Part 1 Team 5 Current Event Key Terms 1. baseline referred to the amount of initial federal funding 2. Project scope crumbled due to funding issues 3. project cost management project cost management team was unable to handle the changes 4. triple constraint Meeting the triple constraint was an issue because the scope was constantly changing. 5. project the project budget increased 5 times from initial baseline. 6. project sponsor looking for project sponsor to provide some aid to continue the construction of the hospital 7. project budget went from $328 million to $800 million 8. project deadline project deadline was pushed back to 2015 9. construction management practices the action VA has taken to change their cmp 10. project planning phase did not end until the end of 2009 Jan’s question: What group, from the textbook, deals with changeorders? Change Control Board Sponsor Question: What could you do to prevent future scope issues? Part 2 Team 4 Current Event Key Terms 1. baseline Qatar’s World Cup project may not meet schedule baseline 2. overrun cost of infrastructure to Qatar greatly exceeds estimates 3. Budget at completion initial estimated budget for infrastructure and labor costs 4. Indirect costs costs for rail and metro systems, and for a new airport 5. Intangible costs deaths of migrant workers that may be related to the World Cup construction

InC6 Group 1

Embed Size (px)

DESCRIPTION

hw

Citation preview

Page 1: InC6 Group 1

Part 1  Team 5 Current Event  Key Terms 

1. baseline ­ referred to the amount of initial federal funding 2. Project scope ­ crumbled due to funding issues 3. project cost management ­ project cost management team was unable to handle 

the changes 4. triple constraint ­ Meeting the triple constraint was an issue because the scope 

was constantly changing. 5. project ­ the project budget increased 5 times from initial baseline. 6. project sponsor­ looking for project sponsor to provide some aid to continue the 

construction of the hospital 7. project budget­ went from $328 million to $800 million 8. project deadline­ project deadline was pushed back to 2015 9. construction management practices­ the action VA has taken to change their 

cmp 10.project planning phase­ did not end until the end of 2009 

  Jan’s question: What group, from the textbook, deals with change­orders? Change Control Board  Sponsor Question: What could you do to prevent future scope issues?  Part 2 Team 4 Current Event  Key Terms 

1. baseline ­ Qatar’s World Cup project may not meet schedule baseline 2. overrun ­ cost of infrastructure to Qatar greatly exceeds estimates 3. Budget at completion ­ initial estimated budget for infrastructure and labor costs 4. Indirect costs ­ costs for rail and metro systems, and for a new airport 5. Intangible costs ­ deaths of migrant workers that may be related to the World Cup 

construction 

Page 2: InC6 Group 1

6. Return on investment ­ Qatar will most likely lose money from hosting the World Cup in the long run, but may benefit economically in other sectors such as increased tourism and foreign investment 

7. risk/risk management ­ Qatar faces the risk of losing the World Cup host 8. outsourcing ­ Qatar needs to outsource resources which could lead to potential 

termination of their World Cup host. 9. process ­ There was possible corruption on the bidding process of deciding who 

would host the World Cup 10.  project cost management ­ The title of their project. 

 Sponsor Question: How could Qatar better their risk management?   Part 3 Earned Value Super Bowl Party  

Earned Value  Scope  Time  Cost 

Plan  4 Rooms  4 Weeks  $8000 

Actual  1 Room  3 Weeks  $4000  

● What is the Budget at Completion? ○ $8000

● What is the PV?

○ ¾ * $8000 = $6000

● What is the EV? ○ ¼ * $8000 = $2000

● What is the AC?

○ $4000

● What is the CV? ○ $2000 - $4000 = -$2000

Page 3: InC6 Group 1

● What is the SV? ○ $2000 - $6000 = -$4000

● What is the CPI?

○ $2000/$4000 = 1/2

● What is the SPI? ○ $2000/$6000 = 1/3

● Based on the work so far, what is the EAC?

○ $8000 / ½ = $16000 ● Based on the work so far, what is the Estimated Time to Complete?

○ 4 Weeks / ⅓ = 12 Weeks ● Based on the work so far, what is the Variance At Completion?

○ $8000 - $16000 = -$8000 ● Is it ahead or behind schedule? Is it over or under budget?

○ The project is behind schedule and over budget.

● Should you continue your project? Why? ○ This project should not be continued, it has already almost taken

the whole time to only do 1 room at half the original budget. The expected time frame to finish the project is 3 times the original estimate and it will take an estimated double the cost.