Indira Awaas Yojana. Performance Review Committee 7 th June, 2013. Salient features of IAY Guidelines. Unit assistance for construction of new house & housesite component enhanced (Cabinet decision - 10 th Dec, 2012) - PowerPoint PPT Presentation
Citation preview
Indira Awaas Yojana
Performance Review Committee7th June, 2013
Salient features of IAY Guidelines
• Unit assistance for construction of new house & housesite component enhanced (Cabinet decision - 10th Dec, 2012)
• An Empowered Committee - oversee operationalisation of new guideline • Special projects from Reserve fund to be sanctioned by EC (5% of Annual budget
for scheme retained by MoRD)
• Administrative expenses – 4% of funds released• Greater role for State in
• Allocation of district wise targets• Distributing admin cost to districts• Identifying Difficult Areas
• Habitation & Individual house approach for better coverage of target group
• IT enabled Monitoring through AwaasSoft
• Annual allocation for States/UTs based on existing formula ( 75% weight to
houselessness & 25% weight to Poverty ratio) rationalised to achieve fair category wise
distribution
• Targets for SCs, STs and Minorities made in proportion to
population of these categories in States/UT’s
• Upto 20% of district allocation can be used for upgradation
• Once SECC is finalised allocation would be based on houseless
people from BPL population for each category
Allocation
• District allocation to include two parts,– Fixed expenditure which would be same for all districts – Working expenses in proportion to the targets allotted
• Formula for distribution to intermediate & Village Panchayats in accordance to workload assigned
Distributed to districts in proportion to their targets in 2013-14.
Eligible items of expenditure• IEC material on designs & technology options• Construction of prototypes & models for demonstration• Cost of hardware/software for MIS, data entry, photographs, quality supervision &
monitoring• Training of master masons, CRPs & NGOs, Elected representatives• Honorarium to CRPs & service charges to NGOs etc.
Administrative Cost
With Nirmal Bharat Abhiyan for construction of Sanitary toilet in IAY houses
– IAY beneficiaries to be accorded priority
– State/District Water and Sanitation Mission would be agency in charge
– State Dept. in charge of MGNREGS to issue directions to GP’s on dovetailing
MGNREGS funds with NBA funds
– IAY Implementing agency to send progress reports to MoDW&S
– Last installment of IAY & NBA funds to be released only after construction of toilet
is completed
– Letter on implementation jointly issued - uploaded on websiteState/ Implementing Agency should promote convergence with other schemes
like RGGVY, RSBY,AABY etc.* Letter dated 16/5/2013
Convergence… with other schemes
• Uploading Annual selection list before release of 1st installment
• Registration of complete beneficiary details• Financial & Physical progress as reflected in AwaasSoft
would be considered for all purposes• All transaction have to be done through AwaasSoft• Use of AwaasSoft reports for monitoring • Regular uploading of photos every quarter• Follow up till completion
Use of AwaasSoft
Progress of MIS 2012-13Status of data entry as on 30.05.2013
StateAnnual Target
Central Scheme
% Houses sanctioned in MIS to MPR
Number of Houses
Sanctioned as per MPR
Registered in Mis
Consolidated At block Sanctioned
1st Installment
released
2nd
Installment released
3rd Installment released
ARUNACHAL PRADESH 8339 1819 0 0 0 0 0 0 0
ASSAM 184408 182021 136425 118204 113622 87205 16443 3174 62.42
MANIPUR 7238 1468 1820 1232 1064 0 0 0 72.48
MEGHALAYA 12608 13232 11427 9034 7932 2319 221 0 60
MIZORAM 2687 1941 2310 1290 1268 876 405 0 65.33
NAGALAND 8343 0 1180 0 0 0 0 0 0
SIKKIM 1596 1596 1746 1595 1594 0 0 0 99.87
TRIPURA 16245 0 18445 10625 7144 3708 4 4 0
Training requirements?
No. of complaints sent for action/report awaited
State 2011-12 2012-13
Assam 2 7
Tripura 1 -
Status of complaints
State Annual Target
Total Houses Sanctioned
Houses under construction
HousesCompleted
%age of targetachieved
Arunachal Pradesh
8.33 1.82 0.65 1.52 18.19
Assam 184.41 182.02 145.69 97.45 52.84
Manipur 7.24 1.47 0.95 1.87 25.86
Meghalaya 12.61 13.23 8.70 5.36 42.48
Mizoram 2.69 1.94 0..24 1.93 71.54Nagaland 8.34 0 0 0 0
Sikkim 1.60 1.60 0 1.41 88.35
Tripura 16.25 0 0 0 0
Physical Performance 2012-13 (In thousand units)
Financial Performance 2012-13
State Central Allocation
Central Release
Total Available funds
Utilization of funds
%age Utilisation
Arunachal Pradesh
3640.22 3327.41 3631.88 689.55 18.99
Assam 80494.43 57349.21 108358.37 64278.28 59.32
Manipur 3159.90 2130.81 2769.18 973.77 35.16
Meghalaya 5503.42 4894.99 5996.06 5216.19 86.99
Mizoram 1172.84 1080.27 1155.94 989.90 85.64
Nagaland 3641.79 3641.79 3641.79 0.00 0.00
Sikkim 696.50 348.25 348.25 540.45 155.15
Tripura 7090.90 6186.32 6566.70 0.00 0.00
(In lakhs of Rupees)
Common Issues • All releases will be linked to AwaasSoft entries
• Compliance of conditions imposed during release of 2nd installment, 2012-13 to
enable releases in 2013-14
• Special audit of special packages sanctioned
• Bank details of DRDAs – CPSMS registration mandatory
• Action Taken Report on complaints and NLMs report
• DRDA’s to submit information as per check list
• Performance Audit – CAG 2007-08 to 2012-13 - States should provide
necessary information & support
Arunachal Pradesh2013-14 Ist instalment – District wise targets awaited
2012-13 – 2nd installment• Proposal not received - Dibang valley, Lower Dibang valley and
Papumpare• Released during 2013-14 - East Siang, East Kumang and West
Siang• Request for 780 houses for the families of freed bonded labour
belonging to Suiling tribe in East Kameng district – needs to be sent to EC
Special PackagesS.No District Amount
(in lakhs)2007-08 DISTRICTS need to submit Utilisation
Certificate, Auditor Report and Completion Certificate
1. Chang lang 37.5002. Dibang Valley 37.5003. Lower Dibang Valley 11.3444. Lower Subansiri 18.7505. Upper Siang 37.1256. Upper Subansiri 18.7507. West Kameng 18.750
2008-098. Kurung Kurmey 37.500
2009-109. Lower Dibang Valley 18.75
S.No District 1st installment 2nd installment Documents requiredYear Amount
(in lakhs)Year Amount
(in lakhs)
1. Dibang Valley 2008-09 18.710 - - DISTRICTS need to submit Utilisation Certificate, Auditor Report
2. Kurung Kurmey 2008-09 261.954 2011-12 261.9543. Tirap 2009-10 112.715 - -4. Upper Subansiri 2009-10 34.475 - -5. Anjaw 2010-11 413.721 - -6. Lower Dibang
Valley2010-11 26.040 - -
7. Upper Subansiri 2010-11 159.105 2011-12 159.105
5% IAY
Border Package
Assam2013-14 1st instalment - under examination
2nd installment 2012-13
• Sanctions for Sonitpur, Golaghat, Darang, Kamrup (M) & Karbi Anglong
issued
• Bongaigaon is under examination
• Kamrup (Rural) – proposal not received
Special Package
• Proposal for 2nd installment under FRA - 2011-12 awaited
• Proposal for 2nd installment under 5% from Kamrup (M) and Nalbari awaited
• Request for 68,832 additional houses for beneficiaries under FRA & people
affected by erosion need to be brought to the EC for approval
Manipur2013-14 1st instalment - under examination
2012-13 – 2nd installment– Proposals not received from Chandel, Bishnupur and Thoubal
Special Package – Settlement of accounts5% IAY – 2009-10 to Senapati district – UC, AR & Completion
Certificate awaitedBorder districts – 2009-10
Chandel - UC, AR & Completion Certificate awaitedSenapati - 2nd installment not availed
Request for 1263 houses as additional target for the families of insurgency affected in Thanlon T.D block of Churachandpur district – needs to be sent to EC
Meghalaya
2013-14 Ist instalment – sanctions issued to 5 districts
2012-13 - 2nd instalment– South Garo hills – proposal not received– East Khasi Hills - under objection
Mizoram
2013-14 Ist instalment – sanctions issued to all districts
Nagaland
2013-14 Ist installment – submitted to IFD
Special Package - Settlement of accounts– 5% IAY – 2007-08 to Peren district – 5% IAY - 2008-09 to Mokokchung district
Both have not availed 2nd installment
Sikkim
• 2013-14 Ist instalment – revised district wise targets awaited • 2012-13 – 2nd installment – Not availed by all districts
Tripura 2013-14 Ist instalment – revised district wise allocation awaited2012-13 – 2nd installment• North Tripura - under objection
Special Package
• Border package - 2010-11 to North Tripura district – 2nd installment not availed
• Incentive package - 2010-11 to all 4 districts – UC, AR & Completion Certificate awaited
• Incentive package - 2011-12 to all 4 districts – Dhalai district has to submit UC,AR & Completion Certificate– Other districts have to submit proposals for 2nd instalment