Upload
buibao
View
216
Download
0
Embed Size (px)
Citation preview
ARKANSAS POLLUTION CONTROL AND ECOLOGY COMMISION
IN THE MATTER OF BIG RIVER
DOCKET NO. 13-006-P STEEL, LLC
ORDER NO. 4
NOTICE OF HEARING
On Thursday, November 7, 2013, a preliminary hearing was
held between counsel for Nucor Corporation, Nucor-Yamato Steel
Company (collectively "NSA"), Big River Steel, LLC ("Big River")
and the Arkansas Department of Environmental Quality ("ADEQ").
Various matters, including the establishment of a procedural
schedule, were discussed at the hearing. The administrative law
judge ("AUJ") finds:
1. The parties are entitled to be present at the hearing,
to be represented by counsel, and to present evidence and
argument on all issues properly raised in this proceeding.
2. The testimony of all witnesses will be taken under oath.
3. The hearing will be recorded by a court reporter.
4. Discovery shall be completed no later than Friday,
January 17, 2014. Discovery is to be asked and answered by this
deadline. Therefore, interrogatories are to be submitted so that
the responding party will have the time allotted under the
Arkansas Rules of Civil Procedure in which to answer by the
discovery deadline date.
5. Motions are to be filed as soon as possible but no later
than Friday, January 31, 2014. This deadline does not apply to a
DOCKET NO. 13-006-P ORDER NO. 4
PAGE 2
motion for summary judgment, which must be filed 45 days prior
to trial. Arkansas Rules of Civil Procedure, Rule 56(a).
6. During the preliminary hearing the parties discussed
the possibility of submitting pre-filed testimony in order to
expedite the hearing process. The ALJ believes pre-filed
testimony will be beneficial in understanding the issues raised
in this appeal, and requires the parties to file pre-hearing
testimony for each witness on their respective witness lists by
Friday, February 7, 2014.
7. Each party shall file with the Commission by Friday,
February 7, 2014, an original and (1) copy of the following
items and shall serve a copy on each other:
A. WITNESS LIST. A list of witnesses which shall include: (i) The name and address of each witness who will be called to testify; (ii) A summary of the testimony to be given by each witness; (iii) If the witness is an expert, a summary of the expert's opinion testimony; (iv) A separate statement by legal counsel of what is expected to be proven through each witness.
B. EXHIBITS. A list of the exhibits in the order they are reasonably anticipated to be introduced into evidence and the name of the witness that will sponsor the exhibit. However, do not pre -number exhibits. Exhibits will be numbered as they are introduced or stipulated to during the hearing.
C. STIPULATION OF FACTS. A list of uncontested facts and exhibits that the parties have agreed to stipulate to shall be provided before the hearing, if at all possible.
D. PRE -HEARING BRIEFS. A pre-hearing brief that sets forth:
DOCKET NO. 13-006-P ORDER NO. 4
PAGE 3
(i) The issues of fact expected to be contested; (ii) The issues of law expected to be contested; (iii) A summary of the facts and law that support the party's position.
E. SUMMARY JUDGMENT. If any party files a motion for summary judgment, with a response filed by the non-moving party, the parties will not be required to file a pre-hearing brief.
8. The parties are relieved from complying with the filing
requirements in Paragraph 7 if the parties file a settlement or
PAR by Friday, February 7, 2014.
9. A pre-hearing conference will not be held. If the
parties desire to have a pre-hearing conference they are
instructed to notify the Commission Secretary via email by
Monday, February 3, 2014. If a pre-hearing conference is
requested the ALJ will be responsible for arranging a date and
time for the conference, and calling the parties.
10. A hearing is scheduled for Wednesday and Thursday,
February 18-21, 2014 at 9:00 a.m. It will be held in the
Commission Room located at the Arkansas Department of
Environmental Quality, 5301 Northshore Dr., North Little Rock,
Arkansas.
IT IS SO ORDERED
This 7th day of November 2013
Administrative Law Judge
DOCKET NO. 13-006-P ORDER NO. 4
PAGE 4
CERTIFICATE OF SERVICE
I, Charles Moulton, hereby certify that a copy of the foregoing Order No. 4, In the Matter of Big River Steel, LLC; Docket No. 13-006-P, has been mailed by certified mail or by first class mail, postage prepaid, to the following parties of record, this 7 th day of November 2013.
Mark H. Allison Dover Dixon Horne, PLLC 425 West Capitol Ave., Ste. 3700 Little Rock, AR 72201
David R. Taggert Bradley, Murchison, Kelly & Shea LLC 401 Edward Street, Suite 1000 Shreveport, LA 71101-5529
Jerald N. Jones Bradley, Murchison, Kelly & Shea LLC 301 Main Street, Suite 2100 Baton Rouge, LA 70825
G. Alan Perkins John F. Peiserich Perkins & Trotter P.O. Box 251618 Little Rock, AR 72225-1618
Martin T. Booher Jason P. Perdion Baker Hostetler LLP 1900 East 9 th , Street, Suite 3200 Cleveland, OH 44114-3482
Stewart Spencer Arkansas Department of Environmental Quality 5301 Northshore Drive North Little Rock, AR 72:18
arles Moulton Arkansas Pollution Control and Ecology Commission 101 East Capitol, Suite 205 Little Rock, Arkansas 72 . 0
BEFORE THE ARKANSAS POLLUTION CONTROL AND ECOLOGY COMMISSION
IN THE MATTER OF: BIG RIVER STEEL, LLC PERMIT No. 2305-A0P-R0
DOCKET NO. 13-0Q-6-P
BIG RIVER STEEL'S MOTION FOR PROTECTIVE ORDER
The only question that is being litigated in this action is whether or not the Arkansas
Department of Environmental Quality's decision to issue an air permit to Big River Steel was in
accordance with law. Normally in such a dispute, a petitioner does not request all documents
relating to the Arkansas Teachers Retirement System. Req. for Prod. No. 4. But rather than
focus discovery on matters related to the air permit, Nucor Steel has embarked on a "fishing
expedition" of overbroad (and sometimes nonsensical) discovery, threatening to make the
administrative appeal process mimic the worst aspects of federal civil litigation. The
Administrative Hearing Officer should nip Nucor Steel's inappropriate discovery conduct in the
proverbial bud by entering the attached protective order, which will allow the parties and the
Commission to focus on the issues that actually matter in this case.
As grounds for its motion, Big River Steel states the following.
1. Pursuant to the Commission Regulation 8, all procedural matters not addressed by
Chapter 6 are governed by the Arkansas Rules of Civil Procedure. APC&EC Reg.8.611.
Chapter 6 is silent with respect to a motion for protective order. Therefore, the Arkansas
Rules of Civil Procedure govern the procedures and process required for such a motion.
2. Arkansas Rule of Civil Procedure 26(b)(1) governs the scope of discovery, providing that
parties "may obtain discovery regarding any matter, not privileged, which is relevant to
1
the issues in the pending actions, whether it relates to the claim or defense of the party
seeking discovery or to the claim or defense of any other party." Commensurately, Rule
26(c) allows the Hearing Officer to grant a protective order in order to "protect a party or
person from annoyance, embarrassment, oppression, or undue burden or expense."
3. The relevancy must be apparent from the face of the interrogatory, request for
production, or request for admission: "[T]o authorize [] production[,] there must be a
substantial showing that the book, paper, or document sought contains material evidence
in support of the cause of action or defense of the party asking for it." Bryant v. Arkansas
Public Service Com'n, 55 Ark.App. 125, 136, 931 S.W.2d 795, 801 (Ark.App. 1996)
(citing Price v. Edmonds, 231 Ark. 332, 337, 330 S.W.2d 82, 85-6 (1959)). A general
allegation of materiality is insufficient, "as this would be the averment of a conclusion
and permit the question of materiality to be decided by the applicant instead of by the
court." Id. The Arkansas Supreme Court does not sanction "outright and unadulterated
fishing expedition[s]." Parker v. Southern Farm Bureau Casualty Ins. Co., 326 Ark.
1073, 1091, 935 S.W.2d 556, 560 (1996) (citing Marrow v. State Farm Ins. Co., 264 Ark.
227, 570 S.W.2d 607 (1978)).
4. Here, Nucor Steel is appealing the Arkansas Department of Environmental Quality
("ADEQ")'s decision to issue Big River Steel a construction and operating permit for a
new $1.4 billion dollar steel mini-mill in Osceola, Arkansas. Although replete with
vague and generic allegations, as well as with claims that Nucor Steel failed to raise in
comments before the ADEQ, the crux of Nucor Steel's appeal is that the Permit does not
comply with the requirements of the Clean Air Act, as implemented through the Arkansas
State Implementation Plan.
2
5. Nucor Steel propounded its First Set of Interrogatories and Requests for Production of
Documents on November 7, 2013. See Exhibit 1. In addition to certain discovery
requests that are not wholly objectionable and to which Big River Steel will respond or
object in due course, Nucor Steel's Requests for Production Numbers 4, 5, 6, 7, and 8,
and Interrogatory Number 4, request information that is completely irrelevant to the air
permit.
6. Interrogatory Number 4 requests that Big River Steel identify "all communications . . .
relating to [Big River Steel] or [Rebel Steel] between [Big River Steel] and any other
person . . . ." Needless to say, all communications by Big River Steel necessarily
"relate[] to . . . [Big River Steel]." This request thus seeks every single communication
Big River Steel has ever had with anyone. Such a request is patently overbroad and aims
to discover wholly irrelevant information.
7. Moreover, Interrogatory Number 4 and Requests for Production Numbers 4, 5, 6, 7 and 8
request far-reaching discovery into Big River Steel's communications with persons or
entities that have no conceivable relation to the air permitting process. The irrelevant
parties are:
• The Arkansas Teachers Retirement System, which has provided limited
development capital for the project but had no involvement in the air permitting
process;
• The Arkansas Economic Development Commission, which is authorized to issue
grants to Big River Steel, but which had no involvement in the air permitting
process;
3
• The Arkansas Development Finance Authority, which has authority to issue
bonds to support the construction of the project to benefit the citizens of
Arkansas, but which had no involvement in the air permitting process;
• The Office of the Governor of the State of Arkansas, whose involvement in the
project is similar only to that of any state executive supporting the construction of
a $1.4 billion investment in its state that is projected to generate over 500 jobs
and inject approximately $250 million into the Arkansas economy;
• Grant Tennille, who is the head of the Arkansas Economic Development
Commission;
• John Correnti, the Chief Executive Officer of Big River Steel, whose
responsibilities with the Company do not include air permitting; and
• George Hopkins, who is the head of the Arkansas Teachers Retirement System.
8. Even where Big River Steel's communications with a person or entity may include some
material subject to discovery, Nucor Steel's requests are so overbroad that they would
inappropriately sweep in information that has nothing to do with Big River Steel's air
permit. Persons or parties that potentially have relevant material but also would possess
significant irrelevant material include the following:
• CV Engineering, an engineering firm engaged for general technical advice and
engineering on the project, most of the technical and financial details of which
are irrelevant to air permitting issues;
• Global Principal Partners, a business entity that is involved in managing
development of all aspects of the steel mini-mill, with air permitting issues
constituting only a small portion of its activity in relation to Big River Steel. It
4
serves as the project development management entity. It raises money and
manages the project development;
• SMS Siemag, the primary equipment provider and engineer on the steel plant,
most of the technical and financial details of which are irrelevant to air permitting
issues;
• David Stickler, Senior Managing Director of Big River Steel LLC, who is
responsible for most or all aspects of Big River Steel's operations; and
• U.S. Environmental Protection Agency, whose environmental responsibilities
extend beyond air law issues into other areas that are irrelevant to the permitting
process.
9. Moreover, Nucor Steel's broad and intrusive discovery requests threaten to require the
production of highly-sensitive business, financial, and trade secret information wholly
outside the scope of Nucor Steel's claims. Presuming good faith on Nucor Steel's part
and that the discovery of this information is not one of its motivating goals in bringing
this proceeding, the attached protective order would keep many such documents where
they belong—out of this case. Any commercially-sensitive documents that are likely to
lead to relevant information should be addressed under a separate protective order in due
course.
10. Counsel for Big River Steel contacted counsel for Nucor Steel on November 8 and 11,
2013, in a good faith attempt to resolve these issues without the Commission's
involvement. Counsel for Big River Steel was unable to come to a resolution with Nucor
Steel.
5
WHEREFORE, Big River Steel respectfully requests that the Administrative Hearing Officer
grant its Motion for Protective Order.
LC
By: Jo F. Peiserich, AR Bar #2002009 ineiserieheperkinstrotter.com G. Alan Perkins, AR Bar #91115 aperkinsOperkinstrotter.corn P.O. Box 251618 Little Rock, AR 72225-1618 Tel: (501) 603-9000 Fax: (501) 603-0556
-and-
BAKER HOSTETLER, LLP Martin T. Booher, OH Bar # 0090333 mboohen@bakerl aw.com Jason P. Perdion, OH Bar #0071089 jpardion@bakerlaw_com 1900 East 9th Street, Suite 3200, Baker Hostetler LLP Cleveland, Ohio 44114.3482 Office: (216) 861-7141 Fax: (216) 861-0740
Attorneys for Big River Steel, LLC
Respectfully Submitted,
PERKINS & TROTTER,
-4110111°..1.
6
CERTIFICATE OF SERVICE
I hereby certify that a copy of the foregoing has been sent via electronic mail to the following parties of record this j3/day of November, 2013.
Mark H. Allison [email protected] Michael Smith msmith®ddh-ar.com William Bird J)birdaddh-at.com DOVER DIXON HORNE, PLLC 425 West Capitol Ave., Ste. 3700 Little Rock, AR 72201 (501) 375-9151 (501) 375-6484
David R. Taggart dtagzart(bradleyfirm.corn Jerald N. Jones jionesahradlevfirrn.com Bradley Murchison Kelly 401 Edwards Street Shreveport, LA 71101 (318) 934-4014 (318) 2274141
Shea LLC
Stuart Spencer [email protected] Arkansas Department of Environmental Quality 5301 Northshore Drive North Little Rock, AR 72118 (501) 682-0743 (501) 682-0891
' G. Alan Perkins
7
ARKANSAS POLLUTION CONTROL AND ECOLOGY COMMISSION
IN THE MATTER OF BIG RIVER
DOCKET NO. 13-006-P
STEEL, LLC
)
ORDER NO. 8
ORDER
A. Introduction
On November 13, 2013, Big River Steel, LLC ("BRS") filed a
Motion for Protective Order. Nucor Steel - Arkansas and Nucor
Yamato Steel Company (collectively "Nucor Steel") propounded its
First Set of Interrogatories and Requests for Production of
Documents upon BRS on November 7, 2013. BRS objects to Nucor
Steel's Interrogatory No. 4 and Requests for Production Nos. 4, 5,
6, 7, and 8. BRS contends, correctly, that the subject of this
appeal is the Director of the Arkansas Department of Environmental
Quality's ("Department" or "ADEQ") decision to issue BRS Permit No.
2305-A0P-R0. BRS argues that the information and documents sought
by Nucor Steel in Interrogatory No. 4 and Requests for Production
Nos. 4, 5, 6, 7, and 8 have absolutely no relation to the air
permitting process that was undertaken by ADEQ. Specifically, BRS
objects to Nucor Steel requesting written and oral communications
between BRS and Rebel Steel and any employee, representative or
agent of:
o The Arkansas Teachers Retirement System
• The Arkansas Economic Development Commission
• The Arkansas Development Finance Authority
• The Office of the Governor of the State of Arkansas
Docket No. 13-006-P Order No. 8
Page 2
• Mr. Grant Tennille, the Director of AEDC
•Mr. George Hopkins, CEO of the Arkansas Teachers
Retirement System
• CV Engineering which was retained by BRS for general
technical advice but, according to BRS, had nothing to
do with the air permit
• Global Principal Partners, a business entity BRS
maintains is managing all aspects of the project but has
little to do with the air permitting issues
• SMS Siemag, the primary equipment provider and engineer
on the project
• David Stickler, Senior Manager of the BRS project; and
finally
• The United States Environmental Protection Agency
BRS claims that Nucor Steel's discovery is too broad, too intrusive
and BRS's responses could result in the production of sensitive
business, financial and trade secret information. BRS also posits
that Nucor Steel is a competitor and obtaining this information may
be the real underlying rationale for Nucor Steel's appeal. BRS
seeks entry of a protective order that limits the scope of
discovery in this case to issues related to the compliance of the
BRS permit with applicable Arkansas law and the Clean Air Act.
In Response Nucor does not object to the entry of a protective
order that would protect the confidentiality of business
Docket No. 13-006-P Order No. 8
Page 3
information, trade secrets, and sensitive financial information.
But, Nucor Steel maintains that these communications, particularly
communications with the various state agencies and state employees
listed in Interrogatory No. 4, are relevant to the issues Nucor has
raised in its appeal. Nucor Steel claims that the financial stake
the State of Arkansas has in this project may have resulted in
these agencies influencing the permitting process and that BRS or
these agencies may have "crossed that line." Nucor Steel claims
that, to the extent these agencies influenced, or attempted to
influence, ADEQ's processing of the BRS permit it is entitled to
discovery of those communications. Nucor Steel also maintains that
CV Engineering, Global Principal Partners, SMS Siemag and David
Stickler and USEPA were all integrally involved in the development
and issuance of the BRS permit and Nucor Steel is entitled to that
information under the rules of discovery.
The administrative law judge ("ALJ") has read the parties'
pleadings, listened to the parties' respective arguments during a
telephone conference held on Friday, November 15, 2013, and grants
in part, and denies in part, BRS's Motion for Protective Order
based on the following reasons.
B. Communications With State Agencies and State Employees
Under Ark. R. Civ. Proc. 26(b)(1) a party may obtain discovery
regarding "any matter, not privileged, which is relevant to the
issues in the pending action." A party is entitled to discovery if
the information sought is reasonably calculated to lead to the
Docket No. 13-006-P Order No. 8
Page 4
discovery of admissible evidence in support of the claims raised,
although the Arkansas Supreme Court does not sanction outright
fishing expeditions. Parker v. Southern Farm Bureau Casualty Ins.
Co., 326 Ark. 1073, 1091, 935 S.W.2d 556, 560 (1996). The ALJ
has reviewed Nucor Steel's Request for Hearing and concludes that
Nucor Steel alleged that ADEQ's permitting process was subject to
undue influence. For this reason and the fact that written
communications, such as emails or letters, between BRS and the
state agencies and state employees listed in Interrogatory No. 4
should not be privileged or confidential and are likely subject to
the Arkansas FOI law should Nucor choose to invoke it, the ALJ
denies BRS's Motion. The ALJ holds that BRS must list oral
communications, and produce written communications such as emails
or letters, between BRS and these state agencies and state
employees. However, the ALJ grants BRS's Motion and narrows BRS's
responses to Interrogatory No. 4 and Requests for Production Nos.
4, 5, 6, 7, and 8 as follows.
The ALJ finds that Interrogatory No. 4's time scope is too
broad. In fact, the only reference to a time frame is in a
footnote contained in Nucor Steel's Response, but the time frame
referenced in the footnote is not set forth in Interrogatory No. 4
or in Requests for Production Nos. 4, 5, 6, 7, and 8. The ALJ
finds that, to the extent that other agencies of the State of
Arkansas influenced, or attempted to influence, ADEQ's processing
of the BRS permit this alleged conduct could not have arisen until
Docket No. 13-006-P Order No. 8
Page 5
after ADEQ received BRS's permit application. Therefore, BRS will
only be required to produce written communications, if any, that
occurred between BRS and the state agencies and state employees
listed in Interrogatory No. 4 from January 30, 2013 to June 27,
2013 - the date BRS submitted its permit application to ADEQ and
the date ADEQ issued BRS's draft permit.
The same applies to Nucor Steel's request for oral
communications between BRS and the state agencies and state
employees listed in Interrogatory No. 4. BRS will only be
required to list oral communications, if any, between BRS and the
state agencies and state employees listed in Interrogatory No. 4
that occurred between January 30, 2013 and June 27, 2013.
C. Communications With John Correnti, CV Engineering, Global Principal Partners, SMS Siemag, David Stickler, and USEPA
Nucor Steel argues on page five (5) of its Response that these
individuals, and apparently USEPA, were integrally involved in the
development and issuance of the BRS permit. Nucor Steel also
claims that financing considerations may have played a role in the
processing and issuance of the BRS permit and therefore Nucor is
entitled this information.
The ALJ agrees that there could be a nexus between financing
and the BRS permit. The ALJ also believes that John Correnti, CV
Engineering, Global Principal Partners, SMS Sieman, and David
Stickler may have information, however slight, regarding the BRS
permit. The ALJ believes that USEPA's involvement in the BRS
permit is dubious because Nucor Steel never states how, or when,
Docket No. 13-006-P Order No. 8
Page 6
EPA become involved in the BRS permit process. Nevertheless,
communications between USEPA and BRS, if they did occur, are also
likely not privileged or confidential and are discoverable. The
ALJ therefore denies BRS's Motion as it relates to John Correnti,
CV Engineering, Global Principal Partners, SMS Sieman, David
Stickler and USEPA with two (2) caveats. The first is that BRS's
response to Interrogatory No. 4 and Requests for Production Nos. 4,
5, 6, 7, and 8 should also include a time element. According to
Nucor Steel's footnote number 2 in its Response, BRS was formed in
January, 2013. Therefore BRS is ordered to respond to Nucor
Steel's Interrogatory No. 4 and Requests for Production Nos. 4, 5,
6, 7, and 8 as it relates to these individuals and entities from
January 2013 to the present. The second caveat is that some of
these communications may fall under the umbrella of a protective
order because they consist of sensitive business, financial and
trade secret information. The ALJ is aware that the parties are
attempting to fashion a mutually agreeable protective order and is
optimistic that the parties will provide such an order to the ALJ
in the near future.
D. ALJ Guidance
The ALJ has issued the rulings set forth above with the
understanding that the rules of discovery are to be liberally
construed. However, the ALJ cautions the parties that this case
involves one paramount issue - whether Permit No. 2305-A0P-R0 meets
applicable state and federal law. The ALJ does not care what
Docket No. 13-006-P Order No. 8
Page 7
motivated Nucor Steel to file this appeal. The ALJ does not care
why BRS decided to construct its steel mill. The ALJ does not care
who may have pressured or motivated ADEQ to issue Permit No. 2305-
A0P-RO. If this were an enforcement case then ADEQ's motivation
and reasoning for issuing a Notice of Violation would play a
pivotal role. But this is a permit appeal, not an enforcement
action. The outcome of this case will ultimately rest on the terms
and conditions that are contained in Permit No. 2305-A0P-R0 and
Nucor Steel demonstrating, by a preponderance of the evidence, why
those terms and conditions do not comport with state and federal
law. ADEQ allegedly being pressured to issue Permit No. 2305-A0P-
RO; Nucor Steel's rationale for appealing Permit No. 2305-A0P-R0;
BRS's reasoning for seeking financing from the State; the
Governor's office, AEDC, Teachers Retirement System, and ADFA are
all, in the ALJ's view, ancillary to the core issue - does Permit
No. 2305-AOP-R0 meet the requirements of state and federal law?
IT IS SO ORDERED
This 19th day of November 2013
Charles Moulton Administrative Law Judge
Docket No. 13-006-P Order No. 8
Page 8
CERTIFICATE OF SERVICE
I, Charles Moulton, hereby certify that a copy of the foregoing Order No. 8, In the Matter of Big River Steel, LLC; Docket No. 13-006-P, has been mailed by certified mail or by first class mail, postage prepaid, to the following parties of record, this 20 th day of November 2013.
Mark H. Allison Dover Dixon Horne, PLLC 425 West Capitol Ave., Ste. 3700 Little Rock, AR 72201
David R. Taggert Bradley, Murchison, Kelly & Shea LLC 401 Edward Street, Suite 1000 Shreveport, LA 71101-5529
Jerald N. Jones Bradley, Murchison, Kelly & Shea LLC 301 Main Street, Suite 2100 Baton Rouge, LA 70825
G. Alan Perkins John F. Peiserich Perkins & Trotter P.O. Box 251618 Little Rock, AR 72225-1618
Martin T. Booher Jason P. Perdion Michael J. Montgomery Baker Hostetler LLP 1900 East 9 th , Street, Suite 3200 Cleveland, OH 44114-3482
Stewart Spencer Arkansas Department of Environmental Quality 5301 Northshore Drive North Little Rock, AR 72118
rleATon Arkansas Pollution Control and Ecology Commission 101 East Capitol, Suite 205 Little Rock, Arkansas 72201
ARKANSAS POLLUTION CONTROL AND ECOLOGY COMMISSION
IN THE MATTER OF: BIG RIVER STEEL, LLC
DOCKET NO. 13-006-P
PERMIT NO. 2305-A0P-R0
PROTECTIVE ORDER
Upon review of Big River Steel, LLC's ("Big River Steel") Motion for Protective Order, the
Administrative Hearing Officer orders as follows:
1. Scope. This Protective Order governs the treatment of discovery of matters that are not
relevant to the Petitioners' challenge to ADEQ's decision to issue Permit No. 2305-A0P-
RO.
2. Persons Entitled to Claim Protections. The procedures and protections set forth within
this Protective Order may be employed and/or asserted not only by Big River Steel but
also by any other party subject to discovery in this matter, including without limitation
any of Big River Steel's corporate affiliates, owners, direct or indirect investors, officers,
contractors, representatives, employees, servants, or agents.
3. Protection Re2ardine the Breadth of Discovery. This Protective Order limits the
scope of discovery to the compliance of Big River Steel's Permit No. 2305-AOP-R0 with
the requirements of the Clean Air Act, 42 U.S.C. §§ 7401, et seq, and Arkansas law,
including the Arkansas Water and Air Pollution Control Act, Ark. Code. Ann. § 8-4-101,
et seq, and administrative procedures and substantive rules of the APC&EC, including
Regulation 8, the Arkansas State Implementation Plan (Regulation 19), the Arkansas
Operating Permit Program (Regulation 26), and National Ambient Air Quality Standards
(40 C.F.R. Part 50); the rules regarding Prevention of Significant Deterioration (40
C.F.R. Section 52.21); and the rules regarding Title V Operating Permits (40 C.F.R. Part
70), including the application(s) and other materials submitted by Big River Steel to the
ADEQ in support of Permit No. 2305-AOP-RO.
a. General Limitation on Discovery. This Protective Order prohibits discovery
into matters that are not relevant to the appeal of Permit No. 2305-AOP-R0.
b. Discovery of Documents and Communications with Persons and Entities Not
Relevant to the Appeal of Permit No. 2305-AOP-RO is Prohibited. This
Protective Order prohibits discovery of documents related to, as well as
communications with, persons and entities that are not relevant to the appeal of
Permit No. 2305-A0P-R0. Such persons and entities specifically include: the
Arkansas Teachers Retirement System, the Arkansas Economic Development
Commission, the Arkansas Development Finance Authority, the Office of the
Governor of the State of Arkansas, Grant Tennille, John Correnti, and George
Hopkins.
4. Procedure for Invoking the Protective Order. Any party providing discovery material
in response to discovery propounded by Nucor Steel, including without limitation Big
River Steel and any of its corporate affiliates, owners, direct or indirect investors,
officers, contractors, representatives, employees, servants, or agents, who believes in
good faith that such discovery material is governed by this Protective Order shall so note
on its response to Nucor Steel's discovery requests, and shall not provide such
information to Nucor Steel.
5. Inadvertent Production or Designation. The inadvertent production of information
governed by this Protective Order does not remove it from the scope of this Protective
Order, provided that the producing party notifies the receiving party, in writing, within
three (3) business days of becoming aware that the material was not properly excluded
from production. Such written notice shall identify with specificity the information or
documents the producing party is designating to be excluded, consistent with this
Protective Order. The receiving party shall return such material and any copies thereof to
the producing party within three (3) business days, and destroy any electronic files
containing such material. The receiving party's counsel shall certify in writing to the
producing party that all such materials in its possession, custody, or control have been
destroyed.
6. Amendment. Any party to this Action may apply to the Administrative Hearing Officer
or Court for an Order amending, modifying, or vacating all provisions of this Protective
Order. Nothing in this Protective Order shall be construed as prejudicing any producing
party's right to seek an agreement or Order providing additional confidentiality or
limitation on discovery.
7. Administrative Hearing Officer Retains Jurisdiction. This Protective Order shall
survive the final conclusion of this Action and the Administrative Hearing Officer or
Court shall maintain jurisdiction to enforce this Protective Order.
8. Limitation on Use of Protective Order Designations. Neither the entry of this
Protective Order, nor the designation of any information, document, or the like as not
discoverable under this Protective Order, nor the failure to make such designation, shall
constitute evidence with respect to any issue in this Action.
9. Adoption by the Administrative Hearing Officer. The Administrative Hearing Officer
adopts the foregoing statements as a Protective Order in this Action.
IT IS SO ORDERED.
This day of November, 2013
The Honorable Charles Moulton Administrative Law Jud f e