Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
INDEXS.No
DESCRIPTION P.No. 1 INDEX MAP 2
2 EXECUTIVE SUMMARY 3-5
3 PROJECT BACKGROUND 6
4 CONTRACT DATA 7-8
5 SALIENT FEATURES OF THE PROJECT 9
6 SUBMISSION OF RELEVANT MANUAL & DOCUMENTS BY CONCESSIONAIRE
10
7 STATUS OF PERMITS 11
8 TECHNICAL MAN POWER- INDEPENDENT ENGINEER 12
9 TECHNICAL MAN POWER- CONCESSIONAIRE 13
10 TECHNICAL MAN POWER- SUB CONTRACTOR 14-16
11 PRE CONSTRUCTION ACTIVITIES17-18
12 DETAILS OF CORRESPONDENCE FROM IE 19-20
13 STATUS OF PLANT & MACHINERY 21
14 STATUS OF DRAWING (Structures/Highways) 22
15 CONSTRUCTION PROGRAMME BY THE CONCESSIONAIRE, S-CURVE
23
16 PROJECT WORK PROGRESS 24-25
17 DETAILS STATUS OF STRUCTURE 26-35
18 E
EMERGENCY SERVICE 3619 QUALITY ASSURANCE & QUALITY CONTROL 37-3820 SAFETY AND TRAFFIC MANEGEMENT 3921 WEATHER REPORT 40
22 PHOTOGRAPHS 41
Page | 1
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
Page | 2
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
EXECUTIVE SUMMARY BACKGROUND:
Ministry of Road Transport and Highways (MORT&H) has embarked on a staged up gradation programme of various National Highway. The widening is necessary to develop National Highway corridors where traffic intensity has increased significantly and there is requirement of augmentation of capacity for safe and efficient movement of traffic. MORT&H has authorized National Highway Authority of India (NHAI) to implement the development projects for six laning of Barwa Adda to Panagarh section of National Highway No.2 in the state Jharkhand and West Bengal by way of Public-Private Partnership (PPP) mode.
The project corridor on NH-2, a part of Golden Quadrilateral is passing through plains of Gangetic region of landlocked states of Bihar & Jharkhand and connects the National Capital with Kolkata traversing almost 1465 km, passing through the states of west Bengal, Bihar, Jharkhand, Uttar Pradesh, Haryana & Delhi. Apart from cutting across several other NFs it traverses through major towns of Durgapur-Asansol, Dhanbad, Aurangabad, Varanasi, Allahabad, Kanpur, Agra, Faridabad, thereby catering to traffic with East West spectrum within the country.
The project road of NH-2 starts from Barwa-Adda in Dhanbad district in the State of Jharkhand Km 398.240 and ends at Panagarh in Bardhaman district of West Bengal km 521.120. Total length of stretch is 122.88 km passes through Barwaadda, Ponrki, Bhitiya, Kaladih, Amarpur, Govindpur Bajar,Fakirdih,Phufwadih, Gopalganj, Nirsa, Belchahri in the district of Dhanbad in Jharkhand State and Salanpur, Niyamatpur, Asansol, Bogra Chatti, Palas danga, Raniganj More, Mangalpur, Andal More, Kada Road, Durgapur, Muchipara, Rajbandh Chati, Panagarh in the district of Bardhman in West Bengal.
NHAI have awarded the task of Feasibility and Detailed engineering for improvement of this section of NH-2 to M/s ICT, India.
NHAI has awarded the work of “Design, Build, Finance, Operate and Transfer of Km. 398.240 to Km.521.120 including a bypass of length 8.120 Km. and service road of length 149.310 at selected locations to M/s Barwa Adda Expressway Ltd. ( Mumbai).
NHAI has awarded the Independent Consultancy for the project to M/s SA Infrastructure Consultants Pvt. Ltd. in association with Sugam Technocarts Pvt.Ltd.
Page | 3
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
Project Milestones
Page | 4
Mile
stone
DescriptionScheduled
Time PeriodCurrent Status
1
Construction of Project Highway shall have commenced.
(Expended not less than 10% of the total capital cost set forth in Financial Package)
27th September 2014 ( 180th day from Appointed
Date)
One month completed
2
Construction of all bridges shall have commenced.
(Expended not less than 25% of the total capital cost set forth in Financial Package)
31st March 2015 (365th day from Appointed Date)
-
3
Construction of all Project Facilities shall have commenced.
(Expended not less than 75% of the total capital cost set forth in Financial Package)
30th March 2016 (730th day from Appointed Date)
-
4 The scheduled six Laning Date
26th September 2016 (910th day from Appointed
Date)
-
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014CONDITION PRECEDENT
S. N.
Compliance Responsible
Authority
Execution date
Current Status
1
ROW Handing Over NHAI 28.03.2014 NHAI has handed over EROW of 535.74 Hac.
72.24 %
2Permission of Environment
Protection & Conservation of Site
NHAIReceived.
3 Escrow Agreement BDU Nov 01, 2013
Executed
4 Substitution Agreement BDU Nov 01, 2013
Executed
5Performance Security to
Client BDUOct 24, 2013
Submitted
6 Delivery of Financial Model to Client BDU Nov 01,
2013Executed
7Delivery of Warranties from All Consortium Member to
clientBDU
Apr 23, 2013
Executed
8Delivery to the client a legal
opinion from the legal counsel of the Concessionaire
BDUApr 30, 2013
Executed
9
Appointment of Independent Engineer
NHAI
20.02.2014 M/s S.A. Infrastructure
Consultants Pvt Ltd in association
with Sugam Technocrats Pvt.
Ltd.
10 State Support Agreement NHAI Available for both the States.
11Approval from Railway
Authorities in form of GAD for construction of ROB
NHAIGADs for both the ROB’s have been
approved.
Page | 5
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
PROJECT DETAILS:
The Project Road is 122.88 KM Long consisting of 1-Bypass of Length 8.120 Km for Congested Area at Panagarh including structures as under:-
A. HIGHWAYS:-(a) Total Length of Existing Carriage Way = 121.990 Km.(b) Total No. of lane = 2*3 lane(c) Total length of Service Road =149.310km(d) Width of Service Road =7m
(c) Bypass Details:- . Panagarh Bypass = 8.120km
B. STRUCTURES:-
(a) Major Bridges = 3Nos.
(b) Minor Bridges = 21Nos. (11 New & 10 Widening)
(c) Grade Separator = 12Nos.
(d) ROBs = 2 Nos.
(e) VUPs and PUPs = 20/11 Nos.
(f) Box Culverts /Hume Pipe/Slab Culverts = 203 Nos.
(g) Over Pass/ Under Pass = 2/2 Nos.
Page | 6
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
CONTRACT DATA
CONCESSIONAIRE:
Name of Project : Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Employer : National Highways Authority of India
Concessionaire : Barwa Adda Expressway Limited,Plot No. C-22, G Block, Bandra
KurlaComplex, Mumbai-400051
Project Developer : IL&FS Transportation Networks Limited
Construction Contractor : M/s Apco Infratech Pvt. Ltd. & M/s Oriental Structural Engineers
Pvt.Ltd.
Date of Agreement : May 08, 2013
Development Period : From 8/05/2013 to 31/03/2014
Appointed Date : 01/04/2014
Project Cost/ Premium : Rs. 1665 Crore Premium of Rs. 42 Crore
on appointed date and shall be increased by 5 % as compared to the immediately preceding year.
Construction Period : 910 days.
Scheduled Date of Project Completion : 26/09/2016
Concession Period : 20 Years Including 30 months of Construction Period.
Performance Security : Rs. 107.19 Crore Page | 7
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
INDEPENDENT CONSULTANT/ENGINEER:
Engineer (Consultants) : M/s SA Infrastructure Consultants Pvt. Ltd in Association with Sugam Technocrats Pvt.Ltd.
Head Office Address : C/o S.A. Infra Structure Consultants Pvt. Ltd.101-102, CS-1 Gyandkhand-II, Indrapuram, Ghaziadad – (UP) 201014. Ph.No.: 0120-2607756, [email protected]
Office Address : Plot No.16/14, Bengal Ambuja, City Center, Durgapur, Dist:- Burdwan (W B), Pin-713216 [email protected]
Date of Agreement : 20.01.2014
Commencement date : 20.02.2014
Contract Period : 36 months
Scope of Consultancy : Independent Engineer
Page | 8
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
SALIENT FEATURES OF THE PROJECT :-THE PROJECT ROADThe Project road comprises off from 398.240 to Km.521.120 Km of existing road of NH-2. The Salient Features of the project are as under:-
S.No. Description Quantity
1 Length of Project 122.88 KM
2 (a) By Pass – Total Length – 8.120 Km (b) Existing
Carriageway Length – 121.990 Km.
3 Width of carriageway 2*12.25=24.50M
4 Service Road 149.310 Km.
5 Width of service road 7 M6 ROB’s 2 Nos at Km 443+710 & Km 520+373
7 Grade Separator12 Nos. at km.398+811,407+538,408+326,456+312,464+185,475+670,476+050,496+609,501+996,504+287,506+200,515+983
8 Major Bridges - (3 No’s) MJB 3 Nos. at Km.464+674,517+095,518+829
9 Minor Bridges – (20 No’s)
MNB 11 Nos. at Km. 405+330,409+876,415+120,429+973,437+047,450+140,461+652,464+903,468+620,497+840,509+953, Widening 9 Nos. at Km. 445+596,462+895,463+091,463+710,471+006,485+002,492+871,495+735,507+503
10 Vehicular Under Passes
VUP 20 Nos. at Km. 403+440,411+374,413+886,421+400,428+208,433+563,447+771,451+153,460+036,467+115,469,750,473+340,479+109,486+427,489+702,491+451,494+430,509+559,518+221,519+349
11 Pedestrian UnderpassesPUP 11 Nos. at Km. 398+495,399+230,407+400,409+088,417+953,424+400,476+430,504+555,510+700,512+920,514+900
12 Box /HP/Slab Culverts 203 Nos.
13 BUS Lay Byes LHS 20 Nos.RHS 20 Nos.
14 Truck Lay Byes LHS 10 Nos.RHS 04 Nos.
Page | 9
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
15 Toll Plaza 2 Nos. at Km. 438+500,507+000.
16 Truck Parking Places 2 Nos. at Km. 398+250 to Km 398+750 & Km 441+800 to Km 442+300.
Submission of Relevant Manual & Documents by Concessionaire:-
SI. No
Description Remarks
1 QAP Received
2 Work Methodology Received
3 Work Schedule Received
4 EMP Not received
5 R & R Plan Not received
6 Material Report of Borrow areas Not received
7 Quarry location Not received
8 Safety Manual Not received
Page | 10
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
Status of Permits:-
Page | 11
SI . No Descriptions Applied Date
1 Permits for extraction of boulder from quarry from Additional District Magistrate (ADM) Mines
15.06.2012
2 Permit for installation of crusher from village Panchayat and State/Central Pollution Control Board
25.11.2013
3 License for explosives from the office of Explosive controller
09.02.2013
4 NOC consent/Clearance required from village panchayat & State/Central Pollution Control Board/Dept.
Vill Panchayat - 25.11.13West Bengal Pollution Control Board - 20.12.13
5 Clearance required from village panchayat & State/Central Pollution Control Board
Vill Panchayat - 25.11.13West Bengal Pollution Control Board - 20.12.13
6 Permission required from village panchayat and ADM mines for Government & private land Vill Panchayat - 25.11.13
7Permission from Forest Department and other applicable agencies
Dhanbad (Jh) - 08.11.11Burdwan (WB) - 23.09.13, 25.09.13, 30.09.13,30.09.13, 03.10.13
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
List of Technical Man Power of I.E.:-
Technical Manpower- Independent EngineerSl. No.
Name Designation Date of Joining
1. Manoj Kumar Jaiswal (Dhanbad)
Resident Engineer 19.02.2014
2. Saroj Kumar Singh (Durgapur)
Resident Engineer 20.03.2014
3. Vijay Kumar Singh S.Q.M.E. 19.02.2014
4. Raj Kishore Rai Bridge Engineer 19.02.2014
5. Nityanand Kumar (Durgapur)
Highway Design Engineer
19.02.2014
6. A N Dhodapaka (HQ) Sr. Bridge Engineer 06.03.2014
Page | 12
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
List of Tech. Man Power of Concessionaire:-Sl. No.
Name Designation Remarks
Concessionaire – Durgapur (Km. 398.240 to Km. 521.120)
1. Mr. V.P.KATTI PROJECT DIRECTOR2. Mr. Anil Kumar Mishra Sr. Planning Engineer3. Mr. Vimlesh Kumar Sr. Quantity Surveyor4. Mr. Piyush Jain Assistant Planning5. Mr. Kaushal Mehta Finance and Accounts6. Mr. Abdesh Jha Administration7. Mr. I. Nagaraju Q.A./Q.C. Head8. Mr. Bipad Bhaanjan Ghosh Sr. Surveyor/CAD9. Mr. Vikram Dutta L.A. Officer10. Mr. S.P.Singh Utility Shifting (Electrical) 11. Mr. U C Srivastav Sr. Manager – O & M
Tolling12. Mr. Praveen Jindal Manager - Tolling
Concessionaire – I Dhanbad (Km. 398.240 to Km. 441.565)
13. Mr. Sanjiban Dutta Section In-Charge14. Mr. Naresh Chandra Sao Assistant Bridge Engineer15. Mr. Umesh Sharma Assistant Material
Engineer16. Mr. Rajkumar Ghosh Lab Technician
Concessionaire – II Asansol (Km. 398.465 to Km. 471.150)
17. Mr. Malay Dutta Section In-Charge18. Mr. Pramod Kumar Pandey Assistant Highway
Engineer19. Mr. Himanshu Bushan
PandaBridge Engineer
20. Mr. Suresh R Assistant Bridge Engineer21. Mr. Pravin Kumar Sharma Assistant Material
Engineer22. Mr. Somnath Chatterjee Lab Technician
Concessionaire – III Durgapur (Km. 471.150 to Km. 521.120)
23. Mr. Zulfequar Ahmed Bridge EngineerPage | 13
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 201424. Mr. Rajesh Kumar Assistant Highway
Engineer25. Mr. Aman Sachdeva Assistant Bridge Engineer26. Mr. Jyoti Prakash Lab Technician
List of Tech. Man Power of the Sub-Contractor :- (APCO Infratech Limited) – Section ISl. No. Name Designation RemarksSr. Project Manager
1. Mr. Satpal Singh Sr. General ManagerHighway
2. Mr. Umesh Chand Singh AGM3. Mr. Sanjiv Kumar Sr. Material4. Mr. Kapil Kumar Jr. Engineer5. Mr. Bhanu Prakash Gupta GET
Structure
6. Mr. B. Ramaseshaiah Dy. Project Manager7. Mr. Jai Prakesh Tiwari Sr. Project Engineer8. Mr. Abhishek Pratap Singh DET
Planning & Billing
9. Mr. Krishan Chand Document ControllerQuality Control Engineers
10. Mr. Natabar Patra Jr. Engineer11. Mr. Praveen Kumar Singh GET
Surveyor
12. Mr. Praveen K Srivastav Sr. Supervisor13. Mr. Sarya Pratap Kunwar Sr. Supervisor14. Mr. Uttam Kumar Verma Sr. Supervisor15. Mr. Ashish Kumar Mishra Asst. Supervisor
Mechanical Engineer
16. Mr. Mohd. Rashid Sr. Engineer Plant17. Mt. Umesh Biht Mechanical Engineer18. Mr. Rajat Singh GET
Civil Supervisor
19. Mr. Bineshwar Singh Supervisor20. Mr.Amit Mani Tripathi Site Supervisor21. Mr. Dharmendra Singh Civil Supervisor
Page | 14
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 201422. Mr. Ranjeet Singh Highway Supervisor23. Mr. Shahrukh Khan Supervisor24. Mr. Arun Kumar Upadhyay Civil Supervisor25. Mr. Digvijay Singh Civil Supervisor
(APCO Infratech Limited) – Section IISl. No. Name Designation RemarksSr. Project Manager
1. Mr. Sanjay Kumar Singh Sr. Project ManagerHighway
2. Mr. R.P.Chowdhury Manager3. Mr. Sharad Kumar Mishra Dy. Manager4. Mr. Mukesh Kumar Singh Engineer
Structure5. Mr. Jagadish Srivastava Manager6. Mr. Arun Kumr Asst. Engineer7. Mr. Yogesh Chandra Jr. Engineer8. Mr. Rajendra Kumar Asst. Engineer
Planning & Billing9. Mr. Prasenjit Chakrabortty Engineer
Quality Control Engineers10. Mr. Suman Sanyal Manager11. Mr. Chandan Singh Jr. Engineer12. Mr. Md. Shakil Sr. Lab Technician13. Mr. Raj Kamal Tiwari Lab Technician
Surveyor14. Mr. Ashutosh Kumar Sing Sr. Surveyor15. Mr. Santosh Kumar Tripathi Sr. Surveyor16. Mr. Atul Kumar Asst. Survyor17. Mr. Sandip Mishra Asst. Surveyor
Mechanical & Mining Engineer18. Mr. Gautam Kumar Paul Asst. Manager19. Mr. P Bhaskar Reddy Engineer20. Mr. Sayed Patauddin Sr. Engineer21. Mr. Sk. Anisur Rehman Asst. Engineer22. Mr. Sashi Kumar Gupta Data Entry Operator23. Mr. Atul Singh Supervisor24. Mr. Jitendra Kumar Manager- Mining
(Oriental Structural Engineers Pvt. Ltd.) – Section IIISl. No. Name Designation RemarksChief Project Manager
1. Mr. V. K. Chauhan Chief Project ManagerHighway
2. Mr. N. K. Singh Sr. Project Manager3. Mr. Arjit Mittal Sr. Manager4. Mr. S. S Negi Dy. Manager5. Mr. Chandra Mani Kishore Dy. Engineer6. Mr. Avimanyu Pal Dy. Manager7. Mr. Suresh Kushwah Asst. Manager8. Mr. U. K. Jha Jr. Officer9. Mr. K. K. Jha Sr. Supervisor10. Mr. Manoj Kumar Supervisor11. Mr. Vinod Kumar Sharma Supervisor
Page | 15
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 201412. Mr. Sanjay Kumar Bhrti Sr. Supervisor13. Mr. Jitendra Kumar Yadav Supervisor14. Mr. Shivajo Suryanvanshi Sr. Supervisor
Structure15. Mr. Rajeev Naryal Sr. Project Manager16. Mr. Ramavatar Sharma Dy. Project Manager17. Mr. Ashok Kumar Singh Dy. Project Manager18. Mr. Chandan Rikhi Engineer19. Mr. Pawan Kumar Engineer20. Mr. Rajeev Kumar Foreman21. Mr. Ugrasen Singh Asst. Manager22. Mr. Durga Prasad Gautam Officer23. Mr. Amit Kumar Singh Asst. Officer24. Mr. Ramjee Singh Sr. Supervisor
Planning & Billing25. Mr. Sumanta Chakraborty Jt. GM26. Mr. Faishal Rizwan Siddqui Sr. CAD Engineer27. Mr. Brijesh Kumar Mishra Officer
Quality Control Engineers28. Mr. Mukesh Kumar Singh Asst. Engineer29. Mr. Ravish Kumar GET30. Mr. Abhisit Singh Bhaduriya GET31. Mr. Sunil Kumar Jha Lab Technician31. Mr. Jay Prakash Lab Technician33. Mr.Rajendra Prasad Singh Lab Assistant
Surveyor34. Mr. Janmejay Rai Engineer35. Mr. Vijay Kumar Sr. Surveyor36. Mr. Santosh Kumar Pradhan Surveyor37. Mr. Hardev Singh Surveyor38. Mr. Ravindra Tiwari Surveyor39. Mr. Bishwanath Mondal Surveyor40. Mr. Ashok Kumar Singh Asst. Surveyor41. Mr. Nandu Kumar Survey Helper42. Mr. Kishore Kumar Survey Helper
Mechanical & Mining Engineer43. Mr. B.B. Singh Project Manager (P&M)44. Mr. J. S. Virdhi Project Manager (Crusher)
Page | 16
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
PRE CONSTRUCTION ACTIVITIES:-
SUB HEAD
STATUS OF LAND ACQUISITIONS:-
Description Jharkhand
West Bengal Total Remarks
Length 43.320km 79.560km 122.880 km
Total land required
266.920 Ha
473.360 Ha 740.280 Ha
Handed over 201.200 Ha
333.550 Ha 534.750 Ha
To be handed over
65.72 Ha 139.81 Ha 205.530 Ha
STATUS OF UTILITIES SHIFTING:-
S. N. Activity Unit Total
Attended till this month
BalanceRemarks
1 Tree Cutting Nos. 26018 2944 23074 88.7% balance
2 Electric Poles Nos 7194 nil 7194
3 Electric Towers Nos 12 nil 12
Page | 17
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
4 Water Pipe lines RM 82379 nil 82379
5Gas Pipe Lines (GEECL)
RM52100 nil 52100
6Petroleum Pipe line
RM837 nil 837
STATUS OF ENCUMBRANCES:-
SI. N. Descriptions
Side
Units(affect
ed length
)
Total
Attended till this
month
Balance Remarks
1. Pucca Buildings
LHS
RHS
M
M
971
944
Nil
Nil
971
944
2. Semi pucca Buildings
LHS
RHS
M
M
991
1033
Nil
Nil
991
1033
3. Kachha Buildings
LHS
RHS
M
M
409
381
Nil
Nil
409
381
4. Religious Structures
LHS
RHS
M
M
41
43
Nil
Nil
41
43
Page | 18
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
DETAILS OF CORRESPONDENCE FROM IE’s OFFICE-DURGAPUR
(APRIL , 2014)Correspondence with PD, NHAI PIU-Durgapur:
Sl. No. Ref.No. Date Subject
1. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/3708 03.04.2014 Submission of CV's of AHE 2 & AME 2
2. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/45 10.04.2014 Submission of Insurance paper
3. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/46 11.04.2014 Parliamentary election 2014 enforcement
of model code of conduct
4. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/47 12.04.2014 Submission of rent agreement and vehicle
agreement
5. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/69 25.04.2014 Election utility shifting estimates of
DPSC/India power limited
6. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/71 25.04.2014 Submission of weekly traffic census
(05.04.2014-11.04.2014)
7. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/72 25.04.2014 Submission of weekly traffic census
(12.04.2014-20.04.2014)
8. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/74 25.04.2014 Joining report
9. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/77 25.04.2014 Zebra Crossing / Stop line marking in
different places in Durgapur on NH-2.
10. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/78 25.04.2014
Installation / Maintenance of Traffic Signals at 4 location on NH-2 under
Durgapur Sub-Division
11. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/79 26.04.2014 Request to personally intervene to find
out a probable solution reg.
Page | 19
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
12. SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/3759 25.04.2014 Submission of CV of Sub professional staff
- Mr. Tanu Behera.
Correspondence with Concessionaire:
Sl. No.
Ref.No. Date Subject
1.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/33
04.04.2014 Use of bottom ash and pond ash for NH work
2.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/39
10.04.2014
Prevention of unauthorized median cut in NHAI
3.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/40
10.04.2014 Realignment from 508.350 to 510.350
4.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/41
10.04.2014
Allotment of residential accommodation for SAICPL
5.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/42
10.04.2014
Repair of NH-2 from Air force station cut out to Paragarh ROB
6.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/43
10.04.2014
Source approval for processment of NP4 RCC Hume pipe
7.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/44
10.04.2014
Utility shifting of 1 mm dia water pipe line of Jharkhand DW&SD
8.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/48
12.04.2014
Road maintenance, safety and traffic regulation
9.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/49
12.04.2014
Source approval for processment of NP4 RCC Hume pipe
10.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/50
12.04.2014 Source approval for steel reinforcement
11.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/51
14.04.2014
Repair and maintenance of entrusted highway
12.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/52
14.04.2014
Vehicle tracking system (GPS) to track ambulance, patrol vehicle and crane
13SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/53
14.04.2014 Source approval for cement
14.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/54
15.04.2004 Independent laboratory testing approval
15. SAICPL-Sugam/Barwa- 15.04.201 Maintenance of traffic signals at Subhas chak Page | 20
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014Adda-Panagarh/IE/NH-2/2014/55 4 at Govindpur (408.000)
16.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/56
16.04.2014
Permission for 11 KV underground double circuit electrical line to proposed
17.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/59
16.04.2014
Repair of NH-2 from Air force station cut out to Paragarh ROB
18.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/65
19.04.2014 Repair of roads
19.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/67
21.04.2014 Road maintenance
20.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/70
25.04.2014
Ensuring repair of NH handed over to the concessionaire
21.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/73
25.04.2014 Site inspection on 29.04.2014
22.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/80
26.04.2041 Review of QAP
23.SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/81
26.04.2014 Review of drawing and design
STATUS OF PLANTS AND MACHINERY:-The details of major plants and equipment deployed are mentioned
below;
A. PLANTS
SI.No.
Description of Items Unit Total
Remarks
1. Crusher Plant Nos. 1 Installation in progress
2. WMM Plant Nos. 2 Installation in progress
3. Batching plant Nos 3 1. mobilization in progress2. installation in progress.3. ready for calibration
4. Hot mix Plant Nos. 2 1. mobilization in progress.2. installation in progress
B.MACHINERY
Page | 21
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 20141. Dozer Nos 22. Excavator(1-1.2 cu.m bucket) Nos 53. Motar Grader (135-195HP) Nos 44. Vibr. Soil Compactor(8-10 t) Nos 45. Tendam Roller Nos 26. PTR No 17. Front Wheel Loader (3.0 cu.m) Nos 28. Tipper (10T/25T) Nos 109. Water tanker (10kl) No 1
10. JCB loader Nos 211. Hydra Crane (14 MT) Nos 312. Broomer No 113. Diesel Tanker No 114. DG (25-750KVA) Nos 5
C. SURVEY EQUIPMENTS1. Total station Nos 5
2. Auto level Nos 4
STATUS OF DESIGN AND DRAWING-HIGHWAY :-
Km 398+240 to 521+120
Sl. No. Description & Design Scope
BAEL Letter No. for Submission Review by IE
1 Plan & Profile Drawings, TCS
BAEL/PRJ/TEC/IEO/0002 dt. 22/02/14
SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/81 dt.26.04.2014
2 Structures and CD works
BAEL/PRJ/TEC/IEO/0003 dt. 22/02/14
SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/81 dt.26.04.2014
3 Pavement Design BAEL/PRJ/TEC/IEO/0012 dt. 04/03/14
SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/81 dt.26.04.2014
4 Design & Drawings of ROB at Km 520+385
BAEL/PRJ/TEC/IEO/0011 dt. 04/03/14
SAICPL-Sugam/Barwa-Adda-Panagarh/IE/NH-2/2014/81
Page | 22
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014dt.26.04.2014
5
GAD for retained with widening of Box culvert
Design of Box culvert
Reinforcement details of cast in situ Box culvert
GAD & Reinforcement detail of box culvert
Analysis and design of box culvert
BAEL/PRJ/TEC/IEO/0014 dt. 12/03/14
BAEL/PRJ/TEC/IEO/0046-47 dt. 15/04/14
BAEL/PRJ/TEC/IEO/0053 dt. 22/04/14
BAEL/PRJ/TEC/IEO/0059 dt. 26/04/14
BAEL/PRJ/TEC/IEO/0060-61 dt. 26/04/14
Under review
Under review
Under review
Under review
Under review
6GAD,Analysis and design of Minor Bridge
BAEL/PRJ/TEC/IEO/0004to8&15-17,19 dt. 25 &28/02/14,12-13/3/14
Under review
7GAD Drawings for double cell pipe culvert
BAEL/PRJ/TEC/IEO/0032 dt. 29/03/14
Under review
8 GAD Drawings for Grade separator
BAEL/PRJ/TEC/IEO/0045 dt. 15/04/14
Under review
9 Reinforcement Details for VUP
BAEL/PRJ/TEC/IEO/0060 dt. 26/4/2014
Under review
Concessionaire work progress:- S-Curve
Page | 23
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
PROJECT WORK PROGRESS:-
Road Works Progress:-
Linear Progress (Road Works)Main Carriageway
Activity Description
Unit Total Length/Qt
y
Completed % progress
Main Carriageway Six laneC & G Km.
Ha122.88306.53
1.774.47
1.44%1.46%
Embankment Km.cum
122.881897473
-
Page | 24
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014Sub-Grade Km.
cum122.88
1544213-
GSB/ CT sub baseGSBCT sub-base
Km.Cumcum
122.88881086291830
-
WMM /CT Base WMMCT Base
Km.Cumcum
122.88192599120889
-
AG Layer Km.cum
42.93187020
-
DBM Km.cum
122.88250351
-
BC Km.cum
122.88152516
-
Service RoadActivity
DescriptionUnit Total
Length/Qty
Completed % progress
C & G Km.Ha
149.310141.97
1.181.18
0.79%0.83%
Embankment Km.cum
149.310655085
-
Sub-Grade Km.cum
149.310644416
-
CT Sub base Km.cum
149.310290445
-
CT Base Km.cum
149.31073124
-
AG Layer Km.cum
149.310103876
-
BC Km.cum
149.31040192
-
Structure Work Progress:-
Type of structures
Total Completed In progress Not yet started
ROB 2 1 1
Major bridge 3 3Page | 25
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
Minor bridge 20 20
Grade Separator 12 12
Over pass 2 2
Under pass 2 2
Vehicular underpass
20 20
Pedestrian Underpass
11 11
Box culverts 47 47
Slab culverts 67 67
Pipe culverts 88 1 87
Total 274 O 2 272
DETAIL STATUS OF STRUCTURE :-Sl No.
Chainage No. as per Drawin
g
Name of Structure Status Remarks
1 464+674
MAJOR BRIDGE
NYS.
2 517+095 NYS.
3 518+829 NYS.
4 398+811
Grade Separato
r
NYS.
5 407+538 NYS.
6 408+326 NYS.
7 456+312 NYS.
8 464+185 NYS.
Page | 26
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
9 475+670 NYS.
10 476+050 NYS.
11 496+609 NYS.
12 501+996 NYS.
13 504+287 NYS.
14 506+200 NYS.
15 515+983 NYS.
16 405+330
MINOR BRIDGE (NEW)
NYS. New 3 Lane Bridge on LHS
17 409+876 NYS. New 3 Lane Bridge on LHS
18 415+120 NYS. New 3 Lane Bridge on LHS
19 429+973 NYS. New 3 Lane Bridge on LHS
20 437+047 NYS. New 3 Lane Bridge on LHS
21 450+140 NYS. New 3 Lane Bridge on LHS
22 461+652 NYS. New 3 Lane Bridge on LHS
23 464+903 NYS. New 3 Lane Bridge on RHS
24 468+620 NYS. New 3 Lane Bridge on LHS
25 497+840 NYS. New 3 Lane Bridge on LHS
26 509+953 NYS. New 3 Lane Bridge on LHS & Existing LHS Replaced by New 2 Lane Bridge
27 445+596
MINOR BRIDGE
(WIDENING)
NYS. Widening on both Side
28 462+895 NYS. Widening on both Side
29 463+091 NYS. Widening on both Side
30 463+710 NYS. Widening on both Side
31 471+006 NYS. Widening on both Side
32 485+002 NYS. Widening on both Side
33 492+871 NYS. Widening on both Side
34 495+735 NYS. Widening on both Side
35 507+503 NYS. Widening on both Side
36 520+373 ROB Work in progress (Test
pile). GADs for both the ROBs have been approved37 443+710 NYS.
Page | 27
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
38 403+440
VEHICULAR UNDERPAS
S
NYS.
39 411+374 NYS.
40 413+886 NYS.
41 421+400 NYS.
42 428+208 NYS.
43 433+563 NYS.
44 447+771 NYS.
45 451+153 NYS.
46 460+036 NYS.
47 467+115 NYS.
48 469+750 NYS. Drawing not Submitted
49 473+340 NYS.
50 479+109 NYS.
51 486+427 NYS.
52 489+702 NYS.
53 491+451 NYS.
54 494+430 NYS.
55 509+559 NYS.
56 518+221 NYS.
57 519+349 NYS.
58 398+495
PEDESTRIAN
UNDERPASS
NYS.
59 399+230 NYS.
60 407+400 NYS.
61 409+088 NYS.
62 417+953 NYS.
63 424+400 NYS.
64 476+430 NYS.
65 504+555 NYS.
66 510+700 NYS.
Page | 28
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
67 512+920 NYS.
68 514+900 NYS.
69 398+519
BOX CULVERT
NYS. Reconstruction
70 398+782 NYS. Reconstruction
71 403+335 NYS. Reconstruction
72 407+212 NYS. Reconstruction
73 407+422 NYS. Reconstruction
74 407+657 NYS. Left side widening & Right side Reconstruction
75 408+867 NYS. Reconstruction
76 409+060 NYS. Reconstruction
77 409+366 NYS. Reconstruction
78 411+332 NYS. Reconstruction
79 411+391 NYS. Reconstruction
80 413+926 NYS. Retained with widening but change to Reconstruction
81 415+216 NYS. Existing Retained (RHS) New slab (LHS)
82 417+933 NYS. Reconstruction
83 421+327 NYS. Reconstruction
84 421+497 NYS. Reconstruction
85 424+467 NYS. Reconstruction
86 427+882 NYS. Reconstruction
87 428+025 NYS. Reconstruction
88 443+615 NYS. Reconstruction
89 443+931 NYS. Reconstruction
90 444+047 NYS. Reconstruction
91 448+029 NYS. Retained with widening but change to Reconstruction
92 450+883 NYS. Reconstruction
93 451+334 NYS. Reconstruction
94 456+131 NYS. Retained with widening but change to Reconstruction
95 456+175 NYS. Retained with widening but change to Reconstruction
Page | 29
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
96 456+355 NYS. Retained with widening but change to Reconstruction
97 461+940 NYS. Retained with widening but change to Reconstruction
98 467+300 NYS. Reconstruction
99 470+025 NYS. Reconstruction
100 475+615 NYS. Reconstruction
101 486+816 NYS. Reconstruction
102 489+549 NYS. Reconstruction
103 489+860 NYS. Reconstruction
104 494+593 NYS. Reconstruction
105 496+719 NYS. Reconstruction
106 496+749 NYS. Reconstruction
107 502+182 NYS. Reconstruction
108 502+372 NYS. Reconstruction
109 502+538 NYS. Reconstruction
110 505+934 NYS. Left side widening & Right side
Reconstruction111 506+169 NYS. Left side widening & Right side
Reconstruction112 509+255 NYS. Reconstruction
113 512+635 NYS. Reconstruction
114 512+997 NYS. Reconstruction
115 515+180 NYS. New
116 516+290 NYS. New
117 518+180 NYS. New
118 519+690 NYS. New
119 399+140
PIPE CULVERT
NYS. Retained with widening
120 400+070 NYS. Retained with widening
121 400+450 NYS. Retained with widening
122 401+625 NYS. Retained with widening
123 404+115 NYS. Retained with widening
124 405+204 NYS. Retained with widening
Page | 30
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014125 405+777 NYS. Retained with widening
126 408+207 NYS. Retained with widening
127 409+125 NYS. Retained with widening
128 409+707 NYS. Existing Retained (RHS) New Pipe
(LHS)129 410+140 NYS. Retained with widening
130 410+760 NYS. Retained with widening
131 414+040 NYS. Retained with widening
132 414+240 NYS. Retained with widening
133 414+750 NYS. Retained with widening
134 418+107 NYS. Retained with widening
135 418+748 NYS. Retained with widening
136 420+178 NYS. Retained with widening
137 425+330 NYS. Retained with widening
138 425+900 NYS. Retained with widening
139 426+935 NYS. Retained with widening
140 429+325 NYS. Retained with widening
141 429+449 NYS. Retained with widening
142 430+200 NYS. Retained with widening
143 431+110 NYS. Retained with widening
144 433+265 NYS. Retained with widening
145 433+600 NYS. Retained with widening
146 434+231 NYS. Retained with widening
147 435+200 NYS. Retained with widening
148 435+750 NYS. Retained with widening
149 435+915 NYS. Retained with widening
150 436+127 NYS. Retained with widening
151 436+655 NYS. Retained with widening
152 438+313 NYS. Retained with widening
153 438+605 NYS. Retained with widening
Page | 31
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014154 438+860 NYS. Retained with widening
155 438+966 NYS. Retained with widening
156 439+370 NYS. Retained with widening
157 439+710 NYS. Retained with widening
158 440+015 NYS. Retained with widening
159 440+095 NYS. Retained with widening
160 440+660 NYS. Retained with widening
161 440+850 NYS. Retained with widening
162 441+010 NYS. Retained with widening
163 444+420 NYS. Retained with widening
164 444+595 NYS. Retained with widening
165 444+897 NYS. Retained with widening
166 446+015 NYS. Retained with widening
167 447+048 NYS. Retained with widening
168 448+397 NYS. Retained with widening
169 449+080 NYS. Retained with widening
170 450+505 NYS. Retained with widening
171 450+690 NYS. Retained with widening
172 450+970 NYS. Retained with widening
173 451+070 NYS. Retained with widening
174 452+452 NYS. Retained with widening
175 452+350 NYS. Retained with widening
176 453+453 NYS. Retained with widening
177 453+940 NYS. Retained with widening
178 454+740 NYS. Retained with widening
179 456+460 NYS. Retained with widening
180 457+530 NYS. Retained with widening
181 459+750 NYS. Retained with widening
182 460+000 NYS. Retained with widening
Page | 32
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014183 460+120 NYS. Retained with widening
184 460+410 NYS. Retained with widening
185 460+495 NYS. Retained with widening
186 460+652 NYS. Retained with widening
187 460+775 NYS. Retained with widening
188 461+505 NYS. Existing Retained (RHS) New Pipe
(LHS)189 462+175 NYS. Retained with widening
190 462+300 NYS. Retained with widening
191 462+360 NYS. Retained with widening
192 462+735 NYS. Retained with widening
193 463+015 NYS. Retained with widening
194 463+345 NYS. Retained with widening
195 463+530 NYS. Retained with widening
196 467+040 NYS. Retained with widening
197 473+415 Work in progress (LHS) Retained with widening
198 473+980 NYS. Retained with widening
199 476+446 NYS. Retained with widening
200 477+500 NYS. Retained with widening
201 478+570 NYS. Retained with widening
202 478+611 NYS. Retained with widening
203 478+990 NYS. Retained with widening
204 479+325 NYS. Retained with widening
205 485+790 NYS. Retained with widening
206 486+075 NYS. Retained with widening
207 511+920 NYS. Retained with widening
208
406+115
SLAB CULVERT NYS. Retained with widening
209
406+475 NYS. Retained with widening
210
409+525 NYS. Retained with widening
211
411+755
NYS. Retained with widening
Page | 33
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014212
412+325 NYS. Retained with widening
213
412.616 NYS. Retained with widening
214
412+836 NYS. Retained with widening
215
413+356 NYS. Retained with widening
216
413+555 NYS. Retained with widening
217
415+830 NYS. Retained with widening
218
416+283 NYS. Retained with widening
219
416+985 NYS. Retained with widening
220
420+790 NYS. Retained with widening
221
422+485 NYS. Retained with widening
222
422+645 NYS. Retained with widening
223
423+026 NYS. Retained with widening
224
423+592 NYS. Retained with widening
225
423+986 NYS. Retained with widening
226
432+316 NYS. Retained with widening
227
432+749 NYS. Retained with widening
228
432+989 NYS. Retained with widening
229
439+900 NYS. Retained with widening
230
441+850 NYS. Retained with widening
231
442+567 NYS. Retained with widening
232
442+745 NYS. Retained with widening
233
444+675 NYS. Retained with widening
234
446+410 NYS. Retained with widening
235
446+655 NYS. Retained with widening
236
449+421 NYS. Retained with widening
237
449+821 NYS. Retained with widening
238
452+685 NYS. Retained with widening
239 453+58 NYS. Retained with widening
Page | 34
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 20140
240
455+705 NYS. Retained with widening
241
457+130 NYS. Retained with widening
242
457+260 NYS. Retained with widening
243
465+060 NYS. Retained with widening
244
465+087 NYS. Retained with widening
245
465+525 NYS. Retained with widening
246
465+765 NYS. Retained with widening
247
468+375 NYS. Retained with widening
248
469+220 NYS. Retained with widening
249
472+225 NYS. Retained with widening
250
474+862 NYS. Retained with widening
251
481+930 NYS. Retained with widening
252
484+030 NYS. Retained with widening
253
487+904 NYS. Retained with widening
254
488+660 NYS. Retained with widening
255
489+128 NYS. Retained with widening
256
491+970 NYS. Retained with widening
257
493+834 NYS. Retained with widening
258
495+445 NYS. Retained with widening
259
497+040 NYS. Retained with widening
260
497+367 NYS. Retained with widening
261
499+890 NYS. Retained with widening
262
500+278 NYS. Retained with widening
263
501+260 NYS. Retained with widening
264
501+562 NYS. Retained with widening
265
502+863 NYS. Retained with widening
266
503+456
NYS. Retained with widening
Page | 35
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014267
505+226 NYS. Retained with widening
268
505+700 NYS. Retained with widening
269
506+723 NYS. Retained with widening
270
507+738 NYS. Retained with widening
271
512+383 NYS. Retained with widening
272
438+500 Toll Plaza
NYS. 273
507+000 NYS.
NYS- Not Yet Started
EMERGENCY SERVICES:-SI. N. Description Contact No
1 Control Room 8170006300
2 Highway Petrol (Jharkhand) 8229800282
3 Highway Ambulance(Jharkhand) 8229800281
4 Highway Crane(Jharkhand) 9525953313
5 Highway Pertol (West Bengal) 8170040455
6 Highway Ambulance(West Bengal) 8170040456
7 Highway Crane (West Bengal) -
Page | 36
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
Quality Assurance & Quality Control:-
Site Laboratory in Dhanbad camp, Asansol camp and Panagarh has been partial established.
Sl. No. Description of material & source STATUS
I CEMENT
a Ultratech OPC 53 Grde- Rawan APPROVED.
II REINFORCEMENT
a. SAIL – Durgapur APPROVED
b. Tata Tiscon – Bokaro APPROVED
III HUME PIPES
a. Hindustan Concrete pipe Industry – Ranchi
REVIEWED
b. Greenfield Industries – Makarampur REVIEWED
c. Aggrawal Construction – Bolpur REVIEWED
Page | 37
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
Details of QC Tests conducted during the month (01st April 2014 to 30th April 2014)
S. N.
DESCRIPTION
Description of tests
as per BIS/Agree
ment provisions
Frequency of tests as
per MoRTH/C.A.
No. of tests conducted up to previous
month
No. of tests conducted this month
Total no. of tests
conducted up to this month
pass
Fail Total Pass
Fail Total Pass
Fail Total
1.0 Earth Work1.1 OGL/
EGLGrain size analysis
As required - - - 26 26 26 26
1.2 MDD & OMC
As required - - - 74 74 74 74
1.3 Atterberg limit
As required - - - 26 26 26 26
1.4 FSI As required - - - 26 26 26 26
1.5 CBR As required - - - - - - -
1.6 Field density of original ground
1st test per 1000m2
1.7 Borrow area used for
embankment
and sub
grade
Grain size analysis
2nd test per 3000m3
- - - 22 22 22 22
1.8 MDD & OMC
2nd test per 3000m3
- - - 16 16 16 16
1.9 Atterberg limit
2nd test per 3000m3
- - - 17 17 17 17
1.10 FSI 2nd test per 3000m3
- - - 22 22 22 22
1.11 CBR 1st test per 3000m3
- - - - - - -
1.12 Deleterious Content Test
As required
1.13 NMC 1st test per - - - 4 4 4 4
Page | 38
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014250m3
Safety and traffic management:- Status of PPE on site :- Usage :- Personal protective equipment (PPE) to reduce employee exposure to hazards
when engineering and administrative controls are not feasible or effective in reducing these exposures to acceptable levels. Employers are required to determine if PPE should be used to protect their workers.
a. Be appropriate for the risks involved and the conditions at the place of exposure.b. Take account of ergonomic requirements, the state of health of the person who
wears it and the duration of its use;c. Be capable of fitting the wearer correctly.d. Be, so far as is reasonably practicable, effective to prevent or adequately control
risks involved without increasing the overall risks.
PPE availability on site :-
a. These 750 mm one piece composite Rubber traffic cones (CRC) come complete with D2 reflective sleeve which fully conforms to BS EN 13422:2004. These road cones are manufactured from recycled material.
b. Reflective tapes.c. Head Protection, Hand Protection, Safety Footwear, Yellow High Visibility
Clothing.
Functionality :-
a. Rubber Traffic Cones : Its function is on the crossing of roadways, maintenance of freeways, dangerous zone and road sites and so on.
b. Reflective tapes :- One of the most important attributes of road safety is line visibility. The importance of this function to resist the wear the tear cause by regular traffic and changing climate conditions. These reflective road tapes suitable for both longitudinal and transverse installation in locations that experience substantial traffic activity.
c. Head Protection, Hand Protection, Safety Footwear, Yellow High Visibility Clothing. : - These PPE are function in such manner, that the labour on site should be visible from long distance due to the reflective material and protect them from any uncertain hazard happen on site.
Maintenance of Existing Highways:-
Page | 39
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014The Maintenance of existing highway has to be taken up immediately by concessionaire for repairing of pot holes and rutting. Specially at Panagarh town portion and existing toll plaza location & Check post location should be taken up in priority basis.
WEATHER REPORT:-
DATE
Section -I Section -II Section – IIIDhanbad Asansol Durgapur
Temperature Rain Fall
Temperature Rain
FallTemperature Rain
Fall0C 0C 0CMax Min (mm) Max Min (mm) Max Min (mm)
01-Apr-14 39.0 27.0 Nil 39.0 28.6 Nil 37.0 22.0 Nil02-Apr-14 38.0 28.0 Nil 39.2 29.9 Nil 39.0 22.0 Nil03-Apr-14 40.0 27.0 Nil 39.0 29.0 Nil 40.0 23.0 Nil04-Apr-14 41.0 28.0 Nil 40.0 29.9 Nil 39.0 24.0 Nil05-Apr-14 39.0 28.0 Nil 41.0 31.0 Nil 39.0 19.0 Nil06-Apr-14 40.0 29.0 Nil 39.5 30.4 Nil 40.0 20.0 Nil07-Apr-14 38.0 28.0 Nil 42.0 33.0 Nil 41.0 22.0 Nil08-Apr-14 41.0 29.0 Nil 40.0 32.7 Nil 41.0 24.0 Nil09-Apr-14 39.0 28.0 Nil 38.5 30.3 Nil 38.0 25.0 Nil10-Apr-14 40.0 28.0 Nil 39.5 30.1 Nil 39.0 23.0 Nil11-Apr-14 41.0 29.0 Nil 40.0 31.5 Nil 38.0 22.0 Nil12-Apr-14 43.0 31.0 Nil 39.0 31.0 Nil 39.0 22.0 Nil13-Apr-14 42.0 29.0 Nil 41.0 31.0 Nil 40.0 22.0 Nil14-Apr-14 44.0 30.0 Nil 41.0 33.5 Nil 40.0 22.0 Nil15-Apr-14 46.0 32.0 Nil 41.2 33.0 Nil 40.0 24.0 Nil16-Apr-14 43.0 31.0 Nil 42.0 32.0 Nil 41.0 25.0 Nil17-Apr-14 41.0 29.0 Nil 43.0 33.5 Nil 41.0 24.0 Nil18-Apr-14 45.0 32.0 Nil 42.0 32.5 Nil 39.0 25.0 Nil19-Apr-14 42.0 29.0 Nil 41.8 34.0 Nil 39.0 27.0 Nil20-Apr-14 44.0 32.0 Nil 40.5 33.2 Nil 39.0 26.0 Nil21-Apr-14 41.0 30.0 Nil 42.0 33.0 Nil 40.0 24.0 Nil
Page | 40
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 201422-Apr-14 43.0 31.0 Nil 43.0 32.0 Nil 40.0 25.0 Nil23-Apr-14 44.0 32.0 Nil 42.6 31.0 Nil 41.0 24.0 Nil24-Apr-14 42.0 29.0 Nil 42.4 30.3 Nil 41.0 24.0 Nil25-Apr-14 43.0 30.0 Nil 42.0 29.0 Nil 42.0 25.0 Nil26-Apr-14 45.0 31.0 Nil 43.0 31.5 Nil 42.0 25.0 Nil27-Apr-14 48.0 32.0 Nil 40.0 28.2 Nil 43.0 25.0 Nil28-Apr-14 44.0 31.0 Nil 43.3 33.0 Nil 43.0 26.0 Nil29-Apr-14 45.0 31.0 Nil 43.0 31.5 Nil 44.0 27.0 Nil30-Apr-14 44.0 30.0 Nil 40.0 30.2 Nil 43.0 26.0 Nil
Site Photographs:-
Widening of pipe culvert at km. 473.415
C& G at km 519.350.
Page | 41
Independent Engineer services for Six-Laning of Barwa-Adda-Panagarh Section of NH-2 from km 398.240 to km 521.120 including Panagarh Bypass in the States of Jharkhand and West Bengal under NHDP Phase V on Toll on DBFOT Pattern.
Monthly Progress Report – April 2014
Page | 42