Installation Guide · 2015-12-17 · Horizontal or course lines for two-piece tile Two-piece, or cap and pan tile require lines for both the tops and pans. The first course lines

  • Upload
    others

  • View
    27

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Installation Guide · 2015-12-17 · Horizontal or course lines for two-piece tile Two-piece, or cap and pan tile require lines for both the tops and pans. The first course lines

Installation Guide

Page 2: Installation Guide · 2015-12-17 · Horizontal or course lines for two-piece tile Two-piece, or cap and pan tile require lines for both the tops and pans. The first course lines

Baja Mission 4000 Series

Baja Mission Sandcast 4300 Series

Roman Pan 6000 Series

Junipero 9000 Series

Cambridge Shingle 10000 Series

3"

8.5"

7"

20"

11" on centers

9" on centers

2.75"

6.75"

6"

17.5"

9" on centers

3.1875"

7"

5.75"

16.75"

2.75"

6.75"

6"

17.5"

9" on centers

2.375"

11"

11"

17.75"

13" on centers*

Two-Piece Mission 2000 Series

Two-Piece Mission Sandcast 2300 Series

3"

8.5"

20"

11" on centers

7"

.625"

6.75"

15"

* when used with Baja Mission tops. 18" when used with Roman tops.

Alfaro3000 Series 10"

18"

8" on centers

3"

Page 3: Installation Guide · 2015-12-17 · Horizontal or course lines for two-piece tile Two-piece, or cap and pan tile require lines for both the tops and pans. The first course lines

Horizontal or course lines for two-piece tile Two-piece, or cap and pan tile require lines for both the tops and pans. The first course lines are determined by subtracting the

overhang from the length of the tile. The pan lines will be marked first, then the cap line marked 3" lower. The rest of the courses

will be marked by measuring from the cap lines to the ridge and dividing that distance by the exposure to get the number of

courses. The pan tile will be cut at the ridge, so the final course of tops will end at the ridge nailer. Mark all lines starting at the

eave course up to the ridge and snap with a chalk line.

Vertical or run lines The first run lines in from the

rake boards are at 4". The

balance of the runs can be laid

out with on-center distances

being equal. The range in the

on-center distances varies

with profile.

To view complete instructions,

refer to the Tile Roofing

Institute manuals in the

Redland binder, or visit

www.redlandclaytile.com.

Layout, Coursing and Spacing

max. horizontal max. vertical top course line run line

two-piece mission 17" 11"

two-piece mission sandcast 17" 11"

alfaro 15" 8"

baja mission 14.5" 9"

baja mission sandcast 14.5" 9"

roman pan* 14.5" 13"

junipero 13.75" 9"

cambridge shingle 6.5" †

eave

ridge

top course line pan course line

left rake right rake

* Dimensions shown are for use with Baja Mission tops. For Roman tops: Max. Horizontal = 14.75" and Max. Vertical is 18".

† Placed with gaps in adjacent course staggered 1.5" minimum and spaced approximately .375" between tiles in each course.

Page 4: Installation Guide · 2015-12-17 · Horizontal or course lines for two-piece tile Two-piece, or cap and pan tile require lines for both the tops and pans. The first course lines

redlandclaytile.com 1.800.354.5983

limited lifetime product warranty

All Redland Clay Tile colors and blends have natural

color variations due to the inherent characteristics of the

raw materials used. To avoid excess color patterning,

checker-boarding or stair stepping, the installer should

periodically check the overall roof color from ground level

at a reasonable distance.

012009 © redland clay tile 2009