to discharge that it
exists. For this reason the application must fail. But also for the reason
that the application is not urgent the application must also fail. In the result
the application must be dismissed for both reasons.
[18] It is trite that costs follow the event. Consequently the applicant must bear
the costs of this application. However I do not think that this is a matter
where I must grant punitive costs.
[19] In the premises I make the following order:
1. That the application is dismissed with costs.
N.M. MAVUNDLA
JUDGE OF THE HIGH COURT
HEARD ON THE: 12/06/08
DATE OF JUDGMENT: 19/06/08
APPLICANTS ATT: Mr. BAARTMAN
APPLICANT'S ADV: MR.P ELLIS SC., with
APPLICANT'S ADV: MR. J ROUX.
RESPONDENT ATT: MR. A.P. LEDWABA.