Upload
godfrey-barnett
View
213
Download
0
Embed Size (px)
Citation preview
Incremental Entry Capacity Release Methodology Statement Review 2005
Transmission Workstream - 15th June 2005
Background
IECR describes methodology to be applied by Transco NTS for release of incremental capacity i.e. above obligated capacity
in place since July 2002
Special Condition C15 paragraph 2 of NTS GT Licence:
“…licensee shall before 1st July of each formula year prepare and submit for approval by the Authority an IECR methodology statement…”
Proposed Amendments-Summary
Housekeeping Changes New Licence References
Section 2 “Incremental Investment Costs” Pipeline Costs Updated
Section 3 “Cost Calculation” clarifications No Change to Methodology
Clarification of Investment Lead Times - “three years or more”
Investment Lead Time-Issue
Three year lead time typically sufficient to physically deliver incremental capacity
Exceptional circumstances beyond NGT’s control may require more than three year lead time:
planning permissionconstruction challengesunexpected requested volumes
Fixed 3 year lead time likely to give rise to inappropriate costs for NGT and Industry
Can we clarify when more than three year lead time appropriate?
Investment Lead Time-Proposal
If known pre-auction that greater than 3 years required NGT to propose revised lead time to OFGEM indicating reasons Ofgem could consult users with UCA proposal If agreed, required lead time included in auction tender
If known post-auction that longer lead time required NGT to propose revised lead time to OFGEM as part of proposal to release
incremental capacity indicating reasons process follows Special Condition C8B 14(5)(b) of GT Licence
Consultation
Responses requested by 24th June 2005 to
Nick Pittarello
NGT House
Warwick Technology Park
Gallows Hill
Warwick
CV34 6DA
Email: [email protected]