1 1 Successful Implementation & Improved Operation

Installation – Issues and Solutions

Andreas Agostin Industrial Network Sales Specialist Asia Pacific

MTL Instruments Singapore, part of Cooper Crouse-Hinds

22.02.2012 Kuala Lumpur

Page 2: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

2 2 Successful Implementation & Improved Operation

Introduction

Fieldbus is in use since 19981, yet still new for

many customers today.

This presentation will look at the installation issues

and the “lessons learned”, so that you can

benefits from their experience.

1 Shell Malampaya is one of the early, larger projects. 1600 FF instruments are in use. The project produced first gas in

Oct 2001. Source: J. Seaver, Shell Philippines Exploration B.V., “Malampaya Deep Water Gas-to-Power Project:

Malampaya Subsea Development”, Offshore Technology Conference, 6 May-9 May 2002, Houston, Texas.

Page 3: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

3 3 Successful Implementation & Improved Operation

Introduction

The pictures you will see are collected from “real”

projects; they are neither simulated nor “demo”.

We will look at – Control room: cabinet design and wiring

– Field: Wiring, field junction boxes, field device installation.

Processes typically involve explosion protection methods

“intrinsic safety” (I.S. / Ex i; energy limitation by a „barrier‟)

or “explosion proof” (Ex d; protection by explosionproof

enclosure).

Many examples use “IS” as this is a key product of my

company and that is where I get involved.

Page 4: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

4 4 Successful Implementation & Improved Operation

Disclaimer

All products shown serve as EXAMPLE only.

In particular, problems shown in conjunction with a product

serve as example only.

The brand/make/model of the product serving as example

is IRRELEVANT.

Problems highlighted serve as example only, are do in no

way express problems with a particular product,

model or brand.

Page 5: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

5 5 Successful Implementation & Improved Operation

The conventional system

Page 6: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

6 6 Successful Implementation & Improved Operation

Control room – Conventional wiring

2nd level 1st level

junction box Marshalling

and barrier Control system

Page 7: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

7 7 Successful Implementation & Improved Operation

Control room – Conventional wiring

Marshalling: to group AI / AO / DI / DO / etc

Page 8: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

8 8 Successful Implementation & Improved Operation

Control room – Conventional wiring

Page 9: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

9 9 Successful Implementation & Improved Operation

Control room – Conventional wiring

Long wires, standard length

Allows pre-fabrication of wire

(ferrules, mounting)

Conventional signals (4-20mA,

RTD, thermocouple, 0-

5V/10V/24V) – slow, hardware

filtered, length less important

Page 10: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

10 10 Successful Implementation & Improved Operation

Field – Conventional wiring

Quality (material)

Safety

Location / access

Weight/size, …

10

Page 11: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

11 11 Successful Implementation & Improved Operation

Fieldbus versus conventional

Page 12: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

12 12 Successful Implementation & Improved Operation

Control room – DCS wiring EXAMPLES

Fieldbus

Conventional

Page 13: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

13 13 Successful Implementation & Improved Operation

Control room – DCS wiring EXAMPLES

Installations do not have

to look messy. They

can be very nice, too.

Fieldbus

Conventional

Page 14: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

14 14 Successful Implementation & Improved Operation

Control room – DCS wiring EXAMPLES Fieldbus Conventional

Page 15: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

15 15 Successful Implementation & Improved Operation

Control room – DCS wiring EXAMPLES

Fieldbus Fieldbus

Page 16: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

16 16 Successful Implementation & Improved Operation

Control room – DCS wiring

Important:

do not use individual wires to

wire cabinet. Use fieldbus cable

and shield properly.

Why?

Higher signal

frequency – protect

them against

disturbances.

Individual wires will

cause crosstalk from

one wire to another –

communication faults

can occur.

?

Page 17: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

17 17 Successful Implementation & Improved Operation

Fieldbus Cable Recommended: Type A cable: Shielded twisted pair Other cable is possible, but there are limitations in terms of achievable cable distance and electromagnetic compatibility (EMC). Fieldbus is a digital “high speed” (31kBit/s) communication, a current modulated signal superimposed on the DC power.

Page 18: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

18 18 Successful Implementation & Improved Operation

Fieldbus Cable

Shielded pair

principle

Foil

shield

Foil plus

braided

shield

SWA

SWA

Multi-pair

Multi-pair (multi-trunk)

Page 19: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

19 19 Successful Implementation & Improved Operation

Please not this way

Images obscured – Brand is irrelevant.

Page 20: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

20 20 Successful Implementation & Improved Operation

Control room – DCS wiring

Page 21: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

21 21 Successful Implementation & Improved Operation

Fieldbus system – Field wiring

? • Parallel wiring

(terminals)

• special wiring

blocks

• (daisy chaining)

Page 22: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

22 22 Successful Implementation & Improved Operation

Fieldbus system – Field junction boxes

Principle of wiring distribution in junction box:

all devices are in parallel

Source: FF AG 140 Rev. 1

Page 23: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

23 23 Successful Implementation & Improved Operation

Fieldbus system – Field junction boxes

Please not this way

Page 24: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

24 24 Successful Implementation & Improved Operation

24

Fieldbus system – Field junction boxes

Use dedicated

wiring blocks

with built-in

electronic

short circuit

protection.

LEDs: - built-in s/c protection

Page 25: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

25 25 Successful Implementation & Improved Operation

Good Wiring Practices

Test segment wiring before connecting components Avoid damaging the wire when removing insulation Ground the cable shield only at one point (at the control

room end) Insulate the ungrounded end of the cable shield (at the

instrument) Ground armor on both sides (potential equalization) Use crimp ferrules

– Ferrule diameter must fit wire – Crimp tool must fit ferrule – Ferrule must fit terminals

Maintain polarity and associated color codes throughout the segment

Page 26: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

26 26 Successful Implementation & Improved Operation

Good Wiring Practices

Lessons learned:

Torque screwdriver

Wire end ferrules

Right (!) wire strippers

Fieldbus tester

Harms

wire strands

Choose

right size

Page 27: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

27 27 Successful Implementation & Improved Operation

Fieldbus Design Tools (Examples)

Page 28: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

28 28 Successful Implementation & Improved Operation

Project Procedure

Best practice:

Bench test

Functional tests and interoperability test

FAT

SAT

Page 29: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

29 29 Successful Implementation & Improved Operation

Installation Guidelines

Cable Tests – Experience has shown that new cable irregularities are

so infrequent that it is more efficient to check cable after installation

Cable Installation – Verify that cable is properly installed, bypassing impact

from wiring components Segment Checkout

– Check of proper wiring of wiring components Device installation

– Check of proper device installation Loop checkout

– Functional test

Page 30: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

30 30 Successful Implementation & Improved Operation

Installation tools

Portable fieldbus diagnostic test equipment

(Handhelds)

Measures relevant fieldbus

parameters

Establish baseline

after commissioning

Page 31: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

31 31 Successful Implementation & Improved Operation

Handheld diagnostic tools

Handheld

Diagnostic

Tool Device 1 Device 3 Device 2

T

Device Coupler

& Terminator

(non-IS) Spurs

FFPS

T

FF Power Supply

& Conditioner

&Terminator

24VDC

Host

Computer

H1 Interface

Connect at respective location to obtain accurate measurement.

Page 32: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

32 32 Successful Implementation & Improved Operation

Handheld diagnostic tools

Handheld

Diagnostic

Tool

FFPS

T

FF Power Supply

& Conditioner

&Terminator

24VDC

Host

Computer

H1 Interface

Fieldbus

barrier

Device 1 Device 3 Device 2

Fieldbus barrier

& Terminator

Intrinsically

Safe Spurs

T

Fieldbus

barrier

To measure at fieldbus barrier/IS segments, Handheld needs to be Ex i approved.

Important since the galvanic isolation of fieldbus barrier impacts on measurement.

Page 33: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

33 33 Successful Implementation & Improved Operation

Earthing/Grounding

Grounding in the control room

One point grounding only

Continuous shield from control room to the field

Shield not connected at the field instrument

Connect cable armor at both ends (potential

equalization)

Page 34: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

34 34 Successful Implementation & Improved Operation

Earthing/Grounding

Device 1 Device 3 Device 2

T

Wiring Block

& Terminator FFPS

T

FF Power Supply

& Conditioner

&Terminator

24VDC

Host

Computer

H1 Interface

Page 35: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

35 35 Successful Implementation & Improved Operation

Fieldbus

barrier

Device 1 Device 3 Device 2

Fieldbus barrier

& Terminator

Intrinsically

Safe Spurs

T

Fieldbus

barrier

Earthing/Grounding

FFPS

T

FF Power Supply

& Conditioner

&Terminator

24VDC

Host

Computer

H1 Interface

Page 36: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

36 36 Successful Implementation & Improved Operation

Local field junction box for 4

instruments. Rust prevented

proper grounding, so that

separate ground connection

was required

Page 37: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

37 37 Successful Implementation & Improved Operation

Field – Fieldbus wiring

Green: fieldbus

Red: Power (Motors, etc)

For easy maintenance

Page 38: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

38 38 Successful Implementation & Improved Operation

Troubleshooting

Page 39: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

39 39 Successful Implementation & Improved Operation

Daisy chaining – not recommended

Page 40: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

40 40 Successful Implementation & Improved Operation

Troubleshooting

Electrical welding can generate significant surges

Page 41: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

41 41 Successful Implementation & Improved Operation

Bend radius too tight, Upward facing gland risks water ingress

Two cables into one gland

prevents sealing of gland

Page 42: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

42 42 Successful Implementation & Improved Operation

Water ingress caused corrosion of wire and terminals

Page 43: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

43 43 Successful Implementation & Improved Operation

Cable jacket stripped back too far

Troubleshooting

Page 44: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

44 44 Successful Implementation & Improved Operation

Wires coming out of ferrules

Page 45: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

45 45 Successful Implementation & Improved Operation

Troubleshooting

Earth stud not connected – internal

surge protectors not working

Page 46: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

46 46 Successful Implementation & Improved Operation

Troubleshooting

Ground not connected

Page 47: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

47 47 Successful Implementation & Improved Operation

Troubleshooting

Poor cable (shield) quality

Page 48: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

48 48 Successful Implementation & Improved Operation

Troubleshooting

Grounding concept failure-prone

Page 49: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

49 49 Successful Implementation & Improved Operation

Troubleshooting

Water marks, fungus inside junction box

Page 50: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

50 50 Successful Implementation & Improved Operation

Troubleshooting

Wire squeezed by enclosure lid – water ingress

Page 51: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

51 51 Successful Implementation & Improved Operation

http://forums.fieldbus.org/showthread.php?t=1298

Page 52: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

52 52 Successful Implementation & Improved Operation

Conclusion

Fieldbus is robust if the installation is adjusted to

the requirements of a digital communication line

Do not simply copy 4-20 methods

Use fieldbus smartly (e.g. eliminate marshalling)

Good wiring practices are more important than

on 4-20 due to bus structure

Train your installers on fieldbus practices

Page 53: Installation Issues and Solutions - Fieldbus · 2012-02-22 · 2 Successful Implementation & Improved Operation Introduction Fieldbus is in use since 19981, yet still new for many

53 53 Successful Implementation & Improved Operation

Installation – Issues and Solutions

Andreas Agostin Industrial Network Sales Specialist Asia Pacific

MTL Instruments Singapore, part of Cooper Crouse-Hinds

22.02.2012 Kuala Lumpur

[email protected]

Ph: +65 97585161