TECTOPANEL A B 300 mm 300 mm 300 mm 160 Knauf Danoline Wall Lining FURRING Tectopanel on walls can be installed on wood or steel furrings depending on current fire regulations. Furrings can be installed vertically or horizontally. Furrings should be at least 45 mm in width. Also see the section “Acoustics” on the next page. LAYOUT Perforated wall panels are normally installed on the upper section of a wall in accordance with acoustic requirements and the shape of the room in question. However, perforated panels can also be used to surface an entire wall depending on the degree of physical impact. Follow any available drawings or divide the surface of the wall so that the perforated modules are positioned symmetrically in the room. INSTALLATION • Install the panels. Install the first row with the help of string. The panels must be flush in their own rows and at right angles to the adjacent panels. Fig. 1 45 mm Z-profile 45 mm U-profile Screw SN 3.5 x 30 Panel edge Legend: A = Max. 200 mm B = 300 mm Best Practice: Handling the panels with care will avoid damage and surface contamination prior to painting and thereby ensure a good end result. CUTTING Cut the elements to size from the front with a fine-toothed saw. INSTALLATION GUIDE

INSTALLATION GUIDE - Knauf Danoline A/Sknaufdanoline.com/wp-content/uploads/Installation_Tectopanel_wall... · installation • install the panels. ... installation guide. tectopanel

Embed Size (px)

Citation preview

Page 1: INSTALLATION GUIDE - Knauf Danoline A/Sknaufdanoline.com/wp-content/uploads/Installation_Tectopanel_wall... · installation • install the panels. ... installation guide. tectopanel

TECTOPANEL

A

B

300 mm

300 mm

300 mm

160 Knauf Danoline Wall Lining

FURRING

• Tectopanel on walls can be installed on wood or steel furrings depending on current fire regulations.

• Furrings can be installed vertically or horizontally.

• Furrings should be at least 45 mm in width.

• Also see the section “Acoustics” on the next page.

LAYOUT

• Perforated wall panels are normally installed on the upper section of a wall in accordance with acoustic requirements and the shape of the room in question.

• However, perforated panels can also be used to surface an entire wall depending on the degree of physical impact.

• Follow any available drawings or divide the surface of the wall so that the perforated modules are positioned symmetrically in the room.

INSTALLATION

• Install the panels.

• Install the first row with the help of string.

• The panels must be flush in their own rows and at right angles to the adjacent panels.

Fig. 1

45 mm Z-profile

45 mm U-profile

Screw SN 3.5

x 30

Panel edge

Legend:

A = Max. 200 mm B = 300 mm

Best Practice: Handling the panels with care will avoid damage and surface contamination prior to painting and thereby ensure a good end result.

CUTTING

• Cut the elements to size from the front with a fine-toothed saw.

INSTALLATION GUIDE

Page 2: INSTALLATION GUIDE - Knauf Danoline A/Sknaufdanoline.com/wp-content/uploads/Installation_Tectopanel_wall... · installation • install the panels. ... installation guide. tectopanel

TECTOPANEL

Knauf Danoline Wall Lining 161

ACOUSTICS

• A perforated gypsum panel will lose its acoustic function if the perforations are blocked (this applies to the front and back of the panel).

• Where applicable, a vapour barrier should therefore always be placed behind the furrings so that it does not come into contact with the back of the perforated panel.

• When installing Tectopanel on a fixed surface we recommend filling the cavity between the back of the panel and the furring with mineral wool. This is primarily to ensure low frequency sound absorption.

FILLING SCREW HOLES

• Check that the screws have been countersunk.

• Apply the first layer of filler (Knauf Uniflott Finish).

• Allow the filler to dry.

• Apply the second layer of filler (Knauf Uniflott Finish), overfill slightly.

• Allow the filler to dry.

SANDING

• Make sure that the filler is completely dry.

• Sand with fine sandpaper until the surface is completely smooth. Be careful not to damage the cardboard surface.

PAINTING

• Make sure that the filler is completely dry and the surface is free from dust.

• Priming should be carried out in accordance with the paint manufacturer’s instructions.

• Apply the paint with a fine mohair roller.

• Make sure that the paint is not too thick and avoid applying too much paint at a time so that the acoustic felt on the perforated panels is not sealed.

• Spraying cannot be recommended as this could influence the acoustic properties of the panels.

INSTALLATION GUIDE

Page 3: INSTALLATION GUIDE - Knauf Danoline A/Sknaufdanoline.com/wp-content/uploads/Installation_Tectopanel_wall... · installation • install the panels. ... installation guide. tectopanel

TECTOPANEL

162 Knauf Danoline Wall Lining

Z profile

Perforated connector

Mineral wool

Tectopanel

Furring

Mineral wool

Tectopanel

Mitex - mitred design element

DETAILS

TECTOPANEL - INTEGRATED ACOUSTIC WALL

TECTOPANEL - ADD-ON ACOUSTIC WALL LINING

Page 4: INSTALLATION GUIDE - Knauf Danoline A/Sknaufdanoline.com/wp-content/uploads/Installation_Tectopanel_wall... · installation • install the panels. ... installation guide. tectopanel

TECTOPANEL

Knauf Danoline Wall Lining 163

PRODUCT NAME SAP NO. W x L x H (mm)

Z-profile 199089 30 x 45 x 45 x 2300

Screw (SN 3.5 x 30) 3503 3.5 x 30 mm

Uniflott Finish 129801 8 kg

Filling knife 73962 -

ACCESSORIES

CURVED PANELS

Apply water on the front face and leave for 30 minutes. If necessary the panel can be covered in plastic to assist the panel in absorbing the water.

Lay the panel over a template. Secure the panel on one side of the template.

To minimize the risk of mold formation during the process, make then sure that a fast drying of the boards is present. A good ventilation with high air exchange and relative high temperature is needed and with advantage the boards can be bended and dried out before mounting.

Press the panel against the template using a batten, moving it every 100 mm. Secure the panel on the other side of the template. Make sure that the panel is fully dry before mounting or closing the construction.