175
Initial Environmental Examination June 2016 IND: Uttarakhand Urban Sector Investment Program Dehradun Water Supply, Construction of 5 Numbers of Tube Wells and 4.8 Kms of Pedestrian Footpath in Dehradun Subproject Tranche II Prepared by Government of Uttarakhand for the Asian Development Bank.

IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

Initial Environmental Examination

June 2016

IND: Uttarakhand Urban Sector Investment Program Dehradun Water Supply, Construction of 5 Numbers of Tube Wells and 4.8 Kms of Pedestrian Footpath in Dehradun Subproject Tranche II Prepared by Government of Uttarakhand for the Asian Development Bank.

Page 2: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

CURRENCY EQUIVALENTS (as of 6 May 2016)

Currency Unit = Indian rupee/s (Re /Rs) Rs1.00 = $0.0150

$1.00 = Rs66.48

Abbreviations

ADB Asian Development Bank ASI Archaeological Survey of India BOD Bio Chemical Oxygen Demand CO Carbon Mono Oxide CFE Consent for Establishment CFO Consent for Operation CH4 Methane CFO Consent for Operation CITES Convention on International Trade in Endangered species of wild

Fauna and flora CMS Convention on Migratory Species CPCB Centre Pollution Control Board DO Dissolved Oxygen dB Decibel DN Dehradun DSC Design and Supervision Consultants EMP Environment Management Plan EA Executing Agency EIA Environmental Impact Assessment EAC Expert Appraisal Committee EC Environmental Clearances GoI Government of India GOU Government of Uttarakhand Ha Hectare H2S Hydrogen sulphide HDPE High Density Poly Ethylene HFL High Flood level IEE Initial Environment Examination IPIU Investment Project Implementation unit IPMU Investment Project Management Unit IUCN International Union for conservation of Nature and Natural Resources JNNURM Jawaharlal Nehru National Urban Renewal Mission Km Kilometre Leq Sound level Mg Milligram MFF Multitranche Financing Facility MoEFCC Ministry of Environment, Forests and Climate Change MLD Million Litter Per day

Page 3: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

Mn Million M Meter mm Millimetre mg/l Milligram per Litre m3 Cubic meter NAAQM National Ambient Air Quality Monitoring NGO nongovernmental organizations NOx Oxides of Nitrogen NA Not Applicable OUR oxygen uptake rate O&M Operation and maintenance PMU Project Management Unit PVC Poly Vinyl Chloride PWD Public works Division PIU Project Implementation Units RCC Reinforced Cement Concrete RoW Right of Way RSPM Respirable suspended particulate matter RP Rehabilitation Plan SEIAA State Environment Impact Assessment Authority SPCB State Pollution Control Board UEPPCB Uttaranchal Environmental Protection and Pollution Control Board SS Suspended Solids SBR Sequential Batch Reactor SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational Procedures TOR term of reference UDD Urban Development Department UPJN Uttaranchal Pay Jal Nigam UJS Uttaranchal Jal Sansthan UP Uttar Pradesh UPCL Uttaranchal Power Corporation Limited μg/m3 Micro Gram per Cubic Meter % Percentage

Page 4: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

CURRENCY EQUIVALENTS

(as of 06 May 2016)

Currency Unit = Indian rupee/s (Re/Rs)

Rs1.00 = $0.0150

$1.00 = Rs 66.48

NOTES

(i) The fiscal year (FY) of the Government of India ends on 31 March. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY 2008 ends on 31 March 2008.

(ii) In this report, "$" refers to US dollars unless otherwise stated.

This initial environmental examination is a document of the borrower. The views expressed

herein do not necessarily represent those of ADB's Board of Directors, Management, or staff,

and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any

designation of or reference to a particular territory or geographic area in this document, the

Asian Development Bank does not intend to make any judgments as to the legal or other status

of any territory or area.

Page 5: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

Table of Content

EXECUTIVE SUMMARY 1

I. INTRODUCTION 5

A. Overview _________________________________________________________________________ 5

B. Environmental Compliance Requirements ______________________________________________ 5

C. Extent of the IEE Study ____________________________________________________________ 15

D. Scope of IEE _____________________________________________________________________ 15

E. Report Structure __________________________________________________________________ 15

II. DESCRIPTION OF SUBPROJECT 17

A. Need for the Sub-project ___________________________________________________________ 17

B. Need of Tube wells in Dehradun _____________________________________________________ 17

C. Description of Subproject __________________________________________________________ 18

D. Energy Efficiency Measures ________________________________________________________ 22

E. Implementation Schedule __________________________________________________________ 23

III. DESCRIPTION OF THE ENVIRONMENT 41

A. Physical Features _________________________________________________________________ 41

B. Ecological Resources _____________________________________________________________ 45

C. Economic Development ____________________________________________________________ 45

IV. ANTICIPATED IMPACTS AND MITIGATION MEASURES 50

A. Pre-Construction – Location and Design ______________________________________________ 50

B. Construction Stage _______________________________________________________________ 53

C. Operations and Maintenance Impacts ________________________________________________ 60

D. Cumulative Impact Assessment _____________________________________________________ 61

V. INSTITUTIONAL ARRANGEMENTS 64

VI. GRIEVANCE REDRESS MECHANISM 64

Page 6: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE 66

A. Public Consultations Conducted ____________________________________________________ 66

B. Future Consultation and Disclosure __________________________________________________ 68

VIII. ENVIRONMENTAL MANAGEMENT PLAN 69

A. Environmental Mitigation and Monitoring Program _____________________________________ 69

B. Environmental Management Plan Costs ________________________________________________ 96

C. Environmental Mitigation and Monitoring Program for Construction of Tube wells ___________ 97

D. Safeguards Items Having Penalty Provision for Construction of Tube Wells ________________ 110

E. Environmental Budget for construction of Tube wells __________________________________ 114

F. Environmental Mitigation and Monitoring Program for Construction of Pedestrian Footpath __ 116

G. Safeguards Items Having Penalty Provision for Construction of Pedestrian Footpath ________ 127

H. Environmental Budget for construction of Pedestrian Footpath __________________________ 131

IX. FINDINGS AND RECOMMENDATIONS 133

X. CONCLUSIONS 135

List of Appendices 136

Appendix 1: Central Pollution Control Board Applicable Environmental Standards 136

Appendix 2: Rapid Environmental Checklist 142

Appendix 3 : Details of Public Consultation and Focussed Group Discussion 147

Appendix 4 : Photographs of Public Consultations of August 2010 156

Appendix 5 : Advertisement of Public Consultation 158

Appendix 6: Recommended Construction Contractors Contract Clauses 160

Appendix 7: Photographs of Sub project Sites 164

Appendix 8 : Proposed Construction Site of Tube wells 165

Appendix 9: Permission for Construction of Tube wells from Central Ground Water Board 167

Page 7: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

List of Tables

Table No 1: - Applicable Environmental National and State Requirements for UUSDIP ___________________ 11

Table No 2: Water Demand of the Project Area ___________________________________________________ 17

Table No 3: Dehradun Water Supply Subproject Components _______________________________________ 18

Table No 4 : Sub-project Details of laying and beautification of 4.8 Kms in Dehradun ___________________ 21

Table No 5 : Sub-project Details of construction of 5 tube wells in Dehradun __________________________ 22

Table No 6 : Findings and recommendations of Hydrogeological study _______________________________ 22

Table No 7 : Climatic Data of Dehradun (Period 1960 to 1990) ________________________________________ 42

Table No 8: Air Quality of Dehradun (Period 2005 to 2006)___________________________________________ 43

Table No 9: Noise Levels in Dehradun (Period 2005 to 2006) _________________________________________ 43

Table No 10 : Existing and Proposed Land Use - Master Plan 2001 ____________________________________ 46

Table No 11: Public Consultations by PPTA Consultant ____________________________________________ 67

Table No 12: Details of public consultation for proposed tube wells and pedestrian footpath ________ 68

Table No 13: Issues discussed during public consultation and its action plan __________________________ 68

Table No 14 : Anticipated Impact and Mitigation Measures – Pre-construction Environmental Mitigation Plan 70

Table No 15: Anticipated Impacts and Mitigation Measures – Construction Environmental Mitigation Plan __ 74

Table No 16 : Anticipated Impacts and Mitigation Measures – Operations and Maintenance Environmental

Mitigation Plan ___________________________________________________________________ 84

Table No 17 : Pre-construction Environmental Monitoring Program __________________________________ 85

Table No 18 : Construction Environmental Monitoring Program _____________________________________ 87

Table No 19 : Operation and Maintenance Environmental Monitoring Program _________________________ 94

Table No 20 : Environmental Management and Monitoring Cost _____________________________________ 96

Table No 21 : Environmental Management Plan for Construction of Tube wells in Dehradun ______________ 98

Table No 22 : Preventive Measures of non-compliance of Safeguards _______________________________ 110

Table No 23 : Environmental Monitoring Plan – Tube well __________________________________________ 112

Table No 24 : Environmental Budget for construction of 5 Tube Wells in Dehradun ____________________ 114

Table No 25 : Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun _____ 117

Table No 26 : Preventive Measures of non-compliance of Safeguards _______________________________ 127

Page 8: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

Table No 27 : Environmental Monitoring Plan – Construction of Pedestrian Footpath ___________________ 129

Table No 28 : Cost of Environmental Management and Monitoring of Pedestrian Footpath in Dehradun ___ 131

List of Figures

Figure 1: Location of Sub project town in Uttarakhand State ________________________________________ 24

Figure 2: Location of WTP & Gravity Mains _____________________________________________________ 25

Figure 3: Water Supply Zonal Coverage in Tranche-1 & II __________________________________________ 25

Figure 4: Galogi Water Intake Layout Plan _______________________________________________________ 26

Figure 5 : Raw Water Main from Massifall to Shahanshahi Asram WTP _______________________________ 27

Figure 6: Layout Plan of Dilaram Bazar __________________________________________________________ 28

Figure 7 : Layout Plan of Purukul Gram WTP _____________________________________________________ 29

Figure 8 : Layout Plan of Shahanshahi Asram WTP ________________________________________________ 30

Figure 9 : Location of Tube Wells in Vijay Park in Dehradun _________________________________________ 31

Figure 10 : Location of Tube Well for Feeding Rajpur Road OHT in Dehradun __________________________ 32

Figure 11 :Location of Tube Well for Rajendra Nagar OHT in Dehradun _______________________________ 32

Figure 12 :Location of Tube Well for Hari Nagar OHT in Dehradun ___________________________________ 33

Figure 13 :Location of Tube Well at Kaulagarh Canal Road _________________________________________ 33

Figure 14 : Location of pedestrian footpath from Dilaram Bazar to Mussoorie diversion (4.8 Km) __________ 35

Page 9: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

1

EXECUTIVE SUMMARY

1. Uttarakhand Urban Sector Development Investment Program (UUSDIP) is intended

to support the Government of India and Government of Uttarakhand in their policy of

balanced regional socio-economic development and poverty reduction throughout the urban

sector in Uttarakhand. This is being achieved through investments in the areas of

infrastructure and service provision, institutional development and capacity building.

Directly the UUSDIP will result in improved living conditions in the urban areas of

Uttarakhand as a result of rehabilitation, upgrading and extension of key infrastructure,

strengthened operation and maintenance, and improved local governance practices and

locally-led pro-poor planning and project identification. The program will also improve the

prospects for accelerated economic growth from the tourism and manufacturing industries

and help create conditions for improved long-term service sustainability and greater

private sector investment in infrastructure and service provision.

2. The investment program is funded by Asian Development Bank (ADB) through

multitranche financing facility and also by Jawaharlal Nehru National Urban Renewal

Mission. The executing agency is the GoU Urban Development Department, which has set

up a state-level urban sector project investment program management unit (IPMU) to

execute the investment program. The implementation agencies are the respective urban

local bodies (ULBs), Uttarakhand Peya Jal Nigam (UPJN), Uttarakhand Jal Sansthan (UJS)

and Public Works Department (PWD), which in collaboration with IPMU will set-up 13

project implementation units (PIU). The towns of Dehradun, Roorkee, Ramnagar, Halwani,

Almora, Pitoragarh, and Nainital are chosen for investment under the investment program

Tranche-II.

3. ADB requires the consideration of environmental issues in all aspects of the Bank’s

operations, and the requirements for Environmental Assessment are described in ADB’s

SPS (2009). This states that ADB requires environmental assessment of all project loans,

program loans, sector loans, sector development program loans, loans involving financial

intermediaries, and private sector loans.

4. This Initial Environmental Examination (IEE) Report has been prepared for

the Dehradun Water Supply Subproject to be undertaken in Tranche II. Following are the

components of this subproject: (i) Optimization of water management in Dehradun through

laying of Rising Mains and Feeder Mains (contract packages No WSS05DN); (ii)

Renovation/ Up-Gradation of Dilaram Water Treatment Plant, Shehenshai Ashram WTP &

installation of softening plant (Contract Package No. WSS06DN); (iii) Water Supply

distribution system in 5 Zones, Dehradun (Contract Package No. WSS07DN); (iv) Raw

water main from Massi fall to Shehenshai Ashram WTP (Contract Package No.

WSS08DN); (v) Water supply distribution system in 7Zones, Dehradun (Contract Package

No. WSS09DN); (vi) Water supply distribution system in 7 outer Zones, Dehradun (Contract

Package No. WSS10DN); (vii) Installing of Domestic water meters (Contract Package No.

WSS011DN); (viii) Supply and Construction of 5 number of Tube well in Dehradun

(Contract package WSS14DN), and (ix) Construction of pedestrian footpath and

beautification work of 4.8 Km at Rajpur road from Dilaram Bazar to Mussoorie Diversion

(Contract Package No. WSS15DN). Construction of tube wells and pedestrian footpath are

likely to commence July 2016 and construction will be completed by the end of June 2017.

Page 10: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

2

5. The subproject sites including tube wells and pedestrian footpath are located in

existing Right of Way and government-owned land and are clear of human habitation.

There are no protected areas, wetlands, mangroves, or estuaries. Trees, vegetation

(mostly shrubs and grasses), and animals in the subproject site are those commonly

found in built-up areas. The proposed intake replacement site near Galogi power house

is located in hilly forest areas. However, no encroachment into forest land is envisaged.

The site is approachable by Power House access road. With the presence of activities and

people, who work and live in the powerhouse, the site is not very sensitive. Moreover there

will be no day-to-day operation, as water will flow by gravity and no personnel will be

required for operation.

6. Locations and siting of the proposed infrastructures were considered to further

reduce impacts. These include: (i) Locating all facilities on government-owned land to avoid

the need for land acquisition and relocation of people; and (ii) Locating the distribution main

in the ROW alongside a main road, to reduce the acquisition of agricultural land and

impacts on livelihoods of farmers and workers.

7. Regardless of these and various other actions taken during the IEE process

and in developing the project, there will still be impacts on the environment when the

infrastructure is built and when it is operating. This is mainly because of the invasive

nature of trenching and other excavation; and because the distribution network is

located in an inhabited town where there are densely populated areas. Because of

these factors the significant impacts are on the physical environment and the human

environment.

8. During the construction phase, impacts mainly arise from the need to dispose

of large quantities of waste soil and import a similar amount of sand to support the pipes

in the trenches; and from the disturbance of residents, businesses, traffic and important

buildings by the construction work. These are common impacts of construction in

urban areas, and there are well developed methods for their mitigation. These

include (i) finding beneficial uses for waste material; (ii) covering soil and sand during

transportation and when stored on site; (iii) planning work to minimize disruption of traffic

and communities; (iv) providing temporary structures to maintain access across

trenches where required.

9. Specific impacts due to construction in the stream flowing through the hilly forested

areas have been identified and measures such as the following are suggested: (i) no

construction material storage/ancillary works in the forest; (ii) no labour camps; (iii) limiting

the work to daylight hours only; (iv) conducting construction work in lean flow season

(summer); (v) protection bunds around construction area; (vi) conducting awareness

programs to workers; (vii) no noisy works; (viii) barricade the construction area, (ix)

implementation of any measures as suggested by the Forest Department; and (x) use

excavated soil for strengthening bunds/road levelling; no waste shall be disposed in or near

forests.

10. There were limited opportunities to provide environmental enhancements, but

certain measures were included. For example it is proposed that the project will: (i) employ

in the workforce to the extent possible, people who live in the vicinity of construction sites to

provide them with a short-term economic gain; and (ii) ensure that people employed in the

longer term to maintain and operate the new facilities are residents of nearby communities.

Page 11: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

3

11. Once the system is operating, most facilities will operate with routine maintenance,

which should not affect the environment. Leaks in the network will need to be repaired from

time to time, but environmental impacts will be much less than those of the construction

period as the work will be infrequent, affecting small areas only.

12. The major impacts of the implementation of water supply subproject will be

beneficial to the citizens of Dehradun as it will provide constant supply of water, which will

serve a greater proportion of the population, including slum-dwellers. This will improve the

quality of life of people as well as benefiting both individual and public health as the

improvements in hygiene should reduce the incidence of disease associated with poor

sanitation. This should lead to economic gains as people will be away from work less and

will spend less on healthcare, so their incomes should increase. The construction of 5

number of tube wells will fulfil the gap of water supply caused due to shortage in extraction

of ground water. Since Dehradun is the capital city of Uttarakhand, the beautification and

construction of pedestrian footpath will enhance aesthetic value of the city.

13. An Environmental Management Plan (EMP) is proposed as part of this IEE which

includes (i) mitigation measures for significant environmental impacts during

implementation, (ii) environmental monitoring program, and the responsible entities for

mitigation, monitoring, and reporting; (iii) public consultation and information disclosure; and

(iv) grievance redress mechanism. Mitigation measures have been developed to reduce all

negative impacts to acceptable levels. A number of impacts and their significance have

already been reduced by amending the designs.

14. Mitigation will be assured by a program of environmental monitoring to be

conducted during construction stages. The environmental monitoring program will ensure

that all measures are implemented, and will determine whether the environment is

protected as intended. It will include observations on- and off-site, document checks, and

interviews with workers and beneficiaries. Any requirements for remedial action will be

reported to the ADB.

15. The stakeholders were involved in developing the IEE through discussions on site

and public consultation after which views expressed were incorporated into the IEE and the

planning and development of the project. The IEE will be made available at public locations

in the city and will be disclosed to a wider audience via the ADB website. The consultation

process will be continued and expanded during project implementation to ensure that

stakeholders are fully engaged in the project and have the opportunity to participate in its

development and implementation.

16. Therefore the components proposed under Tranche-II of this water supply

subproject in Dehradun are unlikely to cause significant adverse impacts. The potential

adverse impacts that are associated with design, construction, and operation can be

mitigated to standard levels without much difficulty through proper engineering design and

the incorporation/application of recommended mitigation measures and procedures.

17. Based on the findings of the IEE, the classification of the Project as Category “B” is

confirmed, and no further study or detailed EIA if required to comply with ADB SPS (2009)

or government’s EIA Notification (2006). Consent for Establishment (CFE) and Consent for

Operation (CFO) under Water Act, 1974 from Uttarakhand Environmental Protection and

Pollution Control Board will be required for proposed new/augmentation of WTPs at Dilaram

Page 12: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

4

Bazar and Purukul Gram. Although project sites are falling in Non-notified area of Central

Ground Water Board (CGWB), abstraction of ground water requires permission from

Central Ground Water Board, which is already obtained for 5 tube wells in lieu of

abandoned wells (Reference Appendix 9).

Page 13: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

5

I. INTRODUCTION

A. Overview

1. Uttarakhand Urban Sector Development Investment Program (UUSDIP) is

intended to support the Government of India and Government of Uttarakhand in their policy

of balanced regional socio-economic development and poverty reduction

throughout the urban sector in Uttarakhand. This is being achieved through investments in

the areas of infrastructure and service provision, institutional development and

capacity building. Directly the UUSDIP will result in improved living conditions in the urban

areas of Uttarakhand as a result of rehabilitation, upgrading and extension of key

infrastructure, strengthened operation and maintenance, and improved local governance

practices and locally-led pro-poor planning and project identification. The program will also

improve the prospects for accelerated economic growth from the tourism and

manufacturing industries and help create conditions for improved long-term service

sustainability and greater private sector investment in infrastructure and service

provision.

2. The investment program is funded by ADB through Multitranche Financing Facility

(MFF) and also by the central-sponsored Jawaharlal Nehru National Urban Renewal

Mission (JNNURM) of the Government of India. This Program is being under

implementation over a period of 10 years. The executing agency is the Urban Development

Department (UDD) of Government of Uttarakhand (GoU), which has set up a state-level

urban sector Project Management Unit (PMU) to execute the investment program.

Implementation agencies are the respective urban local bodies, UPJN, UJS and PWD,

which in collaboration with the IPMU will set-up 13 Project Implementation Units (PIU) for

implementing the Program. Dehradun, Roorkee, Ramnagar, Nainital, Almora, Pitoragarh

and Haldwani are the towns chosen for investment under Tranche-II of the investment

program.

3. ADB classified the investment program as environment Category B and accordingly

initial environmental examination (IEE) is required for all subprojects. In continuation to

Tranche-I, various rehabilitation and augmentation works for water supply system in

Dehradun is also proposed in Tranche-II of the Investment Program. Based on the ADB

policies, the Initial Environmental Examination (IEE) of the subproject has been conducted

and presented in this report.

B. Environmental Compliance Requirements

1. ADB Policy

4. ADB requires the consideration of environmental issues in all aspects of its

operations, and the requirements for environmental assessment are described in ADB

Safeguard Policy Statement (SPS), 2009. This states that ADB requires environmental

assessment of all project loans, program loans, sector loans, sector development program

loans, and loans involving financial intermediaries, and private sector loans.

5. Screening and Categorization. The nature of the environmental assessment

required for a project depends on the significance of its environmental impacts, which are

Page 14: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

6

related to the type and location of the project, the sensitivity, scale, nature and magnitude of

its potential impacts, and the availability of cost-effective mitigation measures. Projects are

screened for their expected environmental impact are assigned to one of the following four

categories:

(i) Category A. Projects could have significant adverse environmental impacts.

An environmental impact assessment (EIA) is required to address significant

impacts.

(ii) Category B. Projects could have some adverse environmental impacts, but

of lesser degree or significance than those in category A. An IEE is required

to determine whether significant environmental impacts warranting an EIA

are likely. If an EIA is not needed, the IEE is regarded as the final

environmental assessment report.

(iii) Category C. Projects are unlikely to have adverse environmental impacts.

No EIA or IEE is required, although environmental implications are reviewed.

(iv) Category FI. Projects involve a credit line through a financial intermediary or

an equity investment in a financial intermediary. The financial intermediary

must apply an environmental management system, unless all projects will

result in insignificant impacts.

6. Environmental Management Plan. An environmental management plan (EMP)

which addresses the potential impacts and risks identified by the environmental

assessment shall be prepared. The level of detail and complexity of the EMP and the

priority of the identified measures and actions will be commensurate with the project’s

impact and risks.

7. Public Disclosure. ADB will post the following safeguard documents on its website

so affected people, other stakeholders, and the general public can provide meaningful

inputs into the project design and implementation:

(i) For environmental category A projects, draft EIA report at least 120 days

before Board consideration;

(ii) Final or updated EIA and/or IEE upon receipt; and

(iii) Environmental Monitoring Reports submitted by IPIU during project

implementation upon receipt

2. Applicable Legislations

8. The implementation of the subprojects will be governed by the national government

and state of Uttarakhand environmental acts, rules, regulations, and standards. These

regulations impose restrictions on the activities to minimize and/or mitigate likely impacts on

the environment. It is the responsibility of the project executing and implementing agencies

to ensure subprojects are consistent with the legal framework, whether national, state or

municipal and/or local. In addition, subprojects shall also be consistent with ADB SPS. The

following legislations are applicable to the subproject:

(i) Environmental (Protection) Act of 1986 as amended in 1991; (ii) Environmental (Protection) Rules of 1986 and amendments; (iii) Environmental Impact Assessment Notification of 2006; (iv) Water (Prevention and Control of Pollution) Act of 1974, Rules of 1975, and

amendments;

Page 15: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

7

(v) Air (Prevention and Control of Pollution) Act of 1981, Rules of 1982 and amendments;

(vi) Noise Pollution (Regulation and Control) Rules of 2000; (vii) Wildlife (Protection) Act of 1972, Rules of 1995 and amendments; (viii) Indian Forest Act of 1927; (ix) Forest (Conservation) Act of 1980, Rules of 1981 and amendments; (x) Guidelines for Diversion of Forest Lands for Non-Forest Purpose under the

Forest (Conservation) Act of 1980; (xi) Central Pollution Control Board (CPCB) Environmental Standards; (xii) Ancient Monuments and Archaeological Sites and Remains Rules of 1959; and (xiii) Land Acquisition Act of 1894 as amended in 1985.

9. Key standards include those related to drinking water quality, air quality, effluent

discharge, and protected areas. Compliance is required in all stages of the project including

design, construction, and O&M.

3. Environmental Assessment Requirements

10. The government’s EIA Notification of 2006, which replaces the EIA Notification of

1994, requires environmental clearance for certain defined activities/projects1 .This

notification classifies the projects and/or activities that require environmental clearance into

‘A’ and ‘B’ categories depending on the impact potential and/or scale of project. For both

category projects, prior to environmental clearance is mandatory before any construction

work, or preparation of land except for securing the land, is started. Clearance provisions

are as follows:

(i) Category ‘A’ projects requires prior environmental clearance from the government’s Ministry of Environment and Forest (MoEF)2 ;

(ii) Environmental Impact Assessment Authority (SEIAA)3.

11. This notification provides that, any project or activity specified in Category ‘B’ will be

treated as Category A, if located in whole or in part within 10 kilometres (km) from the

boundary of: (i) protected areas notified under the Wild Life (Protection) Act, 1972, (ii)

critically polluted areas as notified by the CPCB from time to time, (iii) notified eco-sensitive

areas, and (iv) inter-state boundaries and international boundaries. Also, in the case where

a SEIAA does not exist, Category B project will be reviewed by the MoEF and reclassified

as Category A.

12. Consequently, the proposed Dehradun Water Supply Subproject is not listed in the

EIA Notification of 2006 “Schedule of Projects Requiring Prior Environmental Clearance.”

Thus, environmental clearance for this subproject is required.

_________________________

1 EIA Notification of 2006 “Schedule of Projects Requiring Prior Environmental Clearance”. 2 Category A projects - based on preliminary details provided by the project proponent, the MoEF Expert Appraisal Committee will determine comprehensive terms of reference (TOR) for the EIA studies. This TOR will be finalized within 60 days. On the recommendation of the Expert Appraisal Committee based on EIA studies, MoEF provides the environmental clearance

3 Category B projects – to be further divided by State-Level Expert Appraisal Committee (SEAC) into B1

(require EIA studies) and B2 (do not require EIA studies). The SEAC will determine TOR for EIA studies for B1 projects within 60 days. On the recommendation of the SEAC based on EIA studies, SEIAA provides the environmental clearance.

Page 16: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

8

4. National Legal Requirements

13. Water (Prevention and Control of Pollution) Act of 1974, Rules of 1975, and

amendments. Any component of the project having potential to generate sewage or trade

effluent will come under the purview of the Water (Prevention and Control of Pollution) Act

of 1974, Rules of 1975, and amendments. Such projects have to obtain Consent for

Establishment (CFE) under Section 25 of the Act from State Pollution Control Board

(SPCB) before starting implementation and Consent to Operate (CTO) before

commissioning. The Water Act also requires the occupier of such subprojects to take

measures for abating the possible pollution of receiving water bodies. The following

subprojects require CFE and CTO from SPCB:

(i) New or augmentation of water treatment plants; and (ii) New or augmentation of sewage treatment plants.

14. Air (Prevention and Control of Pollution) Act of 1981, Rules of 1982 and

amendments. The subprojects having potential to emit air pollutants into the atmosphere

have to obtain CFE under Section 21 of the Air (Prevention and Control of Pollution) Act of

1981 from SPCB before starting implementation and CTO before commissioning the

project. The occupier of the project/facility has the responsibility to adopt necessary air

pollution control measures for abating air pollution. The following require CFE and CTO

from SPCB:

(i) Diesel generators; and (ii) Hot mix plants, wet mix plants, stone crushers, etc., if installed

for construction.

15. Emissions and discharges shall comply with standards notified by the CPCB.

Appendix 1 provides applicable standards for effluents, receiving waterbodies, air quality,

water quality and noise levels.

16. Forest Legislations. The government’s forest legislation dates back to enactment

of the Indian Forest Act of 1927. This Act empowers State of Uttarakhand to declare “any

forest land or waste-land, which is the property of government or over which the

government has proprietary rights or to the whole or any part of the forest-produced of

which the government is entitled,” a reserved forest or protected forest. The Act also allows

government control over forest and lands not being the property of the government.

17. For reserved forests and village-forests, activities like clearing or breaking up of any

land for cultivation or for any other purpose, damage to vegetation and/or trees and

quarrying or removing any forest produce are prohibited. For protected forests, with the

provision of the Act, State of Uttarakhand makes rules to regulate activities like cutting of

trees and removal of forest produce; clearing or breaking up of land for cultivation or any

other purpose; and for protection and management of any portion of protected forest.

18. According to the Act, State of Uttarakhand requires prior approval of MoEF for the

use of forest land for non-forest purposes (means the breaking up or clearing of any forest

land) or for assigning lease to any private person or agency not controlled by government.

The Forest (Conservation) Rules of 2003 issued under this Act, provide specific procedures

to be followed for conversion of forest land for non-forest purposes.

19. Conversion of forest lands that are part of National Parks and/or Sanctuaries and

Tiger Reserve areas (notified under Indian Wildlife [Protection] Act of 1972) is not

permitted. In exceptional case, State of Uttarakhand requires consent of the Indian Board of

Wildlife for obtaining approval of the State Legislature for de-notification of the area as a

Page 17: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

9

sanctuary. The State or National Wildlife Board under MoEF is the authority which will grant

a “No Objection Certificate” for any construction within a sensitive area. Every user agency,

who proposes to use any forest land for non-forest purposes and use buffer zone of the

wildlife protected areas for other purposes, must apply for forest and/or wildlife clearance.

20. None of the components of this subproject are located in forest lands. The pipeline

from Massi Fall to Shensai Ashram will be laid along a pedestrian path in the hilly forested

areas. This is a public road and do not fall in the forest.

21. Cutting of trees in non-forest land, irrespective of land ownership, also requires

permission from the State Forest and Environment Department. Afforestation to the extent

of two trees per each tree felled is mandatory.

22. Ancient Monuments and Archaeological Sites and Remains Rules, of 1959.

The Rules designate areas within a radius of 100 meters (m) and 300 m from the “protected

property” as “protected area” and “controlled area” respectively. No development activity

(including mining operations and construction) is permitted in the “protected area” and all

development activities likely to damage the protected property are not permitted in the

“controlled area” without prior permission of the Archaeological Survey of India (ASI).

Protected property includes the site, remains, and monuments protected by ASI or the State

Department of Archaeology. None of the component of subproject falls within the purview of ASI site.

23. For the subproject, activities within Archaeologically Protected Areas will be avoided. If

activities are to be done in the controlled area of protected properties, then the executing and

implementing agencies and the line department will take the necessary No Objection Certificates

from ASI.

24. Land Acquisition Act of 1894 (amended in 1985). Private land acquisition is guided by the

provisions and procedures in this Act. The District Collector or any other officer designated will

function as the Land Acquisition Officer on behalf of the government. There is a provision for consent

award to reduce the time for processing if the land owners are willing to agree on the price fixed by

the Land Acquisition Officer. The option of acquiring lands through private negotiations is also

available.

25. Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and

Resettlement Act, 2013 is application since 2013, this Act takes care of compensation, rehabilitation

and resettlement of title holders of the project affected people.

26. For the subproject, permanent land acquisition is not required as all sites are

government-owned land and/or within existing Right of Ways (ROWs).

5. Applicable International Environmental Agreements

27. In addition, international conventions such as the International Union for

Conservation of Nature and Natural Resources (IUCN), Convention on International Trade

in Endangered Species of Wild Fauna and Flora (CITES), Convention on Migratory Species

of Wild Animals (CMS) and Ramsar Convention on Wetlands of International Importance

are applicable for selection and screening of subprojects under restricted and/or sensitive

areas. India is a party to these conventions.

28. International Union for Conservation of Nature and Natural Resources (IUCN).

The IUCN Red List of Threatened Species (also known as the IUCN Red List or Red Data

List), founded in 1963, is a comprehensive inventory of the global conservation status of

plant and animal species. The IUCN is an authority on the conservation status of species. A

series of Regional Red Lists are produced by countries or organizations, which assess the

risk of extinction to species within a political management unit. The IUCN Red List is set

Page 18: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

10

upon precise criteria to evaluate the extinction risk of thousands of species and subspecies.

These criteria are relevant to all species and all regions of the world. The aim is to convey

the urgency of conservation issues to the public and policy makers, as well as help the

international community to try to reduce species extinction.

29. Convention on Migratory Species of Wild Animals (CMS). CMS was adopted in

1979 and entered into force on 1 November 1983. CMS, also known as the Bonn

Convention, recognizes that states must be the protectors of migratory species that live

within or pass through their national jurisdictions, and aims to conserve terrestrial, marine

and avian migratory species throughout their ranges. Migratory species threatened with

extinction are listed on Appendix I of the Convention. CMS Parties strive towards strictly

protecting these species, conserving or restoring the places where they live, mitigating

obstacles to migration and controlling other factors that might endanger them. Migratory

species that need or would significantly benefit from international cooperation are listed in

Appendix II, and CMS encourages the Range States to conclude global or regional

agreements.

30. Convention on International Trade in Endangered Species of Wild Fauna and

Flora (CITES). It is an international agreement between governments. Its aim is to ensure

that international trade in specimens of wild animals and plants does not threaten their

survival. CITES were first formed, in the 1960s. Annually, international wildlife trade is

estimated to be worth billions of dollars and to include hundreds of millions of plant and

animal specimens. The trade is diverse, ranging from live animals and plants to a vast array

of wildlife products derived from them, including food products, exotic leather goods,

wooden musical instruments, timber, tourist curios and medicines. Levels of exploitation of

some animal and plant species are high and the trade in them, together with other factors,

such as habitat loss, is capable of heavily depleting their populations and even bringing

some species close to extinction. Many wildlife species in trade are not endangered, but the

existence of an agreement to ensure the sustainability of the trade is important in order to

safeguard these resources for the future. Because the trade in wild animals and plants

crosses borders between countries, the effort to regulate it requires international

cooperation to safeguard certain species from over-exploitation.

31. Ramsar Convention on Wetlands of International Importance, 1971. The

Convention on Wetlands of International Importance, called the Ramsar Convention, is an

intergovernmental treaty that provides the framework for national action and international

cooperation for the conservation and wise use of wetlands and their resources. The

Ramsar Convention is an international treaty for the conservation and sustainable utilization

of wetlands The Ramsar Convention is the only global environmental treaty that deals with

a particular ecosystem. According to the Ramsar list of Wetlands of International

Importance, there are 25 designated wetlands in India which are required to be protected.

Activities undertaken in the proximity of Ramsar wetlands shall follow the guidelines of the

convention.

32. The legal framework of the country consists of several acts, notifications, rules and

regulations to protect environment and wildlife. In 1976, the 42nd Constitutional Amendment

created Article 48A and 51A, placing an obligation on every citizen of the country to attempt

to conserve the environment. Specifically for the UUSDIP (Uttarakhand Urban Sector

Development Investment Program), the following environmental laws and regulations are

applicable for sub-projects and require clearance or permission as applicable. The details

are given in Table No.1:

Page 19: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

11

Table No 1: - Applicable Environmental National and State Requirements for UUSDIP

S. No.

Clearances Acts/Rules/Notifications/Guidelines and Application to proposed project

Concerned Agency

Applicable to Contract package

Responsibility

Status of Compliance

A. Pre-construction Stage

1 Environmental Clearance

EIA Notification, 2006 amended till date, promulgated under Environment (Protection) Act 1986

This states that Environmental Clearance (EC) is required for specified activities/projects, and this must be obtained before any construction work or land preparation (except land acquisition) may commence. Projects are categorized as A or B depending on the scale of the project and the nature of its impacts. Categories A projects require Environmental Clearance from the National Ministry of Environment and Forests (MoEF). Category B projects require environmental clearance from the State Environment Impact Assessment Authority (SEIAA).

State Environmental Impact Assessment Authority (SEIAA).

If not constituted then MoEF.

No

The sub-project is not included in schedule of environmental impact assessment notification 2006 and its subsequent amendments till date, so it is not categories as either Category A or Category B. As a result, environmental clearance is not required, either from the state or the central Government.

IPMU / IPU Not required

2. Ground Water (Regulation, Development and Management) Rules, 2007

For withdrawal of ground water

Central Ground Water Board

Yes IPMU / IPIU Obtained and given in Appendix- 9

3 Forest Clearance for felling of trees and acquisition of forest land for widening.

Forest Conservation Act (1980) and Rules 2003 & 2004:

This act provides guidelines for conservation of forests and diversion of forest land for non-forest use. The law also states guidelines on de-reservation of various categories of forests for diversion of forest land. This law describes the penalty for contravention of

District Level Committee constituted by the State Govt.

No (No felling of trees or diversion of forest land required)

IPMU / IPIU Not Required

Page 20: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

12

S. No.

Clearances Acts/Rules/Notifications/Guidelines and Application to proposed project

Concerned Agency

Applicable to Contract package

Responsibility

Status of Compliance

the provisions of the Act. Restriction on the de-reservation of forests or use of forest land for non-forest purpose.

i) If the forest land exceeds 20 hectare then prior permission of Central Government is required; ii) if the forest land is between 5 to 20 hectare, then permission form the Regional Office of Chief Conservator is required; iii) If the forest land is below or equal to 5 hectare the State Government can give permission. If the construction area is more than 40% forest, permission to undertake any work is needed from the Central Government, irrespective of the size of the area.

MoEF issued specific guidelines in July 2013 for state of Uttarakhand for expediting forest clearances to carry out the emergency work in forest areas (excluding works in national parks and sanctuaries) vide no 11-298/2013-FC Dated 24.07.2013

4 Wildlife department clearances

The Indian Wildlife (Protection)

Act, 1972, as amended till 2006

This Act provides guidelines for protection of [Wild animals, birds and plants] and for matters connected therewith or ancillary or incidental thereto. It also states the norms for hunting of wild animals, prohibition of picking, uprooting, etc., of specified plants. The Act deals with the declaration of area as Sanctuary,

National Board for Wildlife

Not Applicable to contract package (The wildlife protection act is not applicable to the proposed subproject. All activities of project are well outside from the boundary fence of the wildlife sanctuary.

IPMU / IPIU Not required

Page 21: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

13

S. No.

Clearances Acts/Rules/Notifications/Guidelines and Application to proposed project

Concerned Agency

Applicable to Contract package

Responsibility

Status of Compliance

National Park, and closed area and also states the restriction of entries in the sanctuary.

The 2002 Amendment Act which came into force in January, 2003 have made punishment and penalty for offences under the Act more stringent.

5 Clearances required for using biological resources

Biodiversity Act 2002 and

Biodiversity Rules 2004:

The Act essentially controls access to indigenous biodiversity resources. No agency/person shall, without previous approval of the National Bio-diversity Authority, obtain any biological resource occurring in India or knowledge associated thereto for research or for commercial utilization or for bio-survey and bio-utilization.

Uttarakhand Biodiversity Board.

Not Applicable for the subproject

IPMU / IPIU Not required

6 Permission to carry out construction activities in the sites of Archaeological Importance

The Ancient Monuments and

Archaeological Sites and Remains Act, 1958, and the rules, 1959:

The Act provides guidance for carrying out activities, including conservation, construction and reuse in and around the protected monuments

Permission from the Archaeological Survey of India for carrying out any construction activities within the prohibited and regulated areas of the ancient monuments and archaeologically protected sites.

State Level Committee constituted by the Central Govt.

Not Applicable for the subproject

IPMU / IPIU Not required

B. Construction Stage

Page 22: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

14

S. No.

Clearances Acts/Rules/Notifications/Guidelines and Application to proposed project

Concerned Agency

Applicable to Contract package

Responsibility

Status of Compliance

7 Permission for Sand Mining from river bed

Mines and Minerals (Regulation and Development) Act, 1957 as amended in 1972

River Board Authorities/ Department of Mining Govt. of Uttarakhand

Yes Contractor -

8 Consent to Establish (CTE) and Consent to Operate (CTO) from the UEPPCB is required for setting up WTP

Water (Prevention and control of pollution) Act, 1974, as amended

Air (prevention and control of pollution) Act, 1981, as amended

UEPPCB Yes, it is applicable for Water Treatment Plants and Sewage Treatment plant of Dehradun. It is not applicable for abstraction of ground water and construction of pumping house

IPMU/ IPIU Obtained for WTP and STP

Consent to Establish (CTE) and Consent to Operate (CTO) from the UEPPCB for setting up hot mix plants, wet mix plants, stone crushers, quarries and diesel generators (if installed for construction)

9 Authorization for Disposal of Hazardous Waste

Hazardous Wastes (Management, Handling and Transboundary movement) Rules, 2008 and Hazardous Waste (Management, Handling and Transboundary Movement) Fourth Amendments Rules, 2010

Uttarakhand Environmental Protection and Pollution Control Board – Dehradun

No Contractor -

10 Pollution Under Control Certificate for construction vehicles

Central Motor and Vehicle Act 1988 and Central Motor and Vehicle Rules,1989 amended till 2013

Department of Transport, Govt. of Uttarakhand

Yes Contractor

11 Employing Labour/ workers - Labour license and Workmen’s

The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 & The Building

District Labour Commissioner

Yes Contractor Contractor to obtain labour license and workmen compensation

Page 23: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

15

S. No.

Clearances Acts/Rules/Notifications/Guidelines and Application to proposed project

Concerned Agency

Applicable to Contract package

Responsibility

Status of Compliance

Insurance and labour permits

and Other Construction Workers Related Laws (Amendment) Bill, 2013

insurance.

12 License for Storing Diesel and other explosives

Petroleum Rules, 2011.

Hazardous Wastes (Management, Handling and Transboundary movement) Rules, 2008 and Hazardous Waste (Management, Handling and Transboundary Movement) Fourth Amendments Rules, 2010

Commissioner of Explosives and Uttarakhand Environmental Protection and Pollution Control Board – Dehradun

No Contractor

13 Child Labour Child Labour Act 1986 - Applicable Contractor No child below 18 years age shall be employed or permitted to work in any of the scheduled occupations

C. Extent of the IEE Study

33. This IEE report has been updated on the basis of detailed screening and analysis

of all environmental parameters, field investigations and stakeholder consultations to

meet the requirements for environmental assessment process and documentation per

ADB’s Safeguard Policy Statement (SPS, 2009) and Government of India

Environmental Impact Assessment (EIA) Notification of 2006.

D. Scope of IEE

34. This is the updated IEE for the Water Supply including 5 tube wells sub-project in

Dehradun and 4.8 Kms of pedestrian footpath from Dilaram Bazar to Mussoorie Diversion

in Dehradun. It discusses the environmental impacts and mitigation measures relating

to the location, design, construction and operation of all physical works proposed under this

sub-project. The IEE is based mainly on secondary sources of information and field

reconnaissance surveys. Stakeholder consultation was an integral part of updated IEE.

E. Report Structure

35. This IEE report is prepared in accordance with the ADB SPS, 2009 and is

documented accordingly. This Report contains eight (8) sections including this

introductory section: (i) Introduction; (ii) Description of the subproject; (iii) Description of the

environment; (iv) Anticipated impacts and mitigation measures; (v) Institutional

Page 24: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

16

arrangements; (vi) Grievance redress mechanism; (vii) Public consultation and information

disclosure; (viii) Environmental management plan (ix) Finding and recommendation; and (x)

Conclusion.

Page 25: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

17

II. DESCRIPTION OF SUBPROJECT

A. Need for the Sub-project

36. Located in the north western part of Uttarakhand, Dehradun is a Capital City of the

State (Figure 1). The first piped water supply was introduced in Dehradun in 1885 from

Kolukhet springs, 25 km from Dehradun. Subsequently due to limited surface sources,

ground water sources are being exploited to meet City demands. At present, ground water

is the main source (provides 76% of its total supply of 102 million liters per day

(MLD)).There are 2 water treatment plants (WTP) of total capacity 34 MLD.

Groundwater is supplied directly after chlorination without pre-treatment. Figure 2 shows

the location of WTP and mains. The City has a distribution network of 1,964.35 km in

addition to 119.65 km of rising mains from 57 tube wells. The water supply zones

covered under the improvement works in Tranche-I & II are depicted in Figure 3.

37. Water is supplied twice a day for four-hours. Due to system deficiencies, the water

supply is unequal across the City. In low-lying areas, supply continues beyond normal

supply hours while in higher-level areas supply is very limited. There are at least 30

localities in the City where water is provided through mobile-tankers. Power supply in the

City is also erratic with frequent power cuts and voltage fluctuations, leading to

disruption of water supply.

38. Deterioration of water quality due to leaks and malfunctioning of WTPs is

common. Due to old and damaged pipelines, particularly in the Old City area, leaks are

frequent leading to water loss and water quality deterioration. Many of the old pipes buried

under roads (due to its subsequent widening) develop leakages and remain undetected

resulting in huge loss of water. Considering these issues as priority, a subproject for

optimization of water supply system in Dehradun is already being implemented under the

Tranche-I of UUSDIP. Tranche-II covers the balance components of water supply system.

B. Need of Tube wells in Dehradun

39. The water demand for Dehradun city at various stages is projected in Table No. 2.

Table No 2: Water Demand of the Project Area

Sl. No. Water Demand Quantity

1 Year 2021 162.05 MLD

2 Year 2026 188.71 MLD

3 Year 2031 216.80 MLD

4 Year 2041 279.11 MLD

40. The sources of water supply to Dehradun city along with its withdrawal is 43.58

MLD. The ground water sources are 105 nos. of tube wells producing and supplying water

which is approx. 166.84 MLD. The total water availability from ground as well as from

surface sources is 210 MLD. Some of the Tube-wells have either become totally non-

functional or their discharge has reduced considerably.

41. Considering the distribution losses at 15% and reduction in discharges of tube wells

by 15%, the net present availability would be 147 MLD. Although the present distribution

losses are much higher than the acceptable norms, it is anticipated that the losses would be

Page 26: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

18

brought within the acceptable limits after the completion of the projects undertaken by

UUSDIP for replacement of existing distribution system.

42. From the above table it is evident that even after reducing the distribution losses in

the present distribution system and after upgradation of WTPs; it will not be enough to meet

the projected water demand for the year 2026. This is because of the considerable

reduction in the discharge & non-Functioning of Existing Tube Wells.

43. Hence, it becomes imperative to construct additional tube-wells to meet the

projected water demand.

C. Description of Subproject

44. This Initial Environmental Examination (IEE) has been prepared and updated for the

following components of Dehradun Water Supply Subproject to be undertaken in Tranche

II: (i) Optimization of water management in Dehradun through laying of Rising Mains

and Feeder Mains (contract package No WSS05DN); (ii) Renovation/ Up-Gradation

of Dilaram Water Treatment Plant, Shehenshai Ashram WTP & Construction of new

conventional WTP and installation of softening plant at Purukul Gram (Contract Package

No. WSS06DN); (iii) Water Supply distribution system in 5 Zones, Dehradun (Contract

Package No. WSS07DN); (iv) Raw water main from Massi fall to Shehenshai Ashram

WTP (Contract Package No. WSS08DN); (v) Water supply distribution system in 7

Zones, Dehradun (Contract Package No. WSS09DN); (vi) Water supply distribution

system in 7 outer Zones, Dehradun (Contract Package No. WSS10DN); (vii) Installing

of Domestic water meters (Contract Package No. WSS011DN); (viii) 5 number of tube wells

in Dehradun (Contract Package WSS014DN) and (ix) construction of pedestrian footpath

and beautification of 4.8 from Dilaram Bazar to Masoorie diversion in Dehradun (Contract

Package No.(WSS15DN). The layout map of Galogi Intake, raw water main from Massi fall

to Shahanshahi Ashram WTP, Dilaram Bazar WTP, Purukul gram WTP and Shahashahi

Ashram WTP are given in Figure No. 4,5,6,7 and 8 respectively. The location maps of 5

tube wells within Dehradun are given in Figure No 9, 10, 11, 12, and 13. The location map

of pedestrian footpath is given Figure No 14. The detail of each component is as under in

Table No.3.

Table No 3: Dehradun Water Supply Subproject Components

Subproject

Component

Description Location

1

Water supply distribution mains

Discarding all existing distribution pipelines and laying of new distribution pipelines:

- 100mm DI K7 pipes – 351.3 km

- 150mm DI K7 pipes – 48.64 km

- 200mm DI K7 pipes – 21.1 km

- 250mm DI K7 pipes – 9.9 km

- 300mm DI K7 pipes – 5.5 km

- 350mm DI K7 pipes – 3.7 km

- 400mm DI K7 pipes – 0.05 km

- 19 zones of the municipal area of Dehradun town, excluding area already covered under the Zones, which has been taken up in Tranche-1

- Pipelines will be laid on or along the roads (within ROW with minimum of 1 m clear cover)

Page 27: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

19

Subproject

Component

Description Location

2

Upgradation of Dilaram Bazar WTP

Capacity of this Water Treatment Plant (WTP) is 20 MLD and receives 6 MLD water from Bandal River source. It is proposed that the water this source will increase once the old and profusely leaking gravity main is replaced and accordingly it is proposed to upgrade the capacity of this WTP from 20 MLD to 27.5 MLD.

Dilaram Bazaar Water Treatment Plant is located within Dehradun town.

3 Renovation of Shenshahi Ashram WTP

The existing capacity of this WTP is 14 MLD and receives raw water from Shekhar and Massi fall sources. It is proposed to rehabilitate some units and operate with its full capacity.

Shehensai Ashram WTP is located in the outskirts of the Dehradun Town.

4 Construction of Purukul gram WTP

It proposed to construct new 15 MLD water treatment plant

Purukul WTP is located at foothill near Purukul village 15 km away from Dehradun Town.

5

Transmission Mains

It is proposed to lay pipeline from Ground level service reservoir at Shehanshahi Ashram WTP to various intermediate overhead tanks to supply water by gravity.

- 100mm DI K7 pipes – 4.3 km

- 250mm DI K7 pipes – 1.0 km

- 300mm DI K7 pipes – 1.58 km

- 400mm DI K7 pipes – 0.66 km

- 600mm DI K7 pipes – 2.74 km

- 150mm DI K9 pipes – 2.45 km

- 200mm DI K9 pipes – 2.0 km

- 250mm DI K9 pipes – 4.7 km

- 300mm DI K9 pipes – 7.58km

- 450mm DI K9 pipes – 3.22 km

Pipeline starts from Shehanshahi Ashram WTP and passes through Rajpur road to reach Dilaram bazaar serving various overhead tanks enroute.

6 Raw Water Gravity Main

Discarding existing raw water gravity main and laying of new pipeline:

-400 mm (OD) with 6.3 mm shell thick ERW MS pipe-Length: 2 km

-CI sluice valve 400 mm -3 Nos

-CI scour valve 250 mm – 2 Nos

-Double Orifice Kinetic Air Valve 80 mm – 4 Nos

Raw Water Gravity Main start from Massi fall in hilly area and follows existing alignment to reach Shehenshai Ashram Water Treatment Plant

7 Galogi Intake Structure

The existing anicut (cross wall of height 1.8 m constructed with local stone boulders) is not in good condition, and the upstream side has been silted up due to a landslide in upper hilly areas. It is proposed to construct

The site is located at about 4 km from Dehradun-Mussorie Road. The intake site is approachable by the Galogi Power Station access road, from Dehradun-

Page 28: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

20

Subproject

Component

Description Location

a new anicut (20 m length and 1.8 m height) at the same location, with rock boulders, wrapped in iron mesh (like gabion wall), and an additional anicut, 20 m upstream, with a purpose to arrest the silt flow into the intake. A new RCC intake well will be constructed in the stream bed from where water will be conveyed by existing gravity main to the WTP at Purukul.

Mussorie Road. This road passes through hilly forest region and follows a difficult terrain for about 2 km.

8 House service connections

House service connections will be given from nearest WS distribution pipe line to the consumer house by Ferrules connection and using 20 to 32 mm GI pipeline.

House service connections will be laid from the distribution box to the household premises covering all population of the town.

9 Water meters

- AMR type water meters will be installed for domestic and commercial households.

- Total 12000 AMR type water meters will be provided.

Water meters will be installed inside the household premises covering whole of the Dehradun municipal area.

10 Construction of Pedestrian Footpath and beautification work of 4.8 km from Dilaram Bazar to Mussoorie Diversion

- Provisioning of tiles of different varieties, provision of Rain water shelters, landscaping, metal plates for advertisements, Grills over the divider warped with radium strips of different colours, harvesting tanks and horticultures works etc

Dilaram bazar to Mussoorie Diversion on both side of the road at the length of 4.8 Kms.

11 Construction of 5 Tube wells in Dehradun

- Installation of tube well at 5 locations in Dehradun of different depth 160 meters to 200 meters.

GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Construction of Pedestrian Footpath of 4.8 Km from Dilaram Bazar to Mussoorie

diversion

45. It is proposed to upgrade and rehabilitate the shoulders along Rajpur road and allied

works such as grills along the median in the centre of road, providing and laying tile of

different varieties made from square cut river stone block of size 5” x 5” x 4” natural sand

stones, Paver blocks, High quality concrete M-30 grade precast tiles having 50% opening

for grass plantation, rain water shelters and lighting etc. The existing old paver blocks will

be replaced with new paver blocks and new plantation will be carried out and plantation will

be secured through tree guards. The corridor along Rajpur Road will be provided lighting

arrangement through cylindrical shape integral decorative LED Bollard with opal acrylic is

proposed under the project.

46. The present work of Providing and laying tiling on shoulders along Rajpur road and

allied works from Mussoorie Diversion to Dilaram Bazar Dehradun city is being considered

to execute the works under Tranche II as an additional work to the ongoing contract for

WSS05DN. The work is proposed to be awarded under separate contract package. The

Page 29: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

21

procurement will be through competitive bidding and will be done as per the procurement

guidelines of ADB. The total cost of this sub-project is estimated as Rs.8.75 Crores

including provisional sum amount. Details are provided as below Table No 4 :

Table No 4 : Sub-project Details of laying and beautification of 4.8 Kms in Dehradun

Sl No.

Item Description

1. Name of the sub- project :

Providing and laying tiling on shoulders along the pipeline corridor on Rajpur road and allied works from Mussoorie Diversion to Dilaram Bazar in Dehradun (WSS15DN)

2. City / Towns Included : Dehradun

3. Special features of the city :

Capital City of Uttarakhand state and important city of the State progressing fast with natural cool pleasant weather conditions and Hilly region and going to be one of the Smart City of India.

Tourist places near to Mussoorie (Queen of Hill station and other tourist spots), important religious places like Rishikesh, Hardwar, Char Dham, Academic famous schools and Institutions of National importance like Doon School, ONGC, FRI, Historic survey of India, Hotel Management, NIVH and other like.

4. Name of the agency responsible for -

4.1 Planning and designing of project : UUSDIP / IPMU/ IPIU / DSC-I/ Architect

4.2 Implementation and Monitoring of project : UUSDIP / IPMU / IPIU/ Sub-IPIU / IPMC / DSC – I

4.3 Design and Concept : By Architect appointed by PIU

5. Sub-project Implementation Period : 2015 – 2016 (1 years)

6. Cost details :

6.1 Sub Project cost (Rupees in Crores) : 8.75 Crores

7. Schedule of Rates followed :

Delhi Schedule of Rates (2014) is adopted and for items which are not available in CPWD AoR, market rates have been considered, as provided by architect.

8 Length in km : 4. 80 km

Construction of 5 number of tube wells in Dehradun

Page 30: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

22

47. As an immediate requirement construction 5 nos. new Tube wells & pump houses in

Dehradun, to reduce the immediate supply - demand gap and ensure a systematic and

smooth water supply to the city is proposed as summaries below in Table No 5:

Table No 5 : Sub-project Details of construction of 5 tube wells in Dehradun

Item Description

Name of the project (WSS14DN) Supply and construction of 5 number of Tube wells in Dehradun

GGIC Rajpur Road,

Rajendra Nagar,

Kaulagarh,

Hari Vihar of Vijay park and

Kanak

City / Towns Included Dehradun

Project Implementation Period 2016 – 2017(12 months)

Project cost (Rupees in Lakhs) INR 8.5 Crores

Number of tube wells Total 5 number of tube wells located one at each location of GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak.

The findings and recommendations of hydrogeological study is given below in Table No- 6.

Table No 6 : Findings and recommendations of Hydrogeological study

S. No.

Location Discharge (lpm)

Depth

(m)

Water Level (m)

Screen Slot Size (mm)

Gravel Size (mm)

1 GGIC Rajpur Road

700-800 200 130-135 Johnson V

1.19 1.6- 4.76

2 Rajendra Nagar

500-600 190 85-90 Johnson V

1.19 1.6- 4.76

3 Kaulagarh 1500-1700 160-170 70-75 Johnson V

1.19 1.6- 4.76

4 Hari Vihar, Vijay Park

1400-1500 170-180 75-80 Johnson V

1.19 1.6- 4.76

5 Kanak Site is close to MKP college therefore no separate study required

D. Energy Efficiency Measures

48. The water supply subproject has been designed with utmost consideration of energy

efficiency in the whole system. The water supply from the surface sources is conveyed to

WTPs by gravity. After treatment, water is pumped to overhead tanks and supplied to

consumers by gravity. There are no pumping stations or energy intensive equipment

proposed in the subproject. While two WTPs (at Shensai Ashram and Purukul Gram) work

Page 31: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

23

on gravity flow, WTP at Dilaram Bazar is pumping based. The pumping systems proposed

at WTP are energy efficient. The equipment has been designed with the maximum

efficiency to optimize the energy consumption. Best pumps with ideal specific speeds have

been considered. Attainable efficiency for procuring the pumps and motors are considered

as 88 to 92 percent for pumps and 94 percent for motors.

49. Further, the augmentation of treated water production envisaged from the proposed

components will result in water augmentation from surface sources and therefore will

reduce the dependence on energy intensive groundwater sources. Accordingly, some tube

wells presently catering to tail end areas will be closed down, and water will be supplied

from WTPs. The pumping main and network design is optimized for terminal pressure

requirements. The reduction in UFW will certainly reduce the total water demand, and will

increase the overall efficiency including the reduction in power consumption. Advance

systems like SCADA is proposed for economy and effective monitoring of water supply.

E. Implementation Schedule

50. Detailed design work has been completed and civil work contracts are likely to be

awarded by end of December 2011. Construction work will commence in February 2012

and will be completed by the end of January 2014. Construction work for 5 numbers of

Tube wells and pedestrian footpath will commence in July 2016 on and will be completed

by June 2017.

51. The sub-project will be implemented by the Investment Program Implementation

Unit (IPIU) under direct administrative and financial control of Investment Program

Monitoring Unit (IPMU) which will be the Executing Agency. The DSC will assist IPIU in

implementation and IPMU on overall project management.

52. Contractor will work simultaneously at more than one location to complete

construction of all tube wells in Dehradun in 12 months. This timeframe includes designing,

site preparation and construction of tube wells. The work of providing & laying tiling on

shoulders along the pipeline corridor on Rajpur road from Mussoorie diversion to Dilaram

Bazar in Dehradun of 4.8 km will also require about 12 months.

Page 32: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

24

Figure 1: Location of Sub project town in Uttarakhand State

Page 33: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

25

Figure 3: Water Supply Zonal Coverage in Tranche-1 & II

Figure 2: Location of WTP & Gravity Mains

Page 34: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

26

Figure 4: Galogi Water Intake Layout Plan

Page 35: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

27

Page 36: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

28

Figure 5 : Raw Water Main from Massifall to Shahanshahi Asram WTP

Page 37: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

29

Figure 6: Layout Plan of Dilaram Bazar

Page 38: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

30

Figure 7 : Layout Plan of Purukul Gram WTP

Page 39: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

31

Figure 8 : Layout Plan of Shahanshahi Asram WTP

Page 40: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

32

Figure 9 : Location of Tube Wells in Vijay Park in Dehradun

Figure 10 : Location of Tube Well for Feeding Rajpur Road OHT in Dehradun

Figure 11 :Location of Tube Well for Rajendra Nagar OHT in Dehradun

Page 41: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

33

Figure 12 :Location of Tube Well for Hari Nagar OHT in Dehradun

Figure 13 :Location of Tube Well at Kaulagarh Canal Road

Page 42: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

34

Page 43: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

35

Figure 14 : Location of pedestrian footpath from Dilaram Bazar to Mussoorie diversion (4.8 Km)

Page 44: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

36

Page 45: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

37

Page 46: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

38

Page 47: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

39

Page 48: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

40

Page 49: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

41

III. DESCRIPTION OF THE ENVIRONMENT

A. Physical Features

1. Location

53. Located in the north western part of Uttarakhand at 30o 11’ 24” N latitude and 78o 2’ 24” E

longitude, Dehradun is the Capital City of the State. Dehradun is situated in the Doon Valley

formed by Himalayas in the north, and the Shivalik Mountain range in the south (Photo 10).

Largest Indian Rivers, the Ganga and the Yamuna form the eastern and western boundaries of

the Valley. Rivers of Song and Tons form the eastern and western boundaries of the City

respectively. In the east City is bounded by the Himalayas. There are numerous rivers and

streams belong to the Ganges and Yamuna River systems flow through the Valley.

54. Dehradun is well connected by road with the national capital Delhi (255 km) and other

major cities Chandigarh, Agra and Shimla in north India. It also connected with Delhi by railways.

Owing to its location and Salubrious climate and natural beauty, Dehradun is home for many well-

known research, administrative, and training institutes. The City is also famous for best schools in

India.

2. Topography, Geology and Soils

55. Dehradun City is surrounded by dense hilly forests. The altitude of the City ranges from

1000 m in the north hilly region to 600 m in the south, with an average altitude of 640 m. It slopes

north to south and is dissected by numerous seasonal streams, locally known as Khalas. City

drainage is borne by the Bindal and Rispana Rivers. The direction of flow of streams in the

eastern part is north to south (Bindal River) and in western part it is north to southwest (Rispana

River).

56. The soils in the City are alluvial, riverine, and non-calcareous to moderate calcareous

soils, which have been carved out by the fast flowing rivers draining the Himalayas. Limited

distribution of red soil is also found in some places. Forest soils, which occur under coniferous

and deciduous forest, are found rich in organic matter. Mountain /hill soils are the collective

terminology used for various types of soils occurring at very high elevations, under a wide range

of forest types trees. All the hill ranges around Dehradun (except the Sivaliks) are rich in lime

stone reserves.

57. Dehradun falls in Sub-Himalayan physiographic zone of Uttarakhand State. The

physiography possesses the least of Himalayan features, and consists of two sub-zones, the

Shivaliks - the youngest of the Himalayan ranges and the Doon (flat longitudinal structural

valleys) to the north of Shivaliks. The Shivaliks extend in a narrow varying width of 6 to 30 km

with altitudes of 300 to 1000 m.

58. Due to the fragile eco-system and geo-dynamic terrain, Uttarakhand State is highly

vulnerable to natural disasters like earthquakes, landslides, forest fires, and cloud burst etc.

According to hazard zoning in the Vulnerability Atlas of India, the whole of Uttarakhand falls

under “very high” to “high” category earthquake zone. The problems of landslides, subsidence,

and erosion are quite common in the hilly regions of the State due to combination of several

factors like geological movements, structure, lithology, water seepage, soil cover, vegetal cover,

weather, and climatic changes.

3. Climate

Page 50: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

42

59. The Climate of the district is generally temperate. It varies greatly from tropical to severe

cold depending upon the altitude. The district being hilly, temperature variations due to difference

in elevation are considerable. Dehradun has typical weather of a north Indian City with cold

winters, hot summer, rainy monsoon season and a balmy spring. The winter, from November to

February, is cold, and temperatures touches near freezing occasionally. The months of

December and January are the coldest due to winter rains, coinciding with snow-fall in the nearby

mountains ranges (maximum and minimum winter temperature is 23.4°C and 5.2°C respectively).

Overall the winters are dry. The spring, lasting from March to April, is very pleasant. Summer

lasts from April-May to July with fairly high temperatures (maximum and minimum summer

temperature is 36°C and 16.7° C respectively).

60. The monsoon months, particularly July and early August are extremely humid. The annual

average rainfall (AAR) of Dehradun is 2075 mm, of which about 62% is concentrated in the

months of July and August. The region around Dehradun does not experience the falling of

leaves, typical of cold regions. Table No. 7 presents the long term average data of climatic

parameters.

Table No 7 : Climatic Data of Dehradun (Period 1960 to 1990)

Month Rainfall

(milli meter)

Relative

Humidity (%)

Temperature (o C)

Maximum Minimum Average

January 46.9 91 19.3 3.6 10.9

February 54.9 83 22.4 5.6 13.3

March 52.4 69 26.2 9.1 17.5

April 21.2 53 32 13.3 22.7

May 54.2 49 35.3 16.8 25.4

June 230.2 65 34.4 29.4 27.1

July 630.7 86 30.5 22.6 25.1

August 627.4 89 29.7 22.3 25.3

September 261.4 83 29.8 19.7 24.2

October 32.0 74 28.5 13.3 20.5

November 10.9 82 24.8 7.6 15.7

December 2.8 89 21.9 4.0 12.0

Annual Average

2051.4 76 27.8 13.3 20.0

4. Air Quality

61. Under the National Ambient Air Quality Monitoring (NAAQM) Programme, Uttarakhand

Environmental Protection and Pollution Control Board (UEPPCB) is regularly monitoring the

ambient air quality at Rajpur Road, and Clock Tower in Dehradun City. The status of ambient air

quality of the City during the period of 2005-2006 is presented in Table 8. While chemical

pollutants, sulphur dioxides (SO2) and oxides of Nitrogen (NOx) are well within the limits of

Page 51: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

43

National Ambient Air Quality standards, the respirable suspended particulate matter (RSPM) and

suspended particulate matter (SPM) are exceeding the limits. Contractors will generate the base

line data of ambient air quality before the commencement of civil works at proposed Tube wells

locations and along the pedestrian footpath.

Table No 8: Air Quality of Dehradun (Period 2005 to 2006)

Month SO2 (μg/m3) NOx (μg/m

3) RSPM (μg/m

3) SPM (μg/m

3)

Apr, 05 24 26 232 618

May, 05 21 27 125 397

Jun, 05 19 24 147 370

Jul, 05 22 25 132 278

Aug, 05 22 26 130 303

Sep, 05 29 28 118 291

Oct, 05 - - - -

Nov, 05 - - - -

Dec, 05 21 25 182 366

Jan, 06 23 26 149 324

Feb, 06 21 24 165 370

Mar, 06 21 18 148 351

National Standard 80 80 100 200

SO2-sulphur dioxide; NOx-oxides of Nitrogen; RSPM-respirable suspended particulate matter; SPM-suspended particulate matter. All units are in μg/m

3

5. Noise

62. UEPPCB conducts monthly noise level monitoring at various locations of the City. As

presented in the Table 9, the noise levels at all monitoring locations is exceeding the standards.

The Contractors will generate the base line data of ambient noise levels before the

commencement of civil works at proposed Tube wells locations and along the pedestrian

footpath.

Table No 9: Noise Levels in Dehradun (Period 2005 to 2006)

Month / Year Race Course Near MLA House

(Residential area)

Doon Hospital (Silence

Zone)

Clock Tower

(Commercial area)

Gandhi Park

(Silence Zone)

Survey Chowk

(Commercial Area)

C.M.I. Hospital (Silence

Zone)

May, 2005 63 60 75 62 74 -

Page 52: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

44

Month / Year Race Course Near MLA House

(Residential area)

Doon Hospital (Silence

Zone)

Clock Tower

(Commercial area)

Gandhi Park

(Silence Zone)

Survey Chowk

(Commercial Area)

C.M.I. Hospital (Silence

Zone)

June, 2005 - 60 75 65 73 61

July, 2005 64 66 80 54 - 66

August, 2005 71 59 90 62 76 65

September, 2005 60 64 77 62 76 63

December, 2005 62 60 73 52 76 64

January, 2006 65 64 88 67 79 64

February, 2006 66 63 87 66 76 64

March, 2006 70 68 91 68 84 73

Standard 55 45 65 45 65 45

All units are in dB(A)

6. Surface Water

63. The Dehradun City is surrounded by River Song in the east and River Tons in the west.

Seasonal rivers of Bindal and the Rispana flow during the monsoon. In the rest of the year these

rivers mostly remain dry or carry wastewater. No water quality data of these rivulets is available.

7. Groundwater

64. The predominantly hilly State of Uttarakhand has a varied hydrogeological setup and is

divided broadly in to two distinct hydrogeological regimes viz. the Gangetic alluvial plain and the

Himalayan mountain belt. The former is covered with a vast expanse of alluvium and

unconsolidated sedimentary material of varying size fractions (ranging from boulder to clay) and

is a promising zone for ground water development. The latter zone, being predominantly hilly,

offers much less potential for large scale development of ground water. Ground water in the hilly

region occurs mostly in fissures/fractures and emerges as springs. The springs are amenable to

small scale development of ground water resources in the State.

65. Dehradun falls in the Himalayan mountain belt. The yield of tube wells in Siwalik formation

is low and ranges from 50.4 m3/hr to 79.2 m3/hr. The depth of groundwater ranges between 80-

100 m.

66. As per the study of central ground water board, Dehradun has three units namely,

Sahaspur, Doiwala and Vikas Nagar. All these blocks are Safe Category and non-notified area4.

These assessment units are categorized on the basis of stage of ground water development and

_________________________

4 Source http://cgwa-noc.gov.in/LandingPage/NotifiedAreas.htm

Page 53: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

45

long term water level trend studied by CGWB and CGWB does not apply any restriction of

Jalsansthan for withdrawal of ground water.

67. The geological conditions of the subproject area is described as Dehradun area falling in

the intermountain Doon Valley and is underlain by recent to sub recent Doon Gravel, which lie

over the Upper Shiwalik Sediments. This gives high degree of porosity and permeability. Since

rainfall in this area is about 2000 mm so it is characterised by high rate of infiltration and resulting

high rate of ground water recharge. The water table in this area in the pre-monsoon ranges from

130 to 135 meters. There is no contaminated area in and around Dehradun so there is no risk of

movement of contaminant or risk of finding Arsenic due to abstraction of water. The aquifers are

composed of mainly sand, Gravel and boulders.

68. The Contractors will generate the base line data of ground water quality before the

commencement of civil works at proposed Tube wells locations.

B. Ecological Resources

69. The hilly State of Uttarakhand has a forest cover of 65 % of its total geographical areas

(slightly lower than the stipulated 66.6 % forest cover for hilly states). In the Dehradun District,

forest areas occupy 43.7% of area. Dehradun City, the district head quarter, is an urban area

surrounded by hilly forested areas. There is no remaining natural habitat within the developed

area of the City (refer the land use pattern given in next section). Some forest areas (Raipur

Reserve Forest, Bandal Reserve Forest) are situated outside the Municipal Area towards north

and north-east. Variety of species of shrubs, climbing plants and grasses are found in these

forests. Sal and Chir are predominant in and around Dehradun.

70. The closet protected area is Rajaji National Park situated 10 km west of the Dehradun

City. Designated as National Park in 1964, it spreads over an area of 820 square kilometres

(sq. km) and is endowed with pristine beauty and rich bio-diversity. This has over 23 species of

mammals, including elephants and tigers, and 315 avifauna species. The other protected areas in

the Dehradun District are: (i) Mussoorie wildlife sanctuary, north of Dehradun, and (ii) Asan

wetland conservation reserve, northwest of Dehradun. However, none of the subproject

components located in or near these protected areas.

71. Proposed locations of tube wells and pedestrian footpath are more than 10 Km from

boundary eco-sensitive zone. Some trees are available in and around the proposed construction

site at tube well locations and pedestrian footpath. These will be kept undisturbed by selecting

and accommodating the layout within available open land. In case any tree is unavoidable to

protect, requisite permission for felling of trees will be obtained from concerned department.

C. Economic Development

72. Located close to the national capital Delhi and with its salubrious climate and natural

beauty, Dehradun has been traditionally an educational and institutional centre and also a most

sought after residential City in the northern India. India's some of the best public schools and

convents are located here. Many well known research and training institutes like the Indian

Military Academy, Forest Research Institute, Survey of India, Wildlife Institute of India etc,

Anthropological Survey of India, Botanical Survey of India, Indian Institute of Petroleum, Indian

Institute of Remote Sensing, Survey of India, Wadia Institute of Himalayan Geology, Zoological

Survey of India, etc are located here. Mussoorie, 34 km north of Dehradun, is a famous summer

tourism destination. Having made the capital of newly formed State, Dehradun has become an

administrative centre. With the fast diminishing agricultural area under the developmental

Page 54: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

46

pressure, and with no major industrial development, Dehradun economy is mainly tertiary

(service) sector based.

1. Land use

73. Located close to the national capital Delhi and with its salubrious climate and natural

beauty, Dehradun has been traditionally an educational and institutional centre and also a most

sought after residential City in the northern India. India's some of the best public schools and

convents are located here. Many well known research and training institutes like the Indian

Military Academy, Forest Research Institute, Survey of India, Wildlife Institute of India etc,

Anthropological Survey of India, Botanical Survey of India, Indian Institute of Petroleum, Indian

Institute of Remote Sensing, Survey of India, Wadia Institute of Himalayan Geology, Zoological

Survey of India, etc are located here. Mussoorie, 34 km north of Dehradun, is a famous summer

tourism destination. Having made the capital of newly formed State, Dehradun has become an

administrative centre. With the fast diminishing agricultural area under the developmental

pressure, and with no major industrial development, Dehradun economy is mainly tertiary

(service) sector based.

74. Table 10 below the land use pattern of 1981 and proposed land use of 2001 based on

the Dehradun Master Plan, 2001. The total developed area was increased from 3,802

hectare (ha) in 1981 to 7,045 ha in 2001. Of the present 7,045 ha, predominant land is under

residential use followed by facilities and services that occupies about 21% of the developed

land. Water bodies occupy 8.7 % while the industrial land use is limited to about 3 %.

75. Land use of proposed tube wells are government land currently being used for abstraction

and pumping of ground water for the purpose of supply of water to the local community. The

proposed site of construction of pedestrian footpath is redundant footpath. So, both sites do not

require land acquisition for construction of tube wells or pedestrian footpath.

Table No 10 : Existing and Proposed Land Use - Master Plan 2001

S. No. Land Use Existing Developed Urban Area 1981

Proposed Urban Area 2001

Area in ha % age to total Area in ha % age to total

1 Residential 1,588.80 41.78 3,001.77 42.60

2 Commercial 81.00 2.14 290.00 4.12

3 Industrial 113.36 2.98 350.00 4.97

4 Govt and Semi govt

267.20 7.00 313.52 4.45

5 Facilities and Services

802.22 21.00 833.21 11.82

6 Orchards and Gardens

205.65 5.40 250.65 3.55

7 Open Spaces, Parks

156.00 4.10 226.00 3.22

8 Circulation 203.03 5.35 400.09 5.68

Page 55: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

47

S. No. Land Use Existing Developed Urban Area 1981

Proposed Urban Area 2001

Area in ha % age to total Area in ha % age to total

9 Rivers and Nalas

331.50 8.74 1,295.88 18.39

10 Undefined Land use

55.00 1.45 84.01 1.20

Total 3,802.75 100 7,045.13 100

2. Industry and Agriculture

76. As earlier stated, Dehradun economy is mainly service sector based. Industrial

development is very limited. After the formation as a separate state in 2000, the industrial

development in Uttarakhand has been picked up. There are no major industries located in and

around the Dehradun City. The Dehradun District houses 37 large and medium scale industrial

units (which include 7 chemical/pharmaceutical units, 8 electrical and 4 food processing units)

providing employment for about 8,278 persons. Though these units are not located in the City,

Dehradun benefits from the presence of these industries as a service provider. Being the

gateway to the Himalayan region of the State, and the last rail head, Dehradun attracts large

number of tourists on their onward journeys to different hill destinations.

77. Owing to its hilly topography, agricultural development in the state is also limited.

Although limited, the State draws advantage from fertile lands availability of abundant water.

Dehradun and surroundings were well known for production the famous “Basmati” rice crop.

However, of late, the development pressure has conversed many of these agricultural lands.

Also, nestled in a wide and thickly forested valley of the Sivalik ranges, Dehradun is also famous

for its fruit orchards such as leechis and mangoes.

3. Infrastructure

78. Water supply: The piped water supply system in Dehradun was provided in 1885 with

Kolukhet springs as a water source. At present, ground water is the main source, providing 76%

of its total supply 102 MLD. Water supply system covers almost the entire City with a

distribution network of 1964 km. Due to old system, water losses are high. Water is supplied four

hours a day; but supply is not constant throughout the City owing to system defects. Water is

currently supplied through mobile tankers in some areas. Average per capita supply is about 124

litres per day. Uttarakhand Peya Jal Nigam (UPJN) and Uttarakhand Jal Sansthan (UJS) have

respectively involved in development and day-to-day operation of water supply system.

79. Sewerage: Sewerage system in Dehradun was provided in 1921, with surface drains,

water flush toilets and short length intercepting sewers. Since, then it has been extended to

various parts of the town and presently covers 50 % of the population. However, as there is no

sewage treatment facility, collected sewage is disposed directly into Rispana and Bindal Rivers.

Remaining 50 % population depend on individual septic tank based waste disposal systems. With

the deep groundwater table (80 – 100 m deep), these systems are said to be functioning well.

The UPJN and UJS are involved in sewerage service provision.

80. Storm water drainage: Owing to high rainfall and the hilly topography, natural drainage is

well developed in Dehradun. Roadside drains, connected to natural streams, are developed all

over the City, except in newly added areas and few slums. Temporary flooding, mainly due to

Page 56: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

48

choking and encroachment of drains, is experienced in some low-lying areas during monsoon

The Dehradun Nagar Nigam (DNN) develops and maintains the storm water drainage system in

the City.

81. Solid waste management: About 200 tons of solid waste is generated in the City daily at

a rate of about 400 gm/day, per household The DDN is responsible for solid waste management

including collection, transportation and safe disposal. Waste is collected through community

bins, and the DDN also introduced door-to-door waste collection in part of the City. Street

sweeping is carried out regularly. Collected waste is transported to the disposal site at Dateda

Lakhond 7 km north east, where waste is disposed in trenches and covered with soil.

82. Transportation: Dehradun has a well developed road network of 463 km, of which 363

km are maintained by DDN and the rest by Public Works Department (PWD). Arterial roads are

wide and surfaced with bitumen, and the internal roads are mostly of cement concrete. Roads in

the City centre are very narrow and congested with traffic and pedestrian, and in the out areas

roads are comparatively wide and under-utilised. City public transportation system mainly

comprises buses and three wheeler auto-rickshaws. National highways (NH) 72 and 72A pass

through the City and is well connected by road with New Delhi (255 km) and other cities

Chandigarh (130 km); Haridwar (54 km); Agra (382 km); Shimla (221 km) and Nainital (297 km).

Dehradun is also well connected by railways with regular services to Delhi Calcutta, Mumbai,

Varanasi and Lucknow. Dehradun has an air port, located at 25 km of the City.

83. Power supply: Hydro power is the main source of energy in Uttarakhand. Uttarakhand Jal

Vidyut Nigam Limited (UJVNL) is responsible for power generation and Uttarakhand Power

Corporation Limited (UPCL) is responsible for power transmission and distribution in the State.

Power is supplied from the central grid by overhead cables carried on metal and concrete poles,

mainly located in public areas alongside roads. The power supply is erratic and there are frequent

outages in warmer months, and large fluctuations in voltage.

4. Social and Cultural Resources

84. Demography: Based on 2001 census, Dehradun population was 0.45 million, up from

0.27 million in1991, registering a decadal growth of around 40 %. Average population density is

6,700 persons/sq. km. Sex ratio (females per 1000 males) was 900 significantly lower than the

State and the national average of 950 and 929 respectively. Literacy rate is reported at 90.3 % for

males and 81.1 % for females.

85. Overall work participation rate is 28.5 %, reported at 46.5% for males and 8.6% for

females. Occupational pattern shows that 96% of the persons are engaged in industrial and

service sector (organised and unorganised). Around 1.5 % workers engaged in agricultural

activities and the rest in household industries.

86. Around 86 % of the population are Hindus and the remainder are mainly Muslims and

Sikhs. Main languages spoken in the District are Hindi, Garhwali, Sindhi, Punjabi, and Urdu.

About 0.5% of the population are from Scheduled Tribes (ST), but these are all part of the

mainstream population; around 11% of the population belong to scheduled castes (SC).

5. History, Culture and Tourism

87. Dehradun City owes its origin to Sikh Guru Ram Rai. Legends say that the name of the

City was derived from “Dehra”, the later version of Dera meaning a temporary camp. The term

Dun or Doon means the low lands at a foot of mountain range. Early history of Dehradun is

unavailable. From the 17th Century, this region was said to be formed part of the Garhwal

kingdom with some interruption from Rohillas. For about two decades, till 1815, it was under the

occupation of the Gorkhas. In 1815 Gorkhas were ousted from Garhwal region and Garhwal was

annexed by the British. In that year the area now comprising tehsil Dehra Dun was added to

Page 57: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

49

district Saharanpur. In 1825, it was transferred to the Kumaon Division. In 1829, the Dehra Dun

district was transferred to the Meerut Division. In 1842, Dun was attached to Saharanpur district

but since 1871 it is being administered as separate district. In 1968 the district was taken out from

Meerut division and included in the Garhwal Division, which finally formed part of the newly

created State of Uttarakhand.

88. Dehradun is well known for its scenic natural beauty, waterfalls and forested areas and is

also the gateway to important Hindu religious places of Rishikesh, Badrinath, Kedarnath, and hill

station Mussoorie. The important places of tourism interest in and around Dehradun are

Gurudwara, Sahastradhara, Robbers Cave, Dakpatthar, Tapkeshwari Mahadeo temple, Guru

Ram Rai Darbar, Malsi Deer Park, Rajaji National Park and Raipur spring. Jhanda Fair, held

every year at the historic Guru Ram Rai Darbar, attracts a large number of pilgrims. Available

statistics show that nearly 1 million tourists visited Dehradun in 2003. None of these places are

located close to the proposed subproject sites.

Page 58: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

50

IV. ANTICIPATED IMPACTS AND MITIGATION MEASURES

89. This section of the IEE reviews possible subproject-related impacts, in order to identify

issues requiring further attention and screen out issues of no relevance. ADB SPS (2009) require

that impacts and risks shall be analyzed during pre-construction, construction, and operational

stages in the context of the subproject’s area of influence.

90. The ADB Rapid Environmental Assessment Checklist for Water Supply in

http://www.adb.org/documents/guidelines/environmental_assessment/eaguidelines002.asp was

used to screen the subproject for environmental impacts and to determine the scope of the IEE

investigation. The completed Checklist is found in Appendix 2 . All the proposed subproject

components, except the supply & installation of domestic waste meters will interact physically

with the environment.

91. In the case of this subproject (i) most of the individual elements are relatively small and

involve straightforward construction and operation, so impacts will be mainly localized and not

greatly significant; and (ii) most of the predicted impacts are associated with the construction

process, and are produced because that process involves excavation and earth movements,

will not cause direct impact on biodiversity values. The subproject will be in properties owned

and acquired by the local government and access to the subproject locations is through public

Right of Way and existing roads hence, land acquisition and encroachment on private property

will not occur.

A. Pre-Construction – Location and Design

92. Design of the Proposed Components. The Central Public Health and Environment

Engineering Organization manual suggests a design period of 15-30 years. The water supply

components were designed following the recommendations of the Central Public Health and

Environment Engineering Organization Manual for Water and Water Supply.

93. Impacts arise from the design of the project including the technology used, scale of

operation/throughput, waste production, discharge specification, pollution sources and ancillary

services. Since this is only a rehabilitation project, no design impacts envisaged.

94. Impacts associated with the planning mainly depend on the site selection. Location

impacts include on-site biophysical array and encroachment / impact either directly or indirectly

on adjacent environments. It also includes the impacts on the people who might lose their homes

or livelihoods due to the development of the proposed site.

95. Encroachment into private properties, forestland and cutting of trees and damage

to vegetation.

96. Distribution Network Improvement. Most subproject components involve simple

construction and low operation and maintenance, so it is unlikely that there will be major impacts.

The pipeline replacement works are located in the City area where there are no sensitive natural

habitats. The pipelines are aligned in the vacant land adjacent to the roads within the ROW, so

there are unlikely to be any location impacts. Selection of site of 5 Tube well in Dehradun.

97. Source and Supply augmentation Through Raw Water Main. The 2.0 km pipe gravity main

from collecting chamber at Shikhar falls to Water Treatment Plant at Shehenshai Ashram WTP in

Dehradun is located completely outside the City. The pipeline will be laid within the existing

alignment. Alignment details are provided below:

Page 59: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

51

(i) From the source, initial 600 m of pipeline will be laid in a narrow earthen road, which runs

along the stream originating from the falls. This is a hilly alignment with steep slopes.

There are no trees, except small bushes/shrubs in the alignment.

(ii) Existing pipeline was laid in the hilly terrain, where at present a road existing all along the

alignment – mostly earthen road, but concrete at few location. This is also in the hilly

terrain. A village is located between 600-1,100 lengths. There are no houses/private

properties or trees in the alignment.

(iii) The last 350 of existing pipeline runs through barren government lands, in the hilly area

covered with small shrubs and bushes.

98. As stated above, for a short distance pipeline passes along a perennial water stream.

This is a hilly stretch; on one side of the pipeline, the water stream is flowing at a much lower

level, and the other side is covered with hills. No major construction work is anticipated, as in

this stretch the existing pipeline was laid in a stone masonry trench covered with stone/concrete

slabs which can be removed for accessing the pipe for repairs. Presently, slabs are covered with

soil overburden. Spillage of soil into the water stream may lead to silting of stream. Following

measures are suggested:

(i) Ensure no spillage of soil/materials into the water stream; place wooden planks to cover

the stream and clear off the soil immediately

(ii) Ensure skilled supervision in removal of soil overburden; work shall be conducted

manually, and no major equipment shall used in this hilly terrain

99. The hilly areas near the alignment gravity main alignment are under forest. However the

entire pipeline alignment is passing through non-forest area, as forests are mostly on hills and

the pipeline follows the foothills. There were few shrubs and bushes of domesticated species in

the alignment which may need to cut-off. Following mitigation measures have been

implemented:

(i) Aligned pipeline in such a way that there will be minimum disturbance and clearance of

vegetation

(ii) No trees shall be felled for construction purpose

100. Replacement of Existing Anicut and Intake at Galogi Power House. The existing anicut

(cross wall of height 1.8 m constructed with local stone boulders) near Galogi Hydro Power

House across Kiliyarkuli Stream is not in good condition, and the upstream side of the intake has

been silted up due to a landslide in upper hilly areas. The intake is unable to provide water

supply at design capacity during summer months. Water also contains high silt that directly

enters the raw water pipeline. It is therefore proposed construct a new anicut (20 m length and

1.8 m height) at the same location, with rock boulders, wrapped in iron mesh (like gabion wall).

An additional anicut, 20 m upstream, with a purpose to arrest the silt flow into the intake, is also

proposed.

101. Kiliyarkuli Stream originates from Bhatta falls near Bhatta Village, in the hilly upstream

areas, about 22 km from the intake site. Water from the stream is tapped for power generation

and disposed back into the stream just upstream side of the water supply intake. This is a

perennial stream, and during rains it carries very heavy flows. In summers, the flow is very less.

The site is surrounded by hilly forest areas. The intake site is approachable by the Galogi Power

Station access road, from Dehradun-Mussoorie Road. This road passes through hilly forest

region and follows a difficult terrain for about 2 km. The site is located at about 4 km from

Dehradun-Mussoorie Road.

Page 60: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

52

102. As no augmentation is proposed, abstraction will be at existing level (12 MLD), no impacts

on stream flow envisaged (minimum flow in lean season is 20 MLD, and flow during monsoon is

very high). This site is located in hilly forest areas, and will require permission of Forest

Department for construction work. However no impacts on forest areas envisaged, as the work

will not encroach into forests. With the presence of activities and people, who work in the

powerhouse and live in nearby residential quarters, the site and surroundings are not very

sensitive; the movement of wildlife around the site is very less. During operation stage, no

impacts are envisaged.

103. Following measures will however be required to avoid any impacts due to construction

works:

(i) No construction material storage/ancillary works shall be conducted in the forest area; this

shall be limited to actual construction area and the access road

(ii) No labour camps shall be located near the site; no labour/construction related persons

shall be allowed to stay after work hours; except security guards on duty

(iii) Limit the work to daylight hours only; no work shall be conducted after sunset;

(iv) The Contractor shall take all necessary precautions to prevent his workmen from

removing and damaging any trees/vegetation/hunting animals in nearby forests; the

contractor will be severely penalized for these activities

(v) Conduct construction work in lean flow season (summer)

(vi) Construction area shall be protected properly with bunds so that stream flows without any

hindrance or mixing of silt/material in the water

(vii) Conduct awareness programs to workers on environment & safety at the site

(viii) No noisy works shall be conducted

(ix) Barricade the construction area – including the material storage area

(x) Implement any measures as suggested by the Forest Department

(xi) Use excavated soil for strengthening bunds/road leveling; no waste shall be disposed in

or near forests

(xii) Hard barricading around the bore well.

104. Up-gradation of Water Treatment Plant. Out of three, Purukul and Shahenshahi Ashram

WTPs are located outside Dehradun, while Dilaram Bazar WTP is within the city. The

rehabilitation/upgradation work will confine to existing WTP sites only. The details are provided

below:

(i) Purukul WTP is located at foothill near Purukul village. There is no habitation close to

existing WTP. However nearby land has been acquired by various real estate people for

housing & commercial purposes. Site is covered with small shrubs and eucalyptus tree.

The design team shall try to avoid/minimize the tree cutting during

rehabilitation/construction of WTP. There are no sensitive environmental features like

forests in the vicinity.

(ii) Shehensai Ashram WTP is also located in the outskirts of the Dehradun Town. As the

proposed works will be confined to the existing WTP facility area, no impacts are

anticipated. There are no trees at the site. There are no sensitive environmental features

like forests in the vicinity.

Page 61: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

53

(iii) Dilaram Bazar WTP is located within the city, along a main road, amidst commercial,

institutional and residential areas. The up gradation of WTP will mainly include the

replacement of electro mechanical equipments and civil work for the construction of new

units. The construction work will be confined to the existing facility, and requires no

acquisition of land. No tree cutting is anticipated for this upgradation work.

105. Construction of tube wells shall be undertaken on the government owned land. There are

some trees available at the construction site and these will be saved with change in layout at

available land. In case the tree cutting is unavoidable, necessary permission shall be obtained

from forest department. Limit the work to daylight hours only; no work shall be conducted after

sunset. Prior information about the construction work will be given to local people.

106. Construction of pedestrian foot path shall be taken up within existing available right of

way. The alignment has been selected in such a way that no tree cutting is required.

107. Site selection of sources of materials. Extraction of materials can disrupt natural land

contours and vegetation resulting in accelerated erosion, disturbance in natural drainage

patterns, ponding and water logging, and water pollution. To mitigate the potential environmental

impacts, locations of quarry site/s and borrow pit/s (for loose material other than stones) would be

included in the design specifications and on plan drawings. Priority would be sites already

permitted by Mining Department. If other sites are necessary, these would to be located away

from population centres, drinking water intakes and streams, cultivable lands, and natural

drainage systems; and in structurally stable areas even if some distance from construction

activities. It will be the construction contractor’s responsibility to verify the suitability of all material

sources and to obtain the approval of the ULB. If additional quarries will be required after

construction is started, then the Construction Contractor shall use the mentioned criteria to select

new quarry sites, with written approval of municipal council.

B. Construction Stage

108. Construction is the activity in which the project interacts physically with the environment,

so during which the environmental impacts occur. Construction impacts are associated with site

cleaning, earth works, physical construction related materials movements and works, machinery,

vehicles, and workers. It also includes erosion, dust, noise, traffic congestion and waste

production associated with the construction activities.

1. Construction Method

109. Distribution Network Improvement and Raw Water Main. About 441 km of pipeline of

100–400 mm diameter is proposed for replacement. The existing pipelines that are traversing

private properties/built up areas will be realigned adjacent to roads within the ROW. In narrower

roads where there is no land available, the trenches will be dug into the edge of the road.

110. Pipes will be buried in trench of 1-2 m deep and width between 0.6 -1.0 m. Trench will be

excavated manually or by a backhoe digger. Excavation in hard surfaces like cement concrete

(CC) roads will be supplemented by pneumatic drills. Excavated soil will be placed nearby and a

bed of sand or gravel - obtained from local quarries, will be prepared at the bottom of the trench.

Pipes (brought to site on trucks and stored on unused land nearby) will be placed in the trench

over the sand/gravel bed manually or using a small rig. Pipes will be joined by hand, after which

excavated soil will be replaced around and on top of the pipe manually and the refilled material

will be compacted by a vibrating compressor.

111. About 2.0 km of raw water main will be laid outside the City. No impacts are envisaged as

the new pipeline will be laid within the existing stone masonry trench covered with stone/concrete

slabs which can be removed for accessing the pipe for repairs. Presently, slabs are covered with

Page 62: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

54

soil overburden. Spillage of soil into the water stream may lead to silting of stream. Pipe will be

laid over/below the road bridge and fixed with hinges at crossing the stream. There will be no

trenching.

112. The earthwork involved in the subproject will be in the tune of about 576,090 m3. About

569,023 m3 of the excavated soil will be used for backfilling and therefore surplus soil generation

will be very minimal. An estimate shows that this will generate about 7,067 m3 of surplus soil

which needs to be disposed off.

113. The old pipes which are mainly of cast iron (CI) and rest of mild steel (MS) will be

removed immediately from the site and transported to UPJN premises or disposed off as scrap

for recycling/reuse. In locations where pipes are realigned due to encroachments, existing

pipeline will be left as it is in the ground.

114. Replacement of Existing Anicut and Intake at Galogi Power House. The proposed

two anicuts at Galogi Power House will be constructed using locally available rock boulders.

These will be arranged as a cross wall and bounded together by wrapping a wire mesh. An

excavation of 0.5-1 m deep will be made, and foundation will be laid using the boulders and the

wall will be raised continuously till it reaches a height of 1.8 m. Work will be constructed manually

with few workers and completed in about 2-3 months. Work will mostly be conducted during lean

flow season.

115. The specific construction impacts of this component, mainly due to its location in the

stream surrounded by forests, were already discussed in earlier section on location impacts.

Measures were also suggested.

116. Up-gradation of Water Treatment Plant. In case of Purukul WTP, earthwork will be

involved for the construction of new WTP, which shall generate spoil material. The excess

material will be utilized for the low lying area filling up nearby WTP. The new pumps will be

placed within the existing pumping stations. The old pumps will be transported to UPJN premises

and disposed as scrap for recycling. Filter media sand of water treatment plant will be removed

and the media (brought from the nearest queries) will be placed manually. Most of the old media

will be suitable for reuse after washing. The leftover sand will be disposed off appropriately.

Construction Methods of Tube Wells:

117. Construction of Tube Wells will be done by drilling of bore hole using Direct Rotary

Method. The work included lowering of well assembly, development of bore well and performance

(yield) test. The diameter of borehole will be suitable for lowering of 300/250/200 mm nominal

diameter well assembly having annual space sufficient to accommodate pea gravel pack of 100

mm thick.

118. Depth of drilling in the project area is generally expected to vary between 100 to 200

meters range. The rig machines suitable as per the geotechnical condition (general classification

of soil given elsewhere) / requirement to drill gravel packed bore wells.

119. Submersible pumping machinery with all associated valves, pipework, fittings,

instrumentation, flowmeters, gauges etc will be provided.

120. Construction of Pump houses, Construction of Boundary Walls, lighting and allied works

are included in this work. All utilities shifting (Electrical line, Telephone line, water supply lines

etc.) falling in the alignment of pipe laying will be executed through the respective Line

Departments.

Page 63: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

55

121. The chemical and bacterial test of water will be conducted by the contractor through

approved environmental monitoring agency to ensure the required quality of water at desired

depth of boring.

Construction methods of Pedestrian Footpath:

122. It is proposed to upgrade and rehabilitate the shoulders along Rajpur road and allied

works such as grills along the median in the centre of road, providing and laying tile of different

varieties made from square cut river stone block of size 5” x 5” x 4” natural sand stones, Paver

blocks, High quality concrete M-30 grade precast tiles having 50% opening for grass plantation,

rain water shelters and lighting etc. The existing old paver blocks will be replaced with new paver

blocks and new plantation will be carried out and plantation will be secured through tree guards.

The corridor along Rajpur Road will be provided lighting arrangement through cylindrical shape

integral decorative LED Bollard with opal acrylic under the project.

2. Construction Impacts

123. Sources of Materials. Significant amount of gravel, sand, and cement will be required for

this subproject. The construction contractor will be required to:

(i) Use material sources permitted by government;

(ii) Verify suitability of all material sources and obtain approval of design and supervision

consultant (DSC); and

(iii) Submit to DSC on a monthly basis documentation of sources of materials.

124. Air Quality. Emissions from construction vehicles, equipment, and machinery used for

excavation and construction will induce impacts on the air quality in the construction sites.

Anticipated impacts include dusts and increase in concentration of vehicle-related pollutants such

as carbon monoxide, sulphur oxides, particulate matter, nitrous oxides, and hydrocarbons) but

temporary and during construction activities only. To mitigate the impacts, construction

contractors will be required to:

(i) Consult with DSC on the designated areas for stockpiling of clay, soils, gravel, and other

construction materials;

(ii) Excavate the overhead storage reservoirs foundations at the same time as the access

roads (if needed) are built so that dug material is used immediately, avoiding the need to

stockpile on site;

(iii) Damp down exposed soil and any stockpiled on site by spraying with water when

necessary during dry weather;

(iv) Use tarpaulins to cover sand and other loose material when transported by trucks; and

(v) Fit all heavy equipment and machinery with air pollution control devices which are

operating correctly.

(vi) Air Quality monitoring will be done at proposed tube wells and pedestrian footpath on

quarterly basis except monsoon. This will be done by the contractor through approved

environmental monitoring agency.

125. Surface Water Quality. Mobilization of settled silt materials, run-off from stockpiled

materials, and chemical contamination from fuels and lubricants during construction works can

contaminate downstream surface water quality of the River. These potential impacts are

temporary and short-term duration only and to ensure these are mitigated, construction contractor

will be required to:

Page 64: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

56

(i) Avoid stockpiling of earth fill especially during the monsoon season unless covered by

tarpaulins or plastic sheets;

(ii) Prioritize re-use of excess spoils and materials in the construction works. If spoils will be

disposed, consult with DSC on designated disposal areas;

(iii) Install temporary silt traps or sedimentation basins along the drainage leading to the water

bodies;

(iv) Place storage areas for fuels and lubricants away from any drainage leading to water

bodies;

(v) Dispose any wastes generated by construction activities in designated sites; and

(vi) Conduct surface quality inspection according to the Environmental Management Plan

(EMP).

126. Noise Levels. There are no health facilities, scheduled or unscheduled historical,

archaeological, paleontological, or architectural sites near the construction sites. However,

construction works will be on settlements, along and near schools, and areas with small-scale

businesses. The sensitive receptors are the general population in these areas. Increase in noise

level may be caused by excavation equipment, and the transportation of equipment, materials,

and people. Impact is negative, short-term, and reversible by mitigation measures. The

construction contractor will be required to:

(i) Plan activities in consultation with DSC so that activities with the greatest potential to

generate noise are conducted during periods of the day which will result in least

disturbance;

(ii) Require horns not be used unless it is necessary to warn other road users or animals of

the vehicle’s approach;

(iii) Minimize noise from construction equipment by using vehicle silencers, fitting

jackhammers with noise-reducing mufflers, and portable street barriers the sound impact

to surrounding sensitive receptor; and

(iv) Maintain maximum sound levels not exceeding 80 decibels when measured at a distance

of 10 m or more from the vehicle/s.

(v) Noise level monitoring will be done at proposed tube wells and pedestrian footpath on

quarterly basis except monsoon. This will be done by the contractor through approved

environmental monitoring agency.

127. Existing Infrastructure and Facilities. Excavation works can damage existing

infrastructure located alongside roads, in particular water supply pipes. It will be particularly

important to avoid damaging existing water pipes. It is therefore important that construction

contractors will be required to:

(i) Obtain from DSC the list of affected utilities and operators; and

(ii) Prepare a contingency plan to include actions to be done in case of unintentional

interruption of services

128. Landscape and Aesthetics. The construction works will produce excess excavated,

excess construction materials, and solid waste such as removed concrete, wood, trees and

plants, packaging materials, empty containers, spoils, oils, lubricants, and other similar items.

These impacts are negative but short-term and reversible by mitigation measures. The

construction contractor will be required to:

Page 65: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

57

(i) Prepare and implement Waste Management List;

(ii) Avoid stockpiling of excess excavated soils;

(iii) Coordinate with UPJN for beneficial uses of excess excavated soils or immediately

dispose to designated areas;

(iv) Recover used oil and lubricants and reuse or remove from the sites;

(v) Manage solid waste according to the following preference hierarchy: reuse, recycling and

disposal to designated areas;

(vi) Remove all wreckage, rubbish, or temporary structures which are no longer required; and

(vii) Request DSC to report in writing that the necessary environmental restoration work has

been adequately performed before acceptance of work.

129. Surface and Groundwater Quality. Another physical impact that is often associated with

excavation is the effect on drainage and the local water table if groundwater and surface water

collect in the voids. To ensure that water will not pond in pits and voids near subproject location,

the construction contractor will be required to conduct excavation works on non-monsoon

season.

130. Ground Water Quality monitoring will be done at proposed tube wells on quarterly basis

except monsoon. This will be done by the contractor through approved environmental monitoring

agency.

131. Accessibility. Hauling of construction materials and operation of equipment on-site can

cause traffic problems. Potential impact is negative but short term and reversible by mitigation

measures. The construction contractor will be required to:

(i) Plan transportation routes so that heavy vehicles do not use narrow local roads, except in

the immediate vicinity of delivery sites;

(ii) Schedule transport and hauling activities during non-peak hours;

(iii) Locate entry and exit points in areas where there is low potential for traffic congestion;

(iv) Keep the site free from all unnecessary obstructions;

(v) Drive vehicles in a considerate manner;

(vi) Coordinate with government’s traffic department for temporary road diversions and with

for provision of traffic aids if transportation activities cannot be avoided during peak hours;

and

(vii) Notify affected sensitive receptors by providing sign boards informing nature and duration

of construction works and contact numbers for concerns and/or complaints.

132. Socio-Economic – Income. The subproject components will be located in government

land. Construction works will impede the access of residents to specific site in limited cases. The

potential impacts are negative and moderate but short-term and temporary. The construction

contractor will be required to:

(i) Leave spaces for access between mounds of soil;

(ii) Provide walkways and metal sheets where required to maintain access across for people

and vehicles;

(iii) Increase workforce in front of critical areas such as institutions, place of worship, business

establishment, hospitals, and schools;

Page 66: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

58

(iv) Consult businesses and institutions regarding operating hours and factoring this in work

schedules; and

(v) Provide sign boards for pedestrians to inform nature and duration of construction works

and contact numbers for concerns and/or complaints.

133. Socio-Economic – Employment. Manpower will be required during the 18-months

construction stage. This can result to generation of contractual employment and increase in local

revenue. Thus potential impact is positive and long-term. The construction contractor will be

required to:

(i) Employ majority of the labor force, or to the maximum extent, local persons within the 2-

km immediate area if manpower is available; and

(ii) If available, secure construction materials from local market.

134. Occupational Health and Safety. Workers need to be mindful of the occupational

hazards which can arise from working in height and excavation works. Potential impacts are

negative and long-term but reversible by mitigation measures. The construction contractor will be

required to:

(i) Develop and implement site-specific health and safety plan which will include measures

such as: (a) excluding public from the site; (b) ensuring all workers are provided with and

use Personal Protective Equipment; (c) health and safety training for all site personnel; (d)

documented procedures to be followed for all site activities; and (e) documentation of

work-related accidents;

(ii) Ensure that qualified first-aid can be provided at all times. Equipped first-aid stations shall

be easily accessible throughout the site;

(iii) Provide medical insurance coverage for workers;

(iv) Secure all installations from unauthorized intrusion and accident risks;

(v) Provide supplies of potable drinking water;

(vi) Provide clean eating areas where workers are not exposed to hazardous or noxious

substances;

(vii)Provide health and safety orientation training to all new workers to ensure that they are

apprised of the basic site rules of work at the site, personal protective protection, and

preventing injuring to fellow workers;

(viii) Provide visitor orientation if visitors to the site can gain access to areas where

hazardous conditions or substances may be present. Ensure also that visitor/s do not

enter hazard areas unescorted;

(ix) Ensure the visibility of workers through their use of high visibility vests when working in or

walking through heavy equipment operating areas;

(x) Ensure moving equipment is outfitted with audible back-up alarms;

(xi) Mark and provide sign boards for hazardous areas such as energized electrical devices

and lines, service rooms housing high voltage equipment, and areas for storage and

disposal. Signage shall be in accordance with international standards and be well known

to, and easily understood by workers, visitors, and the general public as appropriate; and

(xii)Disallow worker exposure to noise level greater than 85 decibels for a duration of more

than 8 hours per day without hearing protection. The use of hearing protection shall be

enforced actively.

135. Community Health and Safety. Hazards posed to the public, specifically in high-

pedestrian areas may include traffic accidents and vehicle collision with pedestrians. In most of

Page 67: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

59

the cases location of project sites at isolated area, hence health and safety risk to community is

minimum. Potential impact is negative but short-term and reversible by mitigation measures. The

construction contractor will be required to:

(i) Plan routes to avoid times of peak-pedestrian activities;

(ii) Liaise with DSC in identifying risk areas on route cards and/or maps;

(iii) Maintain regularly the vehicles and use of manufacturer-approved parts to minimize

potentially serious accidents caused by equipment malfunction or premature failure; and

(iv) Provide road signs and flag persons to warn of dangerous conditions, in case of location

near the road.

(v) Mitigation measures to suppress dust from soil generated from bore wells include

covering of soil and proposal disposal of soil in a designated site.

(vi) Schedule all construction works of tube wells and pedestrian footpath in day time before

sunset.

(vii)Maintain maximum sound level not exceeding 80 dB(A) measured at a distance of 10

meters from construction vehicles/ equipment.

136. There are no new asbestos cement pipes proposed. The existing pipes will be left as it is

in the ground and the new pipelines will be laid. However, an additional, particularly acute health

risk involved when the existing water supply system comprises asbestos cement pipes, so there

is a risk of contact with carcinogenic material if these pipes are disturbed in the course of the

work. Given the dangerous nature of this material for both workers and citizens, one additional

measure should be taken to protect the health of all parties in the event (however unlikely) that

asbestos cement pipes are encountered. Following measures to be applied in any instance that

asbestos cement pipes are handled, to ensure that appropriate action is taken:

(i) Training of all personnel (including manual labourers) to enable them to understand the

dangers of asbestos cement pipes and to be able to recognize them in situ;

(ii) Reporting procedures to inform management immediately if asbestos cement pipes are

encountered;

(iii) Development and application of a detailed health and safey procedure to protect both

workers and citizens. This should comply with national and international standards for

dealing with asbestos, and should include: (a) Removal of all persons to a safe distance;

(b) Usage of appropriate breathing apparatus and protective equipment by persons

delegated to deal with the asbestos cement material; and (c) Procedures for the safe

removal and long-term disposal of all asbestos-containing material encountered.

137. Work Camps. Operation of work camps can cause temporary air and noise pollution from

machine operation, water pollution from storage and use of fuels, oils, solvents, and lubricants.

Potential impacts are negative but short-term and reversible by mitigation measures. Consultation

with DSC revealed that it is unlikely that work camps are required for this subproject. In the case

that it will be needed, the construction contractor will be required to:

(i) Consult with DSC before locating project offices, sheds, and construction plants;

(ii) Minimize removal of vegetation and disallow cutting of trees;

(iii) Provide water and sanitation facilities for employees;

(iv) Prohibit employees from cutting of trees for firewood;

(v) Train employees in the storage and handling of materials which can potentially cause soil

contamination;

Page 68: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

60

(vi) Recover used oil and lubricants and reuse or remove from the site;

(vii) Manage solid waste according to the following preference hierarchy: reuse, recycling and

disposal to designated areas;

(viii) Remove all wreckage, rubbish, or temporary structures which are no longer

required; and

(ix) Request DSC to report in writing that the camp has been vacated and restored to pre-

project conditions before acceptance of work.

138. Social and Cultural Resources. For this subproject, excavation will occur at specific

isolated location, so it could be that there is a low risk of such impacts. Nevertheless, the

construction contractor will be required to:

(i) Stop work immediately to allow further investigation if any finds are suspected

(ii) Inform DSC if a find is suspected, and take any action they require ensuring its removal or

protection in site; and

(iii) Request DSC or any authorized person with archaeological and/or historical field training

to observe excavation.

C. Operations and Maintenance Impacts

139. The main O&M activities of the refurbished infrastructure will be detection, and repair of

leaks and pipe bursts. These are however likely to be minimal as proper design, and selection of

good quality pipe material should mean that leaks are minimal. The water meters that are

provided as part of this subproject will be of great use in detecting leaks in network. Leak repair

work will be similar to the pipe laying work. Trenches will be dug to reveal the leaking area and

the faulty connection will be re-fitted, or the pipe will be removed and replaced if necessary.

140. In the project design, it is proposed to provide recirculation system for wash water in

WTP. For this purpose, wash water will be collected in open tank for alternative use, with a

storage capacity of one day wash water in tank. The settled water will be pumped back into the

Inlet chamber and re-circulated with the raw water. Sludge from these tanks and also from the

clarifier will be collected in a sludge tank. Sludge from the tanks will be sent to sludge drying

beds, and the dried sludge will be sent either for land filling or used as soil conditioner.

141. IPMU will monitor ground water table regularly as per the guidelines of Central Ground

Water Board. If ground water table reduces, the IPMU will take consequential mitigation

measures. This may include recharge of ground water and / or restriction on extraction of ground

water.

142. Recurrence of blockage and leakage problems. Although impact is likely to be minimal

due to new and well-designed efficient system, it should be ensured that leak detection and

restoration time is minimized to the extent possible.

143. Occupational Health & Safety: Chlorine will be used as disinfectant in WTP. There is

invariably a safety risk when considerable quantities of chlorine are handled - chlorine cylinders

will be brought by trucks to the site, installed and operated to disinfect the water supplies.

Chlorine in quantities adequate for 1 month use will be stored at the WTPs. With the dosage of 2

ppm storage of 2 toners/cylinder (chlorine toner of 900 kg) for Dilaram Bazaar WTP, 1 toner for

Shahanshai Ashram WTP and 1 toner for Purukul gram WTP will be required. Besides, there will

standby toners 1 each at WTPs. Comparatively the safety risk will be high at Dilaram Bazar WTP,

which is located in the town area. Following measures are suggested for incorporating into

subproject design and implementation:

Page 69: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

61

(i) Design and develop chlorination facility with all safety features and equipment to meet

with any accidental eventuality, which may include: (a) Chlorine neutralization pit with a

lime slurry feeder; (b) Proper ventilation, lighting, entry and exit facilities; (c) Facility for

isolation in the event of major chlorine leakage; (d) Personal protection and safety

equipment for the operators in the chlorine plant, (e) Alarm facilities to alert chlorine gas

leak; (f) Provide necessary training in handling & application of chlorine and handling

emergency situations.

144. Operation of tube well requires high voltage power supply for operation of pumps. The

operation of motors can generate heat. The installation of motors will be done strictly as per the

manual of manufacturer to avoid fire. Pump house will be provided with sufficient ventilation.

(i) Standard switches and insulation will be provided and maintained in the pump house.

Circuit breakers will also be provided in case of any accidental short circuit.

(ii) Earthling shall also be provided by the contractor done as per the Indian standard.

(iii) The timing of operation can be in day light or in night. So sufficient lighting arrangement

inside the pump house and street light will also be provided by the contractor.

(iv) The protection against lightning strokes (Lightning Arrestor) shall be provided on HV side

of distribution transformer as per IS: 3070.

D. Cumulative Impact Assessment

145. The cumulative impact assessment examined the interaction between the subproject’s

residual effects (i.e., those effects that remain after mitigation measures have been applied) and

those associated with other past, existing and reasonably foreseeable future projects or activities.

The interaction of residual effects associated with multiple projects and/or activities can result in

cumulative impacts, both positive and negative. The subproject’s potential cumulative effects

were considered with respect to valued components in the categories of environmental, socio-

economic, and heritage resources in four areas:

(i) Of any potential residual project effects that may occur incrementally over time;

(ii) Consideration of other known relevant projects or activities within the specified study area

boundaries, even if not directly related to the subproject;

(iii) Potential overlapping impacts that may occur due to other developments, even if not

directly related to the proposed project; and

(iv) Future developments that is reasonably foreseeable and sufficiently certain to proceed.

146. In addition, the cumulative impact assessment considered the scope or influence of the

subproject. Two boundaries, spatial and temporal, were used. Given the water supply

requirement in Dehradun is presently met from both surface and ground water source, and

groundwater is considered adequate, there are no significant cumulative impacts expected on the

future water supply.

147. The subproject IEE has identified the valued components as air quality, water (surface

and groundwater) quality, noise, geophysical (hydrogeological), traffic management, social-

economic and socio-community, and human health. There are no foreseeable projects that will

overlap with the subproject. The spatial boundary of the subproject is the area along the

alignment and the existing ROWs. The temporal boundary can be considered as the whole

Dehradun City.

Page 70: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

62

148. Air quality effects will occur during construction. Consequently, although emissions of

common air contaminants (CAC) and fugitive dust may be elevated in proximity to active work

sites, this impact will be short-term and localized to the immediate vicinity of the alignment.

Greenhouse gas emissions may increase as a result of project activities (i.e., vehicle and

equipment operation, concrete production, disposal of excavated material, landfilling of residual

wastes). Given the subproject’s relatively minor contribution to CAC and greenhouse gas

emissions during construction, the overall significance rating of both these potential residual

effects is considered to be negligible during construction.

149. During construction noise levels in the immediate proximity of most work sites are

expected to increase. The duration of this exposure will be relatively brief. This exposure

represents a temporary, localized, adverse residual effect of low to moderate significance for

affected receptors. While building damage due to ground vibrations is unlikely, there may

annoyance to spatially located receptors during construction. Noise levels associated with the

project operations will be largely imperceptible as the service reservoirs are located in relatively

small sites within the town proper.

150. Land use/traffic management concerns will occur spatially during construction. During

construction, site-specific mitigation measures will be implemented to address temporary

disruptions to land use and access in the vicinity of the alignment such as road and sidewalk

closures, traffic delays and detours, parking modifications, and increased volumes of

construction–related traffic. There should be improved traffic movement along the alignment once

construction is completed. Since the subproject will be built in undeveloped land earmarked for

service reservoirs purposes, it will not conflict with existing or planned land use. However,

following improvement in infrastructures and services, added residential developments,

commercial and business facilities and increased densities are expected to develop and enhance

the subproject area. This can be considered a long-term cumulative benefit of the subproject.

151. Adverse impacts such as localized disruption of vehicle traffic and pedestrian movements

in areas along the alignment, and elevated CAC and fugitive dust emissions in proximity to work

sites, elevated noise and vibration levels and visual impacts will occur during construction. These

short-term effects will be mitigated by providing alternate travel routes or alternating traffic

movements and, where possible, access to businesses, schools and residences. However, upon

completion of construction the socio-community will benefit from improved water supply system.

This is considered a long-term cumulative benefit.

152. Development at the service reservoir and pump houses sites and in the vicinity of the

subproject may result in similar impacts relative to water quality and soils, but each impacts are

independent of one another and are mitigated on a site-specific basis. Further, while water quality

impacts have the ability to compound when taking into account regional water basins into

consideration, the subproject will be required to adhere to the mandatory state and local laws,

ordinances, regulations, and water quality standards. Regional geologic impacts do not generally

compound, and are limited to the site at which they occur.

153. The subproject, when considered with other projects in the same watershed, may result in

cumulative impacts to surface and groundwater quality from increased surface impermeability

and resultant runoff. Construction projects could result in increased erosion from exposed soil

areas, which could contribute sediments into local drainage courses and other waterways.

However, it is reasonably assumed that new construction associated with future projects will be

required to meet national, state, and local construction and operation standards at least as

rigorous as those required at present. Therefore, the potential for cumulative impacts to water

quality and soils is deemed to be less than significant.

Page 71: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

63

154. No adverse residual effects to human health will occur as a result of subproject

construction or operation. While exposure to elevated noise levels and fugitive dust and CAC

emissions will occur in proximity to subproject work sites during construction, due to their short-

term, localized nature, these effects are expected to be minor and insignificant with no

measurable effects on human health. The subproject operations will benefit the general public by

contributing to the long-term improvement of water supply system and community livability in

Dehradun.

Page 72: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

64

V. INSTITUTIONAL ARRANGEMENTS

155. The Urban Development Department is the executing agency. The executing agency has

set up a state-level investment program management unit (IPMU). The implementing agencies

for the investment program are: the UPJN for water supply and sewerage subprojects, and the

PWD for roads and traffic management subprojects. A special cell within the PMU, with

assistance from Urban Local Bodies (ULBs), will be the implementing agency for solid waste

management and slum improvement sub-projects. The IPMU is assisted by Investment Program

Management Consultants (IPMC) who provides program management support, assure the

technical quality of design and construction, and provide advice on policy reforms.

156. The implementing agencies will set-up district-level Investment Program Implementation

Units (PIUs) to manage implementation of sub-projects in their districts. PIUs will be assisted by

Design and Supervision Consultants (DSC), who design the infrastructure, manage tendering of

contracts and supervise the construction process. Construction contractors will be appointed to

build elements of the infrastructure. The contractors are managed by the IPIUs, and construction

activities are supervised by the DSC.

157. An Environment and Social Management Cell has been set up within the IPMU to address

environmental and social issues of the investment program, and is staffed by an Environmental

Specialist and a Social Development Specialist. The Environment and Social Management Cell is

assisted by the PMC. The DSC through their environment specialists are conducting

environmental assessments including the preparation of IEEs or EIAs and other assessments

required for clearances. The DSC is also responsible for incorporation of mitigation measures in

design and construction and construction-stage environmental monitoring.

158. The IPMC reviews and approve IEEs, oversee disclosure and consultations, and will

monitor the implementation of environmental monitoring plan and environmental management

plan where required. The construction contractor is responsible to implement mitigation measures

in construction. Implementation of mitigation and monitoring measures during O&M is the

responsibility of the respective implementing agencies, which are also the O&M agencies.

Government regulatory agencies such as the Uttarakhand Environmental Protection and Pollution

Control Board are also monitor the environmental performance according to government

regulations.

159. The construction of tube wells and pedestrian footpath will be supervised by DSC and

implemented and managed by IPIU and IPMU.

VI. GRIEVANCE REDRESS MECHANISM

160. As the work is being done in inhabited areas, most of the impacts are construction-

related, and therefore it is anticipated that improper or inadequate implementation of EMP may

Page 73: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

65

lead to disturbance and inconvenience to local people. In order to provide a direct channel to the

affected persons for approaching project authorities and have their grievance recorded and

redressed in an appropriate time frame, IPMU will establish a Grievance Redress Mechanism,

which will be functioned throughout the construction period.

161. A Complaint receiving system will be put in place at each site with the help of CAPP

(Community Awareness and Participation Program) nongovernment organization (NGO). A

complaint register and complaint forms will be made available at the site office of each contractor,

with a display board indicating availability of such facility. This will accept complaints regarding

the environment safeguard issues in implementation of the subproject. The grievances received

and actions taken will be included into the environmental monitoring reports submitted to ADB.

The following 4-stage process will be followed in grievance redress:

162. Stage 1: Complaints received (written or oral communication) will be registered in

Complaint Register assigning complaint number with date of receipt.

(i) The DSC/IPIU will review the complaint and direct the contractor for necessary action;

depending on the type/nature of complaint the contractor will be given reasonable time for

corrective action;

(ii) CAPP NGO will inform the complainant, within 24 hours, the time frame in which the

corrective action will be taken by e-mail or telephonically; if the grievance referred will not

fall under the purview of the subproject/program, the same will be intimated to the

complainant;

(iii) Contractor will take corrective action or as directed by DSC;

(iv) The CAPP NGO in coordination with DSC will conduct the site visit to check the action

taken and its appropriateness; and

(v) The action taken will be documented in the Complaint Register, and the complaint will be

closed if it is satisfactorily addressed, and the complainant will be informed through e-mail

or by telephone.

163. Stage 2: In case of no satisfactory action in Stage-1, the complainant can approach

IPMU/IPMC for necessary action; CAPP NGO will assist the complainant in this:

(i) IPMU with the assistance of IPMC will initiate action and take the corrective measures as

required, and CAPP NGO will intimate the complainant about the action taken; and

(ii) Upon satisfaction of complainant, the case will be closed and marked as resolved

164. Stage 3: if non-satisfied stage-2, the complainant can approach the Grievance Redress

Committee (GRC).

165. Stage 4: If it is not resolved at GRC, the complainant can approach Court of Law.

However, as none of the impacts are complex, long-term or significant, it is unlikely that there

will be any unresolved issues after the first three stages.

166. Grievance Redress Committee. The City Level Committee (CLC) will act as a GRC

for both environment & social safeguard issues. The CLC is chaired by Mayor of Dehradun Nagar

Nigam and has members from civil society, elected representatives and government officials.

Grievances related to environmental safeguards will be handling by CLC in its regular meetings.

The IPMU Environment Officer and CAPP NGO will assist the CLC in these matters.

Page 74: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

66

VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

A. Public Consultations Conducted

167. A series of public consultation meetings were conducted during the project preparation.

Various forms of public consultations (consultation through ad hoc discussions on site and town-

level consultation) have been used to discuss the project and involve the community in planning

the project and mitigation measures. The consultation are carried out through out in the year

2010 and continued in year 2011. For construction of tube wells and pedestrian footpath, the

public consultation has also been carried out in Dehradun on 27 April 2016.

168. Some informal discussions were held with the local people during the visits to various

subproject sites. Issues discussed were:

(i) Awareness and extent of the project and development components (ii) Benefits of Project for the economic and social Upliftment of Community

(iii) Labours availability in the project area or requirement of outside labours involvement

(iv) Local disturbances due to project construction work

(v) Necessity of tree felling etc. at project sites

(vi) Water logging and drainage problem if any (vii) Drinking water problem

(viii) Forest and sensitive area nearby the project site (ix) Movement of wild animals etc.

169. Local populations are very much interested on the project and they will help project

authorities in all aspects. Public consultation and focus group discussion results along with list

of participants are given in Appendix 3. Major Issues discussed during Public consultation are:

(i) Proposed water supply project should ensure enough supply of drinking water in all wards of city.

(ii) Executing agency should give preference to engage internationally reputed contractor like as people do not faith about the local contractors in respect of quality of works as well as timely completion of work;

(iii) Efforts should be made by government to supply drinking water round the clock;

(iv) Livelihood affected households should be given assistance in the mode of cash compensation;

(v) Local people should be employed by the contractor during construction work;

(vi) Adequate safety measures should be taken during construction work;

(vii) Local people have appreciated the water supply proposal of the government and they have ensured that they will cooperate with the Executing Agency during project implementation.

170. Public consultation were carried out as integral part of the investment program earlier

during the project preparation phase by the PPTA Consultant, employing various methods to

understand the need, preferences of basic infrastructure facilities and to draw up plans to

improve the quality of life in various urban areas. Environment issues were also discussed

during the consultations. The detail of which are given below in Table No.11.

Page 75: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

67

Table No 11: Public Consultations by PPTA Consultant

Consultation Details Schedule Participants No. of participants

Socio- economic Survey - Field Group Discussions w i t h U r b a n P o o r – Verification of Slums

June- July 2006

Town population with focus on urban poor 1,500

First consultation

workshop for the project

June 2006 Citizens, business community, Nagar

Nigam Councilors, CBO’s and NGO’s, Elected Representatives, Senior Officers of Nagar Nigam, PWD, UJS, UPJN etc.

25

Second Workshop to

formulate and agree on a City Vision

June 2006 Primary , secondary and Tertiary

stakeholders

80

Group Discussions and

Consultation with Working Groups

June 2006 7 groups - a) Urban Planning and Land Management, (b) Water and Sanitation, (c) Roads and Transport, (d) Solid Waste Management, (e) Basic , (f) Urban Services to the Poor, (g) Governance and Finance

80

Series of Consultation

with line departments

May - July 2006

Nagar Nigam, UDA, UPJN, PWD, UJS, Irrigation Department and such other organizations

-

Discussion on Identified

infrastructure projects

July 2006 All Secondary Stakeholders and UDD of GoU

18

Safeguards disclosure

meeting

June 2007 Citizens, business community, Nagar

Nigam Councilors, CBO’s and NGO’s, Elected Representatives, Senior Officers of Nagar Nigam, PWD, UJS, UPJN etc.

21

CBOs – Community based Organizations; NGOs-Non-Governmental Organizations; PWD-Public Works Department; UDA-Urban Development Authority; UDD-Urban Development Department; UJS-Uttarakhand Jal Sansthan; and UPJN-Uttarakhand Peya Jal Nigam.

171. Public Consultation for construction of 5 Tube wells in Dehradun and for work

of providing & laying tiling on shoulders along the pipeline corridor on Rajpur road

from Mussorie diversion to Dilaram Bazar in Dehradun of 4.8 km: The Public

consultation has been organised in Dehradun on 27 April 2016 at Kanak Chowk to discuss

the proposed sub-projects of tube wells and pedestrian footpath of 4.8 km. The details of

public consultation (PC) including attendance sheet, photographs and new paper

advertisements of PC are given in Appendix 3, Appendix 4 and Appendix 5 respectively.

People did not raise any objection of construction of Tube wells and suggested for

restoration of construction sites of tube wells and pedestrian footpath. These concerns were

recorded and will be attended by the contractors. The public consultation notice was published

in daily newspaper. The draft IEE was disclosed to the local community. The description of

proposed construction of tube wells and pedestrian foot path was explained during the public

consultation. The details of public consultation conducted by IPMU/IPIU for proposed tube

wells location and pedestrian footpath are given in Table No 12.

Page 76: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

68

Table No 12: Details of public consultation for proposed tube wells and pedestrian footpath

Consultation Details Schedule Participants No. of participants

Public Consultation for construction of 5 Tube wells in Dehradun and for construction and beautification of 4.8 Kms of pedestrian footpath at Rajpur road from Dilaram Bazar to Mussoorie diversion.

27 April 2016 People of Dehradun 27

Issues raised in the public consultation and its action plan

The issues and action plan are given in Table No 13.

Table No 13: Issues discussed during public consultation and its action plan

Issues Action Plan

Restoration of construction sites of tube wells and pedestrian footpath

Mitigations measures of this IEE will prevail.

B. Future Consultation and Disclosure

172. The public consultation shall be a continuous process and will continue in the future.

The IPMU will extend and expand the consultation and disclosure process during

implementation. An experienced NGO will be appointed to handle this key aspect of the

programme, who will conduct a wide range of activities in relation to all subprojects in each

town, to ensure that the needs and concerns of stakeholders are registered, and are addressed

in project design, construction or operation where appropriate. The programme of activities will

be developed during the detailed design stage, and is likely to include the following:

1. Consultation during construction:

(i) Public meetings with affected communities to discuss and plan work programmes and allow issues to be raised and addressed once construction has started; and

(ii) Smaller-scale meetings to discuss and plan construction work with individual communities to reduce disturbance and other impacts, and provide a mechanism through which stakeholders can participate in subproject monitoring and evaluation.

2. Project disclosure:

(i) Public information campaigns (via newspaper, TV and radio) to explain the project to the wider city population and prepare them for disruption they may experience once the construction programme is underway;

(ii) Public disclosure meetings at key project stages to inform the public of progress and future plans, and to provide copies of summary documents in Hindi;

(iii) Formal disclosure of completed project reports by making copies available at convenient locations in the study towns, informing the public of their availability;

(iv) Providing a mechanism through which comments can be made.

Page 77: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

69

VIII. ENVIRONMENTAL MANAGEMENT PLAN

A. Environmental Mitigation and Monitoring Program

173. The potential impacts identified and assessed and the mitigation measures

formulated to minimize those impacts to acceptable levels identified in the earlier sections

are summarized in the following tables. The table also delegates the responsibility of

implementing mitigation to various agencies involved in the program implemented as listed

above.

174. The environmental impact mitigation plan has been prepared based on the mitigation

hierarchy of avoidance, minimisation, rehabilitation/ restoration and offsetting. Necessary

measures have been suggested to take action in preconstruction stage to avoid and

minimise the impacts. These preconstruction impacts and mitigation plan has been given in

Table No. 14. The construction stage impact and its mitigation plan have been provided in

Table No.15. The operation stage impacts and its mitigation plan have been provided in

Table No 16.

175. The environmental monitoring plans have been prepared for pre-construction, during

construction and operation stage and are given in Table No 17, Table No 18 and Table No

19 respectively.

Page 78: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

70

Table No 14 : Anticipated Impact and Mitigation Measures – Pre-construction Environmental Mitigation Plan

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

Utilities Telephone lines, electric poles and wires, water lines within proposed project area

Identify and include locations and operators of these utilities in the detailed design documents to prevent unnecessary disruption of services during construction phase; and

Require construction Contractors to prepare a contingency plan to include actions to be done in case of unintentional interruption of services.

DSC List of affected utilities and operators;

Bid document to include requirement for a contingency plan for service interruptions

Water Supply Health risk due to closure of water supply

Plan the construction program to keep the cessation of water supplies to the minimum possible (in both area and duration);

In coordination with UPJN, provide alternative potable water to affected households and businesses for the duration of the shut-down; and Liaise with affected persons to inform them of any cessation in advance, and to ensure that they are provided with an alternative supply.

IPIU Schedule of closure;

delivery of potable water to affected people by UPJN

Ecological Resources Laying of pipeline in hilly areas

Aligned pipeline in such a way that there will be

IPIU Visual observation on site

Page 79: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

71

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

minimum disturbance and clearance of vegetation.

No trees shall be felled for construction purpose

Construction of anicut at Galogi intake

(i) No construction material storage/ancillary works shall be conducted in the forest area; this shall be limited to actual construction area and the access road (ii) No labour camps shall be located near the site; no labour/construction related persons shall be allowed to stay after work hours; except security guards on duty (iii) Limit the work to daylight hours only; no work shall be conducted after sunset (iv) The Contractor shall take all necessary precautions to prevent his workmen from removing and damaging any trees/vegetation/hunting animals in nearby forests; the contractor will be severely penalized for these activities (v) Conduct construction work in lean flow season (summer) (vi) Construction area shall be protected properly with bunds so that stream flows without any hindrance or mixing of silt/material in the water

IPIU

Construction schedule & visual observation on site

Page 80: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

72

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

(vii) Conduct awareness programs to workers on environment & safety at the site (viii) No noisy works shall be conducted (ix) Barricade the construction area – including the material storage area (x) Implement any measures as suggested by the Forest Department (xi) Use excavated soil for strengthening bunds/road levelling; no waste shall be disposed in or near forests

Social and Cultural Resources

Ground disturbance can uncover and damage archaeological and historical remains

(i) Consult ASI or concerned department of Uttarakhand government to obtain an expert assessment of the archaeological potential of the site; (ii) Consider alternatives if the site is found to be of medium or high risk; (iii) Develop a protocol for use by the construction contractors in conducting any excavation work, to ensure that any chance finds are recognized and measures are taken to ensure they are protected and conserved.

IPIU & DSC Chance Finds Protocol

Construction work camps (if Disruption to traffic flow and (i) Prioritize areas within or IPIU and DSC to determine List of selected sites for

Page 81: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

73

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

needed), hot mix plants, stockpile areas, storage areas, and disposal areas.

nearest possible vacant space in the subproject location; (ii) If it is deemed necessary to locate elsewhere, consider sites that will not promote instability and result in destruction of property, vegetation, irrigation, and drinking water supply systems; (iii) Do not consider residential areas; (iv) Take extreme care in selecting sites to avoid direct disposal to water body which will inconvenience the community.

locations prior to award of construction contracts.

construction work camps, hot mix plants, stockpile areas, storage areas, and disposal areas.

Sources of Materials Extraction of materials can disrupt natural land contours and vegetation resulting in accelerated erosion, disturbance in natural drainage patterns, ponding and water logging, and water pollution.

(i) Prioritize sites already permitted by the Mining Department; (ii) If other sites are necessary, inform construction contractor that it is their responsibility to verify the suitability of all material sources and to obtain the approval of IPIU and (iii) If additional quarries will be required after construction is started, inform construction contractor to obtain a written approval from IPIU.

IPIU and DSC to prepare list of approved quarry sites and sources of materials

(i) List of approved quarry sites and sources of materials; (ii) Bid document to include requirement for verification of suitability of sources and permit for additional quarry sites if necessary.

ASI = Archaeological Survey of India, DSC = design supervision consultant, IPIU = Investment Program Implementation Units, UPJN = Uttarakhand Peya Jal Nigam.

Page 82: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

74

Table No 15: Anticipated Impacts and Mitigation Measures – Construction Environmental Mitigation Plan

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

Sources of Materials Extraction of rocks and Material may cause ground instability.

(i) Use quarry sites and sources permitted by government;(ii) Verify suitability of all material sources and obtain approval of Investment IPIU; (iii) If additional quarries will be required after construction has started, obtain written approval from IPIU; and (iv) Submit to DSC on a monthly basis documentation of sources of materials.

Construction Contractor Construction Contractor documentation

Air Quality Emissions from construction vehicles, equipment, and machinery used for excavation and construction resulting to dusts and increase in concentration of vehicle-related pollutants such as carbon monoxide, sulfur oxides, particulate matter, nitrous oxides, and hydrocarbons).

(i) Consult with IPIU/DSC on the designated areas for stockpiling of clay, soils, gravel, and other construction materials; (iii) Damp down exposed soil and any stockpiled on site by spraying with water when necessary during dry weather; (iv) Use tarpaulins to cover sand and other loose material when transported by trucks; and (v) Fit all heavy equipment and machinery with air Pollution control devices which are operating correctly.

Construction Contractor (i) Location of stockpiles; (ii) Complaints from sensitive receptors; (iii) Heavy equipment and machinery with air pollution control devices; (iv) Ambient air for RPM and SPM; (v) Vehicular emissions such as SO2, NOx, CO, and hydrocarbons

Surface water quality Mobilization of settled silt materials, run-off from

(i) Avoid stockpiling of earth fill especially during the

Construction Contractor (i) Areas for stockpiles, storage of fuels and

Page 83: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

75

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

stockpiled materials, and chemical contamination from fuels and lubricants during construction works can Contaminate nearby surface water quality.

monsoon season unless covered by tarpaulins or plastic sheets; (ii) Prioritize re-use of excess spoils and materials in the Construction works. If spoils will be disposed, consult with IPIU/DSC on designated disposal areas; (iii) Install temporary silt traps or sedimentation basins along the drainage leading to the water bodies; (iv) Place storage areas for fuels and lubricants away from any drainage leading to water bodies; (v) Dispose any wastes generated by construction activities in designated sites; and (vi) Conduct surface quality inspection according to the EMP.

lubricants and waste materials; (ii) Number of silt traps installed along drainages leading to water bodies; (iii) Records of surface water quality inspection; (iv) Effectiveness of water management measures; (v) For inland water: suspended solids, oil and Grease, BOD, and coliforms.

Spillage of construction Material, debris into stream during replacement of Massi Fall pipeline

(i) Ensure no spillage of soil/materials into the water stream; place wooden planks to cover the stream and clear off the soil immediately (ii) Ensure skilled supervision in removal of soil overburden; work shall be conducted manually, and no major equipment shall be used in this hilly terrain

Construction Contractor Visual observation on site

Page 84: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

76

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

Noise Levels Increase in noise level due to earth-moving and excavation equipment, and the Transportation of equipment, materials, and people.

(i) Plan activities in consultation with IPIU/DSC so that activities with the greatest potential to generate noise are conducted during periods of the day which will result in least disturbance; (ii) Require horns not be used unless it is necessary to warn other road users or animals of the vehicle’s approach; (iii) Minimize noise from construction equipment by using vehicle silencers, fitting jackhammers with noise reducing mufflers, and portable street barriers the sound impact to surrounding sensitive receptor; and (iv) Maintain maximum sound levels not exceeding 80 dB(A) when measured at a distance of 10 m or more from the vehicle/s.

Construction Contractor (i) Complaints from sensitive receptors; (ii) Use of silencers in noise-producing equipment and sound barriers; and (iii) Equivalent day and night time noise levels

Existing Infrastructure and Facilities

Disruption of service and damage to existing infrastructure at specified project location.

(i) Obtain from IPIU/DSC the list of affected utilities and operators if any; (ii) Prepare a contingency plan to include actions to be done in case of unintentional interruption of service

Construction Contractor Existing Utilities Contingency Plan

Landscape and Aesthetics Solid wastes as well as excess construction materials.

(i) Prepare and implement

Waste Management Plan; (ii) Avoid stockpiling of excess excavated soils;

Construction Contractor (i) Waste Management Plan; (ii) Complaints from sensitive receptors; and (iii) IPIU/DSC to report in

Page 85: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

77

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

Coordinate with UPJN for beneficial uses of excess excavated soils or immediately dispose to designated areas; Coordinate with UPJN for beneficial uses of excess excavated soils or immediately dispose to designated areas; (iv) Recover used oil and lubricants and reuse or remove from the sites; (v) Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; (vi) Remove all wreckage, rubbish; and (vii) Request IPIU/DSC to report in writing that the necessary environmental restoration work has been adequately performed before acceptance of work.

writing that the necessary environmental restoration work has been adequately performed before acceptance of work.

Accessibility Traffic problems and conflicts near project locations and haul road

(i) Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites; (ii) Schedule transport and hauling activities during non-peak hours; (ii) Locate entry and exit points in areas where there is low potential for traffic congestion; (iii)

Construction Contractor (i) Traffic Management Plan; (ii) Complaints from sensitive receptors; and (iii) Number of signages placed at subproject location.

Page 86: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

78

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

Keep the site free from all unnecessary obstructions; (iv) Drive vehicles in a considerate manner; (v) Coordinate with Dehradun Traffic Police Office for temporary road diversions and with for provision of traffic aids if transportation activities cannot be avoided during peak hours; (vi) Notify affected sensitive receptors by providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints; and (vii) Provide planks across trenches in front of businesses, and ensure works are completed quickly to avoid disruption.

Socio-Economic – Income. Impede the access of residents and customers to nearby shops.

(i) Leave spaces for access between mounds of soil; (ii) Provide walkways and metal sheets where required for people; (ii) Increase workforce in front of critical areas such as institutions, place of worship, business establishment, hospitals, and schools; (iii) Consult businesses and institutions regarding operating hours and factoring this in work schedules; and (iv) Provide

Construction Contractor

Page 87: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

79

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

sign boards for pedestrians to inform nature and duration of construction works and contact numbers for concerns/complaints.

Socio-Economic Employment Generation of contractual employment and increase in local revenue

(i) Employ at least 50% of the labour force, or to the maximum extent, local persons within the 2-km immediate area if manpower is available; and (ii) Secure construction materials from local market.

Construction Contractor (i) Employment records; and records of sources of materials.

Occupational Health and Safety

Occupational hazards which can arise during work

Develop and implement site-specific health and safety plan which will include measures such as: (a) excluding public from the site; (b) ensuring all workers are provided with and use Personal Protective Equipment like helmet, gumboot, safety belt, gloves, nose musk and ear plugs; (c) health and safety training for all site personnel; (d) documented procedures to be followed for all site activities; and (e) documentation of work-related accidents; (ii) Ensure that qualified first- aid can be provided at all times. Equipped first-aid stations shall be easily accessible throughout the site; (iii)

Construction Contractor (i) Site-specific health and safety plan; (ii) Equipped first-aid stations; (iii) Medical insurance coverage for workers; (iv) Number of accidents; (v) Supplies of potable drinking water; (vi) Clean eating areas where workers are not exposed to hazardous or noxious substances; (vii) record of health and safety orientation trainings (viii) personal protective equipment; (ix) % of moving equipment outfitted with audible back-up alarms; (xi) sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for

Page 88: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

80

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

Provide medical insurance coverage for workers; (iv) Secure all installations from unauthorized intrusion and accident risks; (v) Provide supplies of potable drinking water; (vi) Provide clean eating areas where workers are not exposed to hazardous or noxious substances; (vii) Provide health and safety orientation training to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers; (viii) Provide visitor orientation, if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted; (ix) Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; (x) Ensure moving equipment is outfitted with audible backup alarms; (xi) Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service

storage and disposal.

Page 89: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

81

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and (xii) Disallow worker exposure to noise level greater than 85 dBA for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

Community Health and Safety.

Traffic accidents and vehicle collision with pedestrians during material and waste transportation.

(i) Plan routes to avoid times of peak-pedestrian activities; (ii) Liaise with IPIU/DSC in identifying high-risk areas on route cards/maps; (iii) Maintain regularly the vehicles and use of manufacturer-approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure; and (iv) Provide road signs and flag persons to warn.

Construction Contractor (i) Traffic Management Plan; (ii) Complaints from sensitive receptors

Work Camps (if needed) Temporary air and noise pollution from machine operation, water pollution from storage and use of

(i) Consult with IPIU/DSC before locating project offices, sheds, and construction plants; (ii)

Construction Contractor (i) Complaints from sensitive receptors; (ii) Water and sanitation facilities for employees; and

Page 90: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

82

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

fuels, oils, solvents, and lubricants

Minimize removal of vegetation and disallow cutting of trees; (iii) Provide water and sanitation facilities for employees; (iv) Prohibit employees from poaching wildlife and cutting of trees for firewood; (v) Train employees in the storage and handling of materials which can potentially cause soil contamination; (vi) Recover used oil and lubricants and reuse or remove from the site; (vii) Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; (viii) Remove all wreckage, rubbish, or temporary structures (such as buildings, shelters, and latrines) which are no longer required; and (ix) Request IPIU/DSC to report in writing that the camp has been vacated and restored to pre-project conditions before acceptance of work.

(iii) IPIU/DSC report in writing that the camp has been vacated and restored to pre-project conditions

Social and Cultural Resources

Risk of archaeological chance finds

(i) Strictly follow the protocol for chance finds in any excavation work; (ii) Request IPIU/DSC or any authorized person with archaeological field training

Construction Contractor Records of chance finds

Page 91: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

83

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

to observe excavation; (iii) Stop work immediately to allow further investigation if any finds are suspected; and (iv) Inform IPIU/DSC if a find is suspected, and take any action they require ensuring its removal or protection in situ.

BOD = biological oxygen demand, CO = carbon monoxide, dB(A) = decibels, DSC = design and supervision consultant, IPIU = Investment Program Management Unit, km = kilometer, m = meter, NOx = nitrous oxide, RPM = respirable particulate matter, SO2= sulphur dioxide, SPM = suspended particulate matter, UPJN = Uttarakhand Peya Jal Nigam

Page 92: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

84

Table No 16 : Anticipated Impacts and Mitigation Measures – Operations and Maintenance Environmental Mitigation Plan

Field Anticipated Impact Mitigation Measures Responsible for Mitigation Monitoring of Mitigation

General General impact (i) Refill and re-compact trenches soil and backfilled sand will be removed to expose the leaking junction or pipe (ii) Conduct work during non-monsoon period; and(iii) Cover or wet excavated material to prevent dusts.

UPJN and O&M Contractors Complaints receptors from sensitive

Social and Cultural Resources

Temporary activities disruption of activities

(i) Consult the city authorities to identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity; (ii) Complete work in sensitive areas quickly; (iii) Consult municipal authorities, custodians of important buildings, cultural and tourism authorities and local communities in advance of the work to identify and address key issues, and avoid working at sensitive times, such as religious and cultural festivals.

UPJN and O&M Contractors Complaints receptors from sensitive receptors

O&M = operations and maintenance, UPJN = Uttarakhand Peya Jal Nigam.

Page 93: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

85

Table No 17 : Pre-construction Environmental Monitoring Program

Field Location Responsible for Mitigation

Monitoring of Mitigation

Method of Indicators/ Frequency Responsibility of Monitoring

Utilities As per site requirement

DSC (i) List of affected utilities if any and operators; (ii) Bid document to include requirement for a contingency plan for service interruptions

Checking of records

(i) List of affected utilities and operators prepared; (ii) Requirement for a contingency plan for service interruptions included in bid documents

Once IPIU

Water Supply Cessation

As per site requirement

UPJN (i) schedule of closure; (ii) delivery of UPJN of potable water to affected people

checking of records

(i) Tentative schedule of closure made known to affective people 2 weeks prior to cessation of water supply; (ii) coordination with UPJN for supply of potable water to 100% affected people

Once IPIU, DSC

Social and Cultural Heritage

As per site requirement

IPIU and DSC Chance Finds Protocol

Checking of records

Chance Finds Protocol provided to construction contractors prior to commencement of activities

Once IPIU

Page 94: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

86

Field Location Responsible for Mitigation

Monitoring of Mitigation

Method of Indicators/ Frequency Responsibility of Monitoring

Construction work camps, hot mix plants, stockpile areas, storage areas, and disposal areas.

As per site requirement

IPIU and DSC to determine locations prior to award of construction contracts.

List of selected location for construction work camps, hot mix plants, stockpile areas, storage areas, and disposal areas.

Checking of records

List of selected sites for construction work camps, hot mix plants, stockpile areas, storage areas, and disposal areas provided to construction contractors prior to commencement of works.

Once IPIU

Sources of Materials

As per requirement site requirement

IPIU and DSC to prepare list of approved quarry sites and sources of materials

(i) List of approved quarry sites and sources of materials; (ii) Bid document to include requirement for verification of suitability of sources and permit for additional quarry sites if necessary.

Checking of records

(i) List of approved quarry sites and sources of materials provided to construction contractors (ii) Bid document included requirement for verification of suitability of sources and permit for additional quarry sites if necessary.

Once IPIU

DSC = design and supervision consultant, IPIU = Investment Program Implementation Unit.

Page 95: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

87

Table No 18 : Construction Environmental Monitoring Program

Field Location Responsible for Mitigation

Monitoring of Mitigation

Method of Indicators/ Frequency Responsibility of Monitoring

Sources of Materials

Quarries and sources of materials

Construction Contractor

Construction Contractor documentation

(i) Checking of records; and (ii) visual inspection of sites

(i) Sites are permitted; and (ii) Report submitted by construction contractor monthly (until such time there is excavation work)

Monthly submission for construction contractor As needed for DSC

DSC

Air Quality Construction sites and areas designated for stockpiling of materials

Construction Contractor

(i) Location of stockpiles; (ii) complaints from sensitive receptors; (iii) heavy equipment and machinery with air pollution control devices; (iv) ambient air for RPM and SPM; (v) vehicular emissions such as SO2, NOx, CO, and hydrocarbons

(i) Checking of records; and (ii) visual inspection of sites

(i) Stockpiles on designated areas only; (ii) complaints from sensitive receptors satisfactorily addressed; (iii) air pollution control devices working properly; (iv) The government’s Ambient Quality Standards for ambient air quality; and (v) The government’s Vehicular Emission Standards for SO2, NOx, CO and HC.

Monthly for checking records

DSC in coordination with Pollution Control Board

Surface Water (i) Construction Construction (i) Areas for visual inspection (i) Designated Monthly DSC in

Page 96: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

88

Field Location Responsible for Mitigation

Monitoring of Mitigation

Method of Indicators/ Frequency Responsibility of Monitoring

Quality sites; (ii) areas for stockpiles, storage of fuels and lubricants and waste materials;

Contractor stockpiles, storage of fuels and lubricants and waste materials; (ii) number of silt traps installed along drainages leading to water bodies; (iii) records of surface water quality inspection; (iv) effectiveness of water management measures; and (v) for inland water: suspended solids, oil and grease, BOD, and coliforms.

areas only; (ii) silt traps installed and functioning; (iii) no noticeable increase in suspended solids and silt from construction activities; and (iv) The government’s Standards for Water Discharges to Inland Waters and Land for Irrigation

coordination with Pollution Control Board

Kiliyarkuli Water Quality

50 m upstream and 50 m downstream of Anicut

Contractor Water Quality Sampling & laboratory testing

Comparison with base values

Once in a month (two sampling locations)

Contractor

Noise Levels (i) Construction sites; (ii) areas for stockpiles, storage of fuels and lubricants and waste materials; (iii)

Construction Contractor

(i) Complaints from sensitive receptors; (ii) use of silencers in noise-producing equipment and sound barriers;

(i) Checking of records; and (ii) visual inspection

(i) Complaints from sensitive receptors satisfactorily addressed; (ii) silencers in noise-producing

Monthly DSC in coordination with Pollution Control Board

Page 97: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

89

Field Location Responsible for Mitigation

Monitoring of Mitigation

Method of Indicators/ Frequency Responsibility of Monitoring

work camps and (iii) Equivalent day and night time noise levels

equipment functioning as design; and (iii) sound barriers installed where necessary

Existing Utilities and Infrastructure

Construction sites

Construction Contractor

(i) Existing Utilities Contingency Plan

(i) Checking of records; and (ii) visual inspection

Implementation according to Utilities Contingency Plan

As needed DSC

Landscape and Aesthetics

(i) Construction sites; (ii) areas for stockpiles, storage of fuels and lubricants and waste materials; (iii) work camps

Construction Contractor

(i) Waste Management Plan; (ii) complaints from sensitive receptors; and (iii) IPIU/DSC to report in writing that the necessary environmental restoration work has been adequately performed before acceptance of work.

(i) Checking of records; and (ii) visual inspection

(i) No accumulation of solid wastes on-site; (ii) implementation of Waste Management Plan; and (iii) complaints from sensitive receptors satisfactorily

Monthly DSC

Accessibility (i) Construction sites; (ii) traffic haul road

Construction Contractor

(i) Traffic Management Plan; (ii) complaints from sensitive receptors; and (iii) number of

Visual inspection (i) Implementation of Traffic Management Plan, if required; (ii) complaints from sensitive receptors

Monthly DSC

Page 98: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

90

Field Location Responsible for Mitigation

Monitoring of Mitigation

Method of Indicators/ Frequency Responsibility of Monitoring

signages placed at subproject location.

satisfactorily addressed; and (iii) signages visible and located in designated areas

Socio-Economic - Income

Construction sites

Construction Contractor

(i) Complaints from sensitive receptors; and (ii) number of walkways, signages, and metal sheets placed at subproject location.

Visual inspection (i) Complaints from sensitive receptors satisfactorily addressed; (ii) walkways, ramps, and metal sheets provided; and (iii) signages visible and located in designated areas

Quarterly DSC

Socio-Economic - employment

construction sites Construction Contractor

(i) Employment records; and (ii) records of sources of materials

Number of employees from Uttarakhand equal or greater than 50% of total workforce

Quarterly DSC

Occupational Health and Safety

construction sites Construction Contractor

(i) Site-specific health and safety plan; Equipped first- aid stations; Medical insurance

(i) Checking of records; and visual inspection

(i) Implementation of health and safety plan; (ii) number of work-related accidents; (iii) % usage of personal

Quarterly DSC

Page 99: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

91

Field Location Responsible for Mitigation

Monitoring of Mitigation

Method of Indicators/ Frequency Responsibility of Monitoring

coverage for workers are not

exposed to

hazardous or

noxious substances;

(vii) record of

health and safety orientation

trainings

(viii) personal

protective equipments;

(ix) % of moving equipment

outfitted with

audible back-up

alarms; and

(x) sign boards

for hazardous

areas such as

energized

electrical devices

and lines, service

rooms housing

protective equipment; (iv) number of first

aid stations,

frequency of

potable water

delivery, provision

of clean eating area, and number of sign boards are according to approved plan; and

(v) % of moving

equipment

outfitted with

audible back-up

alarms

Page 100: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

92

Field Location Responsible for Mitigation

Monitoring of Mitigation

Method of Indicators/ Frequency Responsibility of Monitoring

high voltage

equipment, and

areas for storage and disposal.

Community Health and Safety

Construction sites

Construction Contractor

(i) Traffic Management Plan; and (ii) complaints from sensitive receptors

Visual inspection (i) Implementation of Traffic Management Plan; and (ii) complaints from sensitive receptors satisfactorily addressed.

Quarterly DSC

Work Camps Work camps Construction Contractor

(i) Complaints from sensitive receptors; (ii) water and sanitation facilities for employees; and (iii) IPIU/DSC report in writing that the camp has been vacated and restored to pre-project conditions

Visual inspection (i) Designated areas only; (ii) complaints from sensitive receptors satisfactorily addressed

Quarterly DSC

Chance Finds Construction sites

Construction Contractor

Records of chance finds

Checking of records

Implementation of Chance Finds Protocol

As needed DSC

Page 101: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

93

BOD = biological oxygen demand, CO = carbon monoxide, DSC = design supervision consultant, IPIU = Investment Program Implementation Unit, NOx = nitrous oxide, RPM = respirable particulate matter, SO2 = sulphur dioxide, SPM = suspended particulate matter, UPJN = Uttarakhand Peya Jal Nigam

Page 102: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

94

Table No 19 : Operation and Maintenance Environmental Monitoring Program

Field Location Responsible for Mitigation

Monitoring of Mitigation

Method of Indicators/ Frequency Responsibility of Monitoring

Occupational Health and Safety

subproject location

UPJN and O&M Contractors

Complaints from sensitive receptors

(i) Records of training; (ii) health and safety Plan approved by UPJN

Complaints from sensitive receptors satisfactorily addressed

As needed IPIU

General Maintenance work

subproject location

UPJN and O&M Contractors

Complaints from sensitive receptors

Checking of records

Complaints from sensitive receptors satisfactorily addressed

As needed IPIU

Community Health and Safety

subproject location

UPJN and O&M Contractors

Complaints from sensitive receptors

Checking of records

complaints from sensitive receptors satisfactorily addressed

As needed IPIU

Accessibility subproject location

UPJN and O&M Contractors

Complaints from sensitive receptors

Checking of records

Complaints from sensitive receptors satisfactorily addressed

As needed IPIU

Water Quality All treatment plant location

UPJN and O&M Contractors

Drinking water and surface water quality as per BIS specification

Sample collection and laboratory analyses

Government’s Drinking Water Standards

As needed IPIU

Solid Wastes Near treatment UPJN and O&M Complaints from Sample Complaints from Quarterly IPIU

Page 103: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

95

Field Location Responsible for Mitigation

Monitoring of Mitigation

Method of Indicators/ Frequency Responsibility of Monitoring

plant Disposal location

Contractors sensitive receptors

collection and laboratory analyses

sensitive receptors satisfactorily addressed

Hazardous Wastes

Treatment plant UPJN and O&M Contractors

Complaints from sensitive receptors

(ii) Site checking (iii) Checking of document

Complaints from sensitive receptors satisfactorily addressed Awareness and emergency training document

Quarterly IPIU

Air Emissions Treatment plant location

UPJN and O&M Contractors

Complaints from sensitive receptors

Air sample collection and laboratory testing

Government’s air quality standard

Quarterly IPIU

CPCB = Central Pollution Control Board; O&M = operation and maintenance, UPJN = Uttarakhand Peya Jal Nigam , IPIU = Investment Program Implementation Units

Page 104: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

96

B. Environmental Management Plan Costs

176. There were many construction stage impacts but these are typical for the construction activity

and mitigation provided is mainly in terms of good construction practices like water sprinkling to

arrest dust generation, and clearing of excess soil, which will be incorporated into the

construction contractor’s contractual agreements, which will be binding for implementation.

Therefore there will be no additional costs for environmental management. The operation phase

mitigation measures are again for good operating practices, which will be the responsibility of

operating agency; therefore there are no additional costs.

177. The monitoring proposed mainly includes site inspections and informal discussions with workers

and local people, and this will be the responsibility of PMU, costs of which are part of project

management. The air quality, noise level monitoring and water quality monitoring of construction

phase will be conducted by Contractor of each Package, since this is an additional cost, it needs

to be part of subproject cost.

178. The total survey expenses during construction for all Construction Packages estimated to be

Rs. 1,170,000 as given in Table No 20.

Table No 20 : Environmental Management and Monitoring Cost

Item Quantity Unit Cost INR

Total Cost INR

Source of Fund

Implementation of EMP (24 months)

A. Design and Supervision Consultant – DSC Environment Specialist

2 months 225,000 - DSC (cost already allotted)

Total (A)

B. Survey Expenses during Construction for individual Construction Package (Package No: WSS05DN, WSS07DN, WSS08DN, WSS09DN & WSS10DN (Specific sites will be provided to contractors after awarding of the project)

i Ambient air quality during construction

12 samples

12,000 1,44,000 Construction Contractor

ii Noise quality during construction

12 samples

4,000 48,000 Construction Contractor

Sub Total for each Package 1,92,000

Page 105: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

97

Item Quantity Unit Cost INR

Total Cost INR

Source of Fund

Total for all five Packages (B) 9,60,000

C. Survey Expenses during Construction for Packages No: WSS06DN (Specific sites will be provided to construction contractors after awarding of the project)

i Ambient air quality during construction

12 samples

12,000 1,44,000 Construction Contractor

ii Noise quality during construction

12 samples

4,000 48,000 Construction Contractor

iii Water Quality during construction

6 samples 3,000 18,000

Total (C) 2,10,000

DSC = design and supervision consultant, EMP = Environmental Management Plan

C. Environmental Mitigation and Monitoring Program for Construction of Tube wells

179. Environmental mitigation and management plan for construction of 5 number of tube

wells in Dehradun proposed to be constructed at GGIC Rajpur Road, Rajendra Nagar, Kaulagarh,

Hari Vihar of Vijay Park and Kanak respectively. The potential impacts identified and assessed

and the mitigation measures formulated to minimize those impacts to acceptable levels

identified. These are summarized in the following tables. The table also delegates the

responsibility of implementing mitigation to various agencies involved in the program

implemented as listed above. The environmental management plan of pre-construction,

during construction and operation stages are given in Table No 21. Special provision of

penalty has been given in Table No 22 as preventive measures of non-compliance of

safeguards.

180. The environmental monitoring plans have been prepared for pre-construction, during

construction and operation stage and are given in Table No. 23.

Page 106: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

98

Table No 21 : Environmental Management Plan for Construction of Tube wells in Dehradun

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

Pre-construction stage

Tree cutting and removal of vegetation.

Permanent and low

No tree cutting through selection of site for bore well

No removal of vegetation outside actual construction area

Permission of felling of trees from Forest department, if required

PIU GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

---

Permission for abstraction of Ground Water

Temporary and Low

Permission from Central Ground Water Board obtained (refer Appendix 9)

PIU GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

---

Source of Material Permanent at source and significant

Contractor will not open any site for sourcing of material.

Contractor will procure material from authorised sources.

Contractor will provide evidence of material being sources from authorised source or agency.

Contractor All applicable sites Part of contract

Page 107: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

99

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

Land acquisition Permanent Site selected at government location so no land acquisition is required.

PIU GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

---

Construction of Work Camps

Temporary and Significant

Priorities area within or nearest possible vacant space in the sub project location,

The site of construction camp should be so selected, that it will not have conflict with local community. These conflict could be use of water, use of community places like parks, access to local community, generation of waste or air pollutant and dust or smoke.

Contractor Construction Camp Site Part of contractors cost

Generation of Baseline environmental data

- The Ambient Air Quality, Ambient Noise Level, Ground Water Quality before commencement of civil works.

Construction Contractor 5 location of tube well at GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Contractors cost

Construction Stage

Labour camp Temporary air and noise pollution from

Consult with IPIU/DSC before locating project offices, sheds, and

Page 108: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

100

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

machine operation, water pollution

from storage and use of fuels, oils, solvents, and lubricants

construction plants;

Provide water and sanitation facilities for employees;

Train employees in the storage and handling of materials which can potentially cause soil contamination;

Recover used oil and lubricants and reuse or remove from the site;

Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas;

Remove all wreckage, r ub b ish , o r t em pora r y structures (such as buildings, shelters, and latrines) which are no longer required;

Sourcing of Material Significant and permanent

Contractor will not open new site for this project.

Contractor will procure

Contractor All applicable sites. Part construction cost

Page 109: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

101

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

material from authorised source and will provide and provide evidence of source being authentic.

Labour license and Insurance

Significant Obtain labour license from labour commissioner before mobilising labours to site.

Procure Workmen Compensation insurance

IPIU/ Contract For entire sub project Part of Construction cost

Environmental monitoring of Ambient Air Quality, Noise Level and Ground Water Quality monitoring

Monitoring on quarterly basis except monsoon period (Parameters as per Monitoring Plan)

Construction Contractor Locations as per Monitoring Plan Part of construct ion cost and EMP cost

Impacts due to unsuitable material generated from bore well

Temporary- medium

Find beneficial uses of excess soil

Disposal soil to suitable location

Construction Contractor GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Part of construct ion cost

Dust generation Temporary- medium

Storage of excavated soil from bore well drill at safe location and having minimum impact due to dust generation. Sprinkling of water to prevent dust generation

Construction Contractor GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Part of construction cost

Page 110: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

102

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

Impacts due to spillage of fuel and lubricants at construction site and storage yard

Temporary- medium

Storage of fuel and lubricants on non-permeable platform

Construction Contractor Construction Camp and construction site Part of construction cost

Noise from construction vehicles and equipment of construction of tube wells

Temporary-low Schedule all activities including high noise generating activity during the day time before sun set;

Employ equipment/vehicles that comply with emission standards

Take special precaution to minimise noise

Provide PPE including ear plug to the works working at construction site.

Provide temporary noise barrier at construction site in case Noise level exceeds desirable limit.

• Ensure regular maintenance to control emissions

Construction Contractor GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Part of construct ion cost

Air emission from construction vehicles

Proper storage and disposal of unsuitable

Construction Contractor GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and

Part of construct ion

Page 111: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

103

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

and equipment material generated from drilling of bore well.

Provide regular maintenance of construction vehicles and equipment deployed during construction.

Conduct ambient air quality testing and compare with baseline and NAAQS.

Maintain PUC for construction vehicles and maintain standard specified therein.

Kanak cost and EMP cost

Soil contamination by construction wastes, fuel etc

Temporary-low Provide safe disposal or storage of construction wastes, fuel etc. This includes by providing impermeable platform for storage fuel and lubricants.

Construction Contractor GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Part of construct ion cost

Contamination due to waste disposal from labour camps

Temporary-low Provide proper collection and disposal of solid waste in labour camp site.

Provide basic amenities like potable water supply and sanitation facilities in labour camps

Construction Contractor Construction labour camps Part of construct ion cost

Page 112: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

104

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

Community Health and Safety

Temporary and low

Barricading bore well during construction period and provide permanent boundary of the tube well site

Construction Contractor GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Part of construct ion cost

Landscape and Aesthetics

Solid wastes as well as excess construction materials.

(i) Prepare and Waste Management Plan; (ii) Avoid stockpiling of excess excavated soils; Coordinate with UPJN for beneficial uses of excess excavated soils or immediately dispose to designated areas; Coordinate with UPJN for beneficial uses of excess excavated soils or immediately dispose to designated areas; (iv) Recover used oil and lubricants and reuse or remove from the sites; (v) Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; (vi) Remove all wreckage, rubbish; and (vii) Request IPIU/DSC to report in writing that the necessary environmental restoration work has been adequately performed before acceptance of work.

Construction Contractor All locations Part of construct ion cost

Page 113: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

105

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

Occupational Health and Safety

Occupational hazards which can arise during work

Develop and implement site-specific health and safety plan which will include measures such as: (a) excluding public from the site; (b) ensuring all workers are provided with and use Personal Protective Equipment like helmet, gumboot, safety belt, gloves, nose musk and ear plugs; (c) health and safety training for all site personnel; (d) documented procedures to be followed for all site activities; and (e) documentation of work-related accidents; (ii) Ensure that qualified first- aid can be provided at all times. Equipped first-aid stations shall be easily accessible throughout the site; (iii) Provide medical insurance coverage for workers; (iv) Secure all installations from unauthorized intrusion and accident risks; (v) Provide supplies of potable drinking water; (vi) Provide clean eating areas where workers are not exposed to hazardous or noxious substances; (vii) Provide health and safety orientation training to all new workers to ensure that they

Construction Contractor (i) Site-specific health and safety plan; (ii) Equipped first-aid stations; (iii) Medical insurance coverage for workers; (iv) Number of accidents; (v) Supplies of potable drinking water; (vi) Clean eating areas where workers are not exposed to hazardous or noxious substances; (vii) record of health and safety orientation trainings (viii) personal protective equipments; (ix) % of moving equipment outfitted with audible back-up alarms; (xi) sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal.

Part of Contractor cost

Page 114: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

106

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers; (viii) Provide visitor orientation, if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted; (ix) Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; (x) Ensure moving equipment is outfitted with audible backup alarms; (xi) Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and (xii) Disallow worker exposure to noise level greater than 85

Page 115: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

107

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

dB(A) for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

Work Camps (if needed)

Temporary air and noise pollution from machine operation, water pollution from storage and use of fuels, oils, solvents, and lubricants

(i) Consult with IPIU/DSC before locating project offices, sheds, and construction plants; (ii) Minimize removal of vegetation and disallow cutting of trees; (iii) Provide water and sanitation facilities for employees; (iv) Prohibit employees from poaching wildlife and cutting of trees for firewood; (v) Train employees in the storage and handling of materials which can potentially cause soil contamination; (vi) Recover used oil and lubricants and reuse or remove from the site; (vii) Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; (viii) Remove all wreckage, rubbish, or temporary structures (such as buildings, shelters, and latrines) which are no longer required; and (ix) Request IPIU/DSC to report in writing that the camp

Construction Contractor (i) Complaints from sensitive receptors; (ii) Water and sanitation facilities for employees; and (iii) IPIU/DSC report in writing that the camp has been vacated and restored to pre-project conditions

Part Contractor cost

Page 116: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

108

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

has been vacated and restored to pre-project conditions before acceptance of work.

Preventive measures of violation of law related to safety

Temporary and high risk

Risk of imposition of penalty by the regulatory agency in case of violation of safety rules, such as (a) illegal power connection to labour camps, (b) working without safety gears in risky work condition, and (c) release of pollutant having impact on environmental attributes, etc.

If any such instances (listed in Table 22) come to the knowledge of employer, a notice will be issued for compliance. If it is not complied within 30 days, the employer can take precipitative action.

Construction contractor to implement and PIU and DSC to take action in case of non-compliance

GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Part of construct ion cost

Operation and Maintenance Stage

Water Table Permanent and significant

Monitoring of level of water table. In case water table decreases, IPMU has to take mitigative

IPMU All location Operator/ IPMU

Page 117: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

109

Environmental Management Plan for Construction of Tube wells in Dehradun

Description of Impact Magnitude of impact

Mitigation Measures Proposed

Responsibility of Implementation

Location Preliminary Cost

measures. That includes recharge facility or restriction of abstractor of ground water.

Page 118: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

110

D. Safeguards Items Having Penalty Provision for Construction of Tube Wells

181. DSC and PIU will make regular visit to the project site. In case safeguards practices including

safety gears, PPE, statutory and regulatory requirements stipulated in Table No 22 are found to be

violated, a penalty will be imposed on contractor by the employer.

Table No 22 : Preventive Measures of non-compliance of Safeguards

Preventive Measures of non-compliance of Safeguards

Sl. No Particulars of Item Monitoring Frequency

Action in case of non-compliance

A. Personnel Protective Equipment

1 Safety Shoes Worker/Staff/day Issue Notice and

impose penalty

B. Facilities at Construction Site

1 Barricading RMT Issue Notice and

impose penalty

2 Absence of First Aid at construction site

Box / month Issue Notice and

impose penalty

3 Absence of Supervisor at Site Staff / day Issue Notice and

impose penalty

4 Unauthorized Power Connection Per day Issue Notice and

impose penalty

5 Light arrangement during night work Per day Issue Notice and

impose penalty

6 Drinking water availability at construction site

Per day Issue Notice and

impose penalty

C.

Labour Camp

1 Absence of Cot Per Shed / month

Issue Notice and impose penalty

2 Roof without heat insulated Per Shed / month

Issue Notice and impose penalty

3 Drinking Water Per Camp / month

Issue Notice and impose penalty

4 Toilets & Bathroom for Male (Per 10 Labours)

Toilets / month Issue Notice and

impose penalty

5 Toilets & Bathroom for Female (Per Toilets / month Issue Notice and

Page 119: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

111

Preventive Measures of non-compliance of Safeguards

Sl. No Particulars of Item Monitoring Frequency

Action in case of non-compliance

10 Labours) impose penalty

6 Cleanliness of Toilets & Bathrooms Toilets / month Issue Notice and

impose penalty

7 Fire extinguisher Per Camp / month

Issue Notice and impose penalty

8 Absence of Crèche as per norms Per Camp / month

Issue Notice and impose penalty

9 Absence of First Aid at construction site

Box Issue Notice and

impose penalty

Facility for children

D. Construction Camp

1 Absence of First Aid at construction site

Box / month Issue Notice and

impose penalty

2 Fire extinguisher Per Camp / month

Issue Notice and impose penalty

3 Drinking Water Per Camp / month

Issue Notice and impose penalty

4 Soil Contamination due to fuel, lubricant & material

Per Camp / month

Issue Notice and impose penalty

5 Toilets & Bathroom for Male (Per 10 Labours)

Toilets / month Issue Notice and

impose penalty

6 Toilets & Bathroom for Female (Per 10 Labours)

Toilets / month Issue Notice and

impose penalty

E. Unauthorized Land Acquisition for allied facilities

Per camp / month

Issue Notice and impose penalty

F. Air, Water and Noise Testing Per package / quarter

Issue Notice and impose penalty

G. Monthly Safeguard Report Per Month / month

Issue Notice and impose penalty

Page 120: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

112

Table No 23 : Environmental Monitoring Plan – Tube well

Environmental Monitoring Plan – Tube well

Project stage

Parameters to be Monitored Location Responsible for Mitigation

Measurement Frequency Responsible

for Supervision

Preliminary Costing

Pre- construction

i Incorporation of mitigation measures into design and site identification

NA DSC Design check One-off before design approval

PIU/PMU Part of project management (PM) costs

ii Incorporation of construction stage mitigation measures in contract documents

NA DSC Inspection of contract documents

One off before finalization of contract

PIU/PMU Part of PM Cost

iii Baseline Air, Water and Noise level

5 location

Contractor through

approved laboratory

Air Quality, Noise level, Water Quality

Once Contractor Part construction contract

Construction Stage

i Preparation of construction management plan

NA Contractor Inspection of plan

One-off before start of construction

Construction contractor

Part of PM Cost

ii Implementation of mitigation measures

GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Contractor

Site visits Consultation with local people, workers Inspection of construction records

Weekly Construction contractor

Part of PM Cost

Page 121: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

113

Environmental Monitoring Plan – Tube well

Project stage

Parameters to be Monitored Location Responsible for Mitigation

Measurement Frequency Responsible

for Supervision

Preliminary Costing

iii Ambient air quality monitoring

GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Contractor through approved laboratory

Parameters as per National Ambient Air Quality Standard, 2009

5 samples each in 3 times at tube well sites except monsoon Total 15 Samples

Construction

contractor

INR 180,000

iv Noise quality monitoring

GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Contractor through approved laboratory

Sound level, Leq

5 samples each in 3 times at Tube well sites Total 15 Samples

Construction

contractor

INR 60,000

v Ground Water Quality

GGIC Rajpur Road, Rajendra Nagar, Kaulagarh, Hari Vihar of Vijay park and Kanak

Contractor through approved laboratory

Ground Water Testing as per ISO 10500 parameters include heavy metals and pesticides

5 samples each in 3 times at tube well sites = Total 15 Samples

Construction contractor

INR 150000

DSC-design and supervision consultant; PIU-Investment Program Implementation Unit; PMU- Investment Program Management Unit; PM-Program Management; and UPJN-Uttarakhand Peya Jal Nigam.

Page 122: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

114

E. Environmental Budget for construction of Tube wells

182. The Environmental Management and Monitoring cost for construction of 5 number of

tube wells has been budgeted and given in Table No. 24. This is estimated to INR

22,20,000. There were many construction stage impacts but these are typical for the

construction activity and mitigation provided is mainly in terms of good construction

practices like water sprinkling to arrest dust generation, and clearing of excess soil,

which will be incorporated into the construction contractor’s contractual agreements,

which will be binding for implementation. Therefore there will be no additional costs for

environmental management. The operation phase mitigation measures are again for good

operating practices, which will be the responsibility of operating agency; therefore there

are no additional costs.

183. The monitoring proposed mainly includes site inspections and informal discussions with

workers and local people, and this will be the responsibility of PMU, costs of which are

part of project management. The air quality, noise level monitoring and water quality

monitoring of construction phase will be conducted by Contractor of each Package, since

this is an additional cost, it needs to be part of subproject cost.

Table No 24 : Environmental Budget for construction of 5 Tube Wells in Dehradun

Environmental Budget for Construction of 5 Number of Tube Wells in Dehradun

Item Quantity Unit Cost

INR

Total Cost

INR

Source of Fund

Implementation of EMP (12 months)

A.

i. Environmental and Safety engineer in construction package of construction of tube wells

12 months 1,25,000 1500000 Contractor

Total (A) 1500000

B. Generation of Baseline data for Construction of Tube wells in Dehradun

Ambient air quality during construction

(5 samples each in once at tube well sites) Total Number of Samples – 5

12,000 60,000 Contractor

Noise quality during construction (5 samples each in once at tube well sites) Total

Number of

4,000 20,000 Contractor

Page 123: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

115

Environmental Budget for Construction of 5 Number of Tube Wells in Dehradun

Item Quantity Unit Cost

INR

Total Cost

INR

Source of Fund

Samples – 5

Ground Water Testing the parameters will include heavy metals and pesticides

(5 samples each in once at tube well sites) Total

Number of Samples – 5

10,000 50,000 Contractor

Total (B) 1,30,000

C. Construction Time Budget of Tube wells in Dehradun

i Ambient air quality during construction

(5 samples each in 3

seasons at tube well sites) Total

Number of Samples – 15

12,000 180000 Construction Contractor

ii Noise quality during construction 5 samples each in 3 seasons at Tube well sites Total Number of Samples –

15

4,000 60000 Construction Contractor

Ground Water Testing the parameters will include heavy metals and pesticides

5 samples each in 3 seasons at Tube well sites Total Number of Samples –

15

10,000 150000 Construction Contractor

iii Public consultation at 5 tube well locations

Once 50,000 50,000 PIU

Iv Training Once 1,00,000 1,00,000 PIU

Total (B) 590000

Grand Total 22,20,000

Page 124: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

116

F. Environmental Mitigation and Monitoring Program for Construction of Pedestrian Footpath

184. Environmental mitigation and management plan for construction and beautification of

4.8 Kms of pedestrian footpath at Rajpur Road from Dilaram Bazar to Mussoorie diversion.

The potential impacts identified and assessed and the mitigation measures formulated to

minimize those impacts to acceptable levels identified in the earlier sections are

summarized in the following tables. The table also delegates the responsibility of

implementing mitigation to various agencies involved in the program implemented as listed

above. The environmental management plan of pre-construction, during construction and

operation stages are given in Table No 25. Special provision of penalty has been given in

Table No 26 as preventive measures of non-compliance of safeguards.

185. The environmental monitoring plans have been prepared for pre-construction, during

construction and operation stage and are given in Table No. 27.

Page 125: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

117

Table No 25 : Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun

Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun

Description of Impact Magnitude of

impact Mitigation Measures

Proposed Responsibility of Implementation

Location Preliminary Cost

Pre-construction Stage

Tree cutting and removal of vegetation.

Permanent and low

• No tree cutting through proper selection of alignment No removal of vegetation outside actual construction area Permission of felling of trees from Forest department if required

PIU Dilaram Bazar to Massouri Diversion ---

Land acquisition Permanent Construction of footpath within available right of way.

PIU Dilaram Bazar to Massouri Diversion ---

Source of Material Permanent at source and significant

Contractor will not open any site for sourcing of material.

Contractor will procure material from authorised sources.

Contractor will provide evidence of material being sources from authorised source or agency.

Contractor All applicable sites Part of contract

Selection of site for Construction of Work

Temporary and

Priorities area within or nearest possible vacant

Contractor Construction Camp Site Part of contractors

Page 126: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

118

Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun

Description of Impact Magnitude of

impact Mitigation Measures

Proposed Responsibility of Implementation

Location Preliminary Cost

Camps Significant space in the sub project location,

The site of construction camp should be so selected, that it will not have conflict with local community. This conflict could arise out of use of water, use of community places like parks, access to local community, generation of waste or air pollutant and dust or smoke and outbreak of epidemic diseases.

cost

Generation of Baseline Data

Dependent on respective attributes

Conduct Air Quality Testing, Noise Level Testing, Ground Water Testing as per Monitoring plan

Construction Contractor 2 locations at Rajpur Road at the site of construction of pedestrian footpath.

Contractor’s cost

Construction Stage

Labour camp Temporary air and noise pollution from machine operation, water pollution

from storage

Consult with IPIU/DSC before locating project offices, sheds, and construction plants;

Provide water and sanitation facilities for

Contractor At Construction Camp Site Contractor’s Cost

Page 127: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

119

Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun

Description of Impact Magnitude of

impact Mitigation Measures

Proposed Responsibility of Implementation

Location Preliminary Cost

and use of fuels, oils, solvents, and lubricants

employees;

Train employees in the storage and handling of materials which can potentially cause soil contamination;

Recover used oil and lubricants and reuse or remove from the site;

Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas;

Remove all wreckage, r ub b ish , o r t em pora r y structures (such as buildings, shelters, and latrines) which are no longer required;

Labour license and Insurance

Significant Obtain labour license from labour commissioner and

Procure workmen compensation insurance

IPIU/ Contract For entire sub project Part of Construction cost

Sourcing of Material Significant Contractor will not open Contractor All applicable sites. Part

Page 128: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

120

Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun

Description of Impact Magnitude of

impact Mitigation Measures

Proposed Responsibility of Implementation

Location Preliminary Cost

and permanent

new site for this project.

Contractor will procure material from authorised source and will provide and provide evidence of source being authentic.

construction cost

Conduct Ambient Air Quality, Noise Level and monitoring

Parameters as per Monitoring Plan

Construction Contractor Locations as per Monitoring Plan Contractor Cost

Impacts due to soil disposal generated from site preparation

Temporary- medium

Find beneficial uses of excess soil

Disposal soil to suitable location

Construction Contractor

Locations as per Monitoring Plan Part of construct ion cost

Noise from construction vehicles and equipment of construction of pedestrian footpath

Temporary-low

• Schedule all activities including high noise generating activity during the day time. • Employ equipment/vehicles that comply with emission standards • Take special precaution to minimise noise

• Ensure regular maintenance to control emissions

Construction Contractor Locations as per Monitoring Plan Part of construct ion cost

Air emission from construction vehicles and

Provide regular maintenance of construction vehicles and

Construction Contractor Locations as per Monitoring Plan

Page 129: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

121

Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun

Description of Impact Magnitude of

impact Mitigation Measures

Proposed Responsibility of Implementation

Location Preliminary Cost

equipment equipment deployed during construction.

Conduct ambient air quality testing and compare with baseline and NAAQS.

Maintain PUC and maintain standard specified therein.

Construction material for civil structure

Temporary - low

Sourcing of construction material from authorised source

Construction Contractor Locations as per Monitoring Plan

Part of construct ion cost

Contamination due to waste disposal from labour camps

Temporary-low

Provide proper collection and disposal of solid waste in labour camp site.

Provide basic amenities like potable water supply and sanitation facilities in labour camps

Construction Contractor

Construction labour camps Part of construct ion cost

Landscape and Aesthetics

Solid wastes as well as excess construction materials.

(i) Prepare and Waste Management Plan; (ii) Avoid stockpiling of excess excavated soils; Coordinate with UPJN for beneficial uses of excess excavated soils or immediately dispose to designated areas; Coordinate with UPJN for beneficial uses of excess excavated soils or immediately dispose to designated areas; (iv)

Construction Contractor All locations Part of construct ion cost

Page 130: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

122

Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun

Description of Impact Magnitude of

impact Mitigation Measures

Proposed Responsibility of Implementation

Location Preliminary Cost

Recover used oil and lubricants and reuse or remove from the sites; (v) Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; (vi) Remove all wreckage, rubbish; and (vii) Request IPIU/DSC to report in writing that the necessary environmental restoration work has been adequately performed before acceptance of work.

Occupational Health and Safety

Occupational hazards which can arise during work

Develop and implement site-specific health and safety plan which will include measures such as: (a) excluding public from the site; (b) ensuring all workers are provided with and use Personal Protective Equipment like helmet, gumboot, safety belt, gloves, nose musk and ear plugs; (c) health and safety training for all site personnel; (d) documented procedures to be followed for all site activities; and (e) documentation of work-related accidents; (ii) Ensure that qualified first- aid can be provided at all times. Equipped first-aid stations

Construction Contractor (i) Site-specific health and safety plan; (ii) Equipped first-aid stations; (iii) Medical insurance coverage for workers; (iv) Number of accidents; (v) Supplies of potable drinking water; (vi) Clean eating areas where workers are not exposed to hazardous or noxious substances; (vii) record of health and safety orientation trainings (viii) personal protective equipments; (ix) % of moving equipment outfitted with audible back-up alarms; (xi) sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal.

Part of Contractor cost

Page 131: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

123

Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun

Description of Impact Magnitude of

impact Mitigation Measures

Proposed Responsibility of Implementation

Location Preliminary Cost

shall be easily accessible throughout the site; (iii) Provide medical insurance coverage for workers; (iv) Secure all installations from unauthorized intrusion and accident risks; (v) Provide supplies of potable drinking water; (vi) Provide clean eating areas where workers are not exposed to hazardous or noxious substances; (vii) Provide health and safety orientation training to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers; (viii) Provide visitor orientation, if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted; (ix) Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; (x) Ensure moving equipment is outfitted with audible backup alarms; (xi) Mark and

Page 132: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

124

Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun

Description of Impact Magnitude of

impact Mitigation Measures

Proposed Responsibility of Implementation

Location Preliminary Cost

provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and (xii) Disallow worker exposure to noise level greater than 85 dB(A) for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

Work Camps Temporary air and noise pollution from machine operation, water pollution from storage and use of fuels, oils, solvents, and lubricants

(i) Consult with IPIU/DSC before locating project offices, sheds, and construction plants; (ii) Minimize removal of vegetation and disallow cutting of trees; (iii) Provide water and sanitation facilities for employees; (iv) Prohibit employees from poaching wildlife and cutting of trees for firewood; (v) Train employees in the storage and handling of materials which can potentially cause soil

Construction Contractor (i) Complaints from sensitive receptors; (ii) Water and sanitation facilities for employees; and (iii) IPIU/DSC report in writing that the camp has been vacated and restored to pre-project conditions

Part Contractor cost

Page 133: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

125

Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun

Description of Impact Magnitude of

impact Mitigation Measures

Proposed Responsibility of Implementation

Location Preliminary Cost

contamination; (vi) Recover used oil and lubricants and reuse or remove from the site; (vii) Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; (viii) Remove all wreckage, rubbish, or temporary structures (such as buildings, shelters, and latrines) which are no longer required; and (ix) Request IPIU/DSC to report in writing that the camp has been vacated and restored to pre-project conditions before acceptance of work.

Preventive measures of violation of law related to safety

Temporary and high risk

Risk of imposition of penalty by the regulatory agency in case of violation of safety rules. Example - power connection to unsafe labour camps, working without safety gears in risky work condition, release of pollutant having impact on environmental attributes. If any such instances come to the notice of employer, a notice will be issued for compliance. If it is not complied within not more than

Construction contractor to implement and PIU and DSC to take action in case of non-compliance

Locations as per Monitoring Plan

Page 134: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

126

Environmental Management Plan for Construction of Pedestrian Footpath in Dehradun

Description of Impact Magnitude of

impact Mitigation Measures

Proposed Responsibility of Implementation

Location Preliminary Cost

30 days, the employer can take precipitative action.

Operation and Maintenance Stage

Nil Nil Nil Nil Nil Nil

Page 135: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

127

G. Safeguards Items Having Penalty Provision for Construction of Pedestrian Footpath

186. DSC and PIU will make regular visit to the project site. In case safeguards practices

including safety gears, PPE, statutory and regulatory requirements stipulated in Table No 26 are

found to be violated, a penalty will be imposed on contractor by the employer.

Table No 26 : Preventive Measures of non-compliance of Safeguards

Preventive Measures of non-compliance of Safeguards

Sl. No Particulars of Item Monitoring Frequency

Action in case of non-compliance

A. Personnel Protective Equipment

1 Safety Shoes Worker/Staff/day Issue Notice and

impose penalty

B. Facilities at Construction Site

1 Barricading RMT Issue Notice and

impose penalty

2 Absence of First Aid at construction site

Box / month Issue Notice and

impose penalty

3 Absence of Supervisor at Site Staff / day Issue Notice and

impose penalty

4 Unauthorized Power Connection Per day Issue Notice and

impose penalty

5 Light arrangement during night work

Per day Issue Notice and

impose penalty

6 Drinking water availability at construction site

Per day Issue Notice and

impose penalty

C.

Labour Camp

1 Absence of Cot Per Shed / month

Issue Notice and impose penalty

2 Roof without heat insulated Per Shed / month

Issue Notice and impose penalty

3 Drinking Water Per Camp / month

Issue Notice and impose penalty

4 Toilets & Bathroom for Male (Per 10 Labours)

Toilets / month Issue Notice and

impose penalty

5 Toilets & Bathroom for Female (Per 10 Labours)

Toilets / month Issue Notice and

impose penalty

Page 136: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

128

Preventive Measures of non-compliance of Safeguards

Sl. No Particulars of Item Monitoring Frequency

Action in case of non-compliance

6 Cleanliness of Toilets & Bathrooms

Toilets / month Issue Notice and

impose penalty

7 Fire extinguisher Per Camp / month

Issue Notice and impose penalty

8 Absence of Crèche as per norms Per Camp / month

Issue Notice and impose penalty

9 Absence of First Aid at construction site

Box Issue Notice and

impose penalty

Facility for children

D. Construction Camp

1 Absence of First Aid at construction site

Box / month Issue Notice and

impose penalty

2 Fire extinguisher Per Camp / month

Issue Notice and impose penalty

3 Drinking Water Per Camp / month

Issue Notice and impose penalty

4 Soil Contamination due to fuel, lubricant & material

Per Camp / month

Issue Notice and impose penalty

5 Toilets & Bathroom for Male (Per 10 Labours)

Toilets / month Issue Notice and

impose penalty

6 Toilets & Bathroom for Female (Per 10 Labours)

Toilets / month Issue Notice and

impose penalty

E. Unauthorized Land Acquisition for allied facilities

Per camp / month

Issue Notice and impose penalty

F. Air, Water and Noise Testing Per package / quarter

Issue Notice and impose penalty

G. Monthly Safeguard Report Per Month / month

Issue Notice and impose penalty

Page 137: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

129

Table No 27 : Environmental Monitoring Plan – Construction of Pedestrian Footpath

Environmental Monitoring Plan – Construction of Pedestrian Footpath

Project stage

Parameters to be Monitored Location Responsible for Mitigation

Measurement Frequency Responsible

for Supervision

Preliminary Costing

Pre- construction

I

Incorporation of mitigation measures into design and site identification

NA DSC Design check One-off before design approval

PIU/PMU Part of project management (PM) costs

Ii Incorporation of construction stage mitigation measures in contract documents

NA DSC Inspection of contract documents

One off before finalization of contract

PIU/PMU Part of PM Cost

iii Baseline Air, Water and Noise level

2 location

Contractor through

approved laboratory

Air Quality, Noise level, Water Quality

Once Contractor Part construction contract

Construction Stage

I Preparation of construction management plan

NA Contractor Inspection of plan

One-off before start of construction

Contractor Part of PM Cost

ii Implementation of mitigation measures

Mussoorie Diversion to Dilaram Bazar

Contractor

Site visits Consultation with local people, workers Inspection of construction records

Weekly Contractor Part of PM Cost

Page 138: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

130

Environmental Monitoring Plan – Construction of Pedestrian Footpath

Project stage

Parameters to be Monitored Location Responsible for Mitigation

Measurement Frequency Responsible

for Supervision

Preliminary Costing

Iii Ambient air quality monitoring

Mussoorie Diversion to Dilaram Bazar

Contractor through approved laboratory

Parameters as per National Ambient Air Quality Standard, 2009

2 samples each in 3 times at construction of pedestrian footpath site except monsoon Total 6 Samples

Contractor Part of Monitoring cost

iv Noise quality monitoring

Mussoorie Diversion to Dilaram Bazar

Contractor through approved laboratory

Sound level, Leq

2 samples each in 3 times at construction of pedestrian footpath sites Total 6 Samples

Contractor Part of Monitoring cost

DSC-design and supervision consultant; PIU-Investment Program Implementation Unit; PMU- Investment Program Management Unit; PM-Program Management; and UPJN-Uttarakhand Peya Jal Nigam.

Page 139: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

131

H. Environmental Budget for construction of Pedestrian Footpath

187. The Environmental Management and Monitoring cost for construction of 4.8 Kms of

pedestrian and its beautification has been budgeted and given in Table No. 28. This is

estimated to INR 19,08,000. There were many construction stage impacts but these are

typical for the construction activity and mitigation provided is mainly in terms of good

construction practices like water sprinkling to arrest dust generation, and clearing of

excess soil, which will be incorporated into the construction contractor’s contractual

agreements, which will be binding for implementation. Therefore there will be no additional

costs for environmental management. The operation phase mitigation measures are again

for good operating practices, which will be the responsibility of operating agency;

therefore there are no additional costs.

188. The monitoring proposed mainly includes site inspections and informal discussions with

workers and local people, and this will be the responsibility of PMU, costs of which are

part of project management. The air quality, noise level monitoring and water quality

monitoring of construction phase will be conducted by Contractor of each Package, since

this is an additional cost, it needs to be part of subproject cost.

Table No 28 : Cost of Environmental Management and Monitoring of Pedestrian Footpath in

Dehradun

Item Quantity Unit Cost

INR

Total Cost

INR

Source of Fund

Implementation of EMP (12 months)

A.

i. Environmental and Safety engineer in construction package of construction of pedestrian footpath

12 months 1,25,000 1500000 Contractor

Total (A) 1500000

B. Construction of Pedestrian Footpath in Dehradun Baseline

Ambient air quality during construction

(2 samples at 2 location ) Total

Number of Samples – 2

12,000 24,000 Contractor

Noise quality during construction (2 samples at 2 location ) Total

Number of Samples – 2

4,000 8,000 Contractor

Ground Water Testing the parameters will include heavy metals and pesticides

(2 samples at 2 location ) Total

Number of Samples – 2

10,000 20,000 Contractor

Total (B) 52,000

Page 140: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

132

C. Construction of Pedestrian Footpath in Dehradun 12 months

i Ambient air quality during construction

(2 samples in 3 seasons) Total

Number of Samples – 6

12,000 72000 Construction Contractor

ii Noise quality during construction (2 samples in 3 seasons) Total

Number of Samples – 6

4,000 24000 Construction Contractor

Ground Water Testing the parameters will include heavy metals and pesticides

(2 samples in 3 seasons) Total

Number of Samples – 6

10,000 60000 Construction Contractor

iii Public consultation along pedestrian footpath

Once 1,00,000 1,00,000 PIU

iv Training Once 1,00,000 1,00,000 PIU

Total (B) 356000

Grand Total 1908000

Page 141: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

133

IX. FINDINGS AND RECOMMENDATIONS

189. The process described in this document has assessed the environmental impacts of all

elements of the infrastructure proposed under the Dehradun Water Supply Subproject. Potential

negative impacts were identified in relation to both construction and operation of the improved

infrastructure, but no impacts were identified as being due to either the project design or location.

Mitigation measures have been developed in generic way to reduce all negative impacts to

acceptable levels.

190. During the construction phase, impacts mainly arise from the need to dispose of large

quantities of waste soil and import a similar amount of sand to support the pipes in the trenches;

and from the disturbance of residents, businesses, traffic and important buildings by the

construction work. These are common impacts of construction in urban areas, and there are well

developed methods for their mitigation. These include: (i) Finding beneficial uses for waste

material; (ii) Covering soil and sand during transportation and when stored on site; (iii) Planning

work to minimize disruption of traffic and communities; (iv) Providing temporary structures to

maintain access across trenches where required.

191. Specific impacts due to construction of intake/anicut across a stream flowing through hilly

forested areas were identified and measures such as the following have been suggested: (i) No

construction material storage/ancillary works in the forest; (ii) No labour camps; (iii) Limiting the

work to daylight hours only; (iv) Conducting construction work in lean flow season (summer); (v)

Protection bunds around construction area; (vi) Conducting awareness programs to workers; (vii)

No noisy works; (viii) Barricading the construction area; (ix) Implementation of any measures as

suggested by the Forest Department; and (x) Use of excavated soil for strengthening bunds/road

leveling; no waste shall be disposed in or near forests.

192. The constructions of 5 tube wells and pedestrian footpath have temporary and

insignificant impact during construction stage. This arises out of disposal of soil of bore well. The

mitigation measures have been suggested in terms of safe disposal and beneficial use.

193. Once the system is operating, most facilities will operate with routine maintenance, which

should not affect the environment. Leaks in the network will need to be repaired from time to time,

but environmental impacts will be much less than those of the construction period as the work will

be infrequent, affecting small areas only. There is a safety risk involved in handling of chlorine for

disinfection of water supplies. However, all the necessary precautionary measures are included.

194. The major impacts of the implementation of water supply subproject will be beneficial to

the citizens of Dehradun as it will provide constant supply of water, which will serve a greater

proportion of the population, including slum-dwellers. This will improve the quality of life of people

as well as benefiting both individual and public health as the improvements in hygiene should

reduce the incidence of disease associated with poor sanitation. This should lead to economic

gains as people will be away from work less and will spend less on healthcare, so their incomes

should increase.

195. An Environmental Management Plan (EMP) is proposed as part of this IEE which includes

(i) mitigation measures for significant environmental impacts during implementation, (ii)

environmental monitoring program, and the responsible entities for mitigation, monitoring, and

reporting; and (iii) public consultation and information disclosure. Mitigation measures have been

Page 142: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

134

developed to reduce all negative impacts to acceptable levels. A number of impacts and their

significance have already been reduced by amending the designs.

196. The important recommendation of this IEE is that this water supply distribution subproject

can proceed for implementation provided all impacts are addressed through suggested mitigation

measures. The other important recommendation is that the involuntary resettlement issues, which

are identified through a parallel process of resettlement planning, need to be addressed by

resettlement plan implementation. The recommended clauses for the Construction Contractor’s

Contract are attached as Appendix 6 to ensure that mitigation measures are implemented.

Page 143: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

135

X. CONCLUSIONS

197. The main objective of this water supply subproject in Dehradun is to improve the water

supply service in terms of water quality and quantity through source rehabilitation, leak reduction,

network improvement and treatment plant rehabilitation works. Thus ultimately this subproject

aims to improve overall living conditions in the City. This initial environmental examination has

been conducted to identify and assess the negative impacts, if any, of this subproject.

198. All components proposed under this sub-project involve straightforward construction and

simple operation. Not many environmental issues were noted during this initial environmental

examination. In most cases, environmental issues identified are typical for the type of component

construction, and a range of proven mitigation strategies exists to address them.

199. This IEE has assessed all potential environmental impacts associated with the subproject.

There are no impacts, which are significant or complex or which needs an in depth study to

assess the impact or to develop the mitigation measures. The environmental impacts identified

are manageable, and the IPMU will monitor implementation of measures. The subproject,

therefore, does not warrant environmental impact assessment (EIA).

200. Based on the findings of the IEE, the classification of the Project as Category “B” is

confirmed, and no further or additional work is required to comply with ADB SPS (2009) or the

government’s EIA Notification (2006). Consent for Establishment (CFE) and Consent for

Operation (CFO) will be required under the Water Act 1974 from Uttaranchal Environmental

Protection and Pollution Control Board for new/augmentation of Water Treatment Plants at

Dilaram Bazaar and at Purukul Gram.

201. The construction and operation of 5 number of tube wells in Dehradun will comply the

condition of Central Ground Water Board. This stipulates that the permission has been given for

construction of tube wells in lieu of abandoned tube wells.

202. The addition of construction of tube wells and pedestrian foot path do not change its

category ‘B’ and warrants requirement and adherence to permission from Central Ground Water

Board.

Page 144: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

136

List of Appendices

Appendix 1: Central Pollution Control Board Applicable Environmental Standards

General Standards for Discharge of Environmental Pollutants: Effluents

Sl.no Parameter Standards

Inland surface water

Public sewers

Land of irrigation

Marine/coastal areas

(a) (b) (c) (d)

1. Color and odor remove as far as practicable

2. Suspended solids

mg/l, maximum.

100 600 200 (a) For process waste water 100

(b) For cooling water effluent 10% above total suspended matter of influent.

3. Particle size of suspended solids

Shall pass 850 micron IS Sieve

(a) Floatable solids maximum, 3 mm.

(b) Settable solids (maximum 850 micron)

4. pH value 5.5. to 9.0 5.5 - 9.0 5.5 - 9.0 5.5 - 9.0

5. Temperature shallnot exceed 5 ºC above the receiving water temperature

Shall not exceed 5 ºC above the receiving water temperature

6. Oil and grease, mg/l, maximum.

10 20 10 20

7. Total residual chlorine, mg/l, maximum.

1.0 1.0

8. Ammonical nitrogen

(as N.) mg/l, maximum.

50 50 50

9. Total Kjeldahl Nitrogen (as NH3) mg/l, maximum.

100 100

10. Free ammonia (as NH3), mg/l, maximum.

5.0 5.0

Page 145: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

137

11. Biochemical oxygen

demand (3 days at 27

o C), mg/l,

maximum.

30 350 100 100

12. Chemical oxygen demand, mg/l, maximum.

250 250

13. Arsenic (as As) mg/l, maximum.

0.2 0.2 0.2 0.2

14. Mercury(AsHg), mg/l, maximum.

0.01 0.01 0.01

15. Lead (as Pb) mg/l, maximum.

0.1 1.0 2.0

16. Cadmium (as Cd) mg/l. maximum.

2.0 1.0 2.0

17. Hexavalent chromium (as Cr. +6).mg/l, maximum.

0.1 2.0 1.0

18. Total Chromium (as Cr) mg/l, maximum

2.0 2.0

2.0

19. Copper (as Cu) mg/l, maximum.

3.0 3.0 3.0

20. Zinc (as Zn) mg/l, maximum.

5.0 15 15

21. Selenium (as Se)mg/l, maximum.

0.05 0.05 0.05

22. Nickel (as Ni) mg/l, maximum.

3.0 3.0 5.0

23. Cyanide (as CN) mg/l, maximum.

0.2 2.0 0.2 0.2

24. Fluoride (as F) mg/l, maximum.

2.0 15 15

25. Dissolved phosphates (as P) mg/l, maximum.

5.0

26. Sulfide (as S) mg/l, maximum.

2.0 5.0

Page 146: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

138

27. Phenolic compounds (as C6H5OH) mg/l, maximum.

1.0 5.0 5.0

28. Radioactive materials:

(a) Alfa emitters microcurie/ml, maximum.

(b) Beta emitters Micro curie/ml, maximum.

10-7

10 -6

10 -7

10-6

10 -8

10-7

10-7

10-6

29. Bio-assay test 90% Survival of fish after 96 hours in 100% effluent

90%survival of fish after 96 hours in 100% effluent

90% survival of fish after 96 hours in100% effluent

90% survival of fish after 96 hours in 100% effluent

30. Manganese (as Mn) 2 mg/l 2 mg/l 2 mg/l

31. Iron (as Fe) 3 mg/l 3 mg/l 3 mg/l

32. Vanadium (as V) 0.2 mg/l 0.2 mg/l 0.2 mg/l

33. Nitrate Nitrogen 10 mg/l 20 mg/l

mg/l = milligram per litre, mm = millimetre.

Note: These standards shall be applicable for industries, operations or process other than those industries

operations or process for which standards have been specified in schedule of the Environment Protection Rules, 1989.

Central Pollution Control Board Primary Water Quality Criteria

Designated-Best-Use Class of Water

Criteria

Drinking Water Source treatment but after disinfection

without conventional A Total Coliform Organisms: MPN # 50 per 100 Ml

6 .5 # pH # 8.5

Dissolved Oxygen: ∃6 mg/l

Biochemical Oxygen Demand (5 days @ 20

oC):2 mg/L

Outdoor bathing (organized) B Total Coliform Organisms: MPN #

500 per 100 ml

6 .5 # pH # 8.5

Dissolved Oxygen: ∃5 mg/l

Biochemical Oxygen Demand (5 days @ 20

ºC): # 3 mg/l

Drinking water sources after conventional treatment and disinfection

C Total Coliform Organisms: MPN # 5000 per 100 ml

6 # p H # 9

Dissolved Oxygen: ∃4 mg/l

Biochemical Oxygen Demand (5 days @ 20

ºC): # 3 mg/l

Propagation of wildlife and fisheries D 6 .5 # pH # 8.5

Page 147: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

139

Designated-Best-Use Class of Water

Criteria

Dissolved Oxygen: ∃4 mg/l

Free ammonia (as N): # 1.2 mg/l

Irrigation, industrial cooling, controlled waste

disposal

E # p H # 8 . 5

Electrical conductivity at 25 ºC: #2250

micro mhos/cm

Sodium absorption ratio: Maximum 26

Boron: Maximum 2 mg/l

mg/l = milligram/litre, MPN = .Most Probable Number

Indian Standards for Drinking Water - Specification (BIS 10500: 1991

Sl.No Substance or Characteristic Requirement (Desirable Limit)

Permissible Limit in the absence of Alternate source

Essential characteristics

1. Color, ( Hazen units, maximum) 5 25

2. Odor Unobjectionable Unobjectionable

3. Taste Agreeable Agreeable

4. Turbidity ( NTU, maximum) 5 10

5. pH Value 6.5 - 8.5 No Relaxation

6. Total Hardness (as CaCo3 ) mg/l, maximum

300 600

7. Iron (as Fe) mg/l, maximum 0.3 1.0

8. Chlorides (as Cl) mg/l, maximum. 250 1000

9. Residual, free chlorine, mg/l,

minimum

0.2 --

Desirable Characteristics

10. Dissolved solids mg/l, maximum 500 2000

11. Calcium (as Ca) mg/l, maximum 75 200

12. Magnesium (as Mg)mg/l,

maximum.

30 100

13. Copper (as Cu) mg/l, maximum 0.05 1.5

14. Manganese (as Mn)mg/l, maximum 0.10 0.3

15. Sulfate (as SO4 ) mg/l, maximum 200 400

16. Nitrate (as NO3 ) mg/l, maximum 45 100

17. Fluoride (as F) mg/l, maximum 1.0 1.5

18. Phenolic Compounds (as C6

H5OH)

mg/l, maximum.

0.001 0.002

19. Mercury (as Hg)mg/l, maximum 0.001 No relaxation

20. Cadmiun (as Cd)mg/l, maximum 0.01 No relaxation

Page 148: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

140

21. Selenium (as Se)mg/l,maximum 0.01 No relaxation

22. Arsenic (as As) mg/l, maximum 0.05 No relaxation

23. Cyanide (as CN) mg/l, maximum 0.05 No relaxation

24. Lead (as Pb) mg/l, maximum 0.05 No relaxation

25. Zinc (as Zn) mg/l, maximum 5 15

26. Anionic detergents (as MBAS)

mg/l, maximum

0.2 1.0

27. Chromium (as Cr6+

) mg/l, maximum 0.05 No relaxation

28. Polynuclear aromatic hydro

carbons

(as PAH) g/l, maximum

-- --

29. Mineral Oil mg/l, maximum 0.01 0.03

30. Pesticides mg/l, maximum Absent 0.001

31 Radioactive Materials

i. Alpha emitters Bq/l, maximum -- 0.1

ii. Beta emitters pci/l,maximum -- 1.0

32 Alkalinity mg/l. maximum 200 600

33 Aluminium (as Al) mg/l,maximum 0.03 0.2

34 Boron mg/l, maximum 1 5

Ambient Air Quality Standards

Pollutant Time Weighted Average

Industrial, Residential, Rural and Other Areas

Sensitive Area

(Notified by Central Government)

Method of Measurement

Sulphur Dioxide (SO2)

Annual Average

a

24 hours Average

b

50 µg/m3

80 µg/m3

20 µg/m 3 80 µg/m3 . Improved West & Gaeke

Method Ultraviolet Fluorescence

Oxides of Nitrogen (NOX)

Annual Average

a

24 hours Average

b

40 µg/m 3

80 µg/m3

30 µg/m3

80 µg/m3

.Jacobs & Hochheiser modified (NaoH– NaAsO2) method . Gas Chemiluminiscence

Particulate

Matter (PM10) (Size <10 µm)

Annual Average

a

24 hours Average

b

60 pg/m3

100 µg/m3

60 µg/m3

100 µg/m3

. Gravimetric

. TOEM

. Beta Attenuation

Particulate

Matter (PM 2.5) (Size <2.5 µm)

Annual Average

a

24 hours Average b

40 pg/m3

60 µg/m3

40 µg/m3

60 µg/m3

. Gravimetric

. TOEM

. Beta Attenuation

Ozone (O3 ) 8 hours average

b

100 µg/m3

180 µg/m3

100 µg/m3

180 µg/m3

. UV photometric

. Chemiluminiscence

Page 149: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

141

Pollutant Time Weighted Average

Industrial, Residential, Rural and Other Areas

Sensitive Area

(Notified by Central Government)

Method of Measurement

1 hourb . Chemical method

Lead (Pb) Annual Average

a

24 hours Average

b

0.5 µg/m3 1.0 µg/m

3 0.5 µg/m

3

1.0 µg/m3

. AAS method after sampling

using EPM 2000 or equivalent filter paper

Carbon Monoxide (CO)

8 hours Average

b

1 hourb

2.0 mg/m3

4.0 mg/m3

2.0 mg/m3

4.0 mg/m3

. Non Dispersive Infrared

Spectroscopy

Ammonia (NH3 ) Annual Average

a

24 hours Average

b

100 µg/m3

400 µg/m3

100 µg/m3

400 µg/m3

. Chemiluminiscence

. Indophenol blue method

Benzene (C6H6 ) Annual Average

a

5 ng/m3

5 ng/m3 . Gas Chromatography

continuous analyzer

. Adsorption & desorption

followed by GC analysis

Benzo(o)pyrene particulate phase only

Annual Average

a

1 ng/m3 1 ng/m

3 . Solvent extraction followed

by GC/HPLC analysis

Arsenic (As)

Annual Average

a

6 ng/m3 6 ng/m

3 . AAS/ICP method after

sampling using EPM 2000 or equivalent filter paper

Nickel (Ni) Annual Average

a

20 ng/m3 20 ng/m

3 . AAS/ICP method after

sampling using EPM 2000 or equivalent filter paper

AAC = Average Annual Concentration, EPM = EMP 2000 High Volume Sampler Filter Paper, GC = Gas Chromatography, HPLC = High Pressure Liquid Chromatography, a Indicate Annual Arithmetic Mean of Minimum 104 measurement in a year measured twice a week, 24 hourly at uniform intervals. b 24 hourly / 8 hourly/1 hourly values should be met 98% of the time in a year. However, 2% of the time, it may exceed by not on two consecutive days. Source: Central Pollution Control Board, New Delhi, Notification dated 18

th November 2009.

Page 150: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

142

Appendix 2: Rapid Environmental Checklist

Dehradun Water Supply, Construction of Tube well and Pedestrian footpath Subprojects

Screening Questions Yes No Additional Information for

Substantiating Assessment

A. Project Siting

Is the project area

• Densely populated? √ Water supply distribution system, to be implemented in entire Dehradun city area where centrally located core zones are densely populated and remaining zones are sparsely populated. Construction of tube wells and pedestrian footpath at Rajpur Road from Dilaram Bazar to Mussoorie diversion are also falling within densely populated area.

• Heavy with development activities?

• Adjacent to or within any environmentally sensitive areas?

√ No

• Cultural heritage site √ No

• Protected Area √ No; there are some forest areas around the intake site at Galogi

• Wetland √ There are no wetland or notable water bodies within the project area

• Mangrove √ Not a coastal area

• Esturine √ Not a coastal area

• Buffer zone of protected area

√ No

• Special area for protecting biodiversity

√ No

• Bay √ No

Potential Environmental

Impacts

Will the Project cause…

• Pollution of raw water supply from upstream wastewater discharge from communities, industries, agriculture, and soil erosion runoff?

√ There is no major pollution risk for existing sources.

• Impairment of historical/cultural monuments/areas and loss/damage to these sites?

√ There are no such notified sites within project area hence no impacts envisaged.

Page 151: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

143

Screening Questions Yes No Additional Information for

Substantiating Assessment

• Hazard of land subsidence caused by excessive ground water pumping?

√ Subproject does not involve augmentation of source; the extraction of ground water will remain at existing level

• Social conflicts arising from displacement of communities?

√ Subproject does not involve land acquisition or displacement.

• Conflicts in abstraction of raw water for water supply with other beneficial water uses for surface and ground waters?

√ The subproject does not involve augmentation of supply from existing levels. The demand supply gap is to be met through reduction of losses in distribution system and construction of tube wells in lieu of abandoned tube wells.

• Unsatisfactory raw water supply (e.g. excessive pathogens or mineral constituents)?

√ The raw water has excessive hardness (>500ppm) for some sources. Appropriate treatment works is proposed in the subproject.

• Delivery of unsafe water to distribution system?

√ Raw water will be treated before distribution.

• Inadequate protection of intake works or wells, leading to pollution of water supply?

√ Existing Intake structure is adequately planned and designed.

• Over pumping of ground water, leading to salinization and ground subsidence?

√ The subproject does not involve augmentation of supply from existing levels

• Excessive algal growth in storage reservoir?

√ Treated and disinfected water will be stored in the OHTs which are covered, so the problem will be minimal. Regular cleaning during operation will mitigate the problem.

• Increase in production of sewage beyond capabilities of community facilities?

√ Sewerage system of adequate capacity including treatment is being developed under the UUSDIP

• Inadequate disposal of sludge from water treatment plants?

√ Only nominal quantity of sludge is anticipated from WTP. There will be provision of proper sludge disposal from water treatment plant.

•Inadequate buffer zone around pumping and treatment plants to alleviate noise and other possible nuisance and protect facilities?

√ Adequate buffer and protection will be ensured.

•Impairments associate with transmission lines and access roads?

√ No such possibilities as proper precautions will be taken.

• Health hazards arising from inadequate design of facilities for receiving, storing, and handling of chlorine and other hazardous chemicals.

√ Liquid chlorine/chlorine gas is proposed to be used for disinfection of water. Proper facility for storing and handling of chlorine will be maintained, and all safety precautions will be provided.

• Health and safety hazards to workers from handling and

√ Only trained operator will operate the chlorination system. Proper precautionary

Page 152: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

144

Screening Questions Yes No Additional Information for

Substantiating Assessment

management of chlorine used for disinfection, other contaminants, and biological and physical hazards during project construction and operation?

measures will be taken during handling of chlorine.

•Dislocation or involuntary resettlement of people?

√ Subproject does not involve land acquisition or displacement. However, there may be temporary disturbance to business and squatters/vendors during construction.

Appropriate measures will be suggested to mitigate the impact.

•Social conflicts if workers from other regions or countries are hired?

√ No such impact anticipated; local communities in the vicinity of the project would be employed as much as possible.

•Noise and dust from construction activities?

√ Best construction management practice will be adopted during construction activity to minimize dust and noise generation.

•Continuing soil erosion/silt runoff from construction operations?

√ Work will mostly be conducted in dry season mostly; during rains necessary appropriate measures will be implemented.

•Increased road traffic due to interference of construction activities?

√ Proper traffic management and planning will be ensured during construction.

•Delivery of unsafe water due to poor O&M treatment processes (especially mud accumulation in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems?

√ Regular back washing of filters and chlorine dosing is done and also regular water quality monitoring will be carried out.

•Delivery of water to distribution system, which is corrosive due to inadequate attention to feeding of corrective chemicals?

√ Dosing of chemicals such as chlorine and alum will be as per the raw water analysis. GI and DI pipes will be used for distribution system and are non-corrosive in nature.

•Accidental leakage of chlorine gas?

√ All standard safety equipment will be provided and procedure will be followed.

•Excessive abstraction of water affecting downstream water users?

√ The subproject does not involve augmentation of supply from existing levels.

•Competing uses of water? √ No such possibilities.

•Increased sewage flow due to increased water supply?

√ Sewerage system of adequate capacity including treatment is being developed under the UUSDIP.

•Increased volume of sullage (wastewater from cooking and washing) and sludge from

√ As above

Page 153: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

145

Screening Questions Yes No Additional Information for

Substantiating Assessment

wastewater treatment plant

• Large population influx during project construction and operation that causes increased burden on social infrastructure and services (such as water supply and sanitation systems)?

√ No such impact anticipated; local communities in the vicinity of the project would be employed as much as possible.

• Risks to community health and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel and other chemicals during operation and construction?

√ Not applicable. Construction will not involve use of explosives and chemicals.

• Community safety risks due to both accidental and natural hazards, especially where the structural elements or components of the project are

√ Operational area will be clearly demarcated and access will be controlled. Only worker and project concerned members will be allowed to visit the operational sites.

• Accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation and decommissioning?

√ Accessibility shall be provided to affected communities during construction phase.

Climate Change and Disaster Risk Questions The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks.

Yes No Remarks

• Is the Project area subject to hazards such as earthquakes, floods, landslides, tropical cyclone winds, storm surges, tsunami or volcanic eruptions and climate changes (see Appendix I)?

√ According to hazard zoning in the Vulnerability Atlas of India, the whole of Uttarakhand falls under “very high” to “high” Category earthquake zone. All newly developed facilities will require compliance with government rules for seismic design in hilly areas.

• Could changes in temperature, precipitation, or extreme events patterns over the Project lifespan affect technical or financial sustainability (e.g., changes in rainfall patterns disrupt reliability of water supply; sea level rise creates salinity intrusion into proposed water supply source)?

√ No such possibility

• Are there any demographic or socio-economic aspects of the Project area that are already vulnerable (e.g., high incidence of marginalized populations, rural- urban migrants, illegal settlements, ethnic minorities, women or children)?

√ Proposed project will not impact any marginalized population, rural-urban migrants, illegal settlement etc.

Page 154: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

146

Climate Change and Disaster Risk Questions The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks.

Yes No Remarks

• Could the Project potentially increase the climate or disaster vulnerability of the surrounding area (e.g., by using water from a vulnerable source that is relied upon by many user groups, or encouraging settlement in earthquake zones)?

√ No such possibility of vulnerability increase of the Surrounding area.

Page 155: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

147

Appendix 3 : Details of Public Consultation and Focussed Group Discussion

Name of the Sub-Project: Water Supply Distribution System, Dehradun

Number of Participants: 145

Name of the Village/ Ward: Gandhigram, Laxman Chowck, Kurubura, Nagar Nigam, Carzan Road, Sanjay Colony, Pared Ground.

Name of the Block: Dehradun Sadar

Name of the District: Dehradun

Distance from the District Head Quarter: 0 Km

Date: August 2010

Issues Participant’s Opinion, Comments and

Suggestions

General perception about the Investment

Program (UUSDIP). Awareness about the Investment Program especially the Water Supply Distribution System component. Support of the people for the Investment Program.

Government is trying to lay the foundation of sustainable urban development in Uttarakhand through UUSDIP. Yes, local people are aware of the water supply investment programme. There is immense support of local people for the Investment Program.

Support of local people for the proposed Water Supply Distribution System Component of the project.

All peoples gathered for consultations raised one voice for the establishment of clean and hygienic water supply system in Dehradun City.

Any critical issue or concern by the local people regarding this project?

The old water supply distribution line should be in place till the commissioning of new distribution line.

Any criteria you would like to see considered during project design, construction and operation stage?

During construction time the Executing Agency should conduct the work without affecting the common people. No suggestion for operation stage.

Number of Households in this area and Population of the village/ area

Around 5000 households live in this area. Approximately 30,000 populations live in this ward.

Any Ethnic minorities/ tribal population living in this area (Note the name of Tribe/ indigenous community, if any). Any Vulnerable groups are in the village/ Ward (women headed, BPL, ST, PH etc.).

No ethnic minorities/ tribal population living in these area Some BPL families are living in this ward.

Do the village/ ward people face any problems of water supply to their houses?

Water supply to this ward is so erratic that hardly people get clean water. Most of the time water is not coming to their houses due to less pressure.

If there is any problem related to these services, do you think that any up-gradation is necessary?

If water comes sometime with pressure, then also people find it with full iron content or bad smelling water.

Do you have any ideas on what is to be involved in the process of up-gradation?

No idea for the process of this up-gradation.

For this up-gradation, the road/ street/ path may be affected - What is your opinion on this? Is it acceptable?

Yes, it is acceptable to the local people but not for a prolonged period. The timing and period of work should be fixed and notified to the local people before the start of civil works.

Page 156: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

148

Issues Participant’s Opinion, Comments and

Suggestions

What extent this total Water Supply

Distribution System civil works will affect you?

This water supply distribution civil works will affect the normal business of shopkeepers and especially livelihood of vendors selling variety of items. Even some vendors raise the concern of getting two time meal for their families.

Who else is to be affected due to this up- gradation process?

Local residents will also be affected for commuting to their destinations.

How intense could be the effect? The effect could be much intense if the distribution line kept open for longer period after excavation work. The local residents will find it difficult to go office, schools, hospitals or any other destinations.

Do you think the effect will be of a permanent nature?

The effect may likely be of temporary in nature.

If it is not, how intense will be the temporary effect?

The intensity of effect may be temporary in nature and minimum to the local residents.

The work will be executed in this part of the road/footpath. You may require shifting to other side of the road. Please give your comments and suggestions.

Mostly ready to shift other side of the road by showing respect to Government work. If space and assistance provided for shifting to other side, APs have no problem.

During the time of execution of work will you shift to other side of road or any other place in the town?

Some people are positive to the idea of shifting to other side of the road and others are bit apprehensive of shifting and doing business. Because they afraid of customer loss.

If requested to shift, would you like to return here?

Depending on the situation of that time. Some says they may return back to their original place.

If you shift other side of the road/ place, is there any problem? Give your comments

Because they do not like to take risk against their daily normal business.

In what way Executive Agency of GOU can assist you so that your daily business is not affected? What extra support you want from the Executing Agency of GOU?

They have no direct comment on this issue. But said that Government should think about their genuine problem and whatever possible way GoU can help them, it is welcome.

What are your perceived benefits from the

Investment Program?

Only benefit may be un-interrupted purified water supply with good pressure. They may get good and

hygienic water to drink.

Do you think that local labour force would like to participate in construction work?

Obviously, local unemployed labour force would like to participate in the construction work.

Do you think that the local people would like to get regular information regarding this

Investment Program?

Yes, the local people would like to get regular information regarding this project and Investment

Program.

Number of Shops/ Commercial establishments in the village/ town/ area

Around 300 shops/ commercial area in this locality.

Numbers of Industrial Units in the village/ town and surrounding area

No industrial unit available in this and surrounding area.

Page 157: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

149

Issues Participant’s Opinion, Comments and

Suggestions

General socio-economic standing: What are the economic activities?

Land use, cropping pattern (Seasonal), types of crops, value of the crops,

Average land holding size etc.

General socio-economic standing is lower middle class or poor family background. Mainly selling vegetables, fruits, and variety of items for their livelihood and support to family.

Is the land Irrigated and what are the sources of Irrigation?

Not Applicable

Current rates for the agricultural land

(Government as well as market rates).

Not Applicable

Source of drinking water in this area. Dehradun Nagar Nigam water pipe line and hand pump is the source of drinking water in this area.

Loss of residential/ commercial structures, if any due to the project.

No loss to residential / commercial structures due to the project.

Loss of community life like any Market Places or community activities to be affected

No loss to community activities or market places.

Shortage of water for human consumption, irrigation, and other downstream uses? How extensive are they?

Shortage of drinking water takes place frequently due to leakage of pipe and non-availability of water pressure. Sometime the water smells bad and looks

Any conflicts on water use rights and its social impacts?

No conflict yet on water use rights.

Resettlement and Land acquisition (if foreseen due to setting up of Water Supply Distribution

System especially on private land). Has there been land acquisition before? If yes, what was the process of land acquisition and compensation package?

No Private land acquisition and resettlement impacts are seen for this Water Supply Distribution System sub-project. No land acquisition before.

Protected areas (national park, protected forest, religiously sensitive sites, historical or archaeological sites near the project area

around 3km), if any

No protected areas (national park, protected forest, religiously sensitive sites, historical or archaeological sites near to the sub-project area.

Health status, Availability of Hospitals, Is there any chronic disease prevalent in this area. Over all environmental condition of the area. Are you aware about HIV/AIDS and STD?

Health status is normal to this area. Hospital is available but no chronic disease prevalent in this area. Most of the people are aware of HIV/AIDS and STD.

Poverty Level: Is the village/ ward is poor or very poor or well off?

Poor

Education Status in this Village/ward: Literate, illiterate etc.

Mostly literate.

Employment Status: Percentage of employment/ unemployment/underemployment.

The status of Employment – 75%, Unemployment – 15% Underemployment – 10%.

Migration Pattern (If any), inward or outward Mostly inward migration takes place from this area.

Page 158: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

150

Issues Participant’s Opinion, Comments and

Suggestions

Type of compensation expected (Cash or Kind)

Cash compensation expected.

Perceived benefits from the project Regular water supply system will be established for better facilities to the urban population.

Perceived losses from the project Temporary loss of livelihood and support of family.

What other organizations of a social nature

(NGOs/CBOs/ Civil Society) active in this village/ward? Name of these organizations.

Local people do not know about these organisations.

Organization of the village/ ward and its structure. Do you have a village/ ward committee? What is the decision-making

system in your village/ward? Who are the decision makers on community related issues in your village/ward? Are they elected or selected? If elected: By consensus or By majority vote.

There is ward committee and the councillor is the head of the ward. Ward Committee decides issues of ward and finalise it with the presence of councillor. The committee and councillor are all elected members by majority vote.

Any Other Issues you may feel to share: (Demand of any support form Authority and whether they welcome the project, will there be cooperation from the local community during the implementation, security measures, etc).

All issue depends on GoU. If Government is sympathetic to the APs then, they are also ready to cooperate and welcome the project during the implementation and security measures.

Is this consultation useful? Comments Yes, it is useful

Will there be likely involvement of local people in the implementation of this Water Supply Distribution System Project?

It depends on the individual local APs to decide.

Source: Census Survey August 2010

Page 159: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

151

LIST OF PARTICIPANTS: ZONE NO. 24: GANDHIGRAM

Page 160: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

152

Page 161: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

153

Page 162: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

154

Page 163: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

155

List of Participants and Attendance Sheet of Public Consultation for Construction of Tube Wells

and Pedestrian Footpath in Dehradun on Dated 27.4.2016

Page 164: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

156

Page 165: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

157

Appendix 4 : Photographs of Public Consultations of August 2010

Page 166: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

158

Appendix 5 : Advertisement of Public Consultation

for construction of 5 tube wells and pedestrian footpath of 4.8 Kms on 27.04.2016 at Dehradun

Photographs of public consultation for construction of tube wells and pedestrian footpath in Dehradun

Page 167: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

159

Page 168: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

160

Appendix 6: Recommended Construction Contractors Contract Clauses

A. Sources of Materials

(i) Use quarry sites and sources permitted by government; (ii) Verify suitability of all material sources and obtain approval of State Investment

Program Management and Implementation Unit, and design and supervision consultant (DSC);

(iii) If additional quarries will be required after construction has started, obtain written approval from State Investment Program Management and Implementation Unit; and

(iv) Submit to DSC on a monthly basis documentation of sources of materials.

B. Air Quality

(i) Consult with DSC on the designated areas for stockpiling of clay, soils, gravel, and other construction materials;

(ii) Damp down exposed soil and any stockpiled on site by spraying with water when necessary during dry weather;

(iii) Use tarpaulins to cover sand and other loose material when transported by trucks;

(iv) Carry out air quality monitoring as per environmental management plan (EMP); and

(v) Fit all heavy equipment and machinery with air pollution control devices which are operating correctly.

C. Surface Water Quality

(i) Avoid stockpiling of earth fill especially during the monsoon season unless covered by tarpaulins or plastic sheets;

(ii) Prioritize re-use of excess spoils and materials in the construction works. If spoils will be disposed, consult with Investment Program Implementation Unit (IPIU)/DSC on designated disposal areas;

(iii) Install temporary silt traps or sedimentation basins along the drainage leading to the water bodies;

(iv) Place storage areas for fuels and lubricants away from any drainage leading to water bodies;

(v) Dispose any wastes generated by construction activities in designated sites; and (vi) Conduct surface quality inspection according to the EMP.

D Noise Levels

(i) Plan activities in consultation with IPIU/DSC so that activities with the greatest potential to generate noise are conducted during periods of the day before sunset, which will result in least disturbance;

(ii) Require horns not be used unless it is necessary to warn other road users or animals of the vehicle’s approach;

Page 169: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

161

(iii) Minimize noise from construction equipment by using vehicle silencers, fitting jackhammers with noise-reducing mufflers, and portable street barriers the sound impact to surrounding sensitive receptor;

(iv) Measurement of noise level at construction site as per EMP, and (v) Maintain maximum sound levels not exceeding 80 decibels when measured at a

distance of 10 meters or more from the vehicle/s.

E. Existing Infrastructure and Facilities

(i) Obtain from IPIU/DSC the list of affected utilities and operators; (ii) Prepare a contingency plan to include actions to be done in case of unintentional

interruption of services.

F. Accessibility

(i) Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites;

(ii) Schedule transport and hauling activities during non-peak hours; (iii) Locate entry and exit points in areas where there is low potential for traffic

congestion; (iv) Keep the site free from all unnecessary obstructions; (v) Drive vehicles in a considerate manner; (vi) Coordinate with traffic police/concerned department for temporary road

diversions and with for provision of traffic aids if transportation activities cannot be avoided during peak hours; and

(vii) Notify affected sensitive receptors by providing sign boards informing nature and duration of construction works and contact numbers for concerns and/or complaints.

G. Landscape and Aesthetics

(i) Prepare and implement Waste Management Plan; (ii) Recover used oil and lubricants and reuse or remove from the sites; (iii) Manage solid waste according to the following preference hierarchy: reuse,

recycling and disposal to designated areas; (iv) Remove all wreckage, rubbish, or temporary structures (such as buildings,

shelters, and latrines) which are no longer required; and (v) Request IPIU/DSC to report in writing that the necessary environmental

restoration work has been adequately performed before acceptance of work.

H. Socio-Economic – Income

(i) Leave spaces for access between mounds of soil; (ii) Provide walkways and metal sheets where required to maintain access for

people and vehicles; (iii) Increase workforce in front of critical areas such as institutions, place of worship,

business establishment, hospitals, and schools; (iv) Consult businesses and institutions regarding operating hours and factoring this

in work schedules; and (v) Provide sign boards for pedestrians to inform nature and duration of construction

works and contact numbers for concerns and/or complaints.

Page 170: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

162

Socio-Economic – Employment

(i) Employ at least 50% of the labor force, or to the maximum extent, local persons within the 2 kilometer immediate area if manpower is available; and

(ii) Secure construction materials from local market.

J. Occupational Health and Safety

(i) Develop and implement site-specific health and safety plan which will include measures such as: (a) excluding public from the site; (b) ensuring all workers are provided with and use Personal Protective Equipment; (c) health and safety training for all site personnel; (d) documented procedures to be followed for all site activities; and (e) documentation of work-related accidents;

(ii) Ensure that qualified first-aid can be provided at all times. Equipped first-aid stations shall be easily accessible throughout the site;

(iii) Provide medical insurance coverage for workers; (iv) Secure all installations from unauthorized intrusion and accident risks; (v) Provide supplies of potable drinking water; (vi) Provide clean eating areas where workers are not exposed to hazardous or

noxious substances; (vii) Provide health and safety orientation training to all new workers to ensure that

they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers;

(viii) Provide visitor orientation if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted;

(ix) Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas;

(x) Ensure moving equipment is outfitted with audible back-up alarms; (xi) Mark and provide sign boards for hazardous areas such as energized electrical

devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and

(xii) Disallow worker exposure to noise level greater than 85 decibels for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

Asbestos Cement Pipes Risk

(xiii) Training of all personnel (including manual labourers) to enable them to understand the dangers of asbestos cement pipes and to be able to recognize them in situ;

(xiv) Reporting procedures to inform management immediately if asbestos cement pipes are encountered;

(xv) Development and application of a detailed health and safety procedure to protect both workers and citizens. This should comply with national and international standards for dealing with asbestos, and should include: (a) Removal of all persons to a safe distance; (b) Usage of appropriate breathing apparatus and protective equipment by persons delegated to deal with the asbestos cement material; and (c) Procedures for the safe removal and long-term disposal of all asbestos-containing material encountered.

K. Community Health and Safety

(i) Plan routes to avoid times of peak-pedestrian activities. (ii) Liaise with IPIU/DSC in identifying high-risk areas on route cards/maps. (iii) Maintain regularly the vehicles and use of manufacturer-approved parts to

Page 171: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

163

minimize potentially serious accidents caused by equipment malfunction or premature failure.

(iv) Provide road signs and flag persons to warn of dangerous conditions.

L. Work Camps

(i) Consult with IPIU/DSC before locating project offices, sheds, and construction plants;

(ii) Minimize removal of vegetation and disallow cutting of trees; (iii) Provide water and sanitation facilities for employees; (iv) Prohibit employees from poaching wildlife and cutting of trees for firewood; (v) Train employees in the storage and handling of materials which can potentially

cause soil contamination; (vi) Recover used oil and lubricants and reuse or remove from the site; (vii) Manage solid waste according to the following preference hierarchy: reuse,

recycling and disposal to designated areas; (viii) Remove all wreckage, rubbish, or temporary structures (such as buildings,

shelters, and latrines) which are no longer required; and (ix) Request IPIU/DSC to report in writing that the camp has been vacated and

restored to pre-project conditions before acceptance of work.

M. Social and Cultural Resources

(i) Strictly follow the protocol for chance finds of any historical remnants in any excavation work;

(ii) Request IPIU/DSC or any authorized person with field training to observe excavation;

(iii) Stop work immediately to allow further investigation if any finds are suspected; and

(iv) Inform IPIU/DSC if a find is suspected, and take any action they require ensuring its removal or protection in site.

Page 172: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

164

Appendix 7: Photographs of Sub project Sites

Page 173: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

165

Appendix 8 : Proposed Construction Site of Tube wells

Location of MKP site and Kaulagarhi Road near FRI for construction of Tube well.

Location of GGIC proposed tube wells construction where overhead reservoir is available.

GGIC Rajpur Road and consultation with local Secretary of Resident Welfare Society for selection of Tube well construction

Page 174: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

166

Photographs of Pedestrian Footpath Proposed at Dilaram Bazar to Mussoorie Diversion Road

Page 175: IND: Uttarakhand Urban Sector Investment Program Dehradun ...SPM Suspended Particulate Matter SO2 sulphur dioxides ST Scheduled Tribes SC Scheduled Castes SOP Standard Operational

167

Appendix 9: Permission for Construction of Tube wells from Central Ground Water Board