Upload
randima-madhuranga
View
167
Download
2
Embed Size (px)
DEPARTMENT OF ELECTRICAL AND INFORMATION ENGINEERING
FACULTY OF ENGINEERING
UNIVERSITY OF RUHUNA
INDUSTRIAL TRAINING REPORT SUBMITTED IN PARTIAL FULFILMENT
OF THE DEGREE OF BACHELOR OF SCIENCE IN ENGINEERING
1st June 2015
STATE DEVELOPMENT &
CONSTRUCTION CORPORATION
(From 26th
January 2015 to 24th
April 2015)
MADHURANGA S.H.R (EG/2012/1986)
2 | P a g e
PREFACE
This report was prepared in relation to the Industrial Training Program for
Engineering Undergraduates conducted by University of Ruhuna. The training period
was 12 weeks at State development & Construction Corporation. Normally SD&CC is
doing construction. There are three division included as the construction division,
mechanical division and designs planning & production division. I had my training
related to traffic light system unit (TLS unit) which is the sub division of mechanical
division.
SD & CC do the traffic light projects of International Construction
Consortium (Pvt) Ltd (ICC) and Road Development Authority (RDA). Their traffic
light systems are installed in Matara , Colombo , Kandy , Galle road and etc. All the
projects are consulted by two electrical engineers and one computer programmer. And
also they have trained supervisors , electricians and labours.
In the beginning they used PIC (Peripheral Interface Controller) based traffic
light controller unit which introduced by faculty of engineering, university of
moratuwa. But now they use PLCs(Programmable Logic Controllers) to control the
traffic lights because of the easiness of programming , reprogramming , repairing and
reliability. And also they improved their lighting system and added some extra
facilities. As the examples they change from halogen bulb to LED bulb arrays. And
now they used three colour count-down , two colour pedestrian count-down , two
colour running man or normal man , loop detectors , pedestrian camera & push
button, traffic officer on/off switch or remote controller and fiber optics linking.
According to that I had good experience about traffic light control system
which use in Sri Lanka. As an engineering student I was lucky to have this valuable
and rare chance to have my first industrial training experience at State Development
and Construction Corporation where I was able to gain great work place experience
and technical knowledge.
Madhuranga S.H.R.
EG/2012/1986
Department of Electrical and Information Engineering,
University of Ruhuna.
3 | P a g e
ACKNOWLEDGEMENT
I would like to thank some persons and organizations who really helped me
during the training period. First of all I take this opportunity to express my profound
gratitude and deep regards for Director Dr.J.M.R.S Appuhami who coordinated and
guided us in selecting training places and taking all the arrangements to make it more
successful. And also I express my deep regard for Dr.Keeerthi Gunawickrama, Head
of the Department, Electrical & Information Engineering and all the academic and
none-academic members of my faculty who associated to arrange my industrial
training at State Development and construction corporation.
My sincere gratitude goes to Engineering Education Center of Ruhuna
Engineering Faculty for giving me this opportunity and also to NAITA for granting us
for the training.
I convey my special thanks to Mr. D.M.N. Kanchana, the software developer
& designer at SD & CC who arranged my Training Plane. And also I would like to
thank Chief Electrical Engineer Mr. P.S.R Perera , Electrical Engineer M.A.W.S
Udayarathne , Mechatronic programmer Mr. Dasun and all the TLS Supervisors and
Electrician at State Development & Construction Corporation.
My heartiest gratitude goes to my parents, my brothers and friends who helped
me a lot to make my industrial training a success .The blessing, help and guidance
given by them time to time shall carry me a long way in the journey of life on which I
am about to embark.
Thank you.
Madhuranga S.H.R.
EG/2012/1986
Department of Electrical and Information Engineering,
University of Ruhuna.
4 | P a g e
Contents Introduction to the Training Establishment. .............................................................8
1.1 Company Profile. .............................................................................................8
1.1.1 Introduction. .............................................................................................8
1.1.2 Vision. ......................................................................................................9
1.1.3 Mission. ....................................................................................................9
1.1.4 History. ...................................................................................................10
1.1.5 Achievements. ........................................................................................10
1.1.6 Objectives ....................................................................................................13
1.2 Organization Structure. ..................................................................................14
1.2.1 Organization Structure of CD&CC. ............................................................14
1.2.2 Organization Structure of Traffic Light System Unit. ................................15
1.2.3 Divisions......................................................................................................16
1.2.4 Services provides by State Development & Construction Corporation. .....17
1.2.5 Strengths of State Development & Construction Corporation. ...................18
1.2.6 Weaknesses of State Development & Construction Corporation and ........19
Suggestions to overcome them. ............................................................................19
1.2.7 Usefulness of State Development & Construction Corporation to the .......20
Society. .................................................................................................................20
Technical Details. .......................................................................................................21
2.1 Introduction to Project. .......................................................................................21
2.2 Introduction to the work site. .............................................................................22
2.3 Traffic light design and Drawing. ......................................................................23
2.4 Writing LADDER program for PLC ..................................................................25
2.4.1 What is PLC? ..............................................................................................25
2.4.2 Ladder programming. ..................................................................................29
2.5 Preparing control unit .........................................................................................36
2.5.1 Solid-State Relay (SSR) ..............................................................................38
2.5.2 Multiplexor box ...........................................................................................38
2.5.3 DC power Supply. .......................................................................................38
2.6 Making structure and wiring. .............................................................................39
2.6.1 3-aspect signal head ....................................................................................39
2.6.2 Red, amber & green count-down ................................................................40
2.6.3 2-aspect signal head with red & green count-down ....................................40
2.6.4 3-aspect right arrow .....................................................................................40
2.6.5 Push button ..................................................................................................41
2.6.6 Camera ........................................................................................................41
5 | P a g e
2.6.7 Loop detector & Frequency counter............................................................42
2.6.8 Fiber to Ethernet converter ..........................................................................43
2.6.9 Router ..........................................................................................................44
2.6.9 Traffic officer on/off switch ........................................................................45
2.7 Maintaining and Repairing .................................................................................45
Management Details ...................................................................................................47
3.1 Management Techniques....................................................................................48
3.1 5S system........................................................................................................48
3.2 Listen, Then Speak Out ..................................................................................48
3.3 Gather the Group ............................................................................................48
3.4 Be Impartial ....................................................................................................49
3.5 Do Not Postpone Conflict Resolution ............................................................49
3.6 Promote Teamwork ........................................................................................49
3.7 Broadcast Praise .............................................................................................49
3.2 Labor Management ............................................................................................50
3.6 Financial Management .......................................................................................51
3.6.1 Valuation of Assets and their Measurement Bases .....................................51
3.6.2 Liabilities and Provisions ............................................................................54
3.6.3 Income Statement ........................................................................................55
3.7 Safety Management ............................................................................................57
Summary and Conclusions ........................................................................................58
4.1 Summary ............................................................................................................58
4.2 Conclusions ........................................................................................................59
References ...................................................................................................................60
6 | P a g e
LIST OF TABLES
2.1 The legend of traffic light drawings…..………………………………. 8
2.2 The basic ladder logic contact symbols……..………………………… 30
7 | P a g e
LIST OF FIGURES
1.1 : SD&CC Logo……………………………………………………………08
1.2 : Organization Structure……………………………………………….…..14
1.3 : TLS unit Organization Structure……………………………………..…..15
2.1 : Map of ongoing projects are located………………………………….....21
2.2 : The traffic light drawing of Vivekananda junction……………………....24
2.3 : Phase arrangement of the Vivekananda junction………………………...26
2.4 : Idec MicroSmart Pentra brick PLC……………………………………... 26
2.5 : Siemens 1200 PLC……………………………………………………….26
2.6 : Parts of Idec MicroSmart Pentra brick PLC……………………………...27
2.7 : Parts of Siemens 1200 PLC……………………………………………....28
2.8 : Module of Idec MicroSmart Pentra brick PLC………………………..….28
2.9 : Module of Siemens 1200 PLC…………………………………………….28
2.10: Siemens LOGO! 8 PLC…………………………………………………...39
2.11: Simple LADDER program……………………………………………..…39
2.12: WindLDR software interface…………………………………………..….35
2.13: TIA portal 13 software interface………………………………………..…35
2.14: Siemens laptop………………………………………………………..…...36
2.15: Control unit……………………………………………………………..…37
2.16: Current indicator………………………………………………………..…37
2.17: MCB, RCB & CB………………………………………………………….37
2.18: SSR that used for LED bulbs………………………………………..... .….37
2.19: Normal relay that used for halogen bulb……………………………...……37
2.20: Multiplexor box…………………………………………………………....37
2.21: DC power Supply……………………………………………………….…39
2.22: Junction & pedestrian traffic lights…………………………………….….39
2.23: 3-aspect signal head…………………………………………………….…39
2.24: Red, amber & green count-down…………………………………………40
2.25: 2-aspect signal head with red & green count-down………………………40
2.26: 3-aspect right arrow……………………………………………………….40
2.27: Push button………………………………………………………………..41
2.28: FLIR’s SafeWalk camera………………………………………………….41
2.29: Analog to digital image converter…………………………………………42
2.30: Loop detector………………………………………………………………42
2.31: Frequency counter…………………………………………………………42
2.32: Fiber to Ethernet converter………………………………………………...43
2.33: Fiber optics cables…………………………………………………………44
2.34: Router……………………………………………………………………...44
2.35: Ethernet cable………………………………………………………………44
2.36: Key switch………………………………………………………………….45
2.37: Remote switch………………………………………………………………45
2.38: Maintaining and Repairing………………………………………………….45
2.39: User login interface of plants management system…………………………46
8 | P a g e
Chapter One
Introduction to the Training Establishment.
1.1 Company Profile.
1.1.1 Introduction.
State Development & Construction
Corporation (SD&CC) falls under the purview of
Ministry of Construction, Engineering Services,
Housing and Common Amenities.
SD&CC plays a major role in the development of Sri Lanka, especially in the
upliftment of Infrastructure Construction. Various major engineering projects in the
fields of Construction such as bridges, roads, highways, dams, irrigation determent
schemes, hydro power tunnels and power houses, water supply and treatment works,
multi storied buildings have been successfully completed by SD&CC. And also
Traffic Light System is the most important projects of SD&CC now. Always they
improve their technologies that have been used in traffic light control systems until
now. Electro-Mechanical works, all type of steel fabrication work, hire of machinery,
repair & maintain all machinery and equipment owned by the corporation.
The Corporation is rated as a Grade One (M1) Contractor under Grading
Scheme conducted by the Institute of Construction Training and Development
(ICTAD), the National Regulating Body of Sri Lanka.
SD&CC is the leading local organization capable of constructing long span
bridges, under design & build basis.
Name of the Enterprise : State Development & Construction
Corporation (SD&CC)
Legal Status of the entity: Government Corporation
Act of Incorporation : Industrial Corporation Act.No. 49 of 1957
Figure 1.1 : SD&CC Logo
9 | P a g e
Year of Incorporation : 1971
Registered Office : No.7, Borupana Road, Ratmalana
Tele. 0112 607560
Internal Audit Division : No. 07, Gregory’s Avenue,Colombo 7
Tele. 0112 – 672196
Concrete Yards : i. Ratmalana Concrete Yard, No.7, Borupana
Rd,Ratmalana
Tele.No. 0112 – 632786
ii. Bopitiya Concrete Yard, Pannala
Tele.No. 037-2288415
iii. Weragantota Concrete Yard, Mahiyanganaya .
Tele.No. 055 – 2257101
iv. Medawachchiya Concrete Yard ,Jaffna Road,
Medawachchiya
Tele.No. 025-3899916
v. Peradeniya Sales Centre
Tele No. 081-2387056
1.1.2 Vision.
To be the best infrastructure development and construction organization,
providing value for money for the Nation.
1.1.3 Mission.
To, assist economic development of the country, by participating in national
infrastructure development and other construction activities and carrying out such
activities to the highest standards of quality and be the market leader in the civil
construction industry and in the production of heavy reinforced and pre-stressed
concrete members in the pre- cast concrete industry.
10 | P a g e
1.1.4 History.
State Development and Construction Corporation was established in 1971 as a
State organization by an extra ordinary gazette notification of 29th March 1971 under
the State Industrial Corporation Act No. 49 of 1957 to undertake heavy civil
engineering construction works.
The turnover of work services was derive from the services rendered
by Central Mechanical Division. The main objective of this division is provide
services to existing project of the Corporation. In addition to that the Traffic
Light Signal Unit ( TLS) also function under the Central Mechanical Division,
which was established in 2005 to install and maintain Traffic Light signal systems
for Road Development Authority. The contribution of this work services to the
turnover of Corporation is 2%. In the beginning they used PIC (Peripheral Interface
Controller) control unit which introduced by the faculty of engineering university of
moratuwa. But at the mean time they replaced their systems by PLCs (Programmable
Logic Controllers) with some changing of the traffic lights wiring. And also they
replaced their all the halogen bulb by LED lights. In 2013, they change from IDEC
PLC to SEIMENCE PLC because of the synchronous purposes. Now they are using
many advance devices for their traffic light systems.
1.1.5 Achievements.
Traffic Light Signal Systems.
SD&CC undertakes maintenance and operation of existing traffic light signal
system and installation of new systems. This new systems has already been
implemented at many road junctions and pedestrian crossing in suburbs of Colombo.
The system has been extend for cities outside Colombo [Katugastota, Nittambuwa,
Kandy and Matara etc.]
11 | P a g e
Hydro Power Tunnels and Power Projects.
SD&CC is capable of handling any type of tunneling work either for hydro power or
Irrigation projects.
Welioya tunnel of 1.25km in length was constructed for Department of
Irrigation.
Tunnel repair works and another works of Pollgolla, Canyon, Bowatena and
Wimalasurendra tunnels.
Canyon Hydro Power Project with an installed capacity of 60 MW was
constructed for Ceylon Electricity Board, with
4,000 meters long D-shaped fully concrete lined Tunnel of 3m
diameter,
Surge chamber & tail race canal,
Power houses, switchyard and other ancillary service structures.
Bridges.
With the construction of over 300 bridges throughout Sri Lanka to its credit,
since its inception, the SD&CC can claim with confidence that it specializes in bridge
building. Almost all the bridges constructed have been concrete structures using
concrete cylinders or concrete piles for foundations, reinforced concrete sub structures
with pre-stressed concrete beams for the decks.
The Road Development Authority (RDA) and the Mahaweli Authority of Sri
Lanka (MASL) and Urban Development Authority (UDA) are the major clients for
whom almost all the bridges have been constructed by SD&CC.
Roads.
SD&CC has undertaken the widening and improvement of existing roads and
the construction of new roads to modern standards for Road Development Authority
(RDA) and Mahaweli Authority of Sri Lanka (MASL). This includes a substantial
quantum of road development in mountain terrain as well.
Access road to Kukule Ganga Hydro Power Project, Roads in Kothmale and
Victoria Power Projects, 50km length of New Kandy Girandurukotte road are some of
the major projects undertaken.
12 | P a g e
Buildings.
SD&CC has to its credit the construction of several single and multi -storied
buildings. Among them are,
Coastal Engineering Laboratory Building project at Katubedda (Lanka
Hydraulic Institute)
The Six-Storied Repair Centre Building for the Sri Lanka Telecom.
Staff quarters and Admin. building & Drawing office for Faculty of
Engineering University of Ruhuna.
Awissawella Bus Park & Town centre.
Irrigation Systems.
In the field of Irrigation, SD & CC has undertaken the construction of wide
range of structures,
- Diversion Dams.
- Anicuts.
- Earth bunds.
- Downstream structures.
Water supply Projects.
SD&CC undertakes the construction of water supply projects, such as water
towers, intakes, treatment plants pipe laying etc.
Improvement to Water Treatment Plant at Ambatale, ADB funded
Anuradhapura water supply projects are some major projects undertaken by SD&CC.
13 | P a g e
1.1.6 Objectives
1. To continue as a self-financing Government Organization.
2. To be a viable and profitable entity and maintain a net profit margin of 10% .
3. To achieve an average turnover growth of 25%
4. To reduce direct and indirect fixed overhead factors to 7% and 8%
respectively.
5. To reduce wastage and losses to less than 5%
6. To build a corporate profile for quality and efficiency in executing civil
& electro –mechanical contracts within the given time frame
7. To maintain a highly motivated and contended workforce by providing
a share of profit to the work force annually and provide necessary
welfare facilities
8. To provide opportunities to Managerial / Engineering/ Technical
personnel to enhance knowledge in modern technology and skills in
construction engineering and managerial fields.
9 To be the market leader in high quality concrete, reinforced concrete
and pre-stressed concrete products for the use of construction
industries.
10 To become the foremost organization in the construction industry and
be one of the leading engineering organizations inthe country.
14 | P a g e
Chairman
General Manager
working Directors
Internal Audit
Board of Directors
Figure 1.2: Organization Structure
1.2 Organization Structure.
1.2.1 Organization Structure of CD&CC.
The objectives of State Development & Construction Corporation (SD&CC)
and the means of attaining these objectives and monitoring the performance
were provided through the corporate governance. Therefore, corporate governance
structures that promote effective identification, monitoring and management of all
material business risks are given priority. Therefore the organization structure of the
State Development & Construction Corporation is divided in to separate designations
according to their works and divisions as shown in bellow.
Finance
Security Personnel &
Administration
Mechanical
Supplies
Design
Planning &
Production
Construction
Performance
Monitoring Unit
15 | P a g e
Mechanical division
Repair & Maintanance unit
Traffic Light System unit
Figure 1.3: TLS unit Organization Structure
1.2.2 Organization Structure of Traffic Light System Unit.
When considering above structure Construction, Design Planning &
Production, Supplies, Personnel & Administration, Performance Monitoring Unit,
Finance and mechanical are divided to another sub organization structures. According
to my industrial training program I was included to mechanical division. Traffic Light
System (TLS) unit is the sub part of the mechanical division. I dialed with this TLS
unit. There for I would like to introduce the organization structure of the TLS unit.
Assistant Electrical
Engineer
Software Designer
& Developer
Chief Electrical
Engineer Secretary
Secretary
PLC
Programmer Electricians
Laborers
16 | P a g e
1.2.3 Divisions.
Construction Division.
This division functions under the Deputy General Manager (Construction). All
the construction sites operate under DGM(C) with the assistance of Chief Engineers
(Construction), who manage the work sites from the area offices. All activities
connected with work sites are coordinated by this division.
The Construction Management Unit, which prepares monthly progress claims,
other extra claims and other financial reports related to construction works attached to
construction division and managed by Chief Engineer (Contracts Management).
Mechanical Division.
The Mechanical Division functions under the Deputy General Manager
(Mechanical). All machinery and equipment owned by the corporation are managed
by this Division. Repair and Maintenance Workshops and Transport Division are
operating under the Mechanical Division. The central workshop is located at
Ratmalana capable of handling all repair and maintenance works and functions under
this division. They undertake,
All type of steel fabrication work
Repair works
Hire of machinery
Electro-Mechanical works
Design & Installation of Traffic Light Signal System.
Designs Planning & Production Division.
This Division is managed by Deputy General Manager (Designs Planning &
Production). Design Office and the Estimates Section responsible for the submission
of tenders, function under this division.
Three Concrete Yards owned by the corporation also managed by
DGM(DP&P) with the assistant of Chief Engineer (Concrete Yards).
17 | P a g e
1.2.4 Services provides by State Development & Construction Corporation.
SD&CC undertakes maintenance and operation of existing traffic light
signal system and installation of new systems.
SD&CC is capable of handling any type of tunneling work either for
hydro power or Irrigation projects.
Power houses, switchyard and other ancillary service.
All type of steel fabrication work.
Hire of machinery.
Electro-Mechanical works.
SD&CC specializes in bridge building.
SD&CC undertakes the construction of Diversion Dams, Anicuts, Earth
bunds, Downstream structures.
SD&CC undertakes the widening and improvement of existing roads
and the construction of new roads.
SD&CC constructs of several single and multi -storied buildings.
SD&CC undertakes the construction of water supply projects, such as
water towers, intakes, treatment plants pipe laying etc.
18 | P a g e
1.2.5 Strengths of State Development & Construction Corporation.
The SC&CC is the main Traffic Lights designer in Sri Lanka. They install
Traffic Lights using new technologies. And also they used advanced devises
as the Seimense 1200 PLC, Safewalk pedestrian camera, Loop detector, Bright
LED colour light & countdown and ect.
They mechanical work shop their own. That work shop planed & make
mechanical structures that want to Traffic light installation and civil
construction.
SD&CC have a large vehicle & machinery strength that want any construction
process and they repair their vehicles & machineries in their mechanical
workshop by themselves.
There are number of Civil engineers, Mechanical engineers and Electrical
engineers work in SD&CC. They have the ability to achieve success of any
complex project.
High educated persons are working at administrative level and management
level. Therefore, the supervision is well in the cooperation.
More than 500 trained labourer, technicians and supervises are working at
SD&CC having good experience.
Road Development Authority (RDA), Mahaweli Authority of Sri Lanka
(MASL) and International Construction Consortium (Pvt) Ltd (ICC) usually
work with SD&CC.
SD&CC has concrete yards at Ratmalana, Bopitiya, Weragantota,
Medawachchiya. It manufactures all types of pre stressed post tensioned
beams, electrical transmission poles RCC spun pipes, bridge components,
hollow blocks and other pre-cast concrete products in their yards.
19 | P a g e
1.2.6 Weaknesses of State Development & Construction Corporation and
Suggestions to overcome them.
LED count down, LED running man or normal man, LED lights are imported
from china. LED count down, LED running man or normal man circuit are
complex. But LED lights can be made in Sri Lanka. In the beginning they
install Sri Lankan halogen Light System. Some of them are working until now.
But the brightness of the old system is less than the LED lights. If there is an
electronic engineer with trained labourers, they will do experiment for
electronic parts. Otherwise they should get technical support from an
engineering faculty or other electronic service provider in Sri Lanka. If they
can produce their LED colour lights by themself, the wastage of money will be
stopped.
Now they use galvanized new structure to install the Traffic Lights that
imported from china. Five years ago, a casting engineer worked in SD&CC
and there are all the things that want for casting. If they can fill that vacancy,
the wastage of money will be stopped.
At the mean time SD&CC change from IDEC PLC to SEIMENCE PLC.
SEIMENCE PLCs are more cost than the IDEC PLCs. SEIMENCE is the
German company and their Sri Lankan dealer is the biggest automation
company in Sri Lanka. SD&CC pays about Rs.80,000 for one
PLS(SEIMENCE 1200 PLS). But it real price is around Rs.40,000. Some
Indian dealers supply this PLS to that price. Because of the programing
service and the warranty SD&CC have to buy PLCs from that company. It’s
better they can find low cost and trust another dealer.
In world there are more advance Traffic Light systems are using. Those
systems can be control from the one control unit. But Sri Lankan system runs
according to previous downloaded pregame. It can’t be change when it is
running. But SD&CC is getting steps to solve that problem.
20 | P a g e
1.2.7 Usefulness of State Development & Construction Corporation to the
Society.
In the earlier traffic police faced big troubles when controlling the traffic jam.
And also drivers, pedestrians had to waste their time in the road. Sometimes they have
to die on way. Therefore SD&CC introduce and improve Traffic Light Systems by
associating with Road Development Authority (RDA). Their systems are install in
Colombo city, Galle road, Negombo, Nugegoda, Kandy, Matara, at all the highway
entrance and etc. Traffic police officers always thank for the SD&CC, because they
know what kind of traffic will happen, if they didn’t introduce those Traffic Light
Systems.
And also SD&CC is doing major construction part of Sri Lanka joining with
the Road Development Authority (RDA), Mahaweli Authority of Sri Lanka (MASL),
International Construction Consortium (Pvt) Ltd (ICC) and etc. They construct road,
bridges, buildings, tunneling work either for hydro power or Irrigation projects, water
towers, intakes, treatment plants pipe, diversion dams, anicuts, earth bunds,
downstream structures.
21 | P a g e
Figure 2.1: Map of ongoing projects are located
Chapter Two
Technical Details.
2.1 Introduction to Project.
When I went to
the DC&C they were
doing very many
projects. Their projects
mainly situated around
Colombo. All the Traffic
Lights of Galle road from
Panadura to Colombo is
installed by the SD&CC.
Ramakrishna junction,
Vivekanada junction and
W.A. Silva junction in
Wellawatte were installed
when I went
there. The second day of my training, I had opportunity to participate for system-on,
at above mention Ramakrishna & Vivekananda junctions. And also third day, they
switch on the system at W.A. Silva junction. But that system didn’t work correctly. In
the mean time of my training, they found the error and again switch on the system.
I had opportunity to deal with many ongoing projects in Kolluptiya,
Bouddhaloka road and some pedestrian light on Galle road. And also I had to
participate for some trouble shootings. I went to many junctions & pedestrian lights
that shown in covered area of the above map. Sometimes I had to stay at one junction
in whole day, because we had to change phase times and cycle time according to
traffic jam changing.
Basically SD&CC installs Traffic Light for junctions and pedestrian crossing.
Road Development Authority (RDA) planes the phase arrangement of the road and it
is provided to the SD&CC. Then SD&CC have to,
Prepare the light arrangement design a drawing.
Write a LADDER program for PLC.
22 | P a g e
Send the PLC input & output pin configuration and head-counter details to the
TLS work shop (shop six). Then the control unit is made in there.
Give the wiring arrangement to a supper (normally all the supervisors are
electricians) to set tours and lay the under-ground wires. Then they went to the
location with labours and set the lights and wire. If there is any
synchronization they should lay the fiber-optic cable.
Install the system and connect the wires to the output of SSR (Solid State
Relay). If there is any synchronization, they have to use Fiber to Ethernet
converter and small router for switching.
Download the program to PLC and check whether it’s working correctly.
After above mention process the project is completed. But every maintenance
are done by SD&CC. Sometimes they have to add some extra devices according to
the requirement of the RDA. Some of them are,
Pedestrian camera.
Pedestrian push button.
Loop detectors.
Remote or external system on/off switch for traffic officers.
2.2 Introduction to the work site.
Project Details.
Project Name : Traffic Lights and Pedestrian colour light system installation
and synchronization.
Client : Ministry of transformation.
Contractor : International Construction Consortium (Pvt) Ltd (ICC).
Sub-Contractor : State Development & Construction Corporation (SD&CC).
Consultant : Road Development Authority (RDA).
Engineer : Chief Electrical Engineer Mr. P.S.R Perera.
Electrical Engineer M.A.W.S Udayarathne.
Software Designer & Developer Mr. D.M.N. Kanchana.
23 | P a g e
There are two different work site as,
Inside work site.
Outside work site.
Inside work site.
This is situated in SD&CC, Rathmalana. It is called as TLS shop or shop-6.
Control units making, Lights repairing, making structures and testing are done here.
And also it is the store of Traffic Light unit.
Outside work site.
This outside work sites are situated at all the Traffic Light Systems which are
installed by them. Sometimes it will be working system or installing system. If it is
working system, normally they will go here to upload or download a program and
repairing (Ex: replace SSR or Traffic Lights). If it is installing system, normally they
doing their works at night. Then they have to dig pit, drain or lay wire or install the
tower.
2.3 Traffic light design and Drawing.
Traffic light design and Drawing is very important to install the Traffic light and
repairing. All the details are shown in this drawing. After planning, engineers give
this drawing to the supervisors. Then they install the Traffic Lights according to the
drawing. Supervisors are trained to read the drawings. By referring the drawing, we
can get knowledge about following things;
Phase arrangement.
Number of heads & countdown that want.
Dimension of the junction.
Duct line and gulley.
24 | P a g e
To read a Traffic Light drawing the legend is very important. The legend of above
figure is not very clear. So the sample legend is shown in below.
Symbols Description
DRAW PIT (DP)
DUCT LINE
3 ASPECT SIGNAL HEAD
2 ASPECT SIGNAL HEAD WITH RED & GREEN
COUNTDOWN
RED &GREEN COUNTDOWN
3 ASPECT RIGHT ARROW
Figure 2.2: The traffic light drawing of Vivekananda junction.
Table 2.1: The legend of traffic light drawings.
25 | P a g e
In the Vivekananda junction there are two phase arrangement as shown in
below. The junction runs according to that 2-phase arrangement always
First phase arrangement:
Phase-1, phase-2 and pedestrian are opened. Its mean all the vehicles are
released which are going to Colombo & Rathmalana. And also pedestrian are released
to cross the Vivekananda road. (Some vehicles are waiting to go Colombo &
Rathmalana on the Vivekananda road)
Second phase arrangement:
Phase-3 and phase-4 are opened. Its mean all the vehicles are released which
are going to Colombo & Rathmalana from Vivekananda road. (At that time another
vehicles are waiting to go Colombo and Rathmalna at the Vivekananda junction)
2.4 Writing LADDER program for PLC
2.4.1 What is PLC?
PLCs (Programmable Logic Controllers) is an industrial computer control
system that continuously monitors the state of input devices and makes decisions
based upon a custom program to control the state of output devices. The biggest
benefit in using a PLC is the ability to change and replicate the operation or process
while collecting and communicating vital information. Another benefit is ability to
increase the inputs and outputs by using modules.
1
4 2 3
Figure 2.3: Phase arrangement of the Vivekananda junction.
26 | P a g e
First SD&CC used Idec MicroSmart Pentra brick PLC. Because of the
synchronization now they mainly use Siemens 1200 PLC. But Idec PLCs are used for
small junction. It available with 12V DC, 24V DC and 100-240V AC power, you can
choose from 10, 16 and 24 I/O configurations. The 10 I/O CPU is equipped with six
DC inputs and four relay outputs, while the 16 I/O CPU is equipped with nine DC
inputs and seven relay outputs. The 24 I/O CPU is equipped with 14 DC inputs and
ten relay outputs. The 24 I/O CPU (24V DC and 100-240V AC models) can also be
expanded with a maximum of four functional or discreet expansion modules. With
this latest model, you
can configure the
MicroSmart Pentra
PLC for remote
monitoring and
control. Using
WindLDR software,
you can remotely
monitor or update the
PLC programs
without having to be
near the PLC.
Figure 2.4: Idec MicroSmart Pentra brick PLC.
Figure 2.5: Siemens 1200 PLC.
Figure 2.6: Parts of Idec MicroSmart Pentra brick PLC.
27 | P a g e
Now the SD&CC is using Siemens 1200 PLC for their new projects. The main
purpose of using this PLC is synchronization.
The new modular SIMATIC S7-1200 controller is at the core of our new
offering for simple but highly precise automation tasks. The SIMATIC S7-1200
controller is modular and compact, versatile, a secure INVESTMENT, and is
perfectly suited to a whole range of applications.
The S7-1200 CPUs with Safety Integrated handle both standard and safety-
related tasks. A compact design with integrated IO, communication interfaces that
meet the highest industry requirements and a range of powerful integrated
technological functions make this controller an integral part of a comprehensive
automation solution.
The compact SIMATIC S7-1200 system consists of different CPU
performance classes: CPU 1211C, CPU 1212C, CPU 1214C, CPU 1215C and CPU
1217C and two failsafe versions CPU 1214FC and CPU 1215FC. Each of these may
be expanded according to the machine requirements. The S7-1200 CPUs can be
expanded with up to three communication modules (CM) and eight signal modules
(SM). Signal modules and signal boards can be integrated in order to expand the
digital or analog IOs without affecting the physical size of the controller.
Figure 2.7 : Parts of Siemens 1200 PLC.
28 | P a g e
Modules are used to increase inputs and outputs of the PLCs. But there is a limit for
connecting modules. (EX: 11 modules can be connected to the Siemens 1200 PLC)
Siemens 1200 is very advance PLC. So, its all features are not useful for Traffic Light
project of SD&CC. They use only synchronization. Therefore they plane to change
for Siemens LOGO! 8 PLC.
The successful Siemens logic
module has launched the next
generation. This new module
accommodates virtually every
demand of customers with
simplified handling, a new display,
and full communication options via
Ethernet. And the web server
application makes everything very
simple. A communications module
provides for remote communications via cellular phone network, rounding out the
range of new ways to use LOGO!
Figure 2.8 : Module of Idec MicroSmart
Pentra brick PLC.
Figure 2.9 : Module of Siemens 1200 PLC.
Figure 2.10 : Siemens LOGO! 8 PLC.
29 | P a g e
2.4.2 Ladder programming.
Ladder logic is widely used to program PLCs, where sequential control of a
process or manufacturing operation is required. Ladder logic is useful for simple but
critical control systems or for reworking old hardwired relay circuits. As
programmable logic controllers became more sophisticated it has also been used in
very complex automation systems. Often the ladder logic program is used in
conjunction with an HMI program operating on a computer workstation.
The motivation for representing sequential control logic in a ladder diagram
was to allow factory engineers and technicians to develop software without additional
training to learn a language such as FORTRAN or other general purpose computer
language. Development, and maintenance, was simplified because of the resemblance
to familiar relay hardware systems. Implementations of ladder logic have
characteristics, such as sequential execution and support for control flow features, that
make the analogy to hardware somewhat inaccurate. This argument has become less
relevant given that most ladder logic programmers have a software background in
more conventional programming languages.
Manufacturers of programmable logic controllers generally also provide
associated ladder logic programming systems. Typically the ladder logic languages
from two manufacturers will not be completely compatible; ladder logic is better
thought of as a set of closely related programming languages rather than one
language. Even different models of programmable controllers within the same family
may have different ladder notation such that programs cannot be seamlessly
interchanged between models.
Ladder logic can be thought of as a rule-based language rather than a
procedural language. A "rung" in the ladder represents a rule. When implemented
with relays and other electromechanical devices, the various rules "execute"
simultaneously and immediately. When implemented in a programmable logic
controller, the rules are typically executed sequentially by software, in a continuous
loop (scan). By executing the loop fast enough, typically many times per second, the
effect of simultaneous and immediate execution is achieved, if considering intervals
greater than the "scan time" required to execute all the rungs of the program. Proper
use of programmable controllers requires understanding the limitations of the
execution order of rungs.
30 | P a g e
Some LADDER logic signals are shown in below that use in WindLDR;
Table 2.2: The basic ladder logic contact symbols
Ladder
symbol
Description
Normally open (NO) contact. Passes power (on) if *** is on (closed)
Normally closed (NC) contact. Passes power (on) if *** is off (open).
Positive transition sensing contact. If the state of *** changes from off
to on, this contact passes power for only one scan (until rung is scanned
again).
Negative transition sensing contact. If the state of *** changes from on
to off, this contact passes power for only one scan (until rung is scanned
again).
Table 2.3: The basic ladder logic coil (output) symbols
Ladder
symbol
Description
Output or coil. If any left-to-right rung path passes power, the ***
output is energized (on). If there is no continuous left-to-right rung
path passing power, the *** output is de-energized (off).
Negated coil. If any left-to-right rung path passes power, the ***
output is de-energized (off). If there is no continuous left-to-right rung
path passing power, the *** output is energized (on).
Set coil. If any rung path passes power, *** is energized and remains
energized, even when no rung path passes power.
Reset coil. If any rung path passes power, *** is de-energized and
remains de-energized, even when no rung path passes power.
Positive transition sensing coil. If conditions before this coil change
from off to on, *** is turned on for one scan
31 | P a g e
Negative transition sensing coil. If conditions before this coil change
from on to off, *** is turned on for one scan.
Retentive memory coil. Like the ordinary coil, except the value of ***
is retained even when the PLC is stopped or power fails.
Set retentive memory coil. Like the set coil, except the value of *** is
retained even when the PLC is stopped or power fails.
Reset retentive memory coil. Like the reset coil, except the value of
*** is retained even when the PLC is stopped or power fails.
Some advance LADDER symbols is shown in below that use in WindLDR.
Following blocks are very important in writing Traffic Light program.
Timer
Four types of timers are available;
TML - 1-sec countdown timer,
TIM - 100-msec countdown timer,
TMH - 10-msec countdown timer and
TMS - 1-msec countdown timer.
Each timer must be allocated to a unique number T0 through T255.
Off-Delay Timer
Four types of time-down off-delay timers are available;
TMLO - 1-sec off-delay timer,
TIMO - 100-ms off-delay timer,
TMHO - 10-ms off-delay timer and
TMSO - 1-ms off-delay timer.
A total of 256 on- and off-delay timers can be programmed in a user program
for any type of CPU module. Each timer must be allocated to a unique number T0
through T255.
32 | P a g e
The CNT (Counter) Instruction
Three types of counters are available;
CDP - dual-pulse reversible counter,
CUD - up/down selection reversible counter and
CNT - adding (up) counters.
A total of 32(10-point type) or 100(other types) counters can be programmed.
Each counter must be allocated to a unique number 0 through 255.
CNTD, CDPD, and CUDD (Double-Word Counter)
Three types of double-word counters are available;
CNTD - adding (up) counter,
CDPD - dual-pulse reversible counter and
CUDD - up/down selection reversible counter.
A total of 128 double-word counters can be programmed in a user program for
any type of CPU module. Each double-word counter uses 2 consecutive operands
starting with the allocated operand, which can be C0 through C254. Once used in a
user program, counters cannot be used in any other counter instructions.
Counter Comparison
When a counter comparison instruction is programmed, two addresses are
required. The circuit for a counter comparison instruction must be programmed in the
following order: the CC= or CCe instruction; a counter number C0 through C255,
followed by a preset value to compare from 0 to 65535.
Data Register Comparison
When a data register comparison instruction is programmed, two addresses are
required. The circuit for a data register comparison instruction must be programmed
in the following order: the DC= or DC>= instruction, a data register number D0
through D1999 (all CPU modules) or D2000 through D7999 and D10000 through
D49999 (slim type CPU modules), followed by a preset value to compare from 0 to
65535.
33 | P a g e
Shift Register
The SFR (Forward) and
SFRN (Reverse) Shift Register Instructions
The shift register consists of a total of 256 bits which are allocated to R0
through R255. Any number of available bits can be selected to form a train of bits
which store on or off status. The on/off data of constituent bits is shifted in the
forward direction (forward shift register) or in the reverse direction (reverse shift
register) when a pulse input is turned on.
Master Control Set (MCS) and Master Control Reset (MCR)
The MCS (master control set) instruction is usually used in combination with
the MCR (master control reset) instruction. The MCS instruction can also be used
with the END instruction, instead of the MCR instruction
Jump (JMP) and Jump End (JEND)
The JMP (jump) instruction is usually used in combination with the JEND
(jump end) instruction. At the end of a program, the JMP instruction can also be used
with the END instruction, instead of the JEND instruction.
End
The END instruction is always required at the end of a program; however, it is
not necessary to program the END instruction after the last programmed instruction.
34 | P a g e
Figure 2.11: Simple LADDER program.
Figure 2.12: WindLDR software interface.
35 | P a g e
WindLDR software is introduced by the Idec to program their PLCs. As well as the
TIA portal 13 software is introduce by the Siemens to program their 1200 PLS. TIA
portal 13 software is very complex than the WindLDR software and it is not provided
as free software. And also Siemens softwares are running well in their laptops only.
But Siemens laptops are mainly use for industrial purposes. So it is very difficult to
learn their softwares.
Figure 2.13: TIA portal 13 software interface.
Figure 2.14: Siemens laptop.
36 | P a g e
2.5 Preparing control unit
Engineers send PLC input & output pin configuration and head-counter details
to the TLS work shop (shop six). Then the system unit is made in there. A PLC (Idec
or Siemens PLC), Relays (SSR or normal relays), A Power supply, Multiplexor
boxes, A MCB, A RCB, Indicators and three pin plug bases are installed as shown in
bellow. After that all the devises are wired using red, green and yellow wires. The
special devises of fiber to Ethernet converters and a router are installed by the special
electrician.
Figure 2.15: Control unit.
37 | P a g e
Figure 2.20: Multiplexor box.
Figure 2.18: SSR that used for
LED bulbs.
Figure 2.17: MCB, RCB & CB.
Figure 2.16: Current indicator.
Figure 2.19: Normal relay that used for
halogen bulb.
Figure 2.21: DC power Supply.
38 | P a g e
2.5.1 Solid-State Relay (SSR)
A solid-state relay (SSR) is an electronic switching device that switches on or
off when a small external voltage is applied across its control terminals. SSRs consist
of a sensor which responds to an appropriate input (control signal), a solid-state
electronic switching device which switches power to the load circuitry, and a coupling
mechanism to enable the control signal to activate this switch without mechanical
parts. The relay may be designed to switch either AC or DC to the load. It serves the
same function as an electromechanical relay, but has no moving parts.
Packaged solid-state relays use power semiconductor devices such as
thyristors and transistors, to switch currents up to around a hundred amperes. Solid-
state relays have fast switching speeds compared with electromechanical relays, and
have no physical contacts to wear out. Application of solid-state relays must consider
their lower ability to withstand momentary overload, compared with
electromechanical contacts, and their higher "on" state resistance. Unlike an
electromechanical relay, a solid-state relay provides only limited switching
arrangements
2.5.2 Multiplexor box
Multiplexors box requires for traffic light count-down. SD&CC uses a
Multiplexors box that is produced by China Company specially for them. It has 2
input (A & B), 10 output (D1 to D10) and 2 terminal for power supply.
2.5.3 DC power Supply.
PLC and modules require 24 DC voltage to give output. Therefore every
control units have a DC power supply. For an example they use Siemens SITOP
PSU100L. The power supplies required following features;
● Narrow design
● Good efficiency
● Can be connected in parallel
● Cooling through natural convection
39 | P a g e
2.6 Making structure and wiring.
According to supplied drawing supervisors guided the labours to install the
traffic light tower and hang 3 aspect signal head, red, amber & green count-down, 2
aspect signal head with red & green count-down, 3 aspect right arrow, push button
and camera. After that they set loop detector if it needs. Then install the control unit.
Finally wires and fiber optics are laid through drain and wired all the devices. If
there is a fiber optics connection, fiber to Ethernet converter and router will be
connected by special electrician.
2.6.1 3-aspect signal head
According to the PLC
output signal 3 aspect signal
head’s sequence is changed.
Red : Stop
Red & Amber : Ready
Amber : Ready
Green : Go
This sequence is repeating in cycle time of the PLC. Considering situation of the
junction or pedestrian crossing red, amber and green times are changed. Those times
are not constant in the whole time.
Figure 2.23: 3-aspect signal head.
Figure 2.22: Junction & pedestrian traffic lights.
40 | P a g e
2.6.2 Red, amber & green count-down
The count-down
sequence is also same to
the 3-aspect signal head’s
sequence. But another two
outputs of the PLC are
used to give the signals to
it. Count-down can’t read this two output signal. Therefore those outputs are gave to
the multiplexor box and multiplexor outputs are connected with the red, amber &
green count-down.
2.6.3 2-aspect signal head with red & green count-down
2-aspect signal head with red &
green count-down are used for pedestrian
crossing. Only two output of the PLC is
enough for the 2-aspect signal head and red
& green count-down. There is a special
circuit in the red & green count-down. In the
first two cycles, count-down doesn’t display
anything. But after two cycles later, it
automatically counts the time and displays it.
2.6.4 3-aspect right arrow
3-aspect right arrow is same to the 3-
aspect signal head. Only different between
them is arrow shape lights. It is used in
junction to show L-turn.
Figure 2.24: Red, amber & green count-down.
Figure 2.25: 2-aspect signal head with red & green count-down.
Figure 2.26: 3-aspect right arrow.
41 | P a g e
Figure 2.28: FLIR’s SafeWalk camera.
2.6.5 Push button
Pedestrian pushbuttons are
electronic buttons used by pedestrians to
change traffic signal timing to
accommodate pedestrian street
crossings. Pushbuttons may be needed
at some crossings, but their use should
be minimized. As traffic signals become
more complex pedestrian pushbuttons
are needed. If buttons exist, pedestrians
must push them to get enough time to
cross the street. Standard pushbuttons
often result in longer waits to cross the
street, especially if the pedestrian fails to push the button. Sometimes, pedestrians
push the button and go away. Therefore SD&CC uses a pedestrian camera to check
whether pedestrians are still waiting or not.
2.6.6 Camera
Pedestrian presence sensors are a
safer and more efficient alternative to
push buttons. Research has shown that
70% of pedestrians will cross the road
without waiting for the green signal after
pushing the button. This results in
unnecessary interruption of traffic flows
and in more traffic congestion. In
contrast, pedestrian detection will drop
the green call when pedestrians are no
longer waiting to cross. While
pedestrians are crossing, pedestrian detection will extend the red light signal for
vehicles to enable a safe passage. FLIR’s SafeWalk camera is used by SD&CC. But it
is an analog camera and its output can’t give to the PLC directly. So that they have to
use analog to digital image converter. That device is shown in below.
Figure 2.27: Push button.
42 | P a g e
Figure 2.29: Analog to digital image converter.
Figure 2.31: Frequency counter. Figure 2.30: Loop detector.
2.6.7 Loop detector & Frequency counter.
An induction or inductive loop is an electromagnetic communication or
detection system which uses a moving magnet to induce an electrical current in a
nearby wire. Induction loops are used for transmission and reception of
communication signals, or for detection of metal objects in metal detectors or vehicle
presence indicators.
Vehicle detection loops, called inductive-loop traffic detectors, can detect
vehicles passing or arriving at a certain point, for instance approaching a traffic light
or in motorway traffic. An insulated, electrically conducting loop is installed in the
43 | P a g e
Figure 2.32: Fiber to Ethernet converter.
pavement. The electronics unit transmits energy into the wire loops at frequencies
between 10 kHz to 200 kHz, depending on the model. The inductive-loop system
behaves as a tuned electrical circuit in which the loop wire and lead-in cable are the
inductive elements. When a vehicle passes over the loop or is stopped within the loop,
the vehicle induces eddy currents in the wire loops, which decrease their inductance.
The decreased inductance actuates the electronics unit output relay or solid-state
optically isolated output, which sends a pulse to the traffic signal controller signifying
the passage or presence of a vehicle.
A frequency counter is an electronic instrument, or component of one, that is
used for measuring frequency. Frequency is defined as the number of events of a
particular sort occurring in a set period of time. Frequency counters usually measure
the number of oscillations or pulses per second in a repetitive electronic signal.
SD&CC uses Ultra II D-TEK Plug In Style Vehicle Loop Detector with following
features;
ULTRAMETER™ (displays optimum sensitivity setting / diagnostic aid)
Frequency count/reset switch
10 sensitivity settings
Loop diagnostics
4 operating frequencies
Lightning and surge protection
Frequency counter
Fail safe Operation
CE compliant
Optional accessories include PR-Loop
2.6.8 Fiber to Ethernet converter
A technology that uses glass (or plastic) threads
(fibers) to transmit data. A fiber optic cable consists of a
bundle of glass threads, each of which is capable of
transmitting messages modulated onto light waves.
Fiber optics has several advantages over traditional
metal communications lines.
44 | P a g e
Figure 2.33: Fiber optics cables.
Figure 2.34: Router.
Figure 2.35: Ethernet cable.
In synchronization, normally there are two signals come to the one control unit from
front and back control units. Those signals are passed through the fiber optics cable.
But that signals can’t access directly to the PLCs. So that fiber to Ethernet converter is
required. Therefore two fiber to Ethernet converters(MMF 100BASE-EX) are used in
one control unit.
2.6.9 Router
A router is a device that forwards data
packets along networks. A router is
connected to at least two networks,
commonly two LANs or WANs or a LAN
and its ISP's network. Routers are located at
gateways, the places where two or more
networks connect.
In here they have to use a router for
switching purpose. Because, two Ethernet
cables comes to the PLC and it easy to download and upload program by connecting
router and computer using another Ethernet cable.
45 | P a g e
Figure 2.36: Key switch. Figure 2.37: Remote switch.
Figure 2.38: Maintaining and Repairing.
2.6.9 Traffic officer on/off switch
In special occasion, traffic officers have to switch off the control unit and control the
traffic by themself. For example;
When VIP vehicles coming
If there is any picketing or political meeting on the road
In New Year seasons and etc.
2.7 Maintaining and Repairing
46 | P a g e
Figure 2.39: User login interface of plants management system.
All the Traffic Lights are maintained and repaired by SD&CC that installed by them.
Changing PLC program or camera program.
Repairing control unit.
Repairing and replacing heads & counters.
Do all the electrical repairing.
Specially, one team (One supervisor with four labours) goes inspections daily.
-------------------------------------------------------------------------------------------------------
The Chief Electrical Engineer, Mr.P.S.D. Perera gave me a special
project me to make a web base plants management system. They want
to update all the plant details in to one table, after updating plants
details site wise. Therefore I made a database using html, php &
Mysql. Finally they really appreciate my project.
47 | P a g e
Chapter Three
Management Details The objectives of State Development & Construction Corporation (SD&CC)
and the means of attaining these objectives and monitoring the performance
were provided through the corporate governance. Therefore, corporate governance
structures that promote effective identification, monitoring and management of all
material business risks are given priority.
SD&CC, being a fully Govt. owned institution operate under the purview of
the Ministry of Construction & Engineering Services and the General Treasury. Board
of Directors are directly accountable to the Government through the line
ministry. Therefore the Board of Directors and the senior management of SD&CC
have a duty to ensure that the organization governed and operated in the best
interest of the Corporation and its stake holders in full compliance with the
regulatory frame work.
In terms of the constitution , Parliament has full control of public
finance and therefore public enterprises are subject to Parliamentary control.
The cabinet of ministers is responsible for taking decisions relating to public
enterprises. The General Treasury is responsible for financial and operational
disciplines of the public corporations. For this purpose, the General Treasury issues
regulations, rules, codes, guidelines and directives through circulars to ensure that
the board of directors properly discharge their responsibilities with regard to the
economic efficiency and effectiveness.
Except for the General Treasury representative Director, the other
appointments to the Board of Directors including head of the institutions of Govt.
Corporations are made by the secretary to the line ministry based on the
recommendation of the minister in charge under which the enterprise falls. The
General Treasury, being the shareholder, appoints one director.
The Board of Directors had no personnel interest which conflicted with the
interest of the Corporation. The activities of the Corporation were conducted to build
the Corporation to more financially and operationally viable entity in the
construction industry.
48 | P a g e
3.1 Management Techniques
3.1 5S system
SD&CC uses 5S system very effectively to do their all the works very efficiently. The
whole SD&CC premises are arranged according to the 5S system. 5S is workplace
management where the work area and workplace are organized and ritualized to
minimize the loss of time and the use of movement.
5S is much more than “a place for everything and everything in its place”. 5S
comprises five principles to make people highly efficient and effective in their doing
work.
Sort -Keep near you only what you regularly use
Straighten -Find exactly what you need to use in less than 30 seconds
Shine -Have your workplace and equipment ready for immediate use
Standardize -Everyone does each job in the same way and is challenged to
improve it
Sustain -Everyone does their part to foster a safe, efficient and effective
workplace
3.2 Listen, Then Speak Out
Believe it or not, just listening to an employee’s issue is the first and most
important step in resolving conflict. They simply listen to all parties involved to
completely understand the nature of conflict, and then start troubleshooting solutions.
3.3 Gather the Group
As a leader, they arrange a meeting with all involved parties to discuss the
issue. Give everyone a chance to speak; this is a good opportunity to hear all sides and
gain a full understanding of the conflict. Having a group meeting may also expedite a
resolution that will satisfy everyone.
49 | P a g e
3.4 Be Impartial
Don’t take sides! In a leadership position, they don’t display any sort of
opinion that favors one person over another. If they are partial towards one person, try
to access the situation from all sides to come up with a fair and reasonable solution.
3.5 Do Not Postpone Conflict Resolution
Address the conflict immediately. Otherwise, the situation could escalate and
could affect employee performance. Just make sure not to address the situation too
quickly or without careful consideration, as their decision will directly affect the
demeanor and performance of their staff.
3.6 Promote Teamwork
Encouragement and motivation are powerful. Remind their staff of successful
projects that required teamwork to complete. This is one of the most effective conflict
resolution techniques and will really make the employees think about the importance
of working in a team.
3.7 Broadcast Praise
As stated above, the power of encouragement and motivation can be
multiplied when it is spread to recognize those who are modeling the teamwork and
cooperation that is desired within any conflict. So they try to give suitable models in
these instances because behavior modeling can be risky if there are elements in the
model that are undesirable.
50 | P a g e
3.2 Labor Management
HUMAN RESOURCES
The foremost resource that controls all the other resources in the
Organization is the human resources. The Prime Strength of our Organization is
the Staff who possess wide experience, capabilities, and skills related to our
objectives and targets of the Corporation.
The Human Resources Department played a vital role to achieve the ISO
2008. In achieving the ISO 2008 the Human Resources Division gained varied
experience & all Methods & Systems were developed to the present trend.
The following programs were worked out during the year 2015 in order to
develop the knowledge, skills, and to maintain standards to keep the Employees
satisfied in order to motivate the human resources towards the fulfillment of the
objectives of the Organization.
3.2.1 Staff Promotions
During the year 2015, 41 persons from all grades of Officers and
Workers were given promotions further motivating them in order to achieve the
objectives of the Organization.
3.2.2 Training and Development
A large number of Staff representing various sections were given training to
develop their knowledge and talents. Special mention be made about the Overseas
training given to several Employees during the year.
Steps have been taken to offer Extensive training to the Personnel directed to
us by External Institution to be trained in various fields, which is done as a
contribution towards the General Development of the Country.
51 | P a g e
3.2.3 Staff Welfare
Steps were taken to continue the Medical Insurance Scheme for the
Employees sponsored by the Organization. A compensation Insurance Scheme have
been introduced confirming the security of the work force. All bonus payments were
paid to the Staff of the Corporation in April 2015.
3.2.4 Rewards to Employees
Employees who have completed 25 years of continuous service in the
Corporation were felicitated with a gold Sovereign and a Souvenir as a token
of appreciation at the 38th Anniversary Celebrations of the Corporation held at
the Ministry Auditorium under the distinguish patronage of the Hon. Minister in
Charge.
3.6 Financial Management
3.6.1 Valuation of Assets and their Measurement Bases
3.6.1.1 Inventories
Inventories are valued at the lower of cost and net realizable value, after
making due allowances for obsolete and slow moving items. Net realizable value is
the price at which inventories can be sold in the ordinary course of business less the
estimated cost of completion of the sale.
3.6.1.2 Trade Debtors and Other Receivables
Trade debtors are stated at the amounts they are estimated to realize net of
provisions for bad and doubtful debtors. Other receivables and dues are recognized at
cost less provision for bad and doubtful receivables.
52 | P a g e
3.6.1.3 Cash and Cash Equivalents
Cash and cash equivalents are defined as cash in hand, demand deposits and
short term highly liquid investments, readily convertible to known amounts of
cash and subject to insignificant risk of changes in value.
3.6.1.4 Property, Plant and Equipment
a) Cost
Property, Plant & Equipment is recorded at cost less accumulated depreciation.
b) Cost and Valuation
All items of Property, Plant & Equipment are initially recorded at cost.
Where items of Property, Plant and Equipment are subsequently revalued, the entire
class of such assets is revalued. Revaluations are made with sufficient regularity
to ensure that their carrying amounts do not differ materially from their fair values
as at the balance sheet date.
c) Depreciation
The provision for depreciation is calculated by using the straight line method
on the cost or valuation of all property, plant and equipment other than freehold land,
in order to write off such amounts over the following estimated useful lives by equal
installments.
Land Over prolonged of Period
Buildings Over 20 Years
Office Equipment Over 10 Years
Plant & Machinery Over 10 Years
Motor vehicles Over 05 Years
Other Assets Over 10 Years
53 | P a g e
3.6.1.5 Leases
a) Finance Leases
Property, plant and equipment on finance leases, which effectively
transfer to the Corporation substantially all of the risk and benefits incidental to
ownership of the leased item are capitalized at their cash price and disclosed as
property, plant and equipment and depreciated over the period the Corporation is
expected to benefit from the use of the leased assets.
b) Operating Leases
Leases where the lesser effectively retains substantially all the risks and
benefits of ownership over the leased term are classified as operating leases. Rentals
paid under operating leases are recognized as an expense in the income statement on
a straight-line basis over the lease term.
3.6.1.6 Investments
a) Current Investments
Current investments are stated at lower of cost and market value determined
on an aggregate portfolio basis. The cost of an investment is the cost of acquisition
inclusive of brokerages, fees, duties and bank fees.
b) Associate Company Investments
Investments in associate companies are accounted for on the equity
method, whereby the share of profit of the associates attributable to the company is
accounted for as income and the value of the investment (which was initially
recognized at cost) adjusted by a like amount.
c) Related Parties
Corporation has entered into a Joint Venture with Mass Trust Holdings to
form a Company, Fujima State Corporation (Pvt.) Ltd. during the last year SD&CC
owns 51% of authorized share capital of this Company and Ms. Mass Trust Holdings
owns 49% of authorized share capital. Mr. B.M.S.Samarasekara, Chairman SD&CC
is a Director of Fujima Sate Corporation.
54 | P a g e
3.6.2 Liabilities and Provisions
3.6.2.1 Retirement Benefit Obligations
a) Defined Benefit Plan – Gratuity
Gratuity is a Defined Benefit Plan. The Corporation is liable to pay gratuity in
terms of the relevant statute. In order to meet this liability, a provision is carried
forward in the balance sheet, equivalent to an amount calculated based on a half
month’s salary of the last month of the financial year of all employees for each
completed year of service, commencing from the first year of service. The
resulting difference between brought forward provision at the beginning of a year
and the carried forward provision at the end of a year is dealt with in the income
statement.
3.6.2.2 Bad debts Provision
a) Provision for Debtors
For Debtors over 05 years are provided 100% unlessthere is a possibility of recovery.
For balance debtors provision have been made in the following manner taking with
the account the age analysis, moments and the current position there in.
Age (years) Rate
0-1 --
1-2 2.5%
2-3 25%
3-4 30%
4-5 50%
Over 5 years 100%
b) General Provision for Other Debtors
40% is provided from the other category of debtors which have no transaction for
over more than one year.
55 | P a g e
c) Recognition of work-in- progress
Direct operating Cost in respect of bills not certified and a portion of direct cost
on under certified bills decided by the construction division have been recognized as
work-in progress.
3.6.3 Income Statement
Identified losses on construction contracts.
3.6.3.1 Revenue Recognition
Revenue is recognized to the extent that it is probable that the economic benefits
will flow to the Corporation and the revenue and associated costs incurred or to
be incurred can be reliably measured. Revenue is measured at the fair value of
the consideration received or receivable net of trade discounts and sales taxes. The
following specific criteria are used for the purpose of recognition of revenue.
a) Construction Income
The revenue from certified bills as at the balance sheet date is recognized as
income in full.
b) Identified losses on Construction Contracts
The Corporation policy is to identify the profit or loss on contracts on certified
bills. Therefore profit or loss identified in the financial statements as and when they
are incurred irrespective of the percentage of completion therein.
c). Sale of Goods – Pre Cast Yards
Revenue from sale of goods is recognized when the significant risks and
rewards of ownership of the goods have passed to buyer; with the Corporation
retaining neither continuing managerial involvement to the degree usually
associated with ownership, nor effective control over the goods sold.
56 | P a g e
d). Interest
Interest Income is recognized as the interest accrues (taking into account the
effective yield on the asset) unless collectability is in doubt.
e). Rental income
Rental income is recognized on accrual basis.
f). Others
Other income is recognized on an accrual basis. Net Gains and losses of a revenue
nature on the disposal of property, plant & equipment and other non-current assets
including investments have been accounted for in the income statement, having
deducted from proceeds on disposal, the carrying amount of the assets and related
selling expenses. On disposal of revalued property, plant and equipment, amount
remaining in Revaluation Reserve relating to that asset is transferred directly to
Accumulated Profit.
Expenditure Recognition
Expenses are recognized in the income statement on the basis of a direct association
between the cost incurred and the earning of specific items of income. All
expenditure incurred in the running of the business and in maintaining the property,
plant & equipment in a state of efficiency has been charged to income in arriving at
the profit for the year.
3.6.3.2 Contingent Liabilities
Corporation has issued bonds & guarantees of Rs. 459Mn to its clients for
projects executed as at the Balance Sheet date. There is no any possibility to lodge
claims against these bonds issued.
57 | P a g e
3.7 Safety Management
Safety of the workers in m organization is very critical point. As I observed
during my training period SD&CC management has provided their workers safety
equipments they needed during their working hours such as ladders, helmets, glosses,
belts, jackets and etc. But unfortunately very few workers use them while they are
working. This is very displeasing situation because there can be bad consequences
because of the carelessness of the workers of their own safety. So according to my
knowledge I think management should give their attention more to have programs to
emphasize the safety of workers by not only giving them equipment but also
encouraging workers to use them as well.
SD&CC has a good security system for the protection of the company. If a
visitor comes to the SD&CC office he or she has to leave his ID card at the reception
and should give the specific place and person he or she needs to meet. Then a
permission card only to enter the relevant area is issued for the visitor and this
permission card must be worn inside the SD&CC premises by the visitor.
58 | P a g e
Chapter Four
Summary and Conclusions
4.1 Summary
During 12 weeks of my training experience in State Development &
Construction Corporation, I was able to involve with site work, laboratory work as
well as the administrative and office work. I had to go for site more than two days per
week. Some days we are staying at a junction or pedestrian crossing in whole day. It
was very hard work, but it was very interesting and gave knowledge.
As well as I had good practical knowledge in the TLS workshop (shop six). In
here I was dealing with Siemens and Idec ladder programming. Mechatronic
programmer really helps me to understand the ladder programs. And also I could deal
with PLS, relays, count-down camera and etc. SafeWalk camera programming is very
interesting and there was small image processing part. I had opportunity to make a
control unit in TLS work shop.
Sometimes they asked me to guide two or three labours in the site and TLS
workshop. And also they asked me to prepare a web base plant’s management system.
So I have already prepared it using html, php and Mysql database. They really
appreciated my plant’s management system. So my industrial training period was
remarkable and very important period in my life. The knowledge I got there, not only
about technical aspects but also about human resource management was a great
advantage for my life
59 | P a g e
4.2 Conclusions
At the University, we were taught many theories and given chances to do
several practical, experiments and tests to understand the concepts of Electrical,
Electronic, Software & Telecommunication. But it was truly a remarkable
opportunity to have my first training experience in a leading company as State
Development & Construction Corporation. During this period I was able to gather
vary rare experiences. I was able b to gain new insights and more comprehensive
understanding about the real electronic & electrical industry beyond the theoretical
background.
Those experiences lead me to change my attitudes about working environment
and build good carrier in future. Apart from technical knowledge, the soft skills that
we were exposed to will be invaluable for our future lives. Working with staff of
different statuses, collectively working as a team, handling customers, documentation
and reporting, punctuality, adjusting to the office culture are some of the skills we
developed during these three months.
Finally I can conclude that by undergoing the industrial training program
offered, at the largest Traffic Light service provider and primitive constructor in the
country, have exposed me with many aspects and latest technological trends in the
growing electronic & electrical industry and these valuable experiences have built me
an interest to continue my future career in electronic industry.
I personally believe that State Development & Construction Corporation is
one of the best training place for training Engineer who is in the field of Traffic
Lights. SD&CC provides a special training program.
The three month time of my training at State Development & Construction
Corporation was a very beneficial time for me as an Engineering undergraduate. It is
my firm belief that the experience and knowledge I gathered from this training will be
very useful for me to serve my country as a professional Engineer.
60 | P a g e
References
State Development & Construction Corporation :
http://www.sdcc.lk/
Siemens web site :
http://w3.siemens.com/mcms/programmable-logic-
controller/en/pages/default.aspx
Idec web site :
http://www.idec.com/gben/products/Catalogs/PLCs/MicroSmartPentra/overvie
w.html
FLIR traffic camera web site :
http://www.flir.com/traffic/display/?id=61995
Wikipedia :
http://en.wikipedia.org/wiki/Solid-state_relay