50
Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage

Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Industry PresentationSEM

Capacity Payment Mechanism

27 July 2007

John Parsonage

Page 2: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Agenda

• CPM Objectives

• CPM Design

• Annual Capacity Payment Sum

• Payments to Generators

• Charges to Suppliers

• Summary

• Parameters for 2007/2008

Page 3: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Agenda

• CPM Objectives

• CPM Design

• Annual Capacity Payment Sum

• Payments to Generators

• Charges to Suppliers

• Summary

• Parameters for 2007/2008

Page 4: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Objectives of the CPM1

• Capacity adequacy/reliability of system – new andexisting plants

• Price Stability – take some volatility from energymarket, help promote investment

• Simplicity• Efficient signals for Long Term investments• Susceptibility to gaming• Fairness

1. CPM Options paper: May 20051. CPM Options paper: May 2005

Page 5: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Agenda

• CPM Objectives

• CPM Design

• Annual Capacity Payment Sum

• Payments to Generators

• Charges to Suppliers

• Summary

• Parameters for 2007/2008

Page 6: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

CPM Key Features

• Fixed amount of cash (the Pot) per year• Pot determined as Price x Volume

– Price: Best New Entrant Peaking Plant fixed costs– Volume: Capacity required to meet adequacy standard

• Pot allocated for Generator Payments:– Fixed (year ahead)– Variable (month ahead)– Ex-Post (month end)

• Generators paid when available• Pot allocated for Supplier Charges:

– Based on demand• Suppliers charged on consumption

Page 7: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

CPM Key Features

• Fixed amount of cash (the Pot) per year• Pot determined as Price x Volume

– Price: Best New Entrant Peaking Plant fixed costs– Volume: Capacity required to meet adequacy standard

• Pot allocated for Generator Payments:– Fixed (year ahead)– Variable (month ahead)– Ex-Post (month end)

• Generators paid when available• Pot allocated for Supplier Charges:

– Based on demand• Suppliers charged on consumption

Page 8: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Pot Determination – PriceWhy Peaker Fixed Costs?

Time � 8760h

Most Generation bidsShort Run Marginal Cost.Receive implicitcapacity payment(inframarginal rent)

Peakers “Bid Up” attimes of stress

MW

Baseload

Mid Merit

Increasing prices

Incr

easi

ng m

argi

nal c

osts

Energy Only Pool:

Page 9: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Pot Determination – PriceWhy Peaker Fixed Costs?

Time � 8760h

Price(£/MWh)

BaseloadIncr

easi

ng L

oad

Energy Only Pool:

Mid Merit

Inframarginal rent

Page 10: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Baseload

Medium

All plant in stack receivesrevenue.

Recovers Long-Run (Fixed + SRMC)

Pot Determination – PriceWhy Peaker Fixed Costs?

• Remove Peaker FixedCosts to CPM

• Peaker receives FixedCosts through CPM

• Others receive FixedCosts through CPM andinframarginal rent

• Allows SRMC bidding

Price(£/MWh)

Page 11: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

BNE Peaker Fixed Costs

• Annualised fixed costs of a Best New EntrantPeaking Plant

• Methodology:– Identify appropriate technology for system– Estimate:

• Financial costs (cost of capital over life)• Investment costs (site, equipment, etc.)• Operational costs (service agreement, Transmission charges,

insurance etc.)

– And deduct infra-marginal rents (if there are any)

Page 12: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

BNE Peaker Fixed Costs

Technology Output(MW)

Efficiency Accessibility StartUp

Plant TrackRecord

ScreeningCurve

LM6000SPT 44 39.0LMS100 92 43.6GE 6FA 74 33.9GE9E 124 32.9SGT2000E 159 34.0Alstom 13E2 187 36.9

Aero DerivativeHeavy Duty Industrial Gas Turbine

Page 13: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

BNE Peaker Fixed Costs

0

20

40

60

80

100

120

140

160

180

0% 2% 4% 6% 8% 10% 12% 14% 16% 18%

Load factor (% of year)

Cos

t of G

ener

atio

n (c

ents

per

kW

h)

LM6000SPT

GE 9E

SGT2000E

13E2

Page 14: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

BNE Peaker Fixed Costs

Technology Output(MW)

Efficiency Accessibility StartUp

Plant TrackRecord

ScreeningCurve

LM6000SPT 44 39.0LMS100 92 43.6GE 6FA 74 33.9GE9E 124 32.9SGT2000E 159 34.0Alstom 13E2 187 36.9

Aero DerivativeHeavy Duty Industrial Gas Turbine

Integrated Pollution Prevention Control(IPPC) Best Available Technology (BAT)Directive – best efficiency

Page 15: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

BNE Peaker Fixed Costs

• Original proposal fired the unit on Gas• Responses indicated Gas Capacity Charge not

tradeable• Increased cost led to change to Distillate firing

– Reduced capital cost (cf GCC) but reduced inframarginalrent too

Page 16: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

BNE Peaker Fixed Costs

Net Power Output (Lifetime) 182 MWCapital Cost €81 millionAmortisation Period 15 YearsWACC 7.83%Annualised Capital Cost €9.37 millionFixed O&M Costs €6.11 millionAnnualised Cost of Capacity €85.04/kW

2007 Values2

2. Fixed Cost of New Entrant Peaking Plant for CPM – Final Decision paper: May 2007

Page 17: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

BNE Peaker Fixed Costs

• Inframarginal rent:– Energy

• Determined through multiple Plexos runs• Validated Plexos model and data• Determine SMPs without BNE• Determine running regime with BNE

– Ancillary Service• Based on Eirgrid rates

BNE CharacteristicsMinimum Stable Capacity 20MWIncremental Heat Rate Slope 10.588GJ/MWh at MCRRun Up Rate 10-20MW/minRun Down Rate 10MW/min plus 6-8min Idle TimeMinimum Up Time 25 minsMinimum Down Time 30 minsStart-Up Energy 650GJ (LHV)VOM Costs 1.39 cents/kWh

2007 ValuesEnergy Inframarginal Rent €14.19/kWAncillary Service Revenue €6.12/kW

Final BNE Cost €64.73/kW

Page 18: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

CPM Key Features

• Fixed amount of cash (the Pot) per year• Pot determined as Price x Volume

– Price: Best New Entrant Peaking Plant fixed costs– Volume: Capacity required to meet adequacy standard

• Pot allocated for Generator Payments:– Fixed (year ahead)– Variable (month ahead)– Ex-Post (month end)

• Generators paid when available• Pot allocated for Supplier Charges:

– Based on demand• Suppliers charged on consumption

Page 19: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

• Methodology:– Based on TSO Adequacy Assessment process– Create a demand forecast– Create generation probability distribution– Derive Loss of Load Probability (LOLP) per Trad. Period– Loss of Load Expectationyear (LOLE) = ∑year LOLP– Compare LOLE to Security Standard Deficit/Surplus– Requirement = Installed Capacity ± Deficit/Surplus

Pot Determination – Volume

Page 20: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Capacity Requirement -Methodology

880MW880MW984MW984MW

LOLE hrs/yrLOLE hrs/yrStandardStandard

Includes 125MW Reference (Imperfect) PlantIncludes 125MW Reference (Imperfect) Plant

Initial Generation Stack (8288MW)Initial Generation Stack (8288MW)

Thus a 125MW Imperfect Plant is worth 104MW (984Thus a 125MW Imperfect Plant is worth 104MW (984--880)880)

Imperfect to Perfect ratio = 125 / 104 = 1.2Imperfect to Perfect ratio = 125 / 104 = 1.2

Convert Initial Perfect Surplus to Imperfect SurplusConvert Initial Perfect Surplus to Imperfect Surplus= 880 x 1.2 = 1058MW= 880 x 1.2 = 1058MW

Requirement = StackRequirement = Stack -- SurplusSurplus=8288=8288 –– 1058 = 7230MW1058 = 7230MW

Cap

acity

Cap

acity

Page 21: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

• Demand Forecast• Unit Capacities• Scheduled Outages• Adequacy Standard• Forced Outages• Wind Power

Capacity Requirement -Inputs

– From TSOs– Direct from Generators– Historic Averages–––

Page 22: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Adequacy Standard

• Std > 8h/yr leads to greater EUE compared with current• Select 8h/yr to give security/cost comparable with current

Page 23: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Forced Outage Probabilities

• Existing FOPs vary between NI and RoI– FOPs in NI ~ 4%– FOPs in RoI ~ 14%

• Incentivise Availability improvement (Objective)• NI Average FOP - 4.23% - applied to all units*

* Exception is Interconnectors – not a “true” generator

Page 24: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Treatment of Wind

• Wind generation reliant onfuel – very high FOPs

• Wind penetration set to grow• Forecast output and adjust

demand (i.e. not ingeneration “stack”)

• Apply Capacity Credit whencalculating CapacityRequirement

Page 25: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Treatment of Wind

• All-island Wind 2007~1140MW

• Capacity Credit ~20%

Capacity Requirement = IC + (WICx0.2) + DWhere:IC = Installed Capacity (market registered only) excluding WindWIC = Installed Capacity of Wind (market registered only)D = Difference = Deficit or Surplus (where Surplus is negative)

Total Capacity Requirement for 2007 – 6960MW

Page 26: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Pot Determination –Monthly Values• Annual Pot = BNE Price x Capacity Requirement• For 2007 ~ €450.5 million• Annual Pot split into Monthly Pots, weighted by peak

to trough demand:

• Where:– WFc is the Weighting Factor for the Capacity Period (Mth);– Pc is the peak demand in the Capacity Period; and– MinFDy is the minimum demand in the year

( )∑ −

−=

yincyc

ycc

MinFDP

MinFDPWF

3

3. Capacity Factors Decisions Paper: December 2006

Page 27: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

0

0.02

0.04

0.06

0.08

0.1

0.12

Jan Feb M ar Apr M ay Jun Jul Aug Sep O ct Nov Dec

R elativ e M onthly Pot A llocations

Majority of cash into high demand periods

Pot Determination –Monthly Values

Page 28: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

CPM Key Features

• Fixed amount of cash (the Pot) per year• Pot determined as Price x Volume

– Price: Best New Entrant Peaking Plant fixed costs– Volume: Capacity required to meet adequacy standard

• Pot allocated for Generator Payments:– Fixed (year ahead)– Variable (month ahead)– Ex-Post (month end)

• Generators paid when available• Pot allocated for Supplier Charges:

– Based on demand• Suppliers charged on consumption

Page 29: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

• Need to meet several Objectives• Objectives sometimes conflicting• Fixed:

– Provides certainty to Generators, but– Weak incentives to respond to shortages

• Variable:– Still provides degree of certainty to Generators– Improves forecast of likely shortages, but– No response to un-forecast shortages

• Ex-Post:– Provides short-term response incentive, but– Payment incidence uncertain

Why Have Three?

A balance needs to be struck

30%

40%

30%

Page 30: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

How do the allocations work?

January 2007 Demand Charges (Relative)

0

5

10

15

20

25

30

Relative Demand Charges

Fixed30%

( )∑ −−=

cinhch

ch

MinFDFDMinFDFDFCPWFh

Variable40%

Forecast Demand

0

1000

2000

3000

4000

5000

6000

7000

1 46 91 136 181 226 271 316 361 406 451 496 541 586 631 676 721

Forecast DemandAvailability

0

2000

4000

6000

8000

10000

1 46 91 136 181 226 271 316 361 406 451 496 541 586 631 676 721

Forecast Availability

Example CPM Allocations for Dec 2007, with Ex-post calculated using 1.5% Mean LoadForecast Error and typical Wind Uncertainty. Payments smoothed using a 0.33 power

factor

€0

€50,000

€100,000

€150,000

€200,000

€250,000

€300,000

€350,000

€400,000

01/12/2007 08/12/2007 15/12/2007 22/12/2007 29/12/2007

Fixed Variable (Ex-ante) Ex-post

LOLPCurve

0

0.2

0.4

0.6

0.8

1

1.2

1 447 89313391785223126773123356940154461490753535799

∑=

cinhh

hVCPWFhλλ

Ex-Post30%

Forecast Demand

0

1000

2000

3000

4000

5000

6000

7000

1 46 91 136 181 226 271 316 361 406 451 496 541 586 631 676 721

Actual DemandAvailability

0

2000

4000

6000

8000

10000

1 46 91 136 181 226 271 316 361 406 451 496 541 586 631 676 721

Actual Availability

LOLPCurve

0

0.2

0.4

0.6

0.8

1

1.2

1 447 89313391785223126773123356940154461490753535799

∑=

cinhh

hECPWFhφφ

Example CPM Allocations for Nov 2007, with Ex-post calculated using 1.5% Mean LoadForecast Error and typical Wind Uncertainty

€0

€200,000

€400,000

€600,000

€800,000

€1,000,000

€1,200,000

€1,400,000

€1,600,000

€1,800,000

01/11/2007 08/11/2007 15/11/2007 22/11/2007 29/11/2007

Fixed Variable (Ex-ante) Ex-post

Page 31: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

CPM Key Features

• Fixed amount of cash (the Pot) per year• Pot determined as Price x Volume

– Price: Best New Entrant Peaking Plant fixed costs– Volume: Capacity required to meet adequacy standard

• Pot allocated for Generator Payments:– Fixed (year ahead)– Variable (month ahead)– Ex-Post (month end)

• Generators paid when available• Pot allocated for Supplier Charges:

– Based on demand• Suppliers charged on consumption

Page 32: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Where1. CPuh is the Capacity Payment for unit u in Trading Period h2. CPGPFuh is the Capacity Payments Generation Price Factor for u

in h3. CPEALFuh is the Loss-Adjusted Capacity Payments Eligible

Availability for u in h4. VCGPh is the Variable Capacity Payments Generation Price in h5. FCGPh is the Fixed Capacity Payments Generation Price in h6. ECGPh is the Ex-Post Capacity Payments Generation Price in h

• Allocations (Variable / Fixed / Ex-Post)

• Availability

Generator Payments

TSC Version 24.123 )( ECGPhFCGPhVCGPhCPEALFuhCPGPFuhCPuh ++××=

• Payments depend on available capacity* and price

* Based on production for some unit types (see later)

• Price

Page 33: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Generator Payments

• A unit with Price > VOLL has no value• A unit with Price ~ VOLL has little value• As unit Price approaches VOLL, value decreases

TSC Version 2

4.115

• Capacity Payments depend on Price

Where1. CPGPFuh is the Capacity Payments Generation Price Factor for unit u in

Trading Period h2. MSQuh is the Market Schedule Quantity for u in h3. CPPFh is the Capacity Payments Price Factor in h4. UCOQuhi is the Unscheduled Capacity Offer Quantity for Price Quantity

Pair i for u in h5. VOLL is the Value of Lost Load6. UCOPuhi is the Unscheduled Capacity Offer Price for i for u in h

( )

+

−×+×

=

i

i

UCOQuhiMSQuh

VOLLUCOPuhiVOLLMaxUCOQuhiCPPFhMSQuh

CPGPFuh

0,

Page 34: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Generator Payments

• Avoids payments to Generators exceeding VOLL

( )

−= 0,

VOLLSMPhVOLLMaxCPPFh

Where1. CPPFh is the Capacity Payments Price Factor for Trading Period h2. VOLL is the Value of Lost Load3. SMPh is the System Marginal Price for Trading Period h

If Supply > Demand & Price < VOLL, Price = SMPIf Supply < Demand or Price > VOLL, Price = VOLL

Loss of Load Probability = Probability Supply < Demand:

Probability weighted Price = SMP x (1 – LOLP) + VOLL x LOLP= SMP + LOLP x (VOLL – SMP)

Price€/MWh

supply

Quantity (MW)

VOLL

TSC Version 24.109

Page 35: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

• Allocations (Variable / Fixed / Ex-Post)

• Availability

Generator Payments

TSC Version 24.123 )( ECGPhFCGPhVCGPhCPEALFuhCPGPFuhCPuh ++××=

• Payments depend on available capacity* and price

* Based on production for some unit types (see later)

Where1. CPuh is the Capacity Payment for unit u in Trading Period h2. CPGPFuh is the Capacity Payments Generation Price Factor for u

in h3. CPEALFuh is the Loss-Adjusted Capacity Payments Eligible

Availability for u in h4. VCGPh is the Variable Capacity Payments Generation Price in h5. FCGPh is the Fixed Capacity Payments Generation Price in h6. ECGPh is the Ex-Post Capacity Payments Generation Price in h

• Price

Page 36: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Generator Payments

• Generators paid against Loss-Adjusted CapacityPayments Eligible Availability (CPEALFuh)

• Mostly = APuh x TLAFuh x TPD– Where:– APuh is the Availability Profile of Unit u in Trading Period h– TLAFuh is the Transmission Loss Adjustment Factor of u in h– TPD is the Trading Period Duration

• But TSC Section 5 (Special Units) identifies othercases…

Page 37: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Generator PaymentsCategory Form of

DispatchInstruction

DispatchQuantity(DQuh)

AvailabilityProfile(APuh)

MarketScheduleQuantity(MSQuh)

AutonomousGenerator Units

N/A Actual Output(AOuh)

Actual Output(AOuh)

Actual Output(AOuh)

VariablePrice TakerGenerator Units

Run Actual Output(AOuh)

Actual Output(AOuh)

Actual OutputAOuh

VariablePrice TakerGenerator Units

Unitconstraineddown inDispatchInstructions toremain below alevel of Outputof X MW

Time weightedaverage of(OutturnAvailability whennot constraineddown below XMW, Min{X MW,OutturnAvailability}whenconstraineddown below XMW)

Max {ActualOutput (AOuh),Time weightedaverage ofOutturnAvailability}

Max {ActualOutput (AOuh),Time weightedaverage ofOutturnAvailability}

VariablePrice MakerGenerator Units

Run Actual Output(AOuh)

Actual Output(AOuh)

Calculated bythe MSPSoftware

VariablePrice MakerGenerator Units

Unitconstraineddown inDispatchInstructions toremain below alevel of Outputof X MW

Time weightedaverage of(OutturnAvailability whennot constraineddown below XMW, Min{X MW,OutturnAvailability}whenconstraineddown below XMW)

Max (ActualOutput (AOuh),Time weightedaverage ofOutturnAvailability)

Calculated bythe MSPSoftware

PredictablePrice TakerGenerator Units

Any As set out inSection 4

As set out inSection 4

Minimum ofNominatedQuantity (NQuh)and AvailabilityProfile (APuh)

• Number of Special Cases• Mainly Actual Output• Interconnector Units:

– Dispatch Quantity– Availability and price

• Energy Ltd./Pump. Stge:– Allocate “excess” to

peak LOLP• Demand Side Units:

– Demand Reduction

TSC Version 2, Table 5.1

Page 38: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Generator Payments –Summary

TSC Version 24.123

• Payments depend on available capacity* and price

* Based on production for some unit types

VOLLUCOPuhiVOLL

( )

VOLLSMPhVOLL

∑cinh

h

h

φφ

∑cinh

h

h

λλ

( )∑ −−

cinhch

ch

MinFDFDMinFDFD

Availability /Metered Generation

)( ECGPhFCGPhVCGPhCPEALFuhCPGPFuhCPuh ++××=

Page 39: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

CPM Key Features

• Fixed amount of cash (the Pot) per year• Pot determined as Price x Volume

– Price: Best New Entrant Peaking Plant fixed costs– Volume: Capacity required to meet adequacy standard

• Pot allocated for Generator Payments:– Fixed (year ahead)– Variable (month ahead)– Ex-Post (month end)

• Generators paid when available• Pot allocated for Supplier Charges:

– Based on demand• Suppliers charged on consumption

Page 40: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Allocation for Charges

• Allocated at start of year as for Fixed

• Capacity Period charge known – stability/certainty• Incentivises reduction in consumption during peaks

J a n u a r y 2 0 0 7 D e m a n d C h a rg e s (R e la t iv e )

0

5

1 0

1 5

2 0

2 5

3 0

R e la t iv e D e m a n d C h a rg e sTrading Periods

( )∑ −−=

cinhch

ch

MinFDFDMinFDFDFCPWFh

TSC Version 24.105

Page 41: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

CPM Key Features

• Fixed amount of cash (the Pot) per year• Pot determined as Price x Volume

– Price: Best New Entrant Peaking Plant fixed costs– Volume: Capacity required to meet adequacy standard

• Pot allocated for Generator Payments:– Fixed (year ahead)– Variable (month ahead)– Ex-Post (month end)

• Generators paid when available• Pot allocated for Supplier Charges:

– Based on demand• Suppliers charged on consumption

Page 42: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

( )

−= 0,

VOLLSMPhVOLLMaxCPPFh

Supplier Charges

• Suppliers charged based on consumption• Charges reflect proportion of total consumption

• Trading Period allocations scaled in same way asfor Generator payments

Assimilation of TSC Version 2, 4.126 to 4.128Demand“Fixed” WeightingFactor

Monthly Pot

×××××∑

cinhvCPPFhFCPWFhNDLFvh

CPPScCPPFhFCPWFhNDLFvh

,

)(

Page 43: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Agenda

• CPM Objectives

• CPM Design

• Annual Capacity Payment Sum

• Payments to Generators

• Charges to Suppliers

• Summary

Page 44: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Summary

• The CPM is designed to meet a number ofObjectives:

– Capacity Adequacy:– Efficient Long-Term Signals– Price Stability– Minimise Susceptibility to Gaming– Fairness– Simplicity

• Chosen mechanism is a Fixed Revenuemechanism……..

Page 45: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Summary - continued

• Fixed amount of cash per year• Pot determined as Price x Volume

– Best New Entrant Peaking Plant fixed costs– Capacity required to meet adequacy standard

• Pot allocated for Generator Payments:– Fixed (year ahead)– Variable (month ahead)– Ex-Post (month end)

• Generators paid when available: proportional• Pot allocated for Supplier Charges:

– Based on demand• Suppliers charged on consumption: proportional

Page 46: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

Agenda

• CPM Objectives

• CPM Design

• Annual Capacity Payment Sum

• Payments to Generators

• Charges to Suppliers

• Summary

• Parameters for 2007/2008

Page 47: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

CPM Parameters andTimetable – “On-going”

• Regulatory Authorities determine (Y-4mths):– Annual Capacity Payment Sum (ACPSY)– Capacity Period Payment Sums (CPPSc)– Fixed Capacity Payments Proportion (FCCPY)– Ex-Post Capacity Payments Proportion (ECPPY)

• [and therefore the Variable Capacity Payments Proportion]– Value of Lost Load (VOLL)– Flattening Power Factor (FPFY)*

• Market Operator publishes above ~Y-2mths

* SO recommends value to Regulatory Authorities at this time

Consultation on BNE technology in Spring

Page 48: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

CPM Parameters - 2007

• Capacity Requirement - 6960MW• BNE Peaker Fixed Costs - €64.73/kW• ACPSY = €450,517,348• FCPPY = 0.3• ECPPY = 0.3 [VCPPY = 0.4]• VOLL – Consultation• FPFY = 0.35• CPPSc

Month AmountJan €42,277,947Feb €40,677,812Mar €40,532,345Apr €33,990,746May €32,088,658Jun €30,501,747Jul €30,722,151Aug €32,661,709Sep €32,685,953Oct €38,969,679Nov €47,131,249Dec €48,277,352

Page 49: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

* Indicative Values. Final value to be published August 2007

Month AmountJan €53,344,047Feb €51,602,752Mar €51,019,670Apr €43,050,000May €40,598,406Jun €39,047,938Jul €39,591,264Aug €41,425,322Sep €41,255,698Oct €49,447,999Nov €59,143,062Dec €60,425,842

• Capacity Requirement - 7200MW*• BNE Peaker Fixed Costs - €79.16/kW*• ACPSY = €569,952,000*• FCPPY = 0.3• ECPPY = 0.3 [VCPPY = 0.4]• VOLL – Consultation• FPFY = 0.35• CPPS*c

CPM Parameters – 2008

Page 50: Industry Presentation SEM Capacity Payment Mechanism...Industry Presentation SEM Capacity Payment Mechanism 27 July 2007 John Parsonage. Agenda • CPM Objectives • CPM Design •

End

Thank you for your attention

Ledian House45, Bedford RowLondonWC1R 4LNTel: +44 207 092 1795Fax: +44 207 092 1770Mob:+44 797 061 5309

John Parsonage