INDIANA DEPARTMENT OF TRANSPORTATION ____________ STANDARD SPECIFICATIONS 2020

INDOT 2020 Standard Specifications - in.gov INDOT... · 0.764 6 2.359 7 cubic millimeter cubic meter cubic meter cubic meter cubic meter mm3 m3 m3 m3 m3 (*) Conversion from SI unit

  • Upload
    others

  • View
    19

  • Download
    0

Embed Size (px)

Citation preview

  • INDIANA

    DEPARTMENT OF

    TRANSPORTATION ____________

    STANDARD

    SPECIFICATIONS

    2020

  • ERIC HOLCOMB GOVERNOR

    INDIANA DEPARTMENT OF TRANSPORTATION

    Joe McGuinness

    COMMISSIONER

    STANDARDS COMMITTEE

    CHAIRMAN

    John Leckie, Construction and Materials Management Director

    MEMBERS

    Matt Beeson, Materials Management

    Michael Beuchel, Contract Administration

    David Boruff, Traffic Engineering

    Kumar Dave, Pavement Engineering

    Louis Feagans, Statewide Technical Services

    Michael Koch, Fort Wayne District Construction

    Mark Orton, Bridge Standards and Policy

    Greg Pankow, State Construction Engineer

    Kurt Pelz, Construction Technical Support

    Elena Veksler, Highway Design and Technical Support

    SECRETARY

    Scott Trammell, Construction Specifications Engineer

    Lana Podorvanova, Specifications Coordinator

  • iii

    MEASUREMENTS The first two paragraphs of 109.01, Measurement of Quantities reads as follows: (a) General Requirements All measurements of work completed under the contract will be according to the English System unless otherwise specified. The standard measures shown in this publication are primarily in the English System of Units such as feet and inches, pounds, gallons, and acres. Any metric equivalents, shown in parentheses, are intended only for those contracts in which they are specified, or to maintain consistency with industry standards. No guarantee is provided, explicit or implicit, that the units are accurate conversions. The following table and general notes are provided to assist you in becoming familiar with the metric system.

  • iv

    SI UNITS AND CONVERSION FACTORS

    MEASUREMENT ENGLISH UNIT ENGLISH

    UNIT SYMBOL

    MULTIPLIER FOR CONVERSION FROM ENGLISH UNIT TO

    SI UNIT (*) SI UNIT SI SYMBOL

    Acceleration foot per second squared mile per hour squared

    ft/sec2 mi/h2

    0.304 8 exactly 1.060 93

    meter per second squared kilometer per hour squared

    m/s2 km/h2

    Area square inch square foot square yard acre square mile

    in2 ft2 yd2 ac mi2

    645.16 exactly 0.092 9 0.836 1 0.404 7

    2.59

    square millimeter square meter square meter hectare square kilometer

    mm2 m2 m2 ha km2

    Density pound per cubic foot lb/ft3 16.018 46 kilogram per cubic meter kg/m3 Energy foot·pound force

    kilowatt hour ft lbf kW h

    1.355 8 3 600 000. exactly

    joule joule

    J J

    Force/Weight (Gravity of Force)

    pound force kilopound force ton

    lbf kip t

    4.448 2 4.448 2 8.896 4

    newton kilonewton kilonewton

    N kN kN

    Length inch foot yard mile

    in. ft yd mi

    25.4 exactly 0.304 8 exactly 0.914 4 exactly

    1.609 3

    millimeter meter meter kilometer

    mm m m km

    Mass ounce pound mass ton mass

    oz lbm t

    28.349 5 0.453 6 0.907 2

    gram kilogram megagram

    g kg Mg

    Power horsepower (550 ft·lbf/s) hp 745.669 9 watt W Pressure/Stress pound per square inch

    pound per square foot kilopound per square inch

    lb/in2 lb/ft2 kip/in2

    6.894 8 0.047 88

    6.894 8

    kilopascal kilopascal megapascal

    kPa kPa MPa

    Speed/Velocity foot per second mile per hour

    ft/s mi/h

    0.304 8 exactly 1.609 3

    meter per second kilometer per hour

    m/s km/h

  • v

    Temperature degree Fahrenheit °F (°F -32)/1.8(**) exactly degree Celsius °C Volume, Fluid cubic inch

    fluid ounce gallon 1000 gallons

    in3 fl oz gal. kGAL.

    16.387 1 29.573 4

    3.785 4 3.785 4

    milliliter milliliter liter kiloliter

    mL mL L kL

    Volume, Solid cubic inch cubic foot bushel cubic yard 1000 feet board measure

    in3 ft3 bu yd3 MFBM

    16.387.06 exactly 0.028 32 0.035 24

    0.764 6 2.359 7

    cubic millimeter cubic meter cubic meter cubic meter cubic meter

    mm3 m3 m3 m3 m3

    (*) Conversion from SI unit to English unit may be made by dividing the SI unit by the conversion factor shown in this column. (**) This is a formula, and not a multiplier. The Fahrenheit temperature is substituted for °F in the formula to attain the Celsius temperature. Conversion from Celsius

    temperature to Fahrenheit temperature may be made by substituting the Celsius temperature for °C in the formula (1.8 x °C) +32. This is an exact conversion. Angles will continue to be measured in degrees, minutes, and seconds instead of radians.

  • vi

    GENERAL NOTES 1. The SI unit of millimeter should be used to convert inches to millimeters. 2. The SI unit of Mass is the Kilogram (Kg) which should be used for smaller

    masses expressed in pounds. The megagram (Mg) should be used for larger masses expressed in tons.

    3. All units peculiar to the various cgs systems (measurement systems constructed

    by using the centimeter, gram and second as base units) are to be avoided. 4. In commercial and everyday use, the term weight nearly always means mass;

    thus, when one speaks of a person’s weight, the quantity referred to is mass. In Science and Technology, the term weight of a body has usually meant the force that, if applied to the body, would give it an acceleration equal to the local acceleration of free fall g (acceleration of gravity). When the term is used, it is important to know whether mass or force is intended and to use SI Units properly, by using Kilograms for Mass or Newtons for Force. The use of force of gravity (mass times acceleration of gravity) instead of weight with this meaning is recommended. Because of the dual use of the term weight as a quantity, this term should be avoided in technical practice except under circumstances in which its meaning is completely clear.

    5. The term load means either mass or force, depending on its use. A load that

    produces a vertically downward force because of the influence of gravity acting on a mass may be expressed in mass units. Any other load is expressed in force units.

    6. A quantity stated as limits, such as “not more than” or “maximum”, must be

    handled so that the stated limit is not violated. 7. Conversion of quantities should be handled with careful regard to the implied

    correspondence between the accuracy of the data and the given number of digits. In all conversions, the number of significant digits retained should be such that accuracy is neither sacrificed nor exaggerated. For example, a length of 125 ft converts exactly to 38.1 m. If however, the 125 ft length has been obtained by rounding to the nearest 5 ft, the conversion should be given as 38 m. The proper conversion procedure is to multiply a value by a conversion factor that is more accurate than is required, the result is then rounded to the appropriate number of significant digits.

    8. For calculation of results, avoid rounding of intermediate quantities. For

    reporting results, the rule for addition and subtraction is that the answer shall contain no significant digits farther to the right than occur in the least precise number. The rule for multiplication and division is that the product or quotient

  • vii

    shall contain no more significant digits than are contained in the number with the fewest significant digits used in the multiplication.

    9. When a figure is to be rounded to fewer digits than the total number available,

    the standard “5” up procedures should be used as follows: (a) When the first digit discarded is less than 5, the last digit retained

    should not be changed. For example, 3.46325, if rounded to three digits, would be 3.463; if rounded to two digits, would be 3.46.

    (b) When the first digit discarded is 5 or greater, the last digit retained

    should be increased by one unit. For example, 8.37652, if rounded to three digits, would be 8.377; if rounded to two digits would be 8.38.

    10. Refer to ASTM SI 10 American National Standard for Use of the International

    System of Units (SI) for other conversion factors. 11. This specification book uses the word “shall” to describe the Contractor’s

    responsibilities. The word “will” is used to describe the Department’s responsibilities. The words “shall” and “will” are not required to be followed by the words “by the Contractor” or “by the Department” to retain these meanings.

  • TABLE OF CONTENTS

    Section Title Page

    viii

    DIVISION 100 – GENERAL PROVISIONS

    SECTION 101 – DEFINITIONS AND TERMS .................................................... 1 101.01 Abbreviations ........................................................................................... 1 101.02 Above Normal Inclement Weather Days ................................................. 4 101.03 Blank ........................................................................................................ 4 101.04 Bid Bond .................................................................................................. 4 101.05 Bidder ...................................................................................................... 4 101.06 Bridge ...................................................................................................... 4

    (a) Length ..................................................................................................... 4 (b) Roadway Width ...................................................................................... 5

    101.07 Business Day ........................................................................................... 5 101.08 Calendar Day ........................................................................................... 5 101.09 Change Order ........................................................................................... 5 101.10 Construction Limits ................................................................................. 5 101.11 Contract ................................................................................................... 5 101.12 Contract Information Book ...................................................................... 5 101.13 Contract Item (Pay Item) ......................................................................... 5 101.14 Contract Time .......................................................................................... 5 101.15 Contractor ................................................................................................ 6 101.16 Culvert ..................................................................................................... 6 101.17 Commissioner .......................................................................................... 6 101.18 Department .............................................................................................. 6 101.19 Embankment Foundation ......................................................................... 6 101.20 Engineer ................................................................................................... 6 101.21 Equipment ................................................................................................ 6 101.22 Extra Work .............................................................................................. 6 101.23 Failed Material ......................................................................................... 6 101.24 Force Account Work ................................................................................ 6 101.25 Frequency Manual ................................................................................... 7 101.26 Holidays ................................................................................................... 7 101.27 Invitation for Bids .................................................................................... 7 101.28 Itemized Proposal .................................................................................... 7 101.29 Laboratory ............................................................................................... 7 101.30 Major and Minor Contract Items ............................................................. 7 101.31 Materials .................................................................................................. 8 101.32 Notice to Proceed ..................................................................................... 8 101.33 Open to Unrestricted Traffic .................................................................... 8 101.34 Pavement Structure .................................................................................. 8 101.35 Performance Bond ................................................................................... 8 101.36 Plans ........................................................................................................ 8 101.37 Professional Engineer .............................................................................. 8

  • TABLE OF CONTENTS

    Section Title Page

    ix

    101.38 Profile Grade ............................................................................................ 8 101.39 Project ...................................................................................................... 8 101.40 Proposal ................................................................................................... 9 101.41 Proposal Book .......................................................................................... 9 101.42 Quality Assurances Adjustments ............................................................. 9 101.43 Reasonably Close Conformance .............................................................. 9 101.44 Recurring Special Provisions ................................................................... 9 101.45 Right-of-Way ........................................................................................... 9 101.46 Road ......................................................................................................... 9 101.47 Roadbed ................................................................................................... 9 101.48 Roadside ................................................................................................ 10 101.49 Roadside Development .......................................................................... 10 101.50 Roadway ................................................................................................ 10 101.51 Schedule of Pay Items ........................................................................... 10 101.52 Shoulder ................................................................................................. 10 101.53 Sidewalk ................................................................................................ 10 101.54 Special Provisions .................................................................................. 10 101.55 Specifications ......................................................................................... 10 101.56 Specified Completion Date .................................................................... 10 101.57 State ....................................................................................................... 10 101.58 Street ...................................................................................................... 10 101.59 Structures ............................................................................................... 11 101.60 Substantial Completion .......................................................................... 11 101.61 Subcontractor ......................................................................................... 11 101.62 Subgrade ................................................................................................ 11 101.63 Substructure ........................................................................................... 11 101.64 Superintendent ....................................................................................... 11 101.65 Superstructure ........................................................................................ 11 101.66 Surety ..................................................................................................... 11 101.67 Technician or Inspector ......................................................................... 11 101.68 Titles (Headings) ................................................................................... 12 101.69 Township, Town, City ........................................................................... 12 101.70 Traveled Way ........................................................................................ 12 101.71 Unique Special Provisions ..................................................................... 12 101.72 Work ...................................................................................................... 12 101.73 Work Day .............................................................................................. 12 101.74 Working Drawings................................................................................. 12

    SECTION 102 – BIDDING REQUIREMENTS AND CONDITIONS .............. 13 102.01 Prequalification and Bidding ................................................................. 13 102.02 Certification Regarding Lobbying for Contracts, Grants,

    Loans, and Cooperative Agreements ..................................................... 13

  • TABLE OF CONTENTS

    Section Title Page

    x

    SECTION 103 – AWARD AND EXECUTION OF CONTRACT ..................... 13 103.01 Disadvantaged Business Enterprise Program ........................................ 13

    (a) General Requirements ........................................................................... 13 (b) Definitions ............................................................................................ 14 (c) Goal ....................................................................................................... 15 (d) Affirmative Actions .............................................................................. 17 (e) Determination of Good Faith Efforts .................................................... 18 (f) Affirmative Action Certification ........................................................... 22 (g) Subcontracts .......................................................................................... 23 (h) Leases and Rentals ................................................................................ 23 (i) Records and Reports .............................................................................. 24

    103.02 Specific Equal Employment Opportunity Responsibilities .................... 25 103.02.1 Record Keeping .................................................................................. 25 103.03 Blank ...................................................................................................... 25 103.04 Insurance ................................................................................................ 25

    (a) Worker’s Compensation and Employer’s Liability ............................... 26 (b) Commercial General Liability .............................................................. 26 (c) Business Automobile Liability .............................................................. 27 (d) Railroad’s Protective Liability .............................................................. 27 (e) Owner’s and Contractor’s Protective Liability Insurance

    Coverage for Operations of Designated Contractor .............................. 27 (f) Basis of Payment ................................................................................... 28

    103.05 Waiver of Damages ............................................................................... 28 103.06 Wage and Labor Requirements .............................................................. 28

    (a) Non-discrimination of Employees ........................................................ 28 (b) Affidavits and Payrolls ......................................................................... 29 (c) Wage Stipulations ................................................................................. 29

    103.07 Accident Prevention and Safety ............................................................. 30 SECTION 104 – SCOPE OF WORK .................................................................... 30

    104.01 Intent of Contract ................................................................................... 30 104.02 Changed Conditions............................................................................... 31

    (a) Differing Site Conditions ...................................................................... 31 (b) Suspensions of Work Ordered by the Engineer .................................... 32 (c) Significant Changes in the Character of Work ...................................... 33 (d) Pre-established Remedies to Changed Conditions ................................ 33

    104.03 Extra Work ............................................................................................ 36 104.04 Maintenance of Traffic .......................................................................... 36

    (a) Special Detours ..................................................................................... 37 (b) Maintenance Directed by the Engineer ................................................. 37 (c) Blank ..................................................................................................... 38 (d) Traffic Control for Patching on a Two-Lane Roadway ........................ 38

    104.05 Removal and Disposal of Structures and Obstructions .......................... 38 104.06 Removal and Disposal of Regulated Materials ...................................... 39

  • TABLE OF CONTENTS

    Section Title Page

    xi

    (a) For Such Materials which are Identified in the Proposal Book as Being Present on the Project Site ............................................ 40

    (b) For Such Materials which are not Identified in the Proposal Book as Being Present on the Project Site ............................................ 40

    104.07 Rights in and Use of Materials Found in the Project Site ...................... 43 104.08 Final Clean-Up ...................................................................................... 43

    SECTION 105 – CONTROL OF WORK ............................................................. 44 105.01 Authority of the Engineer ...................................................................... 44 105.02 Plans and Working Drawings ................................................................ 44 105.03 Conformance with Plans and Specifications .......................................... 45 105.04 Coordination of Plans, Standard Specifications, and Special

    Provisions .............................................................................................. 46 105.05 Cooperation by Contractor .................................................................... 47 105.06 Cooperation with Utilities ...................................................................... 47 105.07 Cooperation Between Contractors ......................................................... 48 105.08 Construction Stakes, Lines, and Grades ................................................ 48

    (a) Construction Engineering by the State .................................................. 48 (b) Construction Engineering by the Contractor ......................................... 49 (c) Production Staking by the Contractor ................................................... 52

    105.09 Duties of Technician and Inspector ....................................................... 53 105.10 Inspection of Work ................................................................................ 53 105.11 Removal of Unacceptable and Unauthorized Work .............................. 54 105.12 Load Restrictions ................................................................................... 54 105.13 Maintenance During Construction ......................................................... 55 105.14 Failure to Maintain Roadway, Structures, Barricades, and

    Construction Signs ................................................................................. 55 105.15 Acceptance and Final Inspection ........................................................... 56

    (a) Partial Acceptance ................................................................................. 56 (b) Final Acceptance................................................................................... 56

    105.16 Notice of Changed Conditions and Claims ............................................ 57 (a) Contractual Notice of a Changed Condition ......................................... 57 (b) Claims ................................................................................................... 57 (c) Claim Resolution Process ..................................................................... 59

    SECTION 106 – CONTROL OF MATERIAL .................................................... 62 106.01 Source of Supply and Quality Requirements ......................................... 62

    (a) Approved or Prequalified Materials ...................................................... 62 (b) Material Records ................................................................................... 63 (c) Buy America Requirement .................................................................... 64

    106.02 Samples, Tests, Cited Specifications ..................................................... 64 106.03 Plant Inspection ..................................................................................... 65 106.04 Blank ...................................................................................................... 66 106.05 Storage of Materials ............................................................................... 66

  • TABLE OF CONTENTS

    Section Title Page

    xii

    106.06 Handling of Materials ............................................................................ 66 106.07 Unacceptable Materials ......................................................................... 66 106.08 Hazard Communication Program .......................................................... 66 106.09 Department Furnished Materials ........................................................... 67 106.10 Proportioning Materials ......................................................................... 67 106.11 Sample Asbestos Exclusion Letter ........................................................ 67

    SECTION 107 – LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC ........................................................................................................... 67

    107.01 Laws to be Observed ............................................................................. 67 107.02 Permits, Licenses, and Taxes ................................................................. 69 107.03 Patented Devices, Materials, and Processes .......................................... 69 107.04 Restoration of Surfaces Opened by Permit ............................................ 70 107.05 Federal Aid Provisions .......................................................................... 70 107.06 Equal Employment Opportunity Trainees ............................................. 70 107.07 Sanitary Conditions Requirements ........................................................ 72 107.08 Public Convenience and Safety ............................................................. 72

    (a) Worker Safety ....................................................................................... 72 (b) Dust and Air Pollution .......................................................................... 73 (c) Protection to Traffic .............................................................................. 73 (d) Notice to Local Public Officials ........................................................... 73 (e) Convenience to Traffic and Property Owners ....................................... 74

    107.09 Railroad-Highway Requirements .......................................................... 74 (a) Protection of Track Ballast .................................................................... 75 (b) Hold Harmless Clause .......................................................................... 75

    107.10 Archaeological Artifacts ........................................................................ 75 107.11 Bridges over Navigable Waters ............................................................. 76 107.12 Traffic Control Devices ......................................................................... 76 107.13 Use of Explosives .................................................................................. 77 107.14 Protection and Restoration of Property and Landscape ......................... 78 107.15 Erosion Control Plan and Proof of Publication ...................................... 79 107.16 Forest Protection .................................................................................... 79 107.17 Responsibility for Damage Claims ........................................................ 79 107.18 Opening Sections of Project to Traffic .................................................. 80 107.19 Contractor’s Responsibility for Work .................................................... 81 107.20 Contractor’s Responsibility for Utility Property and

    Services ................................................................................................. 82 107.21 Furnishing Right-of-Way ....................................................................... 83 107.22 Personal Liability of Public Officials .................................................... 83 107.23 Waiver of Legal Rights .......................................................................... 83 107.24 Governing Law ...................................................................................... 84 107.25 Severability ............................................................................................ 84

  • TABLE OF CONTENTS

    Section Title Page

    xiii

    SECTION 108 – PROSECUTION AND PROGRESS ........................................ 84 108.01 Subletting of Contract ............................................................................ 84 108.02 Release of Retainage to Subcontractors ................................................. 85 108.03 Notice to Proceed ................................................................................... 85 108.04 Prosecution of the Work ........................................................................ 85 108.05 Pre-phase Site Construction Meetings ................................................... 88 108.06 Limitation of Operations ........................................................................ 88 108.07 Character of Workers, Methods, and Equipment ................................... 88 108.08 Determination and Extension of Contract Time .................................... 90

    (a) Excusable, Non-Compensable Delays .................................................. 94 (b) Excusable, Compensable Delays .......................................................... 95 (c) Non-Excusable Delays .......................................................................... 96 (d) Concurrent Delays ................................................................................ 96

    108.09 Failure to Complete on Time ................................................................. 96 108.10 Default and Termination of Contract ..................................................... 97 108.11 Termination of Contractor’s Responsibility .......................................... 98 108.12 Contract Documentation ........................................................................ 99

    SECTION 109 – MEASUREMENT AND PAYMENT ....................................... 99 109.01 Measurement of Quantities .................................................................... 99

    (a) General Requirements ........................................................................... 99 (b) Scales and Measurement by Weight (Mass) ........................................101 (c) Measurement by Volume .....................................................................102 (d) Measurement of Asphalt Materials ......................................................103 (e) Measurement of PCC ...........................................................................103 (f) Measurement of Aggregates .................................................................104 (g) Measurement of Timber or Lumber .....................................................105 (h) Rental of Equipment ............................................................................105 (i) Manufactured Materials ........................................................................105

    109.02 Scope of Payment .................................................................................105 109.03 Compensation for Altered Quantities ...................................................106 109.04 Cost Reduction Incentive, CRI .............................................................106

    (a) CRI Initial Requirements .....................................................................107 (b) CRI Formal Proposal Requirements ....................................................108 (c) Approval of Formal CRI Proposal .......................................................110 (d) Payment for Design of Formal Proposal, if Rejected...........................111 (e) Other Conditions ..................................................................................111 (f) Time Savings Proposals .......................................................................112 (g) Adjustments to Contract Time .............................................................112 (h) Method of Measurement ......................................................................112 (i) Basis of Payment ..................................................................................112

    109.05 Payment for Extra Work .......................................................................114 (a) Agreed Price .........................................................................................114 (b) Force Account ......................................................................................114

  • TABLE OF CONTENTS

    Section Title Page

    xiv

    109.05.1 Quality Adjustments ..........................................................................117 (a) HMA ....................................................................................................117 (b) PCCP ...................................................................................................117 (c) Temporary Traffic Control Devices, TTCD .........................................117 (d) Failed Materials, FM ............................................................................118 (e) Pavement Traffic Markings, PTM .......................................................118 (f) Stormwater Management ......................................................................118

    109.05.2 Delay Costs ........................................................................................118 (a) Allowable Delay Costs .........................................................................118 (b) Blank ....................................................................................................120

    109.05.3 PG Asphalt Binder Material Cost Adjustments .................................120 109.06 Eliminated Pay Items ............................................................................122 109.07 Partial Payments ...................................................................................122 109.08 Final Payment .......................................................................................123

    SECTION 110 – MOBILIZATION AND DEMOBILIZATION ......................123 110.01 Description ............................................................................................123 110.02 Limitations ............................................................................................123 110.03 Method of Measurement .......................................................................124 110.04 Basis of Payment ..................................................................................124

    SECTION 111 – STOCKPILED MATERIALS .................................................124 111.01 Description ............................................................................................124 111.02 General Requirements ..........................................................................124 111.03 Structural Steel and Concrete Structural Members ...............................125

    (a) Delivered to the Job Site ......................................................................125 (b) Acceptably Stored at the Fabricator’s or Manufacturer’s

    Storage Facilities ..................................................................................125 111.04 Dowel Bar Assemblies .........................................................................125 111.05 Granular Base, Subbase Materials, and Aggregates for

    HMA and Concrete Pavements ............................................................125 111.06 Bridge Expansion Joints .......................................................................126

    (a) Type SS ................................................................................................126 (b) Type M.................................................................................................126

    111.07 Structural Supports for Signals, Signs, and Luminaires .......................126 111.08 Precast Concrete Median Barrier ..........................................................126 111.09 Concrete Face Panels and Ground Reinforcement for MSE

    Walls .....................................................................................................126 111.10 Additional Requirements ......................................................................127 111.11 Method of Measurement .......................................................................127 111.12 Basis of Payment ..................................................................................127

  • TABLE OF CONTENTS

    Section Title Page

    xv

    SECTION 112 – BLANK SECTION 113 – PARTNERING OVERHEAD ..................................................128

    113.01 Description ............................................................................................128 113.02 Requirements ........................................................................................128

    (a) Meeting Room .....................................................................................128 (b) Meeting Length ....................................................................................128 (c) Facilitator .............................................................................................128

    113.03 Method of Measurement .......................................................................129 113.04 Basis of Payment ..................................................................................129

    DIVISION 200 – EARTHWORK

    SECTION 201 – CLEARING AND GRUBBING ...............................................131 201.01 Description ............................................................................................131 201.02 General .................................................................................................131 201.03 Clearing and Grubbing .........................................................................131 201.04 Scalping ................................................................................................132 201.05 Hedge Removal ....................................................................................132 201.06 Method of Measurement .......................................................................132

    (a) Area Basis ............................................................................................132 (b) Lump Sum Basis ..................................................................................132 (c) Individual Unit Basis ...........................................................................132

    201.07 Basis of Payment ..................................................................................133 (a) Area Basis ............................................................................................133 (b) Lump Sum Basis ..................................................................................133 (c) Individual Unit Basis ...........................................................................133 (d) Clearing Right-of-Way ........................................................................134 (e) Exclusions ............................................................................................134

    SECTION 202 – REMOVAL OF STRUCTURES AND OBSTRUCTIONS .................................................................................................134

    202.01 Description ............................................................................................134 202.02 General Requirements ..........................................................................134

    (a) Type Y Waste ......................................................................................136 (b) Type Z Waste .......................................................................................136

    202.03 Removal of Bridges, Culverts, and Other Drainage Structures ..............................................................................................136

    (a) Complete ..............................................................................................136 (b) Portions ................................................................................................137 (c) Disposal of Concrete ............................................................................138

    202.04 Removal of Pipe and Tile Drains ..........................................................138

  • TABLE OF CONTENTS

    Section Title Page

    xvi

    202.05 Removal of PCCP, Sidewalks, Curbs, RCBA, and Reinforced Concrete Moment Slabs .....................................................138

    202.06 Removal of Houses and Buildings ........................................................139 202.07 Inspection and Removal of Asbestos ....................................................140 202.08 Removal of Underground Storage Tanks Containing

    Petroleum Products or Other Hazardous Chemicals .............................140 (a) Type A Waste ......................................................................................143 (b) Type B Waste ......................................................................................143 (c) Type C Waste .......................................................................................143

    202.09 Remediation of Contaminated Soil and Groundwater ..........................143 202.10 Remediation of Other Regulated Materials ..........................................144 202.11 Transportation and Disposal of Regulated Materials ............................144 202.12 Blank .....................................................................................................145 202.13 Method of Measurement .......................................................................145 202.14 Basis of Payment ..................................................................................145

    SECTION 203 – EXCAVATION AND EMBANKMENT .................................150 203.01 Description ............................................................................................150 203.02 Common Excavation ............................................................................151 203.03 Rock Excavation ...................................................................................151 203.04 Unclassified Excavation .......................................................................151 203.05 Peat Excavation ....................................................................................151 203.06 Waterway Excavation ...........................................................................151 203.07 Class Y Excavation ...............................................................................151 203.08 Borrow or Disposal ...............................................................................152

    (a) Borrow and Disposal Site Requirements .............................................152 (b) Additional Requirements .....................................................................156

    203.08.1 Linear Grading ...................................................................................157 203.08.2 Coal Ash ............................................................................................157 203.09 General Requirements ..........................................................................158 203.10 Disposal of Excavated Material except Waterway and Peat

    Excavation ............................................................................................160 203.11 Disposal of Waterway Excavation ........................................................161 203.12 Disposal of Peat ....................................................................................161 203.13 Slides ....................................................................................................161 203.14 Drainage................................................................................................161 203.15 Excavating Rock ...................................................................................162 203.16 Peat Deposit Treatment .........................................................................165

    (a) Treatment of Existing Fills ...................................................................165 (b) Treatment by Removal .........................................................................165 (c) Treatment by Displacement .................................................................166

    203.17 Cased Test Holes ..................................................................................167 203.18 Embankment Construction ...................................................................167 203.19 Embankment Over and Around Structures ...........................................168

  • TABLE OF CONTENTS

    Section Title Page

    xvii

    203.20 Rock and Shale Embankment ...............................................................168 (a) Rock Embankment ...............................................................................168 (b) Shale, Shale and Soft Rock Mixtures, or Soft Rock ............................169 (c) Shale and Thinly Layered Limestone ...................................................170

    203.21 Embankment on Hillsides or Slopes .....................................................170 203.22 Embankment Over Existing Roadbeds .................................................171 203.23 Embankment other than Rock, with Strength or Density

    Control ..................................................................................................172 203.23.1 Coal Ash Embankment ......................................................................174 203.24 Method of Making Strength, Stiffness and Density Tests ....................176

    (a) Laboratory ............................................................................................176 (b) Field .....................................................................................................176

    203.25 Embankment Without Stiffness Control ...............................................178 203.26 Proofrolling ...........................................................................................179 203.27 Method of Measurement .......................................................................179

    (a) Contract Quantity .................................................................................179 (b) Measured Quantities ............................................................................180 (c) Measurement on a Linear Basis ...........................................................180 (d) Measurement of Excavation Items on a Weight Basis .........................181 (e) Measurement of Embankments ............................................................181 (f) Measurement of Borrow .......................................................................181 (g) Measurement of Embankment Foundation Soils Treatment ................182 (h) Measurement of Water for Shale, Shale and Soft Rock

    Mixtures, or Soft Rock .........................................................................182 (i) Lump Sum ............................................................................................182 (j) Measurement of Exploratory Cores ......................................................182 (k) Measurement of Coal Ash ...................................................................182

    203.28 Basis of Payment ..................................................................................182 SECTION 204 – GEOTECHNICAL INSTRUMENTATION ...........................186

    204.01 Description ............................................................................................186 204.02 Materials ...............................................................................................186 204.03 Settlement Plates ...................................................................................187

    (a) Installation Requirements.....................................................................187 (b) Instrument Readings and Settlement Period ........................................187

    204.04 Standpipe Piezometers ..........................................................................188 (a) Installation Requirements.....................................................................188 (b) Readings and Maintenance of Piezometer ...........................................190

    204.05 Method of Measurement .......................................................................190 204.06 Basis of Payment ..................................................................................190

    SECTION 205 – STORMWATER MANAGEMENT ........................................191 205.01 Description ............................................................................................191 205.02 Materials ...............................................................................................191

  • TABLE OF CONTENTS

    Section Title Page

    xviii

    205.03 General Requirements ..........................................................................191 (a) Stormwater Quality Control Plan Development ..................................192 (b) Stormwater Quality Manager ...............................................................193 (c) Stormwater Quality Control Plan Content ...........................................194 (d) Temporary Stormwater Management Features ....................................195 (e) Permanent Stormwater Management Features .....................................196

    205.04 Temporary Surface Stabilization ..........................................................196 (a) Seed ......................................................................................................196 (b) Mulch ...................................................................................................197 (c) Manufactured Surface Protection Products ..........................................198

    205.05 Concentrated Flow Protection ..............................................................199 (a) Check Dam ...........................................................................................199 (b) Check Dam, Traversable ......................................................................200 (c) Diversion Interceptors ..........................................................................200 (d) Sediment Traps ....................................................................................200 (e) Sediment Basins ...................................................................................200 (f) Slope Drains .........................................................................................200 (g) Vegetative Filter Strips ........................................................................200 (h) Splashpads ...........................................................................................200 (i) Inlet Protection .....................................................................................200

    205.06 Perimeter Protection .............................................................................201 (a) Silt Fence .............................................................................................201 (b) Filter Berm ...........................................................................................201

    205.07 Maintenance ..........................................................................................201 (a) Silt Fence .............................................................................................201 (b) Sediment Basin ....................................................................................201 (c) Filter Berm ...........................................................................................201 (d) Inlet Protection .....................................................................................202 (e) Sediment Traps ....................................................................................202 (f) Concrete Washout ................................................................................202 (g) Check Dams .........................................................................................202

    205.08 Quality Adjustments .............................................................................202 205.09 Removal ................................................................................................203 205.10 Method of Measurement .......................................................................203 205.11 Basis of Payment ..................................................................................204

    SECTION 206 – STRUCTURE EXCAVATION ................................................208 206.01 Description ............................................................................................208 206.02 Class X Excavation ...............................................................................208

    (a) General Excavation ..............................................................................208 (b) Excavation for Foundation of Traffic Support Structures ....................209

    206.03 Wet Excavation .....................................................................................209 206.04 Dry Excavation .....................................................................................209 206.05 Foundation Excavation, Unclassified ...................................................209

  • TABLE OF CONTENTS

    Section Title Page

    xix

    206.06 General Requirements ..........................................................................210 206.07 Disposal of Excavated Material ............................................................210 206.08 Preparation of Foundation Surfaces ......................................................211 206.09 Cofferdams and Temporary Construction Dikes ..................................212 206.10 Method of Measurement .......................................................................213 206.11 Basis of Payment ..................................................................................213

    (a) Culverts ................................................................................................216 (b) Bridges .................................................................................................216 (c) Traffic Structure Supports ....................................................................218

    SECTION 207 – SUBGRADE ..............................................................................218 207.01 Description ............................................................................................218 207.02 Materials ...............................................................................................218 207.03 Construction Requirements...................................................................219

    (a) Subgrade Construction Methods ..........................................................219 (b) General Requirements ..........................................................................219

    207.04 Subgrade Treatment Types ...................................................................219 207.05 Method of Measurement .......................................................................221 207.06 Basis of Payment ..................................................................................221

    SECTION 208 – FINISHING SHOULDERS, DITCHES, AND SLOPES .......................................................................................................221

    208.01 Description ............................................................................................221 208.02 Finishing Shoulders ..............................................................................222 208.03 Finishing Ditches ..................................................................................222 208.04 Finishing Slopes ...................................................................................222 208.05 Blank .....................................................................................................222 208.06 Finishing at Contract Drainage Structures ............................................222 208.07 Method of Measurement .......................................................................223 208.08 Basis of Payment ..................................................................................223

    SECTION 209 – FINISHING EARTH GRADED ROADS ...............................223 209.01 Description ............................................................................................223 209.02 Construction Requirements...................................................................223 209.03 Method of Measurement .......................................................................223 209.04 Basis of Payment ..................................................................................223

    SECTION 210 – FINAL TRIMMING AND CLEANING .................................223 210.01 Description ............................................................................................223 210.02 Construction Requirements...................................................................224 210.03 Method of Measurement .......................................................................224 210.04 Basis of Payment ..................................................................................224

    SECTION 211 – B BORROW AND STRUCTURE BACKFILL .....................225 211.01 Description ............................................................................................225

  • TABLE OF CONTENTS

    Section Title Page

    xx

    211.02 Materials ...............................................................................................225 211.03 General Requirements ..........................................................................226 211.03.1 Structure Backfill Types ....................................................................226

    (a) Type 1 ..................................................................................................227 (b) Type 2 ..................................................................................................227 (c) Type 3 ..................................................................................................227 (d) Type 4 ..................................................................................................228 (e) Type 5 ..................................................................................................228

    211.04 Compaction ...........................................................................................228 211.05 Embankment for Bridges ......................................................................228 211.06 B Borrow Around Bents .......................................................................229 211.07 Blank .....................................................................................................229 211.08 Spandrel Filling ....................................................................................229 211.09 Method of Measurement .......................................................................229 211.10 Basis of Payment ..................................................................................230

    SECTION 212 – STOCKPILED SELECTED MATERIALS ...........................231 212.01 Description ............................................................................................231 212.02 Materials ...............................................................................................231 212.03 Construction Requirements...................................................................231 212.04 Method of Measurement .......................................................................231 212.05 Basis of Payment ..................................................................................232

    SECTION 213 – FLOWABLE BACKFILL ........................................................232 213.01 Description ............................................................................................232 213.02 Materials ...............................................................................................232 213.03 Flowable Backfill Mix Design ..............................................................232 213.04 Flowable Backfill Mix Criteria .............................................................233

    (a) Flow Consistency .................................................................................233 (b) Lightweight Dynamic Cone Penetration Blow Count

    Number .................................................................................................233 (c) Removability Modulus .........................................................................233

    213.05 Flowable Backfill Trial Batch ...............................................................234 213.06 Mixing Equipment ................................................................................234 213.07 Placement .............................................................................................234 213.08 Method of Measurement .......................................................................235 213.09 Basis of Payment ..................................................................................235

    SECTION 214 – GEOSYNTHETICS ..................................................................236 214.01 Description ............................................................................................236 214.02 Materials ...............................................................................................236 214.03 Foundation Preparation .........................................................................236

    (a) Geotextile as a Drainage Blanket .........................................................236 (b) Geotextile Placement for Pavement, Subgrade, or

  • TABLE OF CONTENTS

    Section Title Page

    xxi

    Embankment ........................................................................................237 (c) Geogrid Placement in Embankment and Subgrade ..............................237 (d) Geocell Confining System ...................................................................238

    214.04 Fill Placement .......................................................................................238 214.05 Method of Measurement .......................................................................238 214.06 Basis of Payment ..................................................................................239

    SECTION 215 – CHEMICAL MODIFICATION OF SOILS ...........................239 215.01 Description ............................................................................................239 215.02 Materials ...............................................................................................239 215.03 Testing and Mix Design ........................................................................240 215.04 Storage and Handling ...........................................................................240 215.05 Weather Limitations .............................................................................240 215.06 Preparation of Soils...............................................................................241 215.07 Spreading of Chemical Modifiers .........................................................241 215.08 Mixing ..................................................................................................241 215.09 Compaction ...........................................................................................241 215.10 Curing ...................................................................................................242 215.11 Method of Measurement .......................................................................242 215.12 Basis of Payment ..................................................................................242

    SECTION 216 – CELLULAR CONCRETE FILL, CCF ..................................243 216.01 Description ............................................................................................243 216.02 Materials ...............................................................................................243 216.03 Mix Design ...........................................................................................244 216.04 Properties and Tests ..............................................................................244

    (a) CCF Cast Density .................................................................................244 (b) Foam Density .......................................................................................244

    216.05 Storage and Handling ...........................................................................244 216.06 Weather Limitations .............................................................................245 216.07 Preparation of Subgrade .......................................................................245 216.08 Installation ............................................................................................245 216.09 Lots .......................................................................................................245 216.10 Testing ..................................................................................................245 216.11 Method of Measurement .......................................................................245 216.12 Basis of Payment ..................................................................................245

    SECTION 217 – SOILS DRYING WITH CHEMICAL MODIFIERS ............246 217.01 Description ............................................................................................246 217.02 Materials ...............................................................................................246 217.03 Testing and Mix Design ........................................................................246 217.04 Storage and Handling ...........................................................................247 217.05 Weather Limitations .............................................................................247 217.06 Preparation of Soils...............................................................................247

  • TABLE OF CONTENTS

    Section Title Page

    xxii

    217.07 Spreading of Chemical Modifiers .........................................................247 217.08 Mixing ..................................................................................................247 217.09 Compaction ...........................................................................................247 217.10 Method of Measurement .......................................................................248 217.11 Basis of Payment ..................................................................................248

    DIVISION 300 – AGGREGATE PAVEMENT AND BASES

    SECTION 301 – AGGREGATE BASE ...............................................................249 301.01 Description ............................................................................................249 301.02 Materials ...............................................................................................249 301.03 Preparation of Subgrade .......................................................................249 301.04 Temperature Limitations ......................................................................249 301.05 Spreading ..............................................................................................249 301.06 Compacting ...........................................................................................249 301.07 Checking and Correcting Base .............................................................250 301.08 Priming .................................................................................................250 301.09 Method of Measurement .......................................................................250 301.10 Basis of Payment ..................................................................................251

    SECTION 302 – SUBBASE ..................................................................................251 302.01 Description ............................................................................................251 302.02 Materials ...............................................................................................251 302.03 Preparation of Subgrade .......................................................................252 302.04 Temperature Limitations ......................................................................252 302.05 Spreading ..............................................................................................252 302.06 Compacting ...........................................................................................252

    (a) Aggregate Separation Layers and Dense Graded Subbase ...................252 (b) Aggregate Drainage Layers .................................................................252

    302.07 Checking and Correcting Subbase ........................................................253 302.08 Method of Measurement .......................................................................253 302.09 Basis of Payment ..................................................................................253

    SECTION 303 – AGGREGATE PAVEMENTS OR SHOULDERS ................253 303.01 Description ............................................................................................253 303.02 Materials ...............................................................................................253 303.03 Preparation of Subgrade .......................................................................254 303.04 Temperature Limitations ......................................................................254 303.05 Spreading ..............................................................................................254 303.06 Compacting ...........................................................................................254 303.07 Checking and Correcting Base and Surface ..........................................254 303.08 Dust Palliative .......................................................................................254 303.09 Method of Measurement .......................................................................254

  • TABLE OF CONTENTS

    Section Title Page

    xxiii

    303.10 Basis of Payment ..................................................................................254 SECTION 304 – ASPHALT BASES ....................................................................255

    304.01 Description ............................................................................................255 304.02 Materials ...............................................................................................255 304.03 Sealing Cracks and Joints .....................................................................255 304.04 Patching ................................................................................................255 304.05 Widening ..............................................................................................256 304.06 Method of Measurement .......................................................................256 304.07 Basis of Payment ..................................................................................257

    SECTION 305 – CONCRETE BASES ................................................................257 305.01 Description ............................................................................................257 305.02 Materials ...............................................................................................257 305.03 New PCC Base .....................................................................................258 305.04 Existing PCCP ......................................................................................258

    (a) Patching................................................................................................258 (b) Surface Milling ....................................................................................258 (c) Retrofit Load Transfer .........................................................................258 (d) Rubblizing Existing PCCP ...................................................................258

    305.05 Widening With PCC Base ....................................................................260 305.06 Method of Measurement .......................................................................260 305.07 Basis of Payment ..................................................................................261

    SECTION 306 – MILLING ..................................................................................262 306.01 Description ............................................................................................262 306.02 General .................................................................................................262 306.03 Equipment .............................................................................................262

    (a) Roadway Milling Machine ...................................................................262 (b) Power Saw ...........................................................................................263 (c) Rotary Power Broom ...........................................................................263 (d) Straightedge .........................................................................................263

    306.04 Asphalt or PCCP Scarification Milling .................................................263 306.05 Asphalt or PCCP Profile Milling to Correct Cross-Slope .....................264 306.06 Approach Milling .................................................................................265 306.07 Asphalt or PCCP Milling to a Specified Average Depth ......................265 306.08 Asphalt Overlay Removal .....................................................................266 306.09 Transition Milling .................................................................................266 306.10 Method of Measurement .......................................................................267 306.11 Basis of Payment ..................................................................................267

    SECTION 307 – CEMENT STABILIZED FULL DEPTH RECLAMATION, FDR .......................................................................................268

    307.01 Description ............................................................................................268 307.02 Just-in-Time Training, JITT .................................................................268

  • TABLE OF CONTENTS

    Section Title Page

    xxiv

    307.03 Quality Control .....................................................................................268 307.04 Materials ...............................................................................................269 307.05 Mix Design ...........................................................................................269 307.06 Roadway Preparation ............................................................................270 307.07 Equipment .............................................................................................270

    (a) Spreaders and Distributors ...................................................................270 (b) Additive Slurry Storage and Supply Equipment ..................................271 (c) Mixing and Reclaiming Equipment .....................................................271 (d) Motor Grader .......................................................................................271 (e) Compaction Equipment ........................................................................271 (f) Water Trucks ........................................................................................271

    307.08 Weather Limitations .............................................................................272 307.09 Pulverization .........................................................................................272 307.10 Stabilization ..........................................................................................272 307.11 Control Strip and Compaction ..............................................................273 307.12 Opening to Traffic ................................................................................274 307.13 Maintenance ..........................................................................................274 307.14 Curing ...................................................................................................275 307.15 Proofrolling ...........................................................................................275 307.16 Milling ..................................................................................................275 307.17 Underdrain Installation .........................................................................275 307.18 RBC Overlay ........................................................................................275 307.19 Method of Measurement .......................................................................276 307.20 Basis of Payment ..................................................................................276

    SECTION 308 – ASPHALT EMULSION STABILIZED FULL DEPTH RECLAMATION, FDR .........................................................................277

    308.01 Description ............................................................................................277 308.02 Just in Time Training, JITT ..................................................................277 308.03 Quality Control .....................................................................................277 308.04 Materials ...............................................................................................278 308.05 Mix Design ...........................................................................................278 308.06 Roadway Preparation ............................................................................279 308.07 Equipment .............................................................................................279

    (a) Spreaders and Distributors ...................................................................279 (b) Additive Slurry Storage and Supply Equipment ..................................280 (c) Mixing and Reclaiming Equipment .....................................................280 (d) Motor Grader .......................................................................................280 (e) Compaction Equipment ........................................................................280 (f) Water Trucks ........................................................................................280

    308.08 Weather Limitations .............................................................................281 308.09 Pulverization .........................................................................................281 308.10 Injection ................................................................................................281 308.11 Control Strip and Compaction ..............................................................282

  • TABLE OF CONTENTS

    Section Title Page

    xxv

    308.12 Opening to Traffic ................................................................................283 308.13 Maintenance ..........................................................................................284 308.14 Curing ...................................................................................................284 308.15 Proofrolling ...........................................................................................284 308.16 Milling ..................................................................................................284 308.17 Underdrain Installation .........................................................................285 308.18 RBC Overlay ........................................................................................285 308.19 Method of Measurement .......................................................................285 308.20 Basis of Payment ..................................................................................285

    DIVISION 400 – ASPHALT PAVEMENTS

    SECTION 401 – QC/QA HMA PAVEMENT .....................................................287 401.01 Description ............................................................................................287 401.02 Quality Control .....................................................................................287 401.03 Materials ...............................................................................................287 401.04 Design Mix Formula .............................................................................287 401.05 Volumetric Mix Design ........................................................................288 401.06 Recycled Materials ...............................................................................292 401.07 Lots and Sublots ...................................................................................293 401.08 Blank .....................................................................................................293 401.09 Acceptance of Mixtures ........................................................................294 401.10 General .................................................................................................296 401.11 Preparation of Surfaces to be Overlaid .................................................297 401.12 Process Control .....................................................................................297 401.13 Weather Limitations .............................................................................297 401.14 Spreading and Finishing .......................................................................297 401.15 Joints .....................................................................................................298 401.16 Density ..................................................................................................299 401.17 Pavement Corrugations .........................................................................301 401.18 Pavement Smoothness ..........................................................................301

    (a) Profilograph .........................................................................................301 (b) 16 ft Straightedge and 10 ft Straightedge .............................................302 (c) Smoothness Correction ........................................................................303

    401.19 Pay Factors ...........................................................................................304 (a) Dense Graded Mixture ≥ One Lot ........................................................304 (b) Dense Graded Mixture < One Lot and Open Graded

    Mixture .................................................................................................305 (c) Smoothness ..........................................................................................308

    401.20 Appeals .................................................................................................309 (a) MSG .....................................................................................................310 (b) BSG of the Gyratory Specimen ...........................................................310

  • TABLE OF CONTENTS

    Section Title Page

    xxvi

    (c) Binder Content .....................................................................................310 (d) BSG of the Density Core .....................................................................310

    401.21 Method of Measurement .......................................................................310 401.22 Basis of Payment ..................................................................................311

    SECTION 402 –HMA PAVEMENT ....................................................................312 402.01 Description ............................................................................................312 402.02 Quality Control .....................................................................................312 402.03 Materials ...............................................................................................312 402.04 Design Mix Formula .............................................................................313 402.05 Volumetric Mix Design ........................................................................313 402.06 Blank .....................................................................................................314 402.07 Mix Criteria ..........................................................................................314

    (a) Composition Limits for HMA Transverse Rumble Strip Mixtures ...............................................................................................314

    (b) Composition Limits for HMA Wedge and Leveling Mixtures ...............................................................................................314

    (c) Composition Limits for Temporary HMA Mixtures ............................314 (d) Composition Limits fo