Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Inner HarborNavigation Canal Lock
Victor A. Landry III Operations Manager, GIWW
New Orleans DistrictU.S. Army Corps of Engineers
22 August 2008
PresenterPresentation NotesGood Morning!
GICA103RD Annual Convention
One Team: Relevant, Ready, Responsive, Reliable
• GIWW & IHNC Lock Overview
• Dewatering
• Challenges
PresenterPresentation NotesAgenda
Overview on our district
Navigation Mission
Challenges (Funding, IHNC Dewatering and MRGO)
ND
MN
MIWI
IAIL
INKS
MO KY
OK AR
AL
TN
LA
MSTX
MINNEAPOLISST. PAUL
DUBUQUE
ROCK ISLAND
ST. LOUIS
CAIRO
MEMPHISLITTLE ROCK
SHREVEPORTVICKSBURG
JACKSON
BATON ROUGE
NEW ORLEANS
St. Paul District
Rock Island District
St. Louis District
Memphis District
Vicksburg District
New Orleans District
One Team: Relevant, Ready, Responsive, Reliable
Mississippi Valley Division
PresenterPresentation NotesLocation (Division) MVD 6 districts Incorporates entire length of Miss River
One Team: Relevant, Ready, Responsive, Reliable
30,000 Square Miles
PresenterPresentation NotesLocation (Louisiana) 30,000 square miles South Louisiana
One Team: Relevant, Ready, Responsive, Reliable
Calcasieu Lock
Leland BowmanLock
Port Allen Lock
Harvey LockAlgiers Lock
IHNC Lock
Bayou Sorrel
Bayou Boeuf Lock
Berwick Lock
Mainstem
Alternate Route
Gulf Intracoastal WaterwayThru New Orleans District
PresenterPresentation Notes8 Locks on the GIWW that Operations Division is responsible for.
IHNC Lock Status
• 75’ x 640’
• Completed 1923• Dewater IHNC Lock
- Baptiste Collette currently being used for navigation
- IHNC Lock is currently being dewatered
- Lock closure closely coordinated with industry & USCG
- High river level for safe dewatering start date caused delays along with the oil spill
- MRGO will not be physically closed until the IHNC Lock repairs are complete
One Team: Relevant, Ready, Responsive, Reliable
PresenterPresentation NotesIHNC Lock Status
Corps is committed to dewatering the IHNC Lock.
Dewater will improve reliability for future use before the MRGO closure structure is in place.
Dewater schedule – 11 Aug to 10 Oct 2008 Schedule start date dependent on river levels Carrollton Gage must be at 6 ft or lower Dewaterings typically occur on a 10-15 yr frequency rate Last dewater in 1998
1 of 2
One Team: Relevant, Ready, Responsive, Reliable
One Team: Relevant, Ready, Responsive, Reliable
One Team: Relevant, Ready, Responsive, Reliable
One Team: Relevant, Ready, Responsive, Reliable
IHNC Lock Guidewall
Replaced river end, east side guidewall with Floating Guidewall
Concrete Pontoon with Fiberglass Plastic Composite Wale System
Constructed off-site
Installed Oct 2005 with only 1 day lock closure
Similar guidewall is needed on the west side which takes abuse
One Team: Relevant, Ready, Responsive, Reliable
HYD. GATE OPERATING MACHINERY DESIGN - $200,000
HYD. GATE OPERATING MACHINERY PROCUREMENT (4 SETS) - $2,500,000
PROCURE ADDITIONAL SPARE WEAR PARTS - $500,000
FLOATING GUIDEWALL DESIGN - $300,000
FLOATING GUIDEWALL CONTRACT AWARD - $13,250,000
NEW GATE DESIGN - $60,000 (previously designed, requires updates)
NEW GATE CONTRACT AWARD - $6,000,000
DOLPHIN REPAIR CONTRACT AWARD - $300,000
2 CORPS WORK UNITS + SHOPS - $3,000,000
$26,110,000 REQUIRED FOR FISCAL YEAR 2009 TO
ACCOMPLISH THESE MAJOR IMPROVEMENTS
PRELIMINARY IHNC LOCK REQUIRED
NON-DEWATERING ITEMS
• FY 2008 O&M Budget - $131.3 Million
• O&M appropriations flat-lined since 2002, except for the emergency supplemental appropriations following Hurricanes Katrina and Rita
• O&M budget decrease from $139 million in FY04 to $121 million in FY09
• Additional shoaling in the Mississippi and Atchafalaya Rivers due to high water events this past spring. Escalating fuel costs and rising steel prices impact construction and O&M.
•Dredging costs increase
One Team: Relevant, Ready, Responsive, Reliable
O&M Budget Trend
PresenterPresentation NotesO&M Budget Trends in recent years:
MVN O&M Gen navigation budget has decreased from $139 million in FY2004 to $121 million in FY2009.
MRGO O&M reduced by $13.5 annually since 2006.
O&M Allocation flat-lined for remaining projects since 2002, except for the emergency supplemental appropriations following Hurricanes Katrina and Rita.
Dredging costs have increased.- $83 million maintenance annually 80 million cubic yards of shoal material removed each year (15 superdomes)
Backlog of maintenance for most navigable waterways has increased over the past few years.
2 or 2
Backlog Maintenance
• Ranking of backlog maintenance list for O&M of structures– Projects ranked annually 1 year ahead of FY– Projects compete both regionally and nationally
• Causes for growth of O&M backlog maintenance list– Extended period of “flat” funding– Inflation and market conditions erode buying power of flat budget– O & M deferrals due to lack of funding– Aging locks require additional projects annually
One Team: Relevant, Ready, Responsive, Reliable
PresenterPresentation NotesBacklog Maintenance
Backlog maintenance list includes projects that are needed, but are not yet funded.
The Corps plans to meet with other divisions to rank the backlog list a year in advance.-Next annual meeting to be held this fall to address FY10
Funding challenges include fuel and labor costs.
• Port Allen Lock:- Dewatering to replace river end gates- Sep-Oct 2009 (45-60 day closure)- Dredge the lock forebay at the Mississippi River, Fall 2008
• Calcasieu Lock:- Remove & replace damaged lock dolphin - Sep-Oct 2008 (minimal delays to navigation)
• Dredge GIWW Port Allen to Morgan City Alternate Route:- Dredge below Bayou Sorrel Lock & Miles 19 to 27 (non-continuous) - Sep-Oct 2008
• Dredge Berwick Bay Harbor & Wax Lake Crossing:- Aug 2008, will be complete next week. Wheel washing bought us some extra timeduring high water.
Upcoming Work Summary
One Team: Relevant, Ready, Responsive, Reliable
PresenterPresentation NotesUpcoming Work Summary
The following slide shows our upcoming work summary along the GIWW at the following locations (besides the IHNC dewatering):
Port Allen Lock: - Dewatering to replace river end gates - Sep-Oct 2009 (45-60 day closure) - Dredge the lock forebay at the Mississippi River, fall 2008. Calcasieu Lock: - Remove & replace damaged lock dolphin - Sep – Oct 2008 (minimal closures) Dredge GIWW Port Allen to Morgan City Alternate Route:- Dredge below Bayou Sorrel Lock & Miles 19 to 27 (non-continuous) - Sep - Oct 2008 Dredge Berwick Bay Harbor & Wax Lake Crossing: - Aug 2008
Commitment to Navigation
One Team: Relevant, Ready, Responsive, Reliable
• Critical to New Orleans and the Nation
• Serving navigation purposes
• Working together to overcome challenges
T.E.A.M.
PresenterPresentation NotesCommitment to Navigation
Finally, just want to emphasize the following: Navigation infrastructure and industry are critical to New Orleans and the nation’s economy
Corps committed to working together with its partners to maintain the navigation purposes
Dedicated to maintaining the port as one of the world’s largest
Corps invites all our navigation partners to continuously participate with us:- Mississippi River Forum (for deep draft)- Quarterly forums (for shallow draft)- Project Specific
By working together, we can overcome any challenge
Questions?
Victor A. Landry III Operations Manager, GIWW
New Orleans DistrictU.S. Army Corps of Engineers
22 August 2008
PresenterPresentation NotesThank you for your time.
Do you have any questions?
Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Backlog MaintenanceSlide Number 14Slide Number 15Slide Number 16