Upload
tavion-hulett
View
216
Download
1
Embed Size (px)
Citation preview
Indonesia Railways Development
Directorate General Of Railways
Ministry Of Transportation
Eskisehir, Turkish / June,17th – 22nd 2013
1
1. Preface
2. Existing Railways Network
3. National Railways Masterplan
4. National Signalling Technology
5. National Rolling Stock Technology
6. Financing Scheme
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
OUTLINE
2
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
1. Preface
3
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
2. Existing Railway Network
Railway Network
Active Line Inactive Line Total
Sumatera 1,352 Km 483 Km 1,835 Km
Jawa 3,464 km 2,860 Km 6,324 Km
Banda Aceh
MEDAN
PADANG
PALEMBANG
JAMBI
BENGKULU
Nanggroe Aceh Darrussalam
Lampung
Bangka Belitung
Riau
Jambi
Bengkulu
Sumatera Selatan
Sumatera Barat
Sumatera Utara
PangkalPinang
Tanjung Pinang
Kep.RiauPEKANBARU
B. LAMPUNG
Sibolga
Tebing Tinggi
meulaboh
Bireun
Rantau Prapat
Kisaran
P. Siantar
Tarahan
PrabumulihLahat
Lb. Linggau
Simpang
Tj. Api-Api
Banda Aceh
MEDAN
PADANG
PALEMBANG
JAMBI
BENGKULU
Nanggroe Aceh Darrussalam
Lampung
Bangka Belitung
Riau
Jambi
Bengkulu
Sumatera Selatan
Sumatera Barat
Sumatera Utara
PangkalPinang
Tanjung Pinang
Kep.RiauPEKANBARU
B. LAMPUNG
Sibolga
Tebing Tinggi
meulaboh
Bireun
Rantau Prapat
Kisaran
P. Siantar
Tarahan
PrabumulihLahat
Lb. Linggau
Simpang
Tj. Api-Api
Padang Panjang
SOLOK
B. Putus
B. Tabal
Tj. Enim
Kota Padang
Passenger : 5.249 million passenger/year
Freight : 15.253 million ton/year
Passenger : 196.681 million Passenger/Year
Freight : 3.896 million Ton/Year
4
a. 12.100 Km National Railways Network on 2030 (Jawa-Bali Island, Sumatera, Kalimantan, Sulawesi and Papua) including 3.800 km urban railways network.
b. Passenger Rollingstock: 2.805 unit locomotive, 27.960 unit passenger coachs.c. Freight Trains Rollingstock: 1.995 unit locomotive and 39.655 unit freight wagons.
Railway share 11-13% for passenger and 15-17% for freight transport 10,000 km of railway network, double-track, electrification of Java main
lines Trans Sumatra railways network as backbone of mass transportation in cities/urban areas
the operation of Argo Cahaya (High Speed Train/ HST) in Java railways as the backbone of freight transport in Kalimantan, Sulawesi,
Papua integrated, secured, safe, comfortable, reliable, and affordable of
services
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
3. National Railway Vision On 2030 (National Railway Masterplan)
5
CPO[KEK]CPO
[KEK]
Rubber & CPO
Industry[KEK]
Rubber & CPO
Industry[KEK]
Oil, Gas and Coal Industry
[KEK]
Oil, Gas and Coal Industry
[KEK]
Target in 2030:• Developing intercity railways
network: Aceh, Medan, Pekanbaru, Padang, Jambi, Palembang, Bandar Lampung.
• Developing urban railways network: Medan, Pekanbaru, Padang, Palembang, Bandar Lampung and Batam.
• Developing access to airport: Kualanamu, Minangkabau, Sultan Mahmud Badarudin Dua and Hang Nadim.
• Developing access to seaport: Lhokseumawe, Belawan, Dumai, Tanjung Api-api, Dumai, Teluk Bayur and Panjang.
Sumatera Rail Network plan in 2030 to be 2,856 Km
FUTURE RAIL NETWORKFUTURE RAIL NETWORK
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
1. SUMATERA ISLAND
6
Batam Industry
Area
Target in 2030:• Rail Network connecting
central indutry area and airport and seaport.
• Developing airport train (Hang Nadim Airport)
Batam Island Rail Network Plan in 2030 to be 44 Km
CONT’D...CONT’D...2. BATAM ISLAND
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013 7
Steel and Petrochemical Industry
Petro Chemical Industry
Food Industry
Shipyard Industry (The Biggest in Indonesia)
Jakarta Metropolita
nSurabaya
Metropolitan
Target in 2030:
1. Optimization of existing railway network;
2. Double tracking of North Java line (Jakarta – Cirebon – Semarang – Bojonegoro - Surabaya) and South Java line (Cirebon – Kroya – Jogjakarta – Solo – Madiun – Surabaya ) and other main lines;
3. Electrification in the dense lines, including urban area;
4. High speed train network connecting: Merak, Jakarta, Cirebon, Semarang, Surabaya and Banyuwangi;
5. Urban railways network in Jabodetabek, Bandung, Yogya, Semarang, Surabaya and other cities;
6. Seaport railway network: Tanjung Priok, Cirebon, Bojonegaro, Tanjung Mas and Tanjung Perak;
7. Airport railway network: Soekarno-Hatta, Kertajati, Adi Sucipto, Ahmad Yani, Adi Sumarmo and Juanda.
Java Rail Network Plan in 2030 to be 6,324 Km
HST Track Lines (planned)
CONT’D...CONT’D...3. JAVA ISLAND
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013 8
Bali Tourism
Area
Target in 2030 :
• Rail network connecting central economic activity and tourism area, such as: Denpasar, Tabanan, Gianyar, Singaraja, Negara, Bangli and Amlapura;
• Urban railway network (Denpasar);
• Developing airport train (Ngurah Rai);
Bali Island Rail Network Plan in 2030 to be 326 Km
4. Bali Island4. Bali Island
CONT’D...CONT’D...
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013 9
Coal Industry Area
Coal Industry Area
Steel Industry Area
Steel Industry Area
Aluminum Industry
Area
Aluminum Industry
Area
Oil & Gas Industry
Area
Oil & Gas Industry
Area
Target in 2030: • Developing intercity railways
network: Banjarmasin-Balikpapan-Samarinda-Bontang-Tenggarong-Kotabangun, Banjarmasin-Palangkaraya, Pontianak-Mempawah-Singkawang;
• Developing railways network from mining area to seaport: Samarinda, Balikpapan and Banjarmasin;
• Railways network with coal potency: Puruk Cahu – Bangkuang, Bangkuang – Lupak Dalam, Kudangan – Kumai, Muara Wahau – Lubuk Tutung, Bontang – Sangkulirang – Tanjung Redep, Tanjung Barabai – Martapura – Banjarmasin, Tanjung – Buntok – Muara Teweh.
Kalimantan Rail Network Plan in 2030 to be 1,400 Km
Rencana Jalur KA KhususSpecial Railway (Planned)
CONT’D...CONT’D...5. KALIMANTAN ISLAND
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013 10
Rencana Kebutuhan Sarana Tahun 2030 :
• Lokomotif Penumpang : 50 unit
• Lokomotif Barang : 120 unit
• Kereta : 470 unit
• Gerbong : 2.375 unit
Fisheries and Marine
Tourism Area
Fisheries and Marine
Tourism Area
LNG Industry Area
LNG Industry Area
Nickel Industry
Area
Nickel Industry
Area
MakassarMetropolitan
MakassarMetropolitan
Plantation Industry Area
Plantation Industry Area Target in 2030:
• Developing intercity railways network: Gorontalo, Manado, Bitung (North Sulawesi) also Pare-pare, Makasar, Bulukumba and Takalar (South Sulawesi);
• Developing regional railway network: Makasar, Maros, Sungguminasa and Takalar (Maminasata);
• Developing urban railways network: Makasar and Manado;
• Hasanudin airport railways;
• Developing access to seaport: Bitung and Makasar.
Sulawesi Rail Network Plan in 2030 to be 500 Km
CONT’D...CONT’D...6. SULAWESI ISLAND
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013 11
Target in 2030:• Developing intercity
railways network: Sorong, Manokwari, Nabire, Timika, Sarmi and Jayapura;
• Developing railways network from mining area: to the Manokwari and Jayapura seaports;
• Developing railways network: in Northern Papua connecting cities: Manokwari-Nabire.
Papua Rail Network Plan in 2030 along 500 Km
Oil & GasIndustryOil & GasIndustry
Mining IndustryMining
Industry
Fisheries IndustryFisheries Industry
CONT’D...CONT’D...7. PAPUA ISLAND
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013 12
4. National Rollingstock Technology
Description Number Of Unit Total(unit)Java Island Sumatera Island
A. Locomotive 410
1. Steam Locomotive 3 1
2. Diesel Electric Locomotive 172 120
3. Hydrolic Diesel Locomotive 68 46
B. Rail Cars 2.332
1. Diesel Rail Cars 38 3
2. Diesel Hydrolic Rail Cars 67 18
3. Electric Rail Cars 584 0
C. Passenger Cars (Coach, Coach+Generator, Coach+Dining+Generator)
1.473 149 1.622
D. Wagon 4.097
1. Flat Wagon 507 175
2. Open Wagon 277 1.751
3. Covered Wagon 249 171
4. Tank Wagon 296 511
5. Bagage Cars (Bagage , Bagage+Generator) 155 5
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
A. Avaibility of National Rollingstock
13
Type: CC 300Manufacture: PT. INKASystem: Diesel HydraulicDouble Cabin
Weight & CapacityFuel : Diesel (v: 3000 litre)Net Weight: 87,50 Ton
Main ComponentMain Engine : CAT 3512 (1700 Kw/ 2280 HP)Transmission : VOITH L620 re U2Breaking System : WABTECGenset Type : CAT C15 (410 KVA)
PerformanceMax. Speed: 120 Km/Hour
DimensionTrack gauge : 1067 mmCarbody Length : 19000 mmCarbody Width : 2790 mmDiameters Wheels : 914
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
.... Cont’d
B. National Locomotive Product
14
1. Axle Load : 14 Tons2. Tare Weight, Approximately Trailer Car : 32 Tons Motor Car : 39 Tons3. Bogie Wheel Balance : 2,200 mm4. Wheel Diameter : 860 mm5. Maximum Speed : 100 km/hrs6. Power Supply : 1,500 Volt (DC)7. Starting Acceleration : 0,8 m / s28. Braking Deceleration : 0,8 m / s29. Emergency Braking : 1,0 m / s210. Passenger Capacity Trailer Car : 54 Seating Motor Car : 64 Seating11. Configuration of Train Set : TC1 + M1 + M2 + TC212. Car Body : Stainless Steel with Air Condition13. Propulsion System : VVVF Inverter with IGBT14. Bogie : Bolsterless15. Brake System : Electro pneumatic Blending System16. Coupler : Tight lock coupler and bar coupler
.... Cont’d
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
C. National Electric Rail Cars Product
15
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
.... Cont’d
D. National Diesel Rail Cars Product
16
5. Train Simulator Facility
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
Number of unit : 2 (two)(GE U20EMP Locomotive series & KRDi-INKA series)
Location:Railway Engineering Training Center / BPTP-BekasiWest Java, Indonesia
Software vendor:Orca Railway System
Feature:•Geospesifi Track (Maximum length 200 Km)•Scoring system (based on: time travel, fuel consumption & number of violation)•4 (four) LCD screen ( 42 Inch ; Res. 1280x800)•Alert system (wheel friction, brake etc)•4 unit CCTV (to monitor the trainees)•2 Type scenario (Fixed & Costumized)
17
..... Cont’d
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
A. Simulator of Locomotive
B. Simulator of Diesel Rail Cars
Exterior Driver Cabin Driver Cabin
Exterior Exterior Driver Cabin
18
Signalling System On Indonesia
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
Island
Electric Interlocking
Number of Unit SSI VPI Westrace Ansaldo SIL02
EMI/DRS60/
MIS801/NXJAWA 205 43 74 58 12 8 10
SUMATERA 9 0 0 0 0 7 1
Island
Mechanic Interlocking
Number of unit
S&H With Block EMI S&H Without
Block
Alkmaar/Krian/High Handle /Without
HandleJAWA 188 175 3 0 9
SUMATERA 140 106 0 25 9
A. Electric Interlocking System
B. Mechanic Interlocking System
19
TBI Block Equiptment Mechanic Interlocking System
Local Control Panel Electric InterlockingSystem
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
.... Cont’d
20
Total estimated investment USD 60 Billion(30 % government and 70 % private)
Ministry of Transportation – Directorate General of Railways Eskisehir, Turkish / June,17th – 22nd 2013
6. Financing Scheme
21
DIR
ECTO
RATE
GEN
ERAL
OF
RAIL
WAY
S - M
OT
THANK YOU
Directorate General of Railways - MOTMedan Merdeka Barat No.8 Jakartahttp://perkeretaapian.dephub.go.id