Inspection & Ndt Control

Embed Size (px)

Citation preview

  • 7/28/2019 Inspection & Ndt Control

    1/2

    Company: Agip KCO

    Project: Kashagan Development Experimental Programme

    Subproject: Onshore Processing Facility

    Construction Assessment Checklist

    Checklist No: 12-07 Activity: INSPECTION AND NDE CONTROL

    Revision: 0 Discipline: 12 Pipeline

    Site/Location: Report Number:Contractor: Date:

    Subcontractor: Component:

    Item Action ResultsAccepted

    Yes No

    !Before commencing this surveillance. checkthe area is safe. If working at height doesthe scaffold have a green tag

    1 Is there a register for the WSJVsubcontractor NDT personnel certification

    and validation of qualifications2 2 Where are records of internal audits

    completed on NDT/Inspection activities arethey available for reference by theCompany

    3 Are Contractor's Inspection and NDTpersonnel certification and proceduresapproved as required by Company

    4 Does the contract provide definition of thescope of work and requirements for qualitymatters and inspection/NDT needs betweenthe contractor and NDT sub-contractor.

    5 How does the Company staff monitor thepipeline NDT contractor activities

    6 What Assessment and inspections arecompleted by the Company staff

    7 How are items in 6 reported and recorded

    8 Is a calibration register available

    9 Is all processing materials used in NDT inaccordance with 4.2.3

    10 Are the NDT being carried out on siteadequate and in compliance with theproject requirements, how is this verified bythe CPMT staff

    11 What procedure is used to check/auditradiographic examination of a weld

    12 For radiography does the CPMT staff checkevery weld and comment on interpretationwhere are record of these checks kept

    13 How is verification of NDT of repaired weldscarried out by CPMT

    Checklist No:12-07 Activity : INSPECTION & NDT CONTROL Page 1 of2

    01-Sept-08

  • 7/28/2019 Inspection & Ndt Control

    2/2

    Company: Agip KCO

    Project: Kashagan Development Experimental Programme

    Subproject: Onshore Processing Facility

    14 What verification and checks are carried outby CPMT on subcontractor NDT reports

    Accepted Completed by: Date:

    Rejected Witnessed by: Date:

    (Explain below) (Contractor or Subcontractor Representative)

    Deficiency Description: (What's wrong and why did it happen?)

    Checklist No:12-07 Activity : INSPECTION & NDT CONTROL Page 2 of2

    01-Sept-08