india- farzi logic

Embed Size (px)

Citation preview

  • 8/7/2019 india- farzi logic

    1/11

    Engineering, Construction and Architectural Management 2000 7 1, 93103

    Assessment of working capital requirements by fuzzy set

    theory

    V E L L A N K I S . S . K U M A R*, A W A D S . H A N N A & T E R E S A A D A M S

    *Department of Civil Engineering, University College of Engineering (Autonomous), Osmania University, Hyderabad500

    007, India; Department of Civil and Environmental Engineering, 2260 Engineering Hall, Madison, WI 53706, USA

    Abstract The systematic assessment of working capital This article takes into consideration the uncertainty asso-

    ciated with many of the project resource variables andrequirement in construction projects deals with the anal-

    ysis of various quantitative and qualitative factors in these are reflected satisfactorily in the working capital

    computations. A case study illustrates the application ofwhich information is subjective and based on uncer-

    tainty. There exists an inherent difficulty in the classical the fuzzy set approach. The results of the case study

    demonstrate the superiority of the fuzzy set approach toapproach to evaluate the impact of qualitative factors for

    classical methods in the assessment of realistic workingthe assessment of working capital requirement. This

    capital requirements for construction projects.paper presents a methodology to incorporate linguistic

    variables into workable mathematical propositions for the Keywords fuzzy relation, fuzzy sets, membership func-

    assessment of working capital using fuzzy set theory. tion, working capital

    I N T R O D U C T I O N

    Construction projects are generally complex and often

    confronted by a number of operations and activities

    with varying degrees of uncertainty. From the incep-

    tion of the construction project, the project manager is

    required to make numerous decisions that will deter-

    mine the success or failure of the project both in

    accomplishment of physical and in monetary terms.

    One such decision is the working capital requirement

    for the successful completion of the project.Conventionally, the first step in the estimation of

    working capital is to forecast a total expenditure curve,

    which is derived from a composition of constituent

    expenditures, such as labour, equipment, maintenance

    and material procurement advances. Then, the total

    expenditure is superimposed with the anticipated cu-

    mulative receipts of revenue, and the difference be-

    tween the two curves is the working capital

    requirement at any time during the project.

    The realistic assessment of working capital in con-

    struction projects involves usually quantitative re-

    sources such as money, machinery, material and

    labour, as well as qualitative features such as fluctuat-

    ing market conditions, weather conditions, availability

    and quality of materials, variation in material prices,

    delay in receipts of revenue, technical problems, and

    design changes.

    In practice, experienced project engineers evaluate

    the working capital requirement based on the past

    experience in a similar situation and from cash flow

    calculations. In some cases, experience is limited to

    certain types of projects. Inexperienced project engi-

    neers may overlook qualitative factors when assessing

    the working capital requirement. Thus, there is a need

    to incorporate qualitative factors in addition to quanti-

    tative factors for the realistic assessment of working

    capital requirements.

    This article presents a methodology for the assess-

    ment of working capital requirements by quantifying

    the qualitative factors using fuzzy set theory. A casestudy is presented to demonstrate the use and practi-

    cability of the fuzzy logic approach. In addition, the

    approach described in this paper uncovers any gap in

    experts thinking for optimum utilization of the avail-

    able resources.

    L I T E R A T U R E R E V I E W

    Management of working capital in the construction

    industry is an integral part of overall organization.

    Working capital management involves rational deci-

    sion making regarding the levels of inventory, receiv-

    ables and cash balance to be maintained. In the

    construction industry, working capital accounts for

    about 60% of total investment.

    Van Horne (1984) mentions that gross working

    capital is an asset that converts back into cash within

    an operating cycle, which is usually less than 1 year.

    Major parts of gross working capital is financed by

    2000 Blackwell Science Ltd93

  • 8/7/2019 india- farzi logic

    2/11

    94 Kumar, V.S.S. et al.

    current liabilities, which mature for repayment within

    one operating cycle. He further defines the difference

    between current assets and current liabilities as the net

    working capital, which represents the ownership funds.

    Archer et al. (1983) state the basic principle in working

    capital management is minimization of the investment

    on current assets without affecting the smooth runningof the organization. The rationale of this minimization

    principle is that this investment by itself does not

    generate profit, while the investment made on working

    capital has a costexplicit or implicit.

    Several authors emphasize that the maintenance of

    working capital is intended to meet the current liabili-

    ties promptly to ensure technical solvency of the firm.

    In construction industry, in fact, at any given point of

    time investment on working capital is more than the

    investment on fixed assets. At the final stage of con-

    struction, the entire unit can be viewed as inventory to

    be sold to the owners. If the periodic cash inflows due

    from an owner do not take place promptly, the need

    for working capital will increase for the contractor.

    Similarly, adverse inflationary impact also increases the

    need for working capital.

    Pilcher (1994) suggests that the capital invested on a

    project is normally the initial expenditure for the pur-

    chase of plant and other fixed assets together with the

    associated working capital. He further explains that a

    qualitative factor, for example fluctuating trading con-

    ditions, would include a length of time over which

    credit is allowed and received; accordingly, the amount

    of stock or inventory carried influences the working

    capital requirements.Similarly, the cost of the proposed construction pro-

    ject along with the projects on hand also affect the

    amount of working capital required. The gestation

    period, which is affected by labour unrest, season,

    nonavailability of construction material etc., is another

    important factor that affects the quantum of working

    capital. In fact, the longer the construction period, the

    larger is likely to be the amount of working capital with

    its own corresponding cost implications.

    Desai (1997) suggests that proper management of

    working capital synchronizes the cash receipts and

    cash outlay so that a unit may function with cashreserves.

    Ayyub & Haldar (1984) pioneered the use of fuzzy

    set theory to evaluate the impact of qualitative factors

    on the duration of construction project activities.

    However, their study does not consider the effect of

    qualitative factors on the working capital requirements

    for a construction project.

    The working capital requirements on account of the

    relevant qualitative factors were not assessed so far;

    this can be estimated through the application of fuzzy

    set theory.

    F A C T O R S A F F E C T I N G W O R K I N G

    C A P I T A L R E Q U I R E M E N T S

    The capital invested in construction projects is the

    initial capital for the purchase of material and other

    fixed assets plus associated working capital (Pilcher

    1994). Working capital in this context is the require-

    ment of the day-to-day finance until the completion of

    the project. The working capital requirements vary

    from one project to another and from one type unit to

    another type.

    In reality, the working capital for construction

    projects is also influenced by qualitative factors as

    shown in Fig. 1, in addition to quantitative factors. For

    realistic assessment of working capital, variabilities ofthe qualitative factors have to be considered. For ex-

    ample, fluctuating market conditions include a length

    of time over which credit is allowed and received;

    accordingly, the delay in receipts of revenue may con-

    siderably influence the working capital requirements.

    Similarly, the cost of a construction project relative to

    other ongoing projects also affects the amount of work-

    ing capital required. The down time that is affected by

    labour unrest, season and nonavailability of construc-

    tion materials is another important factor that affects

    the quantum of working capital. In fact, the longer the

    construction period, the greater will be the amount of

    working capital with the corresponding costimplications.

    The fuzzy logic approach presented here incorpo-

    rates qualitative factors in the assessment of working

    capital requirements. This methodology prompts the

    Figure 1 Factors affecting the working capital in construction.

    2000 Blackwell Science Ltd, Engineering, Construction and Architectural Management 7 1, 93103

  • 8/7/2019 india- farzi logic

    3/11

    95Assessment of working capital requirements by fuzzy set theory

    project engineer for information regarding each quali-

    tative factor. In return, the methodology furnishes the

    manager with a realistic working capital requirement

    for each interval of the construction project.

    F U Z Z Y S E T C O N C E P T

    The fuzzy set concept is founded on the notion that

    qualitative expressions usually involve the realm of

    human perception, which are subject to a range of

    interpretations. Although the values of these expres-

    sions are inexact in quality, they are meaningful. Qual-

    itative expressions usually consist of linguistic variables

    and these are routinely used in construction projects.

    These linguistic measures add to the overall uncer-

    tainty in the final outcome of any decision process.

    A linguistic variable is defined as a variable, the

    values of which are expressed in words, phrases or

    sentences in a given language (Ayyub & Haldar 1984).

    The phrase performance of constructed facility, forexample, is a linguistic variable that can take the values

    of excellent, good or low. The information expressed

    in the phrase has a value that is not clearly defined.

    The variabilities of the linguistic variables can be rep-

    resented as fuzzy sets.

    Fuzzy set theory in measuring qualitative criteria

    A fuzzy set can be defined as a class of objects with

    unclear boundaries in which transition from member-

    ship to nonmembership is gradual. Since the transition

    from member to nonmember appears gradual rather

    than abrupt, the fuzzy set introduces vagueness byeliminating the sharp boundaries dividing members of

    the set from nonmembers (Paek et al. 1993). The

    qualitative factors that affect the working requirement

    can be quantified by giving membership values to their

    variabilities. This membership value is denoted by

    vA(x), where x is an element of fuzzy set A. The

    membership value vA(x) is the degree of belief with

    which an element can be stated to belong to the set.

    Therefore the fuzzy set:

    A={x, vA (x)}, xA (1)

    Each element, x, is associated with a membership

    value vA(x), to the set A and is a real number. If A is

    an ordinary, nonfuzzy, or crisp set, then the member-

    ship function is given by:

    1 if x belongs to A

    vA(x)={ (2)

    0 if x does not belong to A

    In Equation (2), there are only two possibilities for

    an element x, either being a member of A, i.e.,

    vA(x)=1 or not being a member of A, i.e., vA(x)=0.

    In this case, A has sharp boundaries. On the other

    hand, if the membership function is allowed to take

    values in the interval (0, 1), A is called a fuzzy set

    (Lorterapong & Moselhi 1996).For example, the linguistic variable weather condi-

    tions is interpreted using the following membership

    function. Here, the linguistic variable is weather con-

    ditions and the values of the linguistic variable are

    poor, medium, good, etc. Dividing the range into

    increments of 0.1, the following fuzzy subset poor

    can be assigned for the variable weather conditions:

    poor={x1=0.0/(vpoor(x1)=1.0), x2=0.1/

    (vpoor(x2)=0.9), x3=0.2/(vpoor(x3)=0.5)} (3)

    In Equation (3), the term x1=0.0/(vpoor(x1)=1.0),

    indicates that if the value of the qualitative factorweather condition is 0.0, then the degree of belief

    that the qualitative factor belongs to the, poor weather

    conditions set is 1.0 (AbouRizk et al. 1994). Similarly,

    for the value of weather condition 0.1, the degree of

    belief is 0.9; and for the value of weather condition

    0.2, the degree of belief is 0.5. For simplicity, Equa-

    tion (3) can be written as in Equation (4):

    poor=(0.0/1.0, 0.1/0.9, 0.2/0.5) (4)

    These membership values are assigned based on sub-

    jective judgement of experts.

    In general, the membership values for variability ofqualitative factors that affect the working capital re-

    quirements can be represented as in Equations (5)

    (7).

    pessimistic=(0.0/1.0, 0.1/0.9, 0.2/0.5) (5)

    average=(0.3/0.2, 0.4/0.8, 0.5/1.0, 0.6/0.8, 0.7/

    0.2) (6)

    optimistic=(0.8/0.5, 0.9/0.9, 1.0/1.0) (7)

    In some cases, a term set including linguistic values

    such as pessimistic, average and optimistic may not besatisfactory in certain domains, and may instead re-

    quire the use of linguistic values such as quite pes-

    simistic and very optimistic. The membership values

    for these variabilities can be defined as:

    quite pessimistic=(pessimistic)1.25=(0.0/1.0, 0.1/

    0.88, 0.2/0.42) (8)

    2000 Blackwell Science Ltd, Engineering, Construction and Architectural Management 7 1, 93103

  • 8/7/2019 india- farzi logic

    4/11

    96 Kumar, V.S.S. et al.

    very optimistic=(optimistic)2=(0.8/0.25, 0.9/

    0.81, 1.0/1.0) (9)

    Equations (5) (9) can be applied to any of the

    variabilities of linguistic variable in the project environ-

    ment such as site conditions, technical problems,

    weather conditions and design changes. For example,

    if we say that the weight of the qualitative factor

    weather condition is small (or low), then the pes-

    simistic fuzzy set of Equation (5) can be applied by

    treating the weight to vary continuously from 0 to 1.

    In order to use fuzzy sets in practical problems such

    as evaluating working capital requirements, some oper-

    ational rules must be defined.

    Assuming that A and B are two fuzzy sets with

    membership functions of vA(x) and vB(x), then the

    following operations can be defined on these sets. The

    complement A0 , of a fuzzy set A with a membership

    function vA(x) is defined as:

    vA0(x)=1vA(x) (10)

    The membership function for the union @ of two

    fuzzy subsets A and B with membership functions

    vA(x) and vB(x) is given in Equation (11).

    vA@B(x)=max{vA(x), vB(x)} (11)

    The membership function for the intersection S of

    two fuzzy subsets A and B is given in Equation (12).

    vASB(x)=min{vA(x), vB(x)} (12)

    A fuzzy relation R or Cartesian product, AB,

    between the two fuzzy subsets A (subset of universe X)

    and B (subset of universe Y) is determined from the

    following membership function in Equation (13).

    vR(xi, yj)=vAB(xi, yj)=min{vA(xi), vB(yj)} (13)

    A fuzzy relation is usually expressed in a matrix

    form. Each element vR(xi, yj) is a membership value

    for the ordered pair (xi, yj) and is a measure of

    association between xi and yj. It is computed as the

    minimum value of the membership values of vA(xi)

    and vB(xj). For example, if A is a subset of weather

    condition (X), and B is a subset of site condition (Y),

    then vAB (xi, yj) is a measure of the associationbetween weather conditions and site conditions.

    If R is fuzzy relation from X to Y, and T is a fuzzy

    relation from Y to Z, the composition of R and T

    (R o T) is a fuzzy relation between the fuzzy subsets X

    and Z using the common fuzzy subset Y (Equation

    (14)). The composition of two fuzzy relations is a

    fuzzy relation.

    vR o T(xi, zk)=max{min[vR(xi, yj), vT(yj, zk)]}

    (14)

    The preceding operational rules for fuzzy sets are

    used in this paper (Ayyub & Haldar 1984).

    M E T H O D O L O G Y

    The applicable qualitative factors must be identified

    for each interval of the project duration for the assess-

    ment of the working capital requirement in the entire

    project. Each of these factors has its own linguistic

    values that can be converted into fuzzy sets by giving

    suitable membership values. These membership values

    are assigned based on subjective judgement. Each

    membership value shows the degree of membership of

    the corresponding element in the fuzzy set and is a real

    number in the interval (0, 1).

    Let the criterion Cij denote qualitative factors (i=1,

    2,n) such as technical problems, design changes and

    delay in receipts of revenue for each project interval

    (j=1, 2,m), and Wij denotes a measurement of the

    weight or importance of a criterion Cij. The impor-

    tance of these criteria will depend on schedule, project

    location, project characteristics, project managers

    preferences and other factors. Here, the weight of a

    criterion is also in terms of linguistic values.

    The weight of qualitative factor, Wij, determines the

    susceptibility of working capital requirement to each

    criterion on each interval of the project duration. Here,

    susceptibility (Sij) is a measure of sensitivity of the

    working capital to the criterion i and project interval j.

    The values of susceptibility also are in linguistic terms

    and vary from zero to one. If the susceptibility ofinterval j to criterion i (Sij) equals to zero, the working

    capital of interval j of the project is not affected by

    criterion i.

    The values of susceptibility and its affect vary with

    different intervals of the project. If Sij equals to one,

    the working capital of interval j is totally susceptible to

    Cij. When Sij falls in the range of (0, 1), working

    capital of interval j has some degree of susceptibility to

    the criterion Cij (Chang et al. 1990). For example, if a

    criterion called severity of rain exists, then by ones

    judgement or expert advice, it is very reasonable to

    believe that working capital of interval j (say, placing of

    concrete) tends to be greatly affected by the rain.The methodology uses two fuzzy relations R and T.

    Using Equation (13), the fuzzy relation R and T can

    be determined. The fuzzy relation R is an association

    of weight of the criterion (Wij) and susceptibility on

    the working capital to the criterion during a particular

    interval (Sij). The fuzzy relation T is an association

    between susceptibility (Sij) and working capital (WCij).

    2000 Blackwell Science Ltd, Engineering, Construction and Architectural Management 7 1, 93103

  • 8/7/2019 india- farzi logic

    5/11

    97Assessment of working capital requirements by fuzzy set theory

    Table 1 Expenditure and revenue of the project

    End of theEnd of the

    Revenue Cum. exp.month Cum. exp.Expenditure RevenueCum. rev. Cum. rev.Expendituremonth

    (3)(1) (4) (5) (6) (7) (8) (9) (10)(2)

    0.0 0.6 0.0 7 3.0 3.71 13.0 11.80.6

    0.0 1.0 0.0 8 1.60.4 2.6 14.6 14.42

    0.83 0.9 1.8 0.9 9 0.7 1.7 15.3 16.1

    2.24 1.0 4.0 1.9 10 0.7 0.9 16.0 17.0

    2.3 7.0 4.2 11 0.43.0 0.4 16.4 17.45

    3.9 10.0 8.1 12 0.66 1.6 17.0 19.03.0

    Cum., cumulative; exp., expenditure; rev., revenue.

    The stepwise procedure for assessing the working

    capital requirement is as follows:

    Step 1. Identify the relevant qualitative factors

    (Cij) that affect each interval of the

    total project duration.

    Step 2. Tabulate the variabilities of the qualita-

    tive factors for assessing working cap-

    ital requirements by assigning weight

    of importance (Wij), susceptibility

    (Sij) and working capital (WCij).

    Translate the variability of qualitativeStep 3.

    factors into numerical measures by

    using the membership values from

    Equations (5)(9)

    Compute fuzzy relation R between theStep 4.

    weight (Wij) of the qualitative factor

    and its susceptibility (Sij) through the

    use of Equation (13).Compute fuzzy relation T between sus-Step 5.

    ceptibility (Sij) and affect on working

    capital (WCij) through the use of

    Equation (13).

    Establish fuzzy relations obtained inStep 6.

    step 4 and 5. This is performed by

    taking the largest membership value

    in each column of the fuzzy relation

    matrix.

    Step 7. Formulate the fuzzy composition matrix

    for all membership values for R and

    T obtained in step 6, using Equation

    (14) to arrive at the combinedinfluence.

    Compute the working capital by choos-Step 8.

    ing the decision subset, which maxi-

    mizes the product of row summation.

    The procedure is illustrated by the following case

    study.

    C A S E S T U D Y

    An established construction company with cash on

    hand of $1000000 is being awarded a contract to

    construct warehouses and the total cost of the project

    is $19000000. The construction work of the above

    project is scheduled to be completed within12 months. From the second month until the end of

    month 8, cumulative revenues lag behind the expendi-

    tures. From the end of month 8 onward, there is an

    increase in net revenue and at the end of the project

    period the total revenue is $19000000. The expected

    net profit for the project is $2000000. Table 1 shows

    the projected monthly cash flow requirements of the

    project.

    To demonstrate the applicability of the fuzzy set

    theory for the assessment of working capital require-

    ment for the case study, the detailed procedure is

    presented for the first interval of the project.

    Analysis of working capital requirement by fuzzy

    set theory

    The first step in the assessment of working capital is to

    identify the qualitative factors that affect the working

    capital requirement. For the first interval, the relevant

    qualitative factors are site conditions (poor, average),

    weather conditions (good), cash flow (excellent) and

    experience of an engineer (high). The weight for each

    classification of these preceding factors as well as the

    susceptibility on the requirement of working capital

    estimation in linguistic terms are shown in Table 2.To translate the impact of qualitative factors for

    i=15, the following fuzzy relations are calculated

    based on Equations (5)(9). The relation R1 is defined

    as: if the site conditions are poor then the susceptibility

    is more for its great importance of the factor. There-

    fore, the fuzzy relation Ri for poor site conditions is:

    Site conditions (poor)

    2000 Blackwell Science Ltd, Engineering, Construction and Architectural Management 7 1, 93103

  • 8/7/2019 india- farzi logic

    6/11

    98 Kumar, V.S.S. et al.

    Weight (great) Susceptibility (more)

    0.8 0.9 1.0

    0.8 0.50 0.500.50

    0.900.500.9R1=W1S11 0.90

    1.000.900.501.0

    (15)

    In the above relation, weight and susceptibility

    are two different fuzzy sets. The membership values of

    the second row of Equation (15), are evaluated as

    follows from Equation (13).

    vR1(0.9, 0.8)=min(0.90, 0.50)=0.50

    From Equation (7), the membership values for the

    variability of great weight and large susceptibility are

    0.9 and 0.5. Then using Equation (13), the fuzzy

    relation is obtained for the two fuzzy sets as the

    minimum value of these two values is 0.5. The value

    0.5 is an association for great weight and large suscep-tibility of the working capital for poor site conditions.

    The second and third values of the second row are:

    vR1(0.9, 0.9)=min(0.90, 0.90)=0.90

    vR1(0.9, 1.0)=min(0.90, 1.00)=0.90

    Similarly, the relations R2, R3, R4 and R5 are calcu-

    lated from Table 2.

    For site conditions (average)

    Weight (small) Susceptibility (medium)

    0.3 0.4 0.5 0.6

    0.0 0. 20 0.80 1.00 0.80

    R2=W21S21 0.1 0. 20 0.80 0.90 0.80

    0.2 0. 20 0.50 0.50 0.50

    (16)

    For weather conditions (good)

    Weight (medium) Susceptibility (small)

    0.0 0.1 0.2

    0.3 0.20 0.200.20

    0.4R3=W31S31 0.500.800.80

    0.5 1.0 0.90 0.50

    0.6 0.80 0.80 0.50

    (17)

    For cash flow (excellent)

    Weight (large) Susceptibility (small)

    0.0 0.1 0.2

    0.500.500.8 0.50

    R4=W41S41 0.9 0.90 0.90 0.50

    1.00 0.90 0.501.0

    (18)

    For engineers experience (high)

    Weight (medium) Susceptibility (very small)

    0.1 0.20.0

    0.20 0.20 0.200.3

    R5=W51S51 0.4 0.80 0.80 0.25

    0.250.811.000.5

    0.250.800.800.6

    (19)

    The total effect of all the factors is obtained by taking

    the union of these five relations.

    Total effect=R=(W11S11)@(W21S21)@(W31S31)@(W41S41)@(W51S51) (20)

    Affect on working capitalSusceptibilityWeight (Wij)Qualitative factors (Cij)

    (3)(2)(1) (4)

    More1. Site conditions (poor) Very largeGreat

    Medium MediumSmall2. Site conditions (average)

    3. Weather conditions (good) SmallMedium Small

    Very smallSmallLarge4. Cash flow (excellent)

    Quite smallVery smallMedium5. Engineers experience (high)

    Table 2

    Qualitative

    description of

    weight and

    susceptibility for

    linguistic variables

    2000 Blackwell Science Ltd, Engineering, Construction and Architectural Management 7 1, 93103

  • 8/7/2019 india- farzi logic

    7/11

    99Assessment of working capital requirements by fuzzy set theory

    Therefore,

    Susceptibility

    0.1 0.2 0.3 0.4 0.5 0.60.0 0.7 0.8 0.9 1.0Weight

    0.0 0.0 0.0 0.2 0.8 1.0 0.8 0.0 0.0 0.00.0 0.0

    0.0 0.0 0.2 0.8 0.9 0.80.0 0.00.1 0.0 0.0 0.0

    0.0 0.0 0.2 0.5 0.5 0.5 0.00.2 0.0 0.0 0.00.00.2 0.2 0.0 0.0 0.0 0.00.2 0.0 0.0 0.0 0.00.3

    0.5 0.50.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.00.8

    0.5 0.5 0.0 0.0 0.0 0.00.9 0.0 0.0 0.0 0.0R=0.5

    0.5 0.5 0.0 0.0 0.0 0.0 0.00.6 0.0 0.0 0.00.8

    0.0 0.0 0.0 0.0 0.0 0.00.0 0.0 0.0 0.0 0.00.7

    0.5 0.50.8 0.0 0.0 0.0 0.0 0.0 0.5 0.5 0.50.5

    0.5 0.5 0.0 0.0 0.0 0.00.9 0.00.9 0.5 0.9 0.9

    0.9 0.51.0 0.0 0.0 0.0 0.0 0.0 0.5 0.9 1.01.0

    (21)

    The fuzzy relations of R1, R2 R3, R4, and R5 are

    projected in relation R using Equation (14) at appro-

    priate positions. The other positions, in relation R are

    given a membership value of 0.0, since there is no

    qualitative factor affecting those positions. To establish

    a fuzzy relation T between the fuzzy subsets of suscep-

    tibility and working capital, the conditional statement

    is as follows: if the susceptibility is more, its affect on

    working capital will be very large. The membership

    values for the variabilities of qualitative factors (affect

    on working capital requirement) are given in the fol-

    lowing Equation (22).

    Very large=550000/0.25, 600000/0.81, 650 000/

    1.00

    Medium=550000/0.60, 600000/1.00, 650000/0.60

    Small=550000/1.00, 600000/0.60, 650000/0.20

    Very small=(small)2=550 000/1.00, 600000/

    0.36, 650000/0.04

    Quite small=(small)1.25=550000/1.00, 600000/

    0.53, 650000/0.13 (22)

    A range of the peak working capital requirement for

    the present interval between $550 000 and $650 000 is

    chosen based on the quantitative data and the experi-

    ence of an engineer. If the range chosen is too small,

    the effect of qualitative factors cannot be adequatelyrepresented. On the other hand, if the range is too

    large, the qualitative factors will dominate the working

    capital requirement. Hence, it is important to choose a

    likely range for the working capital.

    The maximum working capital for the chosen range

    is $650 000. Since the affect on working capital re-

    quirement is very large, the values nearer to $650 000

    will assume higher membership values and large

    membership values are applied for susceptibility factor.

    Therefore, the fuzzy relations (T) from Table 2 are

    as follows:

    For site conditions (poor)

    Susceptibility (more) Working capital (very large)

    550 000 600 000 650 000

    0.25 0.50 0.500.8

    0.25 0.810.9 0.90T1=S11WC111.0 0.25 0.81 1.00

    (23)

    For site conditions (average)

    Working capital (medium)Susceptibility (medium)550 00 600 000 650 000

    0.3 0.20 0.20 0.20

    T2=S21WC21 0.4 0.60 0.80 0.60

    0.5 0.60 1.00 0.60

    0.60 0.80 0.600.6

    (24)

    For weather conditions (good)

    Working capital (small)Susceptibility (small) 550 000 600 000 650 000

    0.0 1.00 0.60 0.20

    0.90 0.600.1 0.20T3=S31WC310.50 0.50 0.200.2

    (25)

    For cash flow (excellent)

    Working capital (very small)Susceptibility (small)

    550 000 600 000 650 000

    1.00 0.360.0 0.04

    T4=S41WC41 0.1 0.90 0.36 0.04

    0.50 0.36 0.040.2

    (26)

    For engineers experience (high)

    2000 Blackwell Science Ltd, Engineering, Construction and Architectural Management 7 1, 93103

  • 8/7/2019 india- farzi logic

    8/11

    100 Kumar, V.S.S. et al.

    Working capital (quite small)Susceptibility

    550 000 600 000 650 000(very small)

    0.0 1.00 0.53 0.13

    0.81 0.53 0.13T5=S51WC51 0.1

    0.25 0.25 0.130.2

    (27)

    By taking the union of T1, T2, T3, T4 and T5, the

    following relation is obtained:

    Susceptibility Working capital

    550 000 600 000 650 000

    0.0 1.00 0.60 0.20

    0.90 0.60 0.200.1

    0.50 0.500.2 0.20

    0.3 0.20 0.20 0.20

    0.60 0.80 0.600.4

    0.60 1.000.5 0.60T=0.6 0.60 0.80 0.60

    0.7 0.00 0.00 0.00

    0.25 0.500.8 0.50

    0.9 0.25 0.81 0.90

    1.0 0.25 0.81 1.00

    (28)

    Therefore, the working capital requirement is calcu-

    lated by taking composition of R and T (R o T), from

    Equation (14).

    Weight Working capital

    600 000 650 000 Sum550 000 Product

    0.600.0 1.00 0.60 2.20 0.00

    0.600.1 0.90 0.60 2.10 0.21

    0.50 0.50 1.500.50 0.300.2

    0.20 0.20 0.60 0.180.3 0.20

    0.60 0.60 2.000.80 0.800.4

    1.000.5 0.60 0.60 2.20 1.10

    0.800.6 0.60 0.60 2.00 1.20

    0.00 0.00 0.000.00 0.000.7

    0.50 0.50 1.500.8 1.200.50

    0.81 0.90 2.610.90 2.350.9

    0.81 1.001.0 2.81 2.811.00

    (29)

    The fuzzy composition (R o T) considers the total

    affect of the factors of Table 2 to assess the working

    capital requirement. For example, the membership

    value of 0.60 in the first row of Equation (29) is the

    total effect of qualitative factors on working capital of

    $550 000 for the weight of 0.0.

    Now a row has to be chosen from the above equa-

    tion, which maximizes the product of the row summa-

    tion and the corresponding weight of the factor, to

    calculate the working capital requirement for the inter-val. The last row of Equation (29) gives the maximum

    value of this product for the case problem under

    consideration. Therefore, the following subset is cho-

    sen for the calculation of working capital requirement:

    D=(550 000/1.00, 600000/0.81, 650000/1.00)

    (30)

    The probability mass function of the working capital

    requirement for the interval can be calculated as fol-

    lows (Zadeh 1968):

    P (550 000)=1.00/(1.00+0.81+1.00)=0.356

    P (600 000)=0.81/(1.00+0.81+1.00)=0.288

    P (650 000)=1.00/1.00+0.81+1.00)=0.356

    Therefore, the mean value of working capital re-

    quirement is calculated as follows:

    Working capital=5500000.356+6000000.288

    +6500000.356=$600000

    In addition to the mean working capital require-

    ments, this methodology provides standard deviation

    (|) and coefficient of variation (COV) for the interval

    of the project as indicated below.

    |2=55000020.356+60000020.288+6500002

    0.356(600 000)2=1.78109 and

    |=$42 190 with COV=42 190/600000=0.07

    Similarly, for each interval in the case study, the

    mean values of the working capital requirements were

    calculated for the project and shown in Table 4. The

    weight of qualitative factors and the adverse suscepti-

    bility on working capital requirements are evaluated

    subjectively based on experts judgement in relation of

    performance to working capital.

    DISCUSSION

    Working capital is the requirement of the day-to-dayfinance until the completion of the project. It is essen-

    tially determined by the difference between expendi-

    ture assessed inclusive of next period expenditure and

    revenue received at any given point of time. The peak

    working capital requirement for the project is the

    maximum value of the difference between cumulative

    revenue of the previous month and the cumulative

    2000 Blackwell Science Ltd, Engineering, Construction and Architectural Management 7 1, 93103

  • 8/7/2019 india- farzi logic

    9/11

    101Assessment of working capital requirements by fuzzy set theory

    Table 3 Working capital requirements of the project (conventional)

    Working capital Net working End of theEnd of the Working capital Net working

    month (conventional)capital capital(conventional) month

    (2) (3) (4) (5) (6)(1)

    0.6 71 4.9 1.20.6

    1.0 1.0 8 2.8 0.22

    3 1.8 0.9 9 0.9 +0.8

    2.1 10 +0.13.1 +1.04

    5.15 2.8 11 +0.6 +1.0

    1.9 12 +0.4 +2.06 5.8

    value represents the WC requirement and + value represents the surplus revenue at hand.

    expenditure of the present month. The peak working

    capital requirement for project can be noted to be

    $5.8 million (Table 3). This can be met through the

    availability of credit facility of the firm with the suppli-

    ers in addition to the cash reserve at hand.

    But in actual practice, due to inflow of revenue, the

    Figure 2 Working capital requirements for project.

    2000 Blackwell Science Ltd, Engineering, Construction and Architectural Management 7 1, 93103

  • 8/7/2019 india- farzi logic

    10/11

    102 Kumar, V.S.S. et al.

    working capital requirement decreases for brief inter-

    mittent intervals. In Fig. 2, the sloping lines represent

    a gradual increase in the project requirements and

    vertical lines represent monetary decreases in out-

    standing working capital as and when the payments are

    received. The discontinuous lines represent the work-

    ing capital requirements in the absence of the expectedrevenue inflows.

    Figure 3 represents the fuzzy-based working capital

    computations and these are in general agreement with

    the conventional evaluation as shown in Table 4.

    However, in the absence of reliable data on the project

    expenditure, the conventional approach cannot assess

    the working capital requirements realistically. In such

    cases, the fuzzy set approach can be applied with

    advantage. This approach makes for explicit communi-

    cation and incorporation of the effects of qualitative

    factors on working capital assessment. Conventionally,

    these relationships are known and retained with the

    experts who may have intuitively used them, oftenunconsciously, to arrive at the assessment of working

    capital requirements for construction projects. The

    experts knowledge of these relationships is made ex-

    plicit in the form of conditional statements (Table 2)

    in order to apply the fuzzy set theory to other projects

    systematically.

    The application of fuzzy set theory to the assessment

    of working capital was illustrated with a case studyincorporating qualitative inputs such as site conditions,

    weather conditions and cash flow. Besides computing

    the expected value of the working capital required,

    fuzzy set analysis also provides the standard deviation

    for this expected value. In projects of high priority to

    the organization where a high degree of confidence in

    the success of the project is called for, this standard

    deviation can be used to establish additional require-

    ments, which would increase the confidence in the

    success of the project.

    The methodology also provides the project manager

    a greater insight and understanding to prepare the

    working capital requirements that may affect the pro-ject implementation schedules.

    Figure 3 Working capital requirements of project (fuzzy).

    2000 Blackwell Science Ltd, Engineering, Construction and Architectural Management 7 1, 93103

  • 8/7/2019 india- farzi logic

    11/11

    103Assessment of working capital requirements by fuzzy set theory

    Table 4 Working capital requirements of the project

    Working capitalWorking capital Working capitalEnd of theEnd of the Working capital

    month(conventional)month (conventional)(fuzzy based)(fuzzy based)

    (1) (6)(2) (3) (4) (5)

    1 0.60 0.60 7 1.28 1.20

    2 1.02 1.00 8 0.25 0.20

    +0.80+0.8590.901.153102.102.05 +0.924 +1.00

    5 2.92 2.80 11 +1.00 +1.00

    6 1.90 1.90 12 +1.72 +2.00

    value represents the WC requirement and + value represents the surplus revenue at hand.

    C O N C L U S I O N S

    In this paper, the fuzzy set theory applied to the

    assessment of the working capital requirement is illus-

    trated with a case study incorporating qualitative inputs

    such as site conditions, weather conditions and cash

    flow. This new methodology takes into consideration

    the uncertainty associated with many of the project

    resource variables and these are reflected satisfactorily

    in the working capital computations.

    Fuzzy set theory, under these circumstances, will be

    useful to construction engineers in order to exercise

    better control on cost allocation and financial planning.

    Application of fuzzy set theory is a step towards the

    elimination of bias or prejudice in the judgement of an

    expert, since the steps leading to the judgement are

    made explicit. This makes for explicit communication

    and incorporation of the effects of qualitative factors for

    the assessment of working capital requirement. Thishelps to uncover any gap in the experts thinking such

    as in regard to qualitative factors, which may have not

    been considered. This methodology can incorporate any

    new information after completion of the project and for

    multi-project planning.

    R E F E R E N C E S

    AbouRizk, S.M., Halpin, D.W. & Sawhney, A. (1994) Mod-

    elling of uncertainty in construction simulation. In: Uncer-

    tainty Modeling and Analysis: Theory and Applications, pp.

    287304. Elseveir Science B.V., Netherlands.

    Archer, S.H., Choate, G.M. & Rocette, G. (1983) Financial

    Management. John Wiley and Sons, Inc., New York.

    Ayyub, B.M. & Haldar, A. (1984) Project scheduling using

    fuzzy set concept. Journal of Construction Engineering and

    Management, 110, 189204.

    Chang, T.C., Ibbs, C.W. & Crandall, K.C. (1990) Network

    resource allocation with support of a fuzzy expert system.

    Journal of Construction Engineering and Management, 116,

    239259.

    Desai, V. (1997) Project Management. Himalaya Publishing

    House, Mumbai, India.

    Lorterapong, P. & Moselhi, O. (1996) Project-network analysis

    using fuzzy set theory. Journal of Construction Engineering and

    Management, 122, 308318.

    Paek, J.H., Lee, Y.W. & Ock, J.H. (1993) Pricing construction

    risk: fuzzy set application. Journal of Construction Engineering

    and Management, 119, 743756.Pilcher, R. (1994) Project Cost Control in Construction. Blackwell

    Scientific, London.

    VanHorne, J.C. (1984) Fundamentals of FinancialManagement.

    Prentice-Hall, Inc., NJ, USA.

    Zadeh, L.A. (1968) Probability measures of fuzzy events. Jour-

    nal of Mathematical Analysis and Applications, 23, 421427.

    2000 Blackwell Science Ltd, Engineering, Construction and Architectural Management 7 1, 93103